SPECIFICATION FOR CGC POMPANO R0.doc
DOC document 3 MB Posted
- Attached to
- DRYDOCK FOR USCGC POMPANO Federal contract opportunity
- Solicitation number
- HSCG80-11-Q-P45010
About this file
SPECIFICATION FOR CGC POMPANO
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPECIFICATION FOR CGC POMPANO R0.doc | DOC document | |
| SF30 Amendment 01 SOL FOR POMPANO.pdf | ||
| BLANK SCHEDULE FOR POMPANO REV1.xls | XLS spreadsheet | |
| SCHEDULE OF SUPPLIES_SERVICES FOR POMPANO.xls | XLS spreadsheet | |
| SOLICITATION FOR POMPANO1.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC POMPANO (WPB-87339)
87 FOOT PATROL BOAT
SPECIFICATION FOR DRYDOCK REPAIRS
Developed By:
MKCM Eric J Heimburger
PLM, Patrol Boat Product Line Surface Forces Logistics Center 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
TABLE OF CONTENTS
Work Item Title Page ivList of Sketches
Revisions Record v List of Applicable References vi List of Government-furnished Property vii List of Critical Inspection Items ix Specification Feedback x Principal Characteristics xi General Requirements Perform Ultrasonic Thickness Measurements (D) Perform Ultrasonic Thickness Measurements (O) Perform Hull and Structural Plating Repairs in Forepeak, Engine room and Lazarette – Eroded Welds (Steel) (O) Clean and Inspect Dirty Oil Tank (D) Clean and Inspect Oily Water Tank (D) Clean and Inspect Fuel Service Tanks (D) Clean and Inspect Grey Water Tank (D) Clean and Inspect Sewage Tank (D) Clean Grey Water Piping System (D) Clean Sewage Piping System (D) Inspect RHIB Notch Skid Pads (D) Renew RHIB Notch Skid Pad Studs (O) Realign Main Engine/Reduction Gear (O) Remove, Inspect, and Reinstall Propeller Shafts (D) Repair Shaft (O) Straighten Shaft (O) Renew Intermediate Water-Lubricated Shaft Bearing (O) Renew Aft Water-Lubricated Shaft Bearing (O) Renew Intermediate Bearing Carrier (O) Renew Aft Bearing Carrier (O) Remove, Inspect, and Reinstall Propellers (D) Perform Minor Repair and Recondition of Propeller (O) Renew Depth Indicating Transducer (D) Renew Sea Valves and Inspect Associated Piping and Strainers (D) Remove, Inspect, and Reinstall Rudder Assemblies (D) Remove, Inspect and Reinstall Stern Launch Door, and Inspect Door Pivot Pins, Bushings, and Washers (D) Preserve Underwater Body – “Partial” (O) Preserve Underwater Body – “100%” (O) Preserve Stern Tubes (O) Modify and Renew Cathodic Protection System (D) Renew Transducer Fairing (O) Routine Drydocking (D) Provide Temporary Logistics (D) Modify and Preserve the Forepeak (EC 087-A-033) Preserve Mast (O)
List of Sketches
Work
Item Sketch Number Page This section is not applicable to this package.
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
| DATE |
| REV# |
| WORK ITEM# |
| CHANGES MADE |
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address: http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp. Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
MIL-A-18001, Aug 2008, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-PRF-16173, Jan 1993, Corrosion Preventive Compound, Solvent Cutback, Cold Application
MIL-PRF-24139, Mar 1987, Grease, Multipurpose, Water Resistant MIL-PRF-24647, Feb 2005, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)
MIL-STD-1687, Sep 1994, Thermal Spray Processes For Naval Ship Machinery Application
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-Petrolatum
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8634_STD, 2004 Edition, Drydocking
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8635_STD, 2004 Edition, Provide Temporary Logistics
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 1001_STD, 2004 Edition, Temporary Hull Accesses
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Code of Federal Regulations (CFR) Title 29, Part 1915, Subpart E, Jul 2004, Scaffolds, Ladders and Other Working Surfaces
DRAWINGS
Coast Guard Drawing 87 WPB 085-003, Rev C, Docking Plan
Coast Guard Drawing 87 WPB 085-010, Rev C, Docking Plan Coast Guard Drawing 87 WPB 085-011, Rev B, Lifting Slings Coast Guard Drawing 87 WPB 085-012, Rev-, Lifting Cradle Coast Guard Drawing 87 WPB 111-001, Rev D, Shell Expansion Coast Guard Drawing 87 WPB 113-001, Rev D, Platform Plating & Framing Coast Guard Drawing 87 WPB 131-002, Rev-, Forepeak Void New Watertight Flat Coast Guard Drawing 87 WPB 161-002, Rev-, Stern Tube Details Anode Access Ports Coast Guard Drawing 87 WPB 163-001, Rev F, Sea Chest Details Coast Guard Drawing 87 WPB 165-001, Rev D, Transducer Details
Coast Guard Drawing 87 WPB 182-001, Rev A, Main Engine and Generator Foundations
Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details
Coast Guard Drawing 87 WPB 245-002, Rev-, Propeller Details
Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details
Coast Guard Drawing 87 WPB 252-001, Rev D, Pilothouse Console Arrangement
Coast Guard Drawing 87 WPB 252-002, Rev K, Alarm & Monitoring System
Coast Guard Drawing 87 WPB 256-001, Rev T, Sea Water Cooling Piping Coast Guard Drawing 87 WPB 302-001, Rev P, Misc. Controls Wiring Diagram, sheets 1, 2, 3, 36, 39, & 42
Coast Guard Drawing 87 WPB 304-001, Rev C, Wireway Arrangement
Coast Guard Drawing 87 WPB 526-001, Rev H, Scuppers & Deck Drains Piping Coast Guard Drawing 87 WPB 529-001, Rev E, Bilge Piping
Coast Guard Drawing 87 WPB 561-001, Rev G, Steering System Details
Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details
Coast Guard Drawing 87 WPB 581-002, Rev-, Anchor Handling & Hawse Pipe Details
Coast Guard Drawing 87 WPB 583-001, Rev K, RHIB Deployment Structure
Coast Guard Drawing 87 WPB 583-001, Rev N, RIB Deployment Structure
Coast Guard Drawing 87 WPB 593-001, Rev K, Sewage Piping Coast Guard Drawing 87 WPB 601-001, Rev F, Outboard Profile, General Arrangements Coast Guard Drawing 87 WPB 635-001, Rev C, Linings and Insulation Plan & Details
Coast Guard Drawing FL 6713-201, Rev B, Transducer adapter assembly
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EL Coast Guard Technical Publication (TP) 4593C, Feb 2002, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255
INDUSTRY STANDARDS
American Bureau of Shipping (ABS), 2, Rules for Survey After Construction, 2008, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2004, Brush-Off Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting The Society for Protective Coatings (SSPC)/NACE International (NACE) 2004, Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning International Organization for Standardization (ISO), 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of diameter between 0.80 and 2.50 m, Inclusive
ASTM International (ASTM), D3951, Re-approved 2004, Standard Practice for Commercial Packaging
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
| WORK ITEM |
| MTIs |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/Unit)
| 14 |
| N |
| **Propeller shaft |
| NSN: 2010-01-458-9175 |
| 2 ea. |
| 9,566.14 |
| N |
| Type FSE Face (split) |
| PN: H75440-01-2-2 |
NSN: 5330-01-521-3559
| 2 ea. |
| 1,995.07 |
| N |
| Type FSE Seal (split) |
| PN: H75440-01-1-1 |
NSN: 2040-01-521-2654
| 2 ea. |
| 4,070.35 |
| N |
| Type FSE Seal Cup (split) |
| PN: H75440-01-1-3 |
NSN: 3120-01-521-2390
| 2 ea. |
| 188.24 |
| N |
| Type FSE O-Cord |
| PN: H75440-01-1-4 |
NSN: 3120-01-521-2268
| 2 ea. |
| 252.84 |
| N |
| Type FSE Emergency Seal |
| PN: H75440-01-3-6 |
NSN: 5330-01-521-4855
| 2 ea. |
| 260.92 |
| N |
| **Shaft Seal Bellow |
| PN: H75440-01-2-1 |
NSN: 5340-01-521-3573
| 2 ea. |
| 270.45 |
| N |
| *Compression Tool Assembly |
| N/A |
| 1 ea. |
| 200.00 |
| N |
| *Alignment Kit |
| N/A |
| 1 set |
| 3,000.00 |
| 17 |
| N |
| **Thordon bearing, Grade Orange |
(5.5" OD x 4" ID x 7.87" (200mm) LG)
PN: F54615-02-8-1
NSN: 3120-21-914-2012
| 2 ea. |
| 325.47 |
| 18 |
| N |
| **Thordon bearing, Grade Orange |
(5.5" OD x 4" ID x 11.41" (290mm) LG)
PN: F54615-02-8-0
NSN: 3120-21-914-2011
| 2 ea. |
| 399.50 |
| 21 |
| Y |
| **Starboard Propeller (RH) |
| PN: RH706-3350.00 |
NSN: 2010-01-457-0573
| 1 ea. |
| 12,498.00 |
| Y |
| **Port Propeller (LH) |
| PN: LH706-3350.00 |
NSN: 2010-01-459-0421
| 1 ea. |
| 12,498.00 |
| N |
| *Propeller Nut Wrench |
| N/A |
| 1 ea |
| 200.00 |
| N |
| Propeller Nut |
| NSN: 2010-01-458-9217 |
| 2 ea. |
| 281.00 |
| N |
| Propeller Nut, Locking |
| NSN: 5310-01-458-9125 |
| 2 ea. |
| 252.94 |
| N |
| Anode, Propeller Nut |
| NSN: 5342-01-481-8403 |
| 2 ea. |
| 272.00 |
| 23 |
| N |
| ***Airmar Depth Sounder Transducer |
| PN: E660151/31-811-5-01 |
| 1 ea. |
| 149.45 |
| 25 |
| Y |
| **Rudder Assembly, port |
| NSN: 2040-01-461-1944 |
| 1 ea. |
| 2,000.00 |
| Y |
| **Rudder Assembly, starboard |
| NSN: 2040-01-461-1943 |
| 1 ea. |
| 2,000.00 |
| N |
| Upper Roller Bearing |
| NSN: 3110-01-512-5534 |
| 2 ea. |
| 244.62 |
| N |
| Wartsila EL Seals Kit |
| NSN: 2040-01-565-9776 |
| 2 ea. |
| 6300.00 |
| N |
| Lower Thordon bearing |
| NSN: 3120-20-000-7677 |
| 1 ea. |
| 332.72 |
| 31 |
| N |
| *Transducer cover plate |
| N/A |
| 1 ea. |
| 149.50 |
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
Work Item Title Perform Ultrasonic Thickness Measurements (D) Perform Ultrasonic Thickness Measurements (O) Inspect RHIB Notch Skid Pads (D) Remove, Inspect, and Reinstall Propeller Shafts (D) Renew Sea Valves and Inspect Associated Piping and Strainers (D) Remove, Inspect, and Reinstall Rudder Assemblies (D) Preserve Stern Tubes (O) Modify and Preserve the Forepeak (EC 087-A-033) Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities. All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
PC_87_WPB
(21 Mar 2005) Principal Characteristics
87' WPB Coastal Patrol Boat
| Length Overall |
| 87' 0" |
| Depth (main deck at frame 13 side to baseline) |
| 10' 11" |
| Maximum Beam |
| 19.4' |
| Height of Highest Projection (above DWL) |
| 50.2' |
| Frame Spacing |
| Various |
| Full Load Draft |
| 5' 9" |
| Full Load Displacement |
| 93.5 long tons |
| Shore Tie Voltage Requirements |
| 450v |
PROPELLERS / SHAFT
| Number of Propellers |
| 2 |
| Number of Blades per Propeller |
| 5 |
| Diameter of Propeller |
| 1040 mm |
| Pitch |
| 1230 mm fixed |
| Revolutions per Minute (RPM) |
| 828 |
| Shaft Diameter |
| 4" |
00000_DLA_FLT (23 Oct 2008)
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
WARNING!
Prior to performing welding, Ship’s Force will take precautions to isolate all electronic equipment installed on the cutter from welding current. Do not perform welding until proper isolation has been verified.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.
3.4 Term substitution - COTR for COR. The Contractor shall be aware that the term "COR" (Contracting Officer's Representative) has been discontinued in favor of "COTR" (Contracting Officer's Technical Representative); consequently, whenever "COR" is encountered in this specification package, including referenced standard specifications and other referenced documents, it shall refer to "COTR", explicitly.
3.5 Small boat storage. When a small boat (Motor Surf Boat (MSB)/Motor Cargo Boat (MCB)/Rigid Hull Inflatable (RHI) boat) is removed as interference to Contractor-work, the Contractor shall provide a suitable pier side storage cradle, for safely storing said boat.
3.5.1 Cradle design. Ensure that the temporary cradle meets the following criteria:
1. Structure is templated from the geometry and arrangement of the contact support areas of the existing cradle onboard the vessel, to provide same or more support area as that which is provided by the existing cradle.
2. Arrangement will allow ship's force to perform maintenance on the small boat, without modification of the cradle.
3. Structure is manufactured using the most economical methods and materials available, and is capable of supporting the full weight of the small boat under normal conditions experienced during routine maintenance.
4. Contact surfaces are no harder or rougher than the contact surfaces for existing cradle onboard the vessel.
3.5.2 Boat accessibility. Ensure the storage is located in the vicinity of the vessel, and is unrestricted, to allow for ship's force to complete maintenance during normal working hours for the entire performance period.
3.5.3 Boat protection. Provide full protection that can be safely and completely secured when the small boat is left unattended (e.g. watertight cover, storage in a warehouse or shop, etc.), in addition to isolating the boat from the elements.
3.5.4 Boat transportation. Transport each small boat to its storage area within one week of docking the vessel and back to the vessel prior to the end of the performance period.
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address:
http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted during preservation of "critical-coated surfaces", are provided at the end of this item.
QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST
CHECKPOINT 1 - COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10?).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 -2.5 for surfaces to be coated w/single coat of inorganic zinc).
Measure soluble salt conductivity (5 measurements per 1000 sqft) - maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 - STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer's instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 - TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer's instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 - FINAL INSPECTION
Verify final system dry film thickness.
Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @ 77 degrees F.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
CHECKPOINT 10 - RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Signature of Inspector:______________________________________________________Date:____________
QA-2. QUALITY ASSURANCE INSPECTION FORM
ENVIRONMENTAL READINGS
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
| DATE |
| TIME |
| ENTER ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc?) |
| LOCATION |
| DEW POINT |
| SURFACE TEMP. |
| % REL. HUMIDITY |
| SIGNATURE OF INSPECTOR |
.Signature of Inspector:__________________________________________________Date:____________
QA-3 QUALITY ASSURANCE INSPECTION FORM
SURFACE PROFILE LOG
Vessel Name And Hull Number:__________________________________________________ Work Item Title:_______________________________________________________________ Location Of Work (Including Frame Numbers):_____________________________________ Area (Square Feet):_____________ Surface Preparation Method:_____________________________________________________ Abrasive Manufacturer And Size:_________________________________________________ Degreasing Method Used:________________________________________________________ Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________ Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________ Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.
Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
AVERAGE MILS
(IAW ASTM D4417, METHOD C)
Place Surface Profile Replica Tape Here
Reading:__________ mils
· Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Date and Time:__________________________________________________ Location of Surface Profile Measurements:___________________________________________________________ Signature of Inspector:____________________________________________________________________________
QA-4. QUALITY ASSURANCE INSPECTION FORM
SURFACE SOLUBLE SALT CONDUCTIVITY LOG
Vessel Name and Hull Number:__________________________________________________ Work Item Title:_______________________________________________________________ Location of Work (including frame numbers):_______________________________________ Area (square feet):____________
| DATE |
| TEST LOCATIONS |
| CONDUCTIVITY |
(microsiemens/cm)
Date and Time:_________________________________________ Signature of Inspector:___________________________________
QA-5. QUALITY ASSURANCE DATA FORM
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
(Use one sheet for each sequence) Vessel Name and Hull Number:__________________________________________________ Work Item Title:______________________________________________________________ Coating Manufacturer:_________________________________________________________ Product Name:________________________________________________________________ Batch Number:________________________________________________________________ Induction Time:_______________________________________________________________ Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat?):__________________
DFT
MEASUREMENT NUMBER
| LOCATION OF READINGS |
| MEASURED DFT |
Application Method (Airless, Conventional Spray, Rolled):____________________ Average DFT: __________________________________________________________ Date and Time: _________________________________________________________ Signature of Inspector: ___________________________________ 11000_087(6 November 2009)
WORK ITEM 1: Perform Ultrasonic Thickness Measurements (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.
1.1.1 Areas that have been pre-determined to require testing.
None
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method Coast Guard Drawing 87 WPB 113-001, Rev D, Platform Plating & Framing
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph:
· 3.2 (Thickness measurement particulars).
3.1.2 Interferences. The Contractor shall be aware that interferences in way of work may include, but are not limited to the following:
· Grating and hardware.
· Wiring.
· Wiring hangers.
· False bulkheads.
· Piping.
· Pipe hangers.
· Valves.
· Framing.
· Deck plates.
· Water manifold.
· Hydraulic unit.
· Hoses.
· Hydraulic fluid.
3.2 Thickness measurement particulars. Using Coast Guard drawing 87 WPB 113-001 as guidance, the Contractor shall perform 250 ultrasonic thickness measurements of hull and hull frame surfaces, in various locations designated by the Coast Guard Inspector (see paragraph 1.1.1 above for possible pre-determined locations). Submit a CIR. Ensure that the ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797, and the report results shall additionally include the following, for each test point:
· Location.
· Original metal thickness.
· Measured metal thickness.
· Percent deterioration (calculation is based on the original metal thickness).
3.3 Apparatus Standardization. The Contractor shall perform ultrasonic equipment standardization in accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).
3.4 Insulation and sheathing renewal. The Contractor shall renew all disturbed insulation and sheathing.
4. NOTES
This section is not applicable to this work item.
11000_087(6 November 2009)
WORK ITEM 2: Perform Ultrasonic Thickness Measurements (O)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform up to 25 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method Coast Guard Drawing 87 WPB 113-001, Rev D, Platform Plating & Framing
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph:
· 3.2 (Thickness measurement particulars).
3.1.2 Interferences. The Contractor shall be aware that interferences in way of work may include, but are not limited to the following:
· Grating and hardware.
· Wiring.
· Wiring hangers.
· False bulkheads.
· Piping.
· Pipe hangers.
· Valves.
· Framing.
· Deck plates.
· Water manifold.
· Hydraulic unit.
· Hoses.
· Hydraulic fluid.
3.2 Thickness measurement particulars. After a Change Request has been release by the KO, using Coast Guard drawing 87 WPB 113-001 as guidance, the Contractor shall perform one or more, as specified in the Change Request, lots of 25 ultrasonic thickness measurements of hull and hull frame surfaces, in various locations designated by the Coast Guard Inspector. Submit a CIR. Ensure that the ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797, and the report results shall additionally include the following, for each test point:
· Location.
· Original metal thickness.
· Measured metal thickness.
· Percent deterioration (calculation is based on the original metal thickness).
3.3 Apparatus Standardization. The Contractor shall perform ultrasonic equipment standardization in accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).
3.4 Insulation and sheathing renewal. The Contractor shall renew all disturbed insulation and sheathing.
4. NOTES
This section is not applicable to this work item.
1100_TEF_ERODED_STL_WELD _87 (30 Oct 2008) 87355_TEF (30 Oct 2009)
WORK ITEM 3: Perform Hull and Structural Plating Repairs in Forepeak, Engine room and Lazarette – Eroded Welds (Steel) (O)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew up to 8 linear feet of eroded steel welds in various compartments.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes MERGEFIELD "A1"
3. REQUIREMENTS
3.1 General.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Piping.
· Wiring.
· Frames.
· Deck plates.
· Grating.
· HPU Unit.
· Strainers.
· Bilge floats.
· Valves.
· Water manifold.
· Work bench.
· Pump foundations.
· Lagging.
3.1.2 Renewal particulars. The Contractor shall renew up to 8 linear feet of eroded steel welds, as designated by the Coast Guard Inspector. The Contractor shall perform all welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD.
3.2 Electronic equipment protection. The Contractor shall safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference. Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs)) of Std Spec 0000_STD.
NOTICE!
Surfaces being preserved are considered "critical-coated surfaces".
3.4 Insulation and sheathing renewal. The Contractor shall renew all disturbed sheathing and insulation. Paint newly installed insulation systems, as applicable, in accordance with COMDTINST M10360.3, using the system specified for “Insulation Surfaces, Fiberglass Sheet/Closed Cell PVC Foam” in Appendix B (Cutter and Boat Interior Paint Systems).
4. NOTES
4.1 Electronic equipment protection.
MERGEFIELD "N1C" The Coast Guard Inspector will accomplish the following prior to welding:
· Secure wheelhouse power supply to the ODR, MCS, and RCS systems.
· Secure engine room power supply to the GCU and CCS box.
· Disconnect all cannon plugs to the main engine governors (ECS-UNI).
· Remove all PIMS on MTU control systems.
· Disconnect all power to the Bridge electronics.
· Secure power to the battery chargers.
· Disconnect engine room batteries.
12310_DLA_FLT (10 Sept 2008)
87 WPB (27 May 2008) WORK ITEM 4: Clean and Inspect Dirty Oil Tank (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank:
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Dirty Oil |
| Port Centerline |
| 85 |
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs (oily water tank) to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Oily water tank - Tank Level Indicator (TLI) and/or float switch condition.
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
· Strainers – verify that strainers are not touching the hull or tank bhds.
3.5 Tank closing. After satisfactory inspection by the Coast Guard Inspector, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
3.6 Operational test – final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI(s) to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12310_DLA_FLT (10 Sept 2008)
87 WPB (27 May 2008) WORK ITEM 5: Clean and Inspect Oily Water Tank (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank:
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Oily Water (coated) |
| Stbd Centerline |
| 85 |
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs (oily water tank) to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Oily water tank - Tank Level Indicator (TLI) and/or float switch condition.
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
· Strainers – verify that strainers are not touching the hull or tank bhds.
3.5 Tank closing. After satisfactory inspection by the Coast Guard Inspector, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
3.6 Operational test – final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI(s) to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12312_DLA_FLT (10 Sept 2008)
87 WPB (27 May 2008) WORK ITEM 6: Clean and Inspect Fuel Service Tanks (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tanks:
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Diesel fuel |
| Stbd, 3-9-1-F |
| 1450 |
| Diesel fuel |
| Port, 3-9-2-F |
| 1450 |
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
NOTICE!
Vessel may come in with less tank fluid contents than specified above.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the tank level indicators (TLIs). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Tank level indicators (TLIs).
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel, 5/16” or 3/8” screws).
· Strainers – verify that strainers are not touching the hull or tank bhds.
3.5 Tank closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tanks. After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
3.6 Operational test - final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12318_DLA_FLT (10 Sept 2008)
87 WPB (05 Sept 2008) WORK ITEM 7: Clean and Inspect Grey Water Tank (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the below designated tank:
| TYPE OF TANK |
| LOCATION |
| CAPACITY (gallons) |
| Grey Water (stainless steel, uncoated) |
| Below Hold Deck between Frames 8 and 9, 3-7-1-W |
| 55 |
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Stateroom berthing locker.
· Piping.
· Tank level indicator (TLI).
3.2 Cleaning requirements. The Contractor shall do the following for the designated tank listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations.
3.2.3 Cleaning requirements. Remove manhole cover(s). Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the TLI. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Tank level indicator (TLI).
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.3 Closing. The Contractor shall ensure that the tank remains open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole cover(s) with new gasket material conforming to ASTM D1330.
3.4 Operational test - final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12319_DLA_FLT (10 Sept 2008)
87 WPB (05 Sept 2008) WORK ITEM 8: Clean and Inspect Sewage Tank (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the below designated tank:
| TYPE OF TANK |
| LOCATION |
| CAPACITY (gallons) |
| Sewage (stainless steel, uncoated) |
| Hold Deck between Frames 6 and 8, 3-7-0-W |
| 363 |
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Pump.
· Piping.
3.2 Cleaning requirement. The Contractor shall do the following for the designated tank listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations.
3.2.3 Cleaning requirements. Remove manhole cover(s). Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank level indicator (TLI). Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Tank level indicator (TLI).
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.3 Closing. The Contractor shall ensure that the tank remains open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole cover(s) with new gasket material conforming to ASTM D1330.
3.4 Operational test - final. After all authorized work is complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
59320_DLA_FLT (03 Sep 2008) 87 WPB (08 Jan 2009) WORK ITEM 9: Clean Grey Water Piping System (D)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the grey water piping system.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 87 WPB 526-001, Rev H, Scuppers & Deck Drains Piping DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to, the following:
· Grey water pumps.
· Valves.
· Pump.
· Check valves.
· Strainers.
· Sink traps.
· Grease trap.
· Sanitizer.
· Wiring.
· Flanges.
· Piping.
· Gauges.
· Fittings.
3.1.3 Cleaning particulars. The Contractor shall clean approximately 190 linear feet of grey water system piping (including condensate lines), shown on Coast Guard Drawing 87 WPB 526-001.
3.2 Contamination prevention. The Contractor shall take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.
3.3 Cleaning plan. The Contractor shall establish a plan for cleaning the designated piping system, listing the step by step procedures necessary to ensure that all foreign debris is removed from the piping system.
NOTICE!
Although the Coast Guard prefers pressurized water as the cleaning fluid, the Contractor may propose chemical cleaning as an alternative, providing that the proposed chemical cleaning agent conforms to DOD-STD-2187 (where applicable), is environmentally safe, and pre-approved by the COTR.