ATTACHMENT 2 – SCHEDULE OF SUPPLIES/SERVICES
SOLICITATION NO. HSCG85-15-R-P30B10
Dockside Repairs of USCGC STRATTON (WMSL 752) FQ4 FY15
B.1
CLIN 0001 - DEFINITE ITEMS
These are the items that, if there is an award at all, will be awarded. The proposal shall be evaluated to include the proposed price for each definite item.
| ITEM NO. |
| DESCRIPTION |
| AMOUNT |
| D-01 |
| Tanks (MP Fuel Service), Clean and Inspect |
| $ |
| D-02 |
| Tank (High Purity Water), Clean and Inspect |
| $ |
| D-03 |
| Circuit Breakers (Draw Out), Inspect and Test |
| $ |
| D-04 |
| Miscellaneous System Relief Valves, 5 Year Certification |
| $ |
| D-05 |
| Cascade Orificial Resistive Device, Clean and Inspect |
| $ |
| D-06 |
| Anchor Windlass Level 2 Inspect and Repair |
| $ |
| D-07 |
| Fixed CO2, FM 200 and Ansul R-102 Systems Annual Certification, Perform |
| $ |
| D-08 |
| Water Mist System, Annual Inspection, Perform |
| $ |
| D-09 |
| Dual Point Davit ,Biennial Maintenance, Perform |
| $ |
| D-10 |
| Folding Boom Cranes, Biennial Maintenance, Perform |
| $ |
| D-11 |
| Vacuum Collection Holding Tank, Clean and Inspect |
| $ |
| D-12 |
| Flight Deck Net, Weight Testing |
| $ |
| D-13 |
| Cofferdam, Install |
| $ |
| D-14 |
| Decks Exterior Preserve, Helicopter Hangar |
| $ |
| D-15 |
| Decks Exterior Surface, Preserve |
| $ |
| D-16 |
| Deck Covering (Polymeric), Seal |
| $ |
| D-17 |
| Temporary Services, Dockside, Home Pier |
| $ |
| D-18 |
| Fire Detector, Relocate |
| $ |
| D-19 |
| Sewage Piping, Hydroblast Clean and Flush |
| $ |
| TOTAL AMOUNT OF ALL DEFINITE ITEMS |
| $ |
B.2
CLIN 0002 - OPTIONAL ITEMS
The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s). See ATTACHMENT 3, Section 17, Page 11, entitled “OPTIONAL ITEMS.”
| ITEM NO. |
| DESCRIPTION |
| AMOUNT |
| O-20 |
| Tanks (Water Mist), Preserve “100%” |
| O-21 |
| Tanks (Water Mist), Preserve “Partial” |
| $ |
| O-22 |
| Vacuum Collection Holding Tank, Preserve “100%” |
| O-23 |
| Vacuum Collection Holding Tank, Preserve “Partial” |
| O-24 |
| Sewage Piping, Clean Out Connections, Install |
| O-25 |
| Sewage Piping, Renew |
| O-26 |
| Helo Nets Chaffing Guard, Renew-Optional |
| $ |
| TOTAL AMOUNT OF ALL OPTIONAL ITEMS |
| $ |
| TOTAL – ALL DEFINITE & OPTIONAL ITEMS |
| $ |
B.3
COMPOSITE LABOR HOUR RATE APPLICABLE TO CONTRACT CHANGES
The following labor hour rate shall be used in pricing all contract changes in accordance with ATTACHMENT 3, Section 14, Pages 9-10, entitled "COMPOSITE LABOR RATE.”
LABOR HOUR RATE
ESTIMATED QUANTITY
1181 hours
EXTENDED AMOUNT
**NOTE: The estimated quantity and extended amount indicated above are for evaluation of proposals only. The proposed rate will apply to all changes involving additional work under this contract regardless of the actual total hours required.