PAGE

Surface Forces Logistics Center Contracting and Procurement Division Contracting and Procurement Branch-2 705 E. Ordnance Road, Suite 100 Baltimore, MD 21226-5000

REQUEST FOR PROPOSAL

HSCG85-13-R-P01531

Boat Gyrocompass System, Technical Documentation, & Spares for the 140 Foot WTGB Ice Breaking Tug Class Cutters

NOTICE FOR FILING AGENCY PROTESTS

United States Coast Guard Ombudsman Program

It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the Government Accountability Office (GAO).

Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative Dispute Resolution (ADR) forum rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.

Informal Forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the Contracting Officer is unable to satisfy their concerns, interested parties are encouraged to contact the U.S. Coast Guard Ombudsman for Agency Protests. Under this informal process the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).

Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest to either the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program. Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103(d) (2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted to:

COMMANDANT (CG-9131)

U S COAST GUARD

OMBUDSMAN PROGRAM FOR AGENCY PROTESTS

2100 2ND ST SW STOP 7112

WASHINGTON DC 20593-7112

The Ombudsman Hotline telephone number is 202-372-3695.

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

2112852P01531

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

HSCG85-13-R-P01531

6. SOLICITATION

ISSUE DATE

17 Jan 2013

7. FOR SOLICITATION INFORMATION CALL:
a. NAME

John Boyd email: John.T.Boyd@uscg.mil

b. TELEPHONE NUMBER (no collect calls)

1-410-762-6905

8. OFFER DUE DATE/ LOCAL TIME

25 Feb 2013 Time: 1:00pm EST

9. ISSUED BY CODE AC42D

USCG Surface Forces Logistics Center

Contracting & Procurement Division (IBCT)

705 Ordnance Road, Suite 100 Baltimore, MD 21226-5000

1 0. THIS ACQUISITION IS UNRESTRICTED X

FORMCHECKBOX

SET ASIDE: 100 % FOR

__ SMALL BUSINESS

__ HUBZONE SMALL BUSINESS

FORMCHECKBOX

8(A)

NAICS: 334511

SIZE STANDARD 500 Employees

11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED

FORMCHECKBOX

SEE SCHEDULE

12. DISCOUNT

TERMS

Net 30 Days

FORMCHECKBOX

13a. THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 700)

13b. RATING D0-N5

14. METHOD OF SOLICITATION

FORMCHECKBOX

RFQ FORMCHECKBOX

IFB FORMCHECKBOX

RFP

15. DELIVER TO CODE

See Description of Supplies/Services

16. ADMINISTERED BY CODE

See Block 9

17a. CONTRACTOR/ CAGE CODE FACILITY

OFFEROR CODE

TELEPHONE NO:

FAX NO:

18a. PAYMENT WILL BE MADE BY CODE USCG Finance Center

1430A Kristina Way

Chesapeake, VA 23326

FORMCHECKBOX

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED __ SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

Contractor is to provide Boat Gyrocompass Systems, provisioning data, on-site technical support, & spare parts lists in accordance with the attached solicitation and specification.

See Continuation Sheets, pages 3 – 12 (Please submit pricing on the attached sheets)

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

To be provided on individual task orders

26. TOTAL AWARD AMOUNT (FOR GOVT USE ONLY)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 5.212-3 & 52.212-5 ARE ATTACHED. ADDENDA FORMCHECKBOX

ARE FORMCHECKBOX

ARE NOT ATTACHED.

FORMCHECKBOX

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4, FAR 42.212-5 IS ATTACHED. ADDENDA FORMCHECKBOX

ARE FORMCHECKBOX

ARE NOT ATTACHED.

FORMCHECKBOX

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1 COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.

FORMCHECKBOX

29. AWARD OF CONTRACT: REFERENCE

OFFER DATED . YOUR OFFER ON SOLICITATION (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

31a. UNITED STATES OF AMERICA (SINGATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER

30c. DATE SIGNED

31b. NAME OF CONTRACTING OFFICER

31c. DATE SIGNED

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED

FORMCHECKBOX

INSPECTED

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER

34. VOUCHER NUMBER

35. AMOUNT VERIFIED CORRECT FOR

36. PAYMENT

FORMCHECKBOX

COMPLETE

FORMCHECKBOX

PARTIAL

FORMCHECKBOX

FINAL

37. CHECK NUMBER

FORMCHECKBOX

PARTIAL FORMCHECKBOX

FINAL

38. S/R ACCOUNT NUMBER

39. S/R VOUCHER NUMBER

40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

42 a. RECEIVED BY (Print)

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41c. DATE

42b. RECEIVED AT (Location)

42c. DATE REC’D (YY/MM/DD)

42d. TOTAL CONTAINERS

SCHEDULE OF SUPPLIES OR SERVICES AND PRICES/COSTS - BASE YEAR

(For the purposes of evaluating the price of vendors as noted on page 45, extended prices & quantities for the Contract Line Item Numbers (CLINs) noted below will be used: CLIN 004AA (Qty 1), CLIN 004AB (Qty 1)

CLIN
WORK ITEM TITLE
UNIT PRICE
UNIT
ESTIMATED

QTY

EXTENDED PRICE

001
Boat Gyrocompass System (Includes first article testing & test reports)
EA
1
002
On-site technical support for training, system testing, commissioning etc…
EA
1
003
Spare parts list with prices for on-board repair parts (Price for list included in CLIN 105)
NSP
EA
1
NSP
003AA
On-board spare parts kit (Final price established IAW price list in CLIN 103 after Coast Guard confirms quantity and items needed)
KIT
1
004
Spare parts lists with prices to support end item for 1 & 3 years with depot level spares (Price for list included CLIN 105)
NSP
EA
1
NSP
004AA
Depot Level Spares - supporting end item for 1 year (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 1
004AB
Depot Level Spares - supporting end item for 3 years (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 1
004AC
Miscellaneous spares kits (Final price established IAW price list in CLIN 103 & 104 after Coast Guard confirms quantity and items needed).
TBD
KIT
0 to 2
TBD
005
Engineering data for provisioning in accordance with Attachment 2 of the specification
EA
1
006
Provisioning technical documentation in accordance with Attachment 1 of the specification
EA
1

BASE YEAR TOTAL:

SCHEDULE OF SUPPLIES OR SERVICES AND PRICES/COSTS - OPTION YEAR 1

(For the purposes of evaluating the price of vendors as noted on page 45, extended prices & quantities for the Contract Line Item Numbers (CLINs) noted below will be used: CLIN 101 (Qty 2), CLIN 102 (Qty 2), CLIN 103AA (Qty 2), CLIN 104AA (Qty 2), CLIN 104AB (Qty 2), CLIN 105 (Qty 2 - to cover two Gyrocompass systems)

CLIN
WORK ITEM TITLE
UNIT PRICE
UNIT
ESTIMATED

QTY

EXTENDED PRICE

101
Boat Gyrocompass System (Includes all necessary testing and test reports)
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

102
On-site technical support for training, system testing, commissioning etc…
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

103
Spare parts list with prices for on-board repair parts (Price for list included in CLIN 105)
NSP
EA
1
NSP
103AA
On-board spare parts kit (Final price established IAW price list in CLIN 103 after Coast Guard confirms quantity and items needed)
KIT
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

104
Spare parts lists with prices to support end item for 1 & 3 years with depot level spares (Price for list included CLIN 105)
NSP
EA
1
NSP
104AA
Depot Level Spares - supporting end item for 1 year (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

104AB
Depot Level Spares - supporting end item for 3 years (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

104AC
Miscellaneous spares kits (Final price established IAW price list in CLIN 103 & 104 after Coast Guard confirms quantity and items needed).
TBD
KIT
0 to 6
TBD
105
Engineering data for provisioning in accordance with Attachment 2 of the specification
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

OPTION YEAR 1 TOTAL:
For Qty of 1:

For Qty of 2:

For Qty of 3:

SCHEDULE OF SUPPLIES OR SERVICES AND PRICES/COSTS - OPTION YEAR 2

(For the purposes of evaluating the price of vendors as noted on page 45, extended prices & quantities for the Contract Line Item Numbers (CLINs) noted below will be used: CLIN 201 (Qty 2), CLIN 202 (Qty 2), CLIN 203AA (Qty 2), CLIN 204AA (Qty 2), CLIN 204AB (Qty 2), CLIN 205 (Qty 2 - to cover two Gyrocompass systems)

CLIN
WORK ITEM TITLE
UNIT PRICE
UNIT
ESTIMATED

QTY

EXTENDED PRICE

201
Boat Gyrocompass System (Includes all necessary testing and test reports)
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

202
On-site technical support for training, system testing, commissioning etc…
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

203
Spare parts list with prices for on-board repair parts (Price for list included in CLIN 105)
NSP
EA
1
NSP
203AA
On-board spare parts kit (Final price established IAW price list in CLIN 103 after Coast Guard confirms quantity and items needed)
KIT
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

204
Spare parts lists with prices to support end item for 1 & 3 years with depot level spares (Price for list included CLIN 105)
NSP
EA
1
NSP
204AA
Depot Level Spares - supporting end item for 1 year (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

204AB
Depot Level Spares - supporting end item for 3 years (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

204AC
Miscellaneous spares kits (Final price established IAW price list in CLIN 103 & 104 after Coast Guard confirms quantity and items needed).
TBD
KIT
0 to 6
TBD
205
Engineering data for provisioning in accordance with Attachment 2 of the specification
EA
1 to 3
For Qty of 1:

For Qty of 2:

For Qty of 3:

OPTION YEAR 2 TOTAL:
For Qty of 1:

SCHEDULE OF SUPPLIES OR SERVICES AND PRICES/COSTS - OPTION YEAR 3

(For the purposes of evaluating the price of vendors as noted on page 45, extended prices & quantities for the Contract Line Item Numbers (CLINs) noted below will be used: CLIN 301 (Qty 2), CLIN 302 (Qty 2), CLIN 303AA (Qty 2), CLIN 304AA (Qty 2), CLIN 304AB (Qty 2), CLIN 305 (Qty 2 - to cover two Gyrocompass systems)

CLIN
WORK ITEM TITLE
UNIT PRICE
UNIT
ESTIMATED

QTY

EXTENDED PRICE

301
Boat Gyrocompass System (Includes all necessary testing and test reports)
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

302
On-site technical support for training, system testing, commissioning etc…
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

303
Spare parts list with prices for on-board repair parts (Price for list included in CLIN 105)
NSP
EA
1
NSP
303AA
On-board spare parts kit (Final price established IAW price list in CLIN 103 after Coast Guard confirms quantity and items needed)
KIT
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

304
Spare parts lists with prices to support end item for 1 & 3 years with depot level spares (Price for list included CLIN 105)
NSP
EA
1
NSP
304AA
Depot Level Spares - supporting end item for 1 year (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

304AB
Depot Level Spares - supporting end item for 3 years (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

304AC
Miscellaneous spares kits (Final price established IAW price list in CLIN 103 & 104 after Coast Guard confirms quantity and items needed).
TBD
KIT
0 to 6
TBD
305
Engineering data for provisioning in accordance with Attachment 2 of the specification
EA
1 to 3
For Qty of 1:

For Qty of 2:

For Qty of 3:

OPTION YEAR 3 TOTAL:
For Qty of 1:

SCHEDULE OF SUPPLIES OR SERVICES AND PRICES/COSTS - OPTION YEAR 4

(For the purposes of evaluating the price of vendors as noted on page 45, extended prices & quantities for the Contract Line Item Numbers (CLINs) noted below will be used: CLIN 401 (Qty 2), CLIN 402 (Qty 2), CLIN 403AA (Qty 2), CLIN 404AA (Qty 2), CLIN 404AB (Qty 2), CLIN 405 (Qty 2 - to cover two Gyrocompass systems)

CLIN
WORK ITEM TITLE
UNIT PRICE
UNIT
ESTIMATED

QTY

EXTENDED PRICE

401
Boat Gyrocompass System (Includes all necessary testing and test reports)
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

402
On-site technical support for training, system testing, commissioning etc…
EA
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

403
Spare parts list with prices for on-board repair parts (Price for list included in CLIN 105)
NSP
EA
1
NSP
403AA
On-board spare parts kit (Final price established IAW price list in CLIN 103 after Coast Guard confirms quantity and items needed)
KIT
1 to 3
Qty of 1:

Qty of 2:

Qty of 3:

404
Spare parts lists with prices to support end item for 1 & 3 years with depot level spares (Price for list included CLIN 105)
NSP
EA
1
NSP
404AA
Depot Level Spares - supporting end item for 1 year (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

404AB
Depot Level Spares - supporting end item for 3 years (Final price established IAW price list in CLIN 104 after Coast Guard confirms quantity and items needed)
KIT
0 to 3
Qty of 1:

Qty of 2:

Qty of 3:

404AC
Miscellaneous spares kits (Final price established IAW price list in CLIN 103 & 104 after Coast Guard confirms quantity and items needed).
TBD
KIT
0 to 6
TBD
405
Engineering data for provisioning in accordance with Attachment 2 of the specification
EA
1 to 3
For Qty of 1:

For Qty of 2:

For Qty of 3:

OPTION YEAR 4 TOTAL:
For Qty of 1:

CONTINUATION OF SF 1449

Block 17a: Contractor shall include DUNS number.

Block 17b: REMITTANCE ADDRESS: Payment will be made to Financial Institution listed in the Central Contractor Registration (CCR). To receive award the contractor must be registered in Central Contractor Registration (CCR) https://www.sam.gov/portal/public/SAM/

Block 18: INVOICES. The Contractor shall submit invoices via one of the following modes, listed in descending order of preference:

1. FINCEN Website invoice receipt form: http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm

2. Commercial Invoices

U.S. Coast Guard Finance Center

1430A Kristina Way

Chesapeake, VA 23326

3. Fax: (757-523-6900)

Blocks 19 through 24: SEE SCHEDULE OF SUPPLIES/SERVICES ABOVE. Insert unit prices in all CLINs listed in the Schedule unless “NSP” is printed in the Unit Price column for any CLIN. “NSP” in the section means “Not Separately Priced.”

Block 25: ACCOUNTING AND APPROPRIATION DATA. This information will be included on individual delivery orders.

REQUIRED DOCUMENTS:

Each quoter shall furnish the information required by the solicitation, which includes:

1. Signed 1449 with offeror’s address, DUNS and other information completed.

2. Price Schedule filled out with a cost associated with each CLIN

3. Past Performance Documentation

Mailed and e-mailed proposals will be accepted. Faxed proposals will not be accepted. E-mailed proposals should be sent to John Boyd at John.T.Boyd@uscg.mil.

PLEASE NOTE: PROPOSALS THAT DO NOT INCLUDE ALL REQUIRED DOCUMENTS MAY BE CONSIDERED INCOMPLETE AND MAY NOT BE CONSIDERED.

Failure to read the specifications in their entirety will not relieve the vendor from the responsibility for properly estimating the difficulty or price of successfully providing product or performing the work. Failure to do so will be at the vendor's risk. All proposals submitted in response to this solicitation shall stand firm for 60 calendar days from the response date of this solicitation.

All contractors are responsible for verifying the receipt of their proposals.

Note 1: This Request for Proposal is issued, in accordance with FAR Part 12 (Acquisition of Commercial Items) & Part 15 (Contracting by Negotiation). For questions concerning this solicitation contact John Boyd, Contract Specialist at 410-762-6905 or via email at John.T.Boyd@uscg.mil. Any questions shall be submitted by February 4, 2013 by 1:00pm Eastern Time. No other questions will be accepted after this time.

Note 2: This project is an unrestricted procurement

Note 3: Contract Type: This Request for Proposals (RFP) will result in a firm fixed-price requirements contract for the supplies or services specified and effective for the period stated in the Schedule consisting of a base year with four one year option periods. The quantities of supplies or services specified in the Schedule are estimates only.

Note 4: ANTICIPATED AWARD DATE: The contract is expected to be awarded by April 15 2013. The performance period is for one year after contract award of the base year with 4 one year option periods.

Note 5: Period of Contract: The ordering period for the base year of this contract shall begin on the date of award or April 15, 2013, whichever is later and end 12 months thereafter. Option periods, if exercised by the Government, will occur consecutively thereafter with each option period continuing for 12 months. Performance dates for ordered work will be established on individual task orders.

Note 6: Per Federal Acquisition Regulation (FAR) clause 52.216-18, “Ordering,” the following individuals are authorized to issue delivery orders against this contract: Any person that is a part of SFLC IBCT contracting and procurement.

CONTRACT CLAUSES

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://www.arnet.gov/far/index.html

FAR 52.204-4

Printed or Copied Double-sided on Recycled Paper (May 2011)

FAR 52.223-3

Hazardous Material Identification and Material Safety Data (JAN 1997), Alternate I (JUL 1995)

FAR 52.223-12

Refrigeration Equipment and Air Conditioners (MAY 1995)

FAR 52.228-5

Insurance – Work on a Government Installation (JAN 1997)

FAR 52.232-18

Availability of Funds (APR 1984)

FAR 52.242-2

Production Progress Reports (APR 1991)

FAR 52.245-1

Government Property (APR 2012)

FAR 52.245-9

Use and Charges (APR 2012)

FAR 52.247-34

F.o.b. Destination (Nov 1991)

HSAR 3052.211-70

Index for Specifications (DEC 2003)

HSAR 3052.217-91

Performance (DEC 2003)

HSAR 3052.217-92

Inspection and Manner of Doing Work (DEC 2003)

HSAR 3052.217-93

Subcontracts (DEC 2003)

HSAR 3052.217-95

Liability and Insurance (DEC 2003)

HSAR 3052.217-96

Title (DEC 2003)

HSAR 3052.217-97

Discharge of liens (DEC 2003)

HSAR 3052.217-98

Delays (DEC 2003)

HSAR 3052.217-99

Department of Labor Safety and Health Regulations for Ship Repair (DEC 2003)

HSAR 3052.217-100

Guarantee (JUN 2006)

HSAR 3052.222-70

Strikes or Picketing Affecting Timely Completion of the Contract Work (DEC 2003)

HSAR 3052.222-71

Strikes or Picketing Affecting Access to a DHS Facility (DEC 2003)

HSAR 3052.223-90

Accident and Fire Reporting (DEC 2003)

HSAR 3052.242-71

Dissemination of Contract Information (DEC 2003)

HSAR 3052.242-72

Contracting Officer’s Technical Representative (DEC 2003)

HSAR 3052.245-70

Government Property Reports (AUG 2008) [Deviation])

52.209-7 – Information Regarding Responsibility Matters (Feb 2012)

(a) Definitions. As used in this provision—

“Administrative proceeding” means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceeding at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

“Federal contracts and grants with total value greater than $10,000,000” means—

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

“Principal” means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror [_] has [_] does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked “has” in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in—

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the Central Contractor Registration database via https://www.acquisition.gov (see 52.204-7).

(End of provision)

52.211-9 Desired and Required Time of Delivery (Jun 1997)

(a) The Government desires and requires delivery to be made according to: the "List of Deliverables and Delivery Schedule" attached to this solicitation.

If the offeror is unable to meet the desired delivery schedule, it may, without prejudicing evaluation of its offer, propose a delivery schedule. However, the offeror’s proposed delivery schedule must not extend the delivery period beyond the time for delivery in the Government’s required delivery schedule noted above.

Offers that propose delivery of a quantity under such terms or conditions that delivery will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. If the offeror proposes no other delivery schedule, the desired delivery schedule above will apply.

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day the award is dated. Therefore, the offeror shall compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor’s date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term “working day” excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of Clause)

52.211-17 Delivery of Excess Quantities (Sep 1989) The Contractor is responsible for the delivery of each item quantity within allowable variations, if any. If the Contractor delivers and the Government receives quantities of any item in excess of the quantity called for (after considering any allowable variation in quantity), such excess quantities will be treated as being delivered for the convenience of the Contractor. The Government may retain such excess quantities up to $250 in value without compensating the Contractor therefore, and the Contractor waives all right, title, or interests therein. Quantities in excess of $250 will, at the option of the Government, either be returned at the Contractor’s expense or retained and paid for by the Government at the contract unit price.

(End of Clause)

52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items. (NOV 2012)

As prescribed in 12.301(b)(4), insert the following clause:

Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items (Nov 2012)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

(1) 52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).

___Alternate I (Aug 2007) of 52.222-50 (22 U.S.C. 7104(g)).

(2) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(3) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Pub. L. 108-77, 108-78).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

[Contracting Officer check as appropriate.]

_X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 253g and 10 U.S.C. 2402).

__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (June 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

_X_ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Aug 2012) (Pub. L. 109-282) (31 U.S.C. 6101 note).

__ (5) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (Jul 2010) (Pub. L. 111-5).

_X_ (6) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Dec 2010) (31 U.S.C. 6101 note).

_X_ (7) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Feb 2012) (41 U.S.C. 2313).

__ (8) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (May 2012) (section 738 of Division C of Pub. L. 112-74, section 740 of Division C of Pub. L. 111-117, section 743 of Division D of Pub. L. 111-8, and section 745 of Division D of Pub. L. 110-161).

__ (9) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).

__ (10) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Jan 2011) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (11) [Reserved]

__ (12)(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2011) (15 U.S.C. 644).

__ (ii) Alternate I (Nov 2011).

__ (iii) Alternate II (Nov 2011).

__ (13)(i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).

__ (ii) Alternate I (Oct 1995) of 52.219-7.

__ (iii) Alternate II (Mar 2004) of 52.219-7.

_X_ (14) 52.219-8, Utilization of Small Business Concerns (Jan 2011) (15 U.S.C. 637(d)(2) and (3)).

_X_ (15)(i) 52.219-9, Small Business Subcontracting Plan (Jan 2011) (15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Oct 2001) of 52.219-9.

__ (iii) Alternate II (Oct 2001) of 52.219-9.

__ (iv) Alternate III (Jul 2010) of 52.219-9.

__ (16) 52.219-13, Notice of Set-Aside of Orders (Nov 2011)(15 U.S.C. 644(r)).

__ (17) 52.219-14, Limitations on Subcontracting (Nov 2011) (15 U.S.C. 637(a)(14)).

X_ (18) 52.219-16, Liquidated Damages—Subcon-tracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).

_X_ (19)(i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (Oct 2008) (10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).

__ (ii) Alternate I (June 2003) of 52.219-23.

__ (20) 52.219-25, Small Disadvantaged Business Participation Program—Disadvantaged Status and Reporting (Dec 2010) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).

__ (21) 52.219-26, Small Disadvantaged Business Participation Program— Incentive Subcontracting (Oct 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).

__ (22) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C. 657 f).

X_ (23) 52.219-28, Post Award Small Business Program Rerepresentation (Apr 2012) (15 U.S.C. 632(a)(2)).

__ (24) 52.219-29, Notice of Set-Aside for Economically Disadvantaged Women-Owned Small Business (EDWOSB) Concerns (Apr 2012) (15 U.S.C. 637(m)).

__ (25) 52.219-30, Notice of Set-Aside for Women-Owned Small Business (WOSB) Concerns Eligible Under the WOSB Program (Apr 2012) (15 U.S.C. 637(m)).

_X_ (26) 52.222-3, Convict Labor (June 2003) (E.O. 11755).

_X_ (27) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Mar 2012) (E.O. 13126).

_X_ (28) 52.222-21, Prohibition of Segregated Facilities (Feb 1999).

_X_ (29) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).

X__ (30) 52.222-35, Equal Opportunity for Veterans (Sep 2010)(38 U.S.C. 4212).

_X_ (31) 52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).

_X_ (32) 52.222-37, Employment Reports on Veterans (Sep 2010) (38 U.S.C. 4212).

_X_ (33) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

__ (34) 52.222-54, Employment Eligibility Verification (Jul 2012). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)

__ (35)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (36) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).

__ (37)(i) 52.223-16, IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products (Dec 2007) (E.O. 13423).

__ (ii) Alternate I (Dec 2007) of 52.223-16.

_X_ (38) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (Aug 2011) (E.O. 13513).

__ (39) 52.225-1, Buy American Act—Supplies (Feb 2009) (41 U.S.C. 10a-10d).

__ (40)(i) 52.225-3, Buy American Act—Free Trade Agreements—Israeli Trade Act (Nov 2012) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43).

__ (ii) Alternate I (Mar 2012) of 52.225-3.

__ (iii) Alternate II (Mar 2012) of 52.225-3.

__ (iv) Alternate III (Nov 2012) of 52.225-3.

__ (41) 52.225-5, Trade Agreements (Nov 2012) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

__ (42) 52.225-13, Restrictions on Certain Foreign Purchases (June 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (43) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).

__ (44) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).

_X_ (45) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).

__ (46) 52.232-30, Installment Payments for Commercial Items (Oct 1995) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).

_X_ (47) 52.232-33, Payment by Electronic Funds Transfer—Central Contractor Registration (Oct 2003) (31 U.S.C. 3332).

__ (48) 52.232-34, Payment by Electronic Funds Transfer—Other than Central Contractor Registration (May 1999) (31 U.S.C. 3332).

__ (49) 52.232-36, Payment by Third Party (Feb 2010) (31 U.S.C. 3332).

__ (50) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).

__ (51)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631).

__ (ii) Alternate I (Apr 2003) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

[Contracting Officer check as appropriate.]

X__ (1) 52.222-41, Service Contract Act of 1965 (Nov 2007) (41 U.S.C. 351, et seq.).

_X_ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 1989) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).

_X_ (3) 52.222-43, Fair Labor Standards Act and Service Contract Act—Price Adjustment (Multiple Year and Option Contracts) (Sep 2009) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Act—Price Adjustment (Sep 2009) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).

__ (5) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Requirements (Nov 2007) (41 351, et seq.).

__ (6) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services—Requirements (Feb 2009) (41 U.S.C. 351, et seq.).

__ (7) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Mar 2009) (Pub. L. 110-247).

__ (8) 52.237-11, Accepting and Dispensing of $1 Coin (Sept 2008) (31 U.S.C. 5112(p)(1)).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records—Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e)(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c), and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).

(ii) 52.219-8, Utilization of Small Business Concerns (Dec 2010) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $650,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(iii) [Reserved]

(iv) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).

(v) 52.222-35, Equal Opportunity for Veterans (Sep 2010) (38 U.S.C. 4212).

(vi) 52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).

(vii) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(viii) 52.222-41, Service Contract Act of 1965 (Nov 2007) (41 U.S.C. 351, et seq.).

(ix) 52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).

___Alternate I (Aug 2007) of 52.222-50 (22 U.S.C. 7104(g)).

(x) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (Nov 2007) (41 U.S.C. 351, et seq.).

(xi) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services-Requirements (Feb 2009) (41 U.S.C. 351, et seq.).

(xii) 52.222-54, Employment Eligibility Verification (Jul 2012).

(xiii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Mar 2009) (Pub. L. 110-247). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(xiv) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.

(End of clause)

Alternate I (Feb 2000). As prescribed in 12.301(b)(4)(i), delete paragraph (d) from the basic clause, redesignate paragraph (e) as paragraph (d), and revise the reference to “paragraphs (a), (b), (c), or (d) of this clause” in the redesignated paragraph (d) to read “paragraphs (a), (b), and (c) of this clause.”

Alternate II (Jul 2012). As prescribed in 12.301(b)(4)(ii), substitute the following paragraphs (d)(1) and (e)(1) for paragraphs (d)(1) and (e)(1) of the basic clause as follows:

(d)(1) The Comptroller General of the United States, an appropriate Inspector General appointed under section 3 or 8G of the Inspector General Act of 1978 (5 U.S.C. App.), or an authorized representative of either of the foregoing officials shall have access to and right to—

(i) Examine any of the Contractor’s or any subcontractors’ records that pertain to, and involve transactions relating to, this contract; and

(ii) Interview any officer or employee regarding such transactions.

(e)(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), and (c), of this clause, the Contractor is not required to flow down any FAR clause in a subcontract for commercial items, other than—

(i) Paragraph (d) of this clause. This paragraph flows down to all subcontracts, except the authority of the Inspector General under paragraph (d)(1)(ii) does not flow down; and

(ii) Those clauses listed in this paragraph (e)(1). Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—

(A) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).

(B) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (June 2010) (Section 1553 of Pub. L. 111-5).

(C) 52.219-8, Utilization of Small Business Concerns (Dec 2010) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $650,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(D) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).

(E) 52.222-35, Equal Opportunity for Veterans (Sep 2010) (38 U.S.C. 4212).

(F) 52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).

(G) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(H) 52.222-41, Service Contract Act of 1965 (Nov 2007) (41 U.S.C. 351, et seq.).

(I) 52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).

(J) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Requirements (Nov 2007) (41 U.S.C. 351, et seq.).

(K) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services—Requirements (Feb 2009) (41 U.S.C. 351, et seq.).

(L) 52.222-54, Employment Eligibility Verification (Jul 2012).

(M) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (Mar 2009) (Pub. L. 110-247). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(N) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(End of Clause) FAR 52.216-18 Ordering (Oct 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from date of contract award through 60 months thereafter.

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

(End of Clause)

FAR 52.216-19 Order Limitations (Oct 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract, in an amount of less than $300.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor --

(1) Any order for a single item in excess of the estimated quantity provided on the schedule;

(2) Any order for a combination of items in excess of the estimated quantities provided on the schedule; or

(3) A series of orders from the same ordering office within 10 days that together call for quantities exceeding the limitation in subparagraph (b)(1) or (2) of this section.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.

(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within five days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

(End of Clause)

FAR 52.216-21 Requirements (Apr 1984) ALTERNATE I

(a) This is a requirements contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government’s requirements do not result in orders in the quantities described as “estimated’’ or “maximum” in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(c) The estimated quantities are not the total requirements of the Government activity specified in the Schedule, but are estimates of requirements in excess of the quantities that the activity may itself furnish within its own capabilities. Except as this contract otherwise provides, the Government shall order from the Contractor all of that activity’s requirements for supplies and services specified in the Schedule that exceed the quantities that the activity may furnish within its own capabilities.

(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.

(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing for the accelerated delivery, the Government may acquire the urgently required goods or services from another source.

(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any…