Text version

DACA is Days After Base or Option Award

CLIN No. CLIN Name CDRL Name SOW Section CDRL's Draft Due (Calendar Days)

Government Comment Period (Calendar Days)

Contractor Comment Period (Calendar Days)

0001AA

Cost As an Independent Variable (CAIV) Assessment

3.2.1.1

3.3 A001, A002 60 DACA 15 15

A003 45 DACA ‐ Alt. A 90 DACA ‐ Alt. B

A005, A008, A010, A011, A013, A016, A017 All others 90 DACA

Option 1 ‐ Additional Industry Heavy Polar Icebreaker Baseline Design Study Support Information Study Support Information

3.2.1.2.2 3.3

A001, A006, A007, A009, A012, A014, A015, A018 30 DACA 15 15

1002 Option 2 ‐ Cost and Schedule for Baseline

Cost and Schedule Estimates for Design and Construction for Baseline Design Report

3.2.1.3

3.3 A001, A019 30 DACA 15 15

1003AA Hull Form and Structures Study Plan 3.2.1.4.3 A022 30 DACA 15 15

1003AB

Hull Form and Structures Report and Study Support Information

3.2.1.4.3

3.3 A001, A039, A040, A041, A042, A043, A044 90 DACA 15 15

1004AA Propulsion Plant / Power Train Study Plan 3.2.1.4.1 A020 30 DACA 15 15

1004AB

Propulsion Plant / Power Train Report and Study Support Information

3.2.1.4.1

3.3 A001, A023, A024, A025, A026, A027, A028 90 DACA 15 15

1005AA

Electric Plant Configuration / Topology Study Plan 3.2.1.4.2 A021 30 DACA 15 15

1005AB

Electric Plant Configuration / Topology Study Report and Study Support Information

3.2.1.4.2 3.3

A001, A029, A030, A031, A032, A033, A034, A035, A036, A037, A038 90 DACA 15 15

1006 Option 6 ‐ Areas of Further Study Proposed Areas of Further Study Report 3.2.1.4.4 A045 15 DACA 5 10

1007AA

Industry Heavy Polar Icebreaker Baseline Design (Rev. 1) Description Report. Study Support Information, Cost and Schedule Estimates

3.2.1.5 3.2.1.6 3.3

A001, A003, A005, A006, A007, A008, A009, A010, A011, A012, A013, A014, A015, A016, A017, A018, A019 30 DACA 15 15

1007AB Regulatory Design Impact Study 3.2.1.5 A004 30 DACA 15 15 1008AA Follow On Studies Plan 3.2.1.7 A046 30 DACA 15 15

1008AB Cold Weather and Remote Operations 3.2.1.7.1

3.3 A001, A047 90 DACA 15 15

1008AC Selected Spaces Arrangements 3.2.1.7.2

3.3 A001, A048, A049, A050, A051, A052, A053 90 DACA 15 15

1008AD Icebreaking Enhancements 3.2.1.7.3

3.3 A054 90 DACA 15 15

1009AA Integration Studies Report 3.2.1.8

3.3 A001, A055 90 DACA 15 15

1009AB CAIV Update 3.2.1.9 A002 60 DACA 15 15

Option 10 ‐ Updated Baseline Design with Cost and Schedule

Industry Heavy Polar Icebreaker Baseline Design (Rev. 2) Description Report. Study Support Information, Cost and Schedule Estimates

3.2.1.10 3.2.1.11 3.3

A001, A003, A005, A006, A007, A008, A009, A010, A011, A012, A013, A014, A015, A016, A017, A018, A019 30 DACA 15 15

1011 Option 11 ‐ Advanced Study Advanced Study Report 3.2.1.12 A056 60 DACA 15 15

0001AB

Initial Industry Heavy Polar Icebreaker Baseline Design (Rev. 0) Description

Report and Study Support Information 3.2.1.2.1 15 15

Option 4 ‐ Initial Study Plan and Propulsion Study

Option 9 ‐ Integration Studies and CAIV Update

Option 7 ‐ Updated Baseline Design with Cost and Schedule

Option 5 ‐ Initial Study Plan, Electric Study

Base ‐ CAIV and Initial Baseline Design

Option 8 ‐ Follow On Studies

Option 3 ‐ Initial Study Plan and Hull Form Study

File details come from the government source that posted it. Updated .