Version 2.2 April 2008
Pre-defined Work Patterns
Immigration and Customs Enforcement System Lifecycle Management
Pre-defined Work Patterns
REVISION HISTORY
ICE SLM Pre-defined Work Patterns April 2008
Version Date Summary of Changes
2.0 April 2006 Reorganized sections
Added Scrum work pattern (Section 3.0) Added Legacy System work pattern (Section 6.0) Added External Service work pattern (Section 7.0)
2.1
January 2008 Brought into alignment with SLM 1.1 Global: Milestone Review changed to Technical Review Global: Office of the Information Systems Security Manager (OISSM) changed to Information Assurance Division (IAD) Director Global: System Owner changed to Business Owner Global: Application Integration Services changed to Application
Hosting Services Global: OISS changed to IAD Global: IAD (formerly OISS) Document Artifacts added to : Document
Artifacts Exhibits: 2, 6, 9, 12, 15, 18, 21 Global: AHS changed to SEB Global: Notice of Intent to Release is required for all Releases Global: Procurement Plan changed to Acquisition Plan Global: formatting in tables simplified and made consistent CH 1.0, page 1:
-IT Project Managers changed to Architecture Assurance -Added: to paragraph 2: Depending on the type of project, Architecture Assurance may use one of these pre-defined work patterns for a project:
-Added to paragraph 3: SLM technical reviews, and types of testing
-Aligned document artifacts list in each section to current Project Tailoring Plan and SLM v1.1 Exhibit 2: Additional comments added to Acquisition (formerly, Procurement) Plan and ITCR, Data conversion Plan, Training Plan Development Test Plan, DTAR, VDD, System Administration and Operations Manual, User Guide, Disposition Plan
Exhibit 5: improved graphic for visual differentiation Exhibit 7: Additional comments added to Acquisition Plan, ITCR, Training Plan, Development Test Plan, DTAR, VDD, System Administration and Operations Manual, Deployment Plan, Disposition Plan
Exhibit 8: Scrum Gate Reviews updated Exhibit 9: Scrum Testing Types Rationale updated Exhibit 11: COTS/GOTS Document Artifacts, updated Acquisition
Plan, Data Conversion Plan, Exhibit 12: Revised comments for Planning Review, PADR, FADR Exhibit 13: COTS/GOTS Testing Types updated Interoperability, Performance, Section 508 Exhibit 15: Infrastructure Document Artifacts, updated Acquisition
Plan Exhibit 15: Infrastructure Gate Reviews, updated Planning Review, TRR, RRR
Exhibit 17: Infrastructure Testing Types, updated System Security, Interoperability, Section 508
6.0 Desktop Image, new chapter, new exhibits as follows:
Exhibit 18: Desktop image Project Examples
Exhibit 19: Desktop Image Document Artifacts Exhibit 20: Desktop Image Gate Reviews Exhibit 21: Desktop Image Testing Types Exhibit 23: Legacy System Document Artifacts, updated Acquisition
Plan, NIR Exhibit 24: Legacy System Gate Reviews, revised Planning Review Exhibit 25: Legacy System Testing Types, revised Interoperability, Performance, Section 508 External Services changed to External Service Exhibit 27: External Service Document Artifacts, updated Acquisition
Plan, System Administration and Operations Manual, User Guide Exhibit 28: External Service Gate Reviews, updated Planning Review Exhibit 29: External Service Testing Types, updated Interoperability, Section 508 Exhibit 31: Simple Content-Based Web Site Document Artifacts, updated PMP, IAD artifacts Exhibit 32: Simple Content-Based Web Site Gate Reviews, updated
Planning Review Exhibit 33: Simple Content-Based Web Site Testing Types, updated
System Acceptance, Interoperability, Section 508 Chapter 6: Desktop Image: new chapter added Testing Types exhibit added to all sections Pr-defined Work Patterns version updated to 2.1 Brought in line with SLM 1.2 planning Chapter 10 Mainframe: new chapter added Chapter 11 SharePoint: new chapter added
2.2 April 2008 Chapter 8 External Service removed
7.3, Exhibit 23: added DTAR 9.2, Exhibit 30: added DTAR
CONTENTS i
CONTENTS
1.0 OVERVIEW
2.0 FAST TRACK
2.1 Fast Track Project Profile
2.2 Fast Track Document Artifacts
2.3 Fast Track Gate Reviews
2.4 Fast Track Testing Types
3.0 SCRUM
3.1 Scrum Sprints
3.2 Scrum Considerations
3.3 Scrum Project Profile
3.4 Scrum Document Artifacts
3.5 Scrum Gate Reviews
3.6 Scrum Testing Types
4.0 COTS/GOTS
4.1 COTS/GOTS Project Profile
4.2 COTS/GOTS Document Artifacts
4.3 COTS/GOTS Gate Reviews
4.4 COTS/GOTS Testing Types
5.0 INFRASTRUCTURE
5.1 Infrastructure Project Profile
5.2 Infrastructure Document Artifacts
5.3 Infrastructure Gate Reviews
5.4 Infrastructure Testing Types
6.0 DESKTOP IMAGE
6.1 Desktop Image Project Profile
6.2 Desktop Image Document Artifacts
6.3 Desktop Image Gate Reviews
6.4 Desktop Image Testing Types
7.0 LEGACY SYSTEM (NON- MAINFRAME)
7.1 Legacy System Considerations
7.2 Legacy System Project Profile
7.3 Legacy System Document Artifacts
7.4 Legacy System Gate Reviews
7.5 Legacy System Testing Types
8.0 SIMPLE CONTENT-BASED WEB SITE
8.1 Simple Content-Based Web Site Project Profile
8.2 Simple Content-Based Web Site Document Artifacts
8.3 Simple Content-Based Web Site Gate Reviews
8.4 Simple Content-Based Web Site Testing Types
i i CONTENTS
April 2008 ICE SLM Pre-defined Work Patterns
9.0 MAINFRAME
9.1 Mainframe System Considerations
9.2 Mainframe System Document Artifacts
9.3 Mainframe Gate Reviews
9.4 Mainframe Testing Types
10.0 SHAREPOINT
10.1 SharePoint Document Artifacts
10.2 SharePoint Gate Reviews
10.3 SharePoint Testing Types
APPENDIX A—REFERENCES
CONTENTS ii i
EXHIBITS
Exhibit 1: Fast Track Project Example Exhibit 2: Fast Track Document Artifacts Exhibit 3: Fast Track Gate Reviews Exhibit 4: Fast Track Testing Types Exhibit 5: Scrum Requirements, Architecture, and Design Maturation... 10 Exhibit 6: Scrum Project Example Exhibit 7: Scrum Document Artifacts Exhibit 8: Scrum Gate Reviews Exhibit 9: Scrum Testing Types Exhibit 10: COTS/GOTS Project Example Exhibit 11: COTS/GOTS Document Artifacts Exhibit 12: COTS/GOTS Gate Reviews Exhibit 13: COTS/GOTS Testing Types Exhibit 14: Infrastructure Project Examples Exhibit 15: Infrastructure Document Artifacts Exhibit 16: Infrastructure Gate Reviews Exhibit 17: Infrastructure Testing Types Exhibit 18: Desktop Image Project Examples Exhibit 19: Desktop Image Document Artifacts Exhibit 20: Desktop Image Gate Reviews Exhibit 21: Desktop Image Testing Types Exhibit 22: Legacy System Project Example Exhibit 23: Legacy System Document Artifacts Exhibit 24: Legacy System Gate Reviews Exhibit 25: Legacy System Testing Types Exhibit 26: Simple Content-Based Web Site Project Example Exhibit 27: Simple Content-Based Web Site Document Artifacts Exhibit 28: Simple Content-Based Web Site Gate Reviews Exhibit 29: Simple Content-Based Web Site Testing Types Exhibit 30: Mainframe Document Artifacts Exhibit 31: Mainframe Gate Reviews Exhibit 32: Mainframe Testing Types Exhibit 33: SharePoint Document Artifacts Exhibit 34: SharePoint Gate Reviews iv CONTENTS
Exhibit 35: SharePoint Testing Types
OVERVIEW 1
1.0 OVERVIEW
Immigration and Customs Enforcement (ICE) established the System Lifecycle Management (SLM) Pre-defined Work Patterns to provide starting points for project teams in tailoring the work patterns of specific types of technology projects. By using pre-defined work patterns, Architecture Assurance is able to reuse and adapt a pre-tailored set of activities, document artifacts, and SLM gate reviews to create a customized project work pattern.
Depending on the type of project, Architecture Assurance may use of one of these pre-defined work patterns for a project:
Fast Track—Used for mission-critical projects with short schedules
Scrum—Used for projects that must respond to evolving requirements during the design and development of a system
COTS/GOTS—Used for commercial off-the-shelf/Government off-the-shelf (COTS/GOTS) products that are not customized
Infrastructure—Used for systems that are part of the ICE infrastructure
Desktop Image—Used exclusively for Desktop Images
Legacy System—Used for projects that desire to come into compliance with the SLM process but which have not historically followed the SLM process or its predecessors
Simple Content-Based Web Site—Used for small ICE Web site/applications that have minimal impact to the ICE environment
Mainframe—Used exclusively for mainframe systems
SharePoint—Used exclusively for applications or workflows developed to work with SharePoint
Architecture Assurance will choose a pre-defined work pattern that appropriately addresses the size, scope, risk, and context of the project.
After making a selection, ICE Architecture Assurance meets with the IT Project Manager at a tailoring review to ensure that the appropriate activities, document artifacts, SLM gate reviews, and types of testing are included. (The tailoring process is conducted for every new project and for every major release.)
During tailoring, an activity, document artifact, and/or SLM gate review may be added or removed depending on the specific characteristics or circumstances of the project. In some cases, only certain elements of a prescribed document artifact may be necessary, and they may be included in the contents of another document. (For example, the Requirements Traceability Matrix [RTM] could be included in the System Requirements Document [SRD].)
2 OVERVIEW
When tailoring is complete, the resulting customized project work pattern must be approved by ICE Architecture Assurance. Proposed changes to this project work pattern after approval by ICE Architecture Assurance must be submitted for consideration via the Request for Deviation (RFD) process.
FAST TRACK 3
2.0 FAST TRACK
The Fast Track work pattern supports projects intending to develop and deploy mission-critical functionality in a highly compressed schedule. To use Fast Track, a project must receive approval from Architecture Assurance.
A Fast Track project will typically follow one of the following three methodologies: abbreviated Waterfall, the first increment in an Incremental methodology, or the first iteration of an Iterative methodology.
By leveraging a subset of the standard SLM methodologies, Fast Track focuses on the most critical tasks and deliverables and defers less critical activities to later in the lifecycle. Increased risk is incurred by following the Fast Track process; however, this additional risk is accepted by the project to meet the imposed schedule constraints.
Following deployment, the project will be managed in the same manner as any other ICE initiative. These efforts serve to mitigate and reduce risks introduced by aggressive project deadlines. Because the concept and scope of subsequent enhancements are better understood, the methodology for future development efforts is determined, and the tailoring procedure is executed to determine the appropriate artifacts and reviews for the project.
If not already created, the project shall form a change control board (CCB) that bears the responsibility of monitoring deployment, managing corrective action, and moderating necessary enhancements.
In the event a further iteration of Fast Track is proposed for the project, authorization must again be obtained from Architecture Assurance.
2.1 Fast Track Project Profile
A project profile is the set of characteristics that Architecture Assurance assesses to determine if a project may use the Fast Track work pattern.
These characteristics include size, scope, risk, and context. Exhibit 1 provides an example of a project that could utilize the Fast Track work pattern.
Exhibit 1: Fast Track Project Example
Fast Track Project Example
Project X must be deployed in 90 days with a set of initial capabilities based on Government mandate or critical business need. There are additional enhancements, but the scope and functionality to be included in the enhancements is not yet known. It is critically important to field the initial capabilities as quickly as possible.
4 FAST TRACK
2.2 Fast Track Document Artifacts
Exhibit 2 identifies the SLM document artifacts associated with this work pattern.
Exhibit 2: Fast Track Document Artifacts
Fast Track Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
Project Tailoring Plan
Yes Collaborate with ICE Architecture Assurance to formalize the document deliverables and reviews for the project
Project Management Plan
Yes Include Procurement Strategy if procurement is necessary Update prior to Test Readiness Review (TRR) to include activities normally addressed in the Deployment Plan
Acquisition Plan Yes Ensure Acquisition Plan or Statement of Work (SOW) is on file with Acquisition Management Branch (AMB)
System Requirements
Document
Yes Provide a high-level description of how the system will operate Include the Requirements Traceability Matrix (RTM) Define system inputs/outputs, data requirements (include data elements, such as entities and attributes), operational requirements, and security requirements
Describe system interfaces by providing communications methods, capacity specifications, throughput specifications, security specifications, and integrity specifications
Requirements Traceability Matrix
No The System Requirements Document includes the required information of this document artifact
System Workload Analysis Document
If Necessary
Include if performance testing will be conducted or if any Office of the Chief Information Officer (OCIO) division raises concern with the application architecture or anticipated workload
Describe the system workload, estimate the capacity requirements, and define the impact on the system if system resources are unavailable or if it operates in a degraded mode
Interface Control Agreement
If Necessary
Include if any interfaces with other systems exist
Data Management Plan
No The System Requirements Document includes the required information of this document artifact
Information Technology Change
Request
If Necessary
Submit ITCR and/or Technology Insertions (TI) as appropriate for any new technology not on the ICE TRM or Department TRM respectively
FAST TRACK 5
Fast Track Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
Design Document Yes Diagram and describe system architecture Identify and describe commercial off-the-shelf (COTS) products
(software and hardware), configurations, and customizations Describe custom software design using high-level algorithms, class diagrams, sequence diagrams, or data/process flows Identify complete hardware inventory including physical locations, redundancies, and software dependencies, such as operating systems and drivers
Describe how system components and external systems are interconnected via networks and protocols
Provide physical data models and schema descriptions where data stores are used
Develop screen mockups for systems with substantial numbers of end users
Note: Much of this information may be provided as diagrams without extensive text
SEB Service Level Agreements
Yes Collaborate with production support teams in determining the level of support for the system in production
Data Conversion Plan
No If data require conversion, the Project Management Plan includes the required information of this document artifact
Training Plan Yes Coordinate with the business owner and the ICE Office of Training and Development (OTD) to provide strategic planning and oversight for training design, development, deployment, and evaluation; and also to provide training project management services
Training Strategies Worksheet
Yes Provide information about how the end users will be trained to operate the system
Development Test Plan
Yes Present the testing strategy, approach, and results from the project team at the TRR
Specify the test environment Define test cases required to verify the requirements and system changes of each release
Development Test Analysis Report
Yes Provide testing results of the requirements and system changes of each release
Version Description Document
Yes Include for each release of any product placed into the production environment
List CCB approved software changes and installation instructions
System Administration and Operations Manual
Yes Can be developed/updated following the release
User Guide Yes Can be developed/updated following the release
Deployment Plan No The Project Management Plan includes the required information of this document artifact
Notice of Intent to Release
Yes Required for all releases
Disposition Plan No Not applicable until project retirement
6 FAST TRACK
Fast Track Document Artifacts
To Be Document Artifact Tailoring, Justification, and Comments Provided
IAD Document Artifacts:
FIPS 199 Security
Categorization Worksheet
Interconnection
Security Agreement
Development Security Test and Evaluation (ST&E)
Report
Privacy Threshold Analysis
Privacy Impact
System of Record Notice
System Security
Plan
Security Risk Assessment
Contingency Plan
Development ST&E
The following documents generated by IAD:
Security Assessment Report
Certification Letter
Accreditation Letter
Yes Project team will work with Information Assurance Division (IAD) to address any security documentation requirements or issues (see the full list of IAD document artifacts to the left)
FAST TRACK 7
2.3 Fast Track Gate Reviews
Exhibit 3 describes the SLM gate reviews associated with this work pattern.
Exhibit 3: Fast Track Gate Reviews
Fast Track Gate Reviews
Gate Review To Be Held Tailoring, Justification, and Comments
Planning Review Yes A signed Project Tailoring Plan (PTP), initiated Project Management Plan (PMP), and initial project schedule required before system exits the Planning phase
In addition, the following System Lifecycle Management (SLM) document artifacts associated with this review must be provided early in the lifecycle:
System Concept of Operations (ConOps) section of the System Requirements Document (SRD)
Security Categorization Worksheet Training Strategies Worksheet Security Risk Assessment (SRA) System Security Plan (SSP)
Requirements Review
Preliminary Architecture and Design Review
Final Architecture and Design Review
Yes Requirements Review, Preliminary Architecture and Design Review (PADR), and Final Architecture and Design Review (FADR) will be combined
Test Readiness Review
Yes Held at the time of product hand-off to independent testing
Release Readiness Review
Yes Held prior to deployment
8 FAST TRACK
2.4 Fast Track Testing Types
Exhibit 4 identifies the independent testing efforts associated with this work pattern.
Exhibit 4: Fast Track Testing Types
Fast Track Testing Types
Test Type To Be Held Rationale
System Acceptance Test Yes All applications will be tested independently
System Security Test Yes All applications will be tested independently
Web Code Review If Necessary
If required by SEB review
Interoperability Testing If Necessary
If system introduces a software or hardware component that potentially conflicts with the existing implementation
Could be a script downloaded to the desktop, a new peripheral device, or other
Performance Testing No Not applicable
Section 508 Compliance Testing
Yes All ICE systems with a user interface must be scanned for Section 508 compliance
SCRUM 9
3.0 SCRUM
The Scrum work pattern supports projects that must respond to evolving requirements during the design and development of a system. To use Scrum, a project must receive approval from ICE Architecture Assurance.
Project teams should contact ICE Architecture Assurance early in the process to determine if the application can be supported by the Scrum work pattern.
A project following the Scrum work pattern will implement the Iterative methodology and will design and develop the system in 30-day cycles called sprints. Typically, in the Scrum process, each sprint produces a fieldable product. ICE departs from the traditional Scrum process by not requiring a fieldable product at the end of each sprint; however, ICE may introduce this requirement when deemed appropriate.
During the first few sprints, project teams execute planning, requirements definition, and preliminary design activities. These sprints conclude in a combined Planning Review/Requirements Review/Preliminary Architecture and Design Review (PADR). Before this review, the project should determine:
The high-level requirements, design, and architecture (technologies, frameworks, interfaces, and external dependencies)
The number of sprints necessary to accomplish the objectives defined in the SLM gate reviews, specifically the Final Architecture and Design Review (FADR) and the Test Readiness Review (TRR). This decision is made by the IT Project Manager.
The FADR is held at the conclusion of the sprint in which the architecture and design are expected to be finalized. The design should be a refinement of the design provided at the combined Planning Review/Requirements Review/PADR. The sprints continue until the TRR, where a handoff to independent testing takes place. The project may propose to ICE Architecture Assurance to continue using sprints for future system development and enhancement.
Exhibit 5 illustrates the expected maturation of requirements, design, and architecture throughout the implementation of the Scrum work pattern within the SLM process.
10 SCRUM
Exhibit 5: Scrum Requirements, Architecture, and Design Maturation
Requirements Architecture and Design Maximum Change Tolerance
SLM Milestones
Tolerance for Modification and Change
Time
Sprints Sprints Sprints
Planning Review/ Requirements
Review/ Preliminary
Architecture and Design Review
Final Architecture and Design
Review
Test Readiness
3.1 Scrum Sprints
To adhere to the Scrum process, for each sprint, project teams must have a sprint planning meeting, morning Scrum meetings, and a sprint review meeting. These reviews are open to all stakeholders and interested parties for contribution or observation. Reports provided at the sprint planning session and review meeting are to be recorded and disseminated to all key personnel as explicit artifacts of the Scrum process.
At the beginning of the sprint, stakeholders convene a sprint planning meeting for the purposes of prioritizing and subsequently selecting a set of tasks from a backlog that will form the basis of work during the sprint. (A backlog is the list of all functional and non-functional requirements.)
Projects may request that the user community be included as a part of the feedback loop that helps to prioritize and modify requirements as they are considered for sprint tasks.
The set of tasks removed from the backlog for inclusion in a particular sprint must be achievable during the course of a sprint. In the event that a
SCRUM 11
task item (requirement) is too broad to be completed, the task must be split into subtasks that will allow individual subtasks to be completed within a single sprint. When this set of tasks is determined, the sprint is initiated and the project team works to complete the tasks.
Each day of the sprint, a 15-minute morning Scrum meeting is held to discuss the goals for the day to achieve the tasks within the current sprint.
The task activities for the day are assigned, and any issues and risks are raised.
At the end of the sprint, a sprint review meeting is conducted. During this review, the project team evaluates the issues and progress/completion of each task item. After the sprint review is completed, the next sprint begins.
3.2 Scrum Considerations
Although the Scrum work pattern provides greater flexibility in defining requirements and designing a system, use of the Scrum work pattern introduces risk for deploying and supporting a system. This risk results from development occurring in the absence of fully solidified requirements, design, and architecture.
The requirements variability necessitates increased oversight of requirements maturation to support the creation of requirements artifacts that protect the interests of the Government. In addition, to support an implementation that is consistent with acceptable design and architectural standards, the project team must support a greater level of guidance and direction from the Architecture Division and production support teams.
To facilitate minimizing these risks, the Architecture Division will actively participate in sprint planning and sprint review meetings.
It is expected that the design and architecture are well formed by the PADR, and not significantly revised as the project progresses. Alterations from the architecture and design approved at the combined Planning Review/Requirements Review/PADR must be developed in conjunction with the Architecture Division.
Project teams may submit document artifacts for ICE Architecture Assurance assessment at the conclusion of any sprint, but must submit document artifacts for assessment at least 30 days prior to the last sprint to provide an opportunity for the project team to incorporate assessment feedback into the activities of the last sprint.
3.3 Scrum Project Profile
A project profile is the set of characteristics that ICE Architecture Assurance assesses to determine if a project may use the Scrum work pattern. These characteristics include size, scope, risk, and context.
12 SCRUM
Exhibit 6 provides an example of a project that could utilize the Scrum Development work pattern.
Exhibit 6: Scrum Project Example
Scrum Project Example
Project X has a defined set of capabilities but contains potentially changing requirements from the user community. The user community would like to steer application development as dictated by requirements that will emerge as the user community evaluates the functional, stable, and efficient development outputs of each sprint.
3.4 Scrum Document Artifacts
Exhibit 7 identifies the SLM document artifacts associated with this work pattern.
Exhibit 7: Scrum Document Artifacts
Scrum Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
Project Tailoring Plan
Yes Collaborate with ICE Architecture Assurance to formalize the document deliverables and reviews for the project
Project Management Plan
Yes State the number of sprints that will occur during the development effort and the testing effort with a high-level intention for each sprint
Identify the sprint in which product design is expected to be finalized
Acquisition Plan
Yes Ensure Acquisition Plan or Statement of Work (SOW) is on file with Acquisition Management Branch (AMB)
System Requirements
Document
Yes Provide a high-level description of how the system will operate During each sprint, as functionality is incorporated and removed from the backlog, the corresponding specifications are added to the System Requirements Document (SRD)
Note: The SRD is not expected to be complete at the time of Requirements Review. Rather, the SRD will be maintained as a living document that the project team will update at the completion of each sprint as functionality is incorporated and removed from the backlog. The SRD must be finalized prior to the Test Readiness Review (TRR).
Requirements Traceability Matrix
Yes Include standard information that allows tracing Include the priority assigned to each requirement in the
Requirements Traceability Matrix (RTM) During each sprint, as functionality is incorporated into the
SRD, add the corresponding specifications to the RTM
Note: The RTM is not expected to be complete at the time of Requirements Review. Rather, the RTM will be maintained as a living document, which the project team will update during each sprint as functionality is incorporated. The RTM must be finalized prior to the TRR.
SCRUM 13
Scrum Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
System Workload Analysis Document
Yes Describe the system workload, estimate the capacity requirements, and define the impact on the system if system resources are unavailable or if it operates in a degraded mode
Include if performance testing will be conducted, if any Office of the Chief Information Officer (OCIO) Division raises concern with the application architecture or anticipated workload, or if the application will share resources (database or application) with other applications currently in production
Note: The SWAD must be reasonably complete prior to the Final Architecture and Design Review (FADR) and must be finalized prior to the TRR.
Interface Control Agreement
If Necessary
Include if any interfaces with other systems exist Update the Interface Control Agreement (ICA) as sprints implement necessary interfaces
Data Management Plan
Yes Include the application logical data model, which contains the data requirements of a system (This includes an entity relationship diagram [ERD] and its supporting entity, attribute, relationship, and unique identifier reports)
Include the application physical data model, which contains the database design of a system (This includes the data schema diagram [DSD] and its supporting table, column, foreign key, and primary key reports)
Information Technology Change
Request
If Necessary
Submit ITCR and/or Technology Insertions (TI) as appropriate for any new technology not on the ICE TRM or Department TRM respectively
Design Document Yes Diagram and describe system architecture Identify and describe commercial off-the-shelf (COTS) products
(software and hardware), configurations, and customizations Describe custom software design using high-level algorithms, class diagrams, sequence diagrams, or data/process flows Identify complete hardware inventory, including physical locations, redundancies, and software dependencies, such as operating systems and drivers
Describe how system components and external system are interconnected via networks and protocols
Provide physical data models and schema descriptions where data stores are used
Develop screen mockups for systems with substantial numbers of end users
Note: In preparation for the initial Requirements Review / Preliminary Architecture and Design Review (PADR), much of this information may be provided as diagrams without requiring extensive text. As the project team nears the FADR, the design documentation should be further updated to include full descriptions of the intended architecture and design. Subsequent updates to the design specification are performed during subsequent sprints to reflect necessary updates.
SEB Service Level Agreement
Yes Collaborate with production support teams in determining level of support for system in production
Data Conversion Plan
If Necessary
Required only if data is being converted from one format to another
14 SCRUM
To Be Document Artifact Tailoring, Justification, and Comments Provided
Training Plan If Necessary
Coordinate with the business owner and the ICE Office of Training and Development (OTD) to provide strategic planning and oversight for training design, development, deployment, and evaluation; and also to provide training project management services
Training Strategies Worksheet
Yes Provide information about how the end users will be trained to operate the system
Development Test Plan
Yes Present testing strategy, approach, and results from project team at the TRR
Specify the test environment Define test cases required to verify the requirements and system changes of each release Maintain the Development Test Plan (DTP) to describe test activities performed during sprints that include Functional Qualification Testing (FQT) activities
Development Test Analysis Report
Yes Provide testing results of the requirements and system changes of each release
Maintain the Development Test Analysis Report (DTAR) to describe the results of test activities performed during sprints that include FQT activities
Version Description Document
Yes Include for each release of any product placed into the production environment
Installation procedures will be verified List CCB approved software changes and installation instructions The Version Description Document (VDD) must be made current and complete for each release prior to TRR
System Administration and Operations Manual
Yes Can be developed/updated following the release
User Guide Yes Can be developed/updated following the release
Deployment Plan Yes A standard deployment plan is required
Notice of Intent to Release
Yes Required for all releases
SCRUM 15
Document Artifact To Be Provided Tailoring, Justification, and Comments
16 SCRUM
3.5 Scrum Gate Reviews
Exhibit 8 describes the SLM gate reviews associated with this work pattern.
Exhibit 8: Scrum Gate Reviews
Scrum Gate Reviews
Gate Review To Be Held Tailoring, Justification, and Comments
Planning Review Yes A signed Project Tailoring Plan (PTP), initiated Project Management Plan (PMP), and initial project schedule required before system exits the Planning phase
A high-level explanation of how Scrum will be applied to the SLM process should be provided; ICE Architecture Assurance will identify the guidelines to follow for artifacts and milestones specific to Scrum
Requirements Review
Yes The scope and the prioritization of the requirements will be evaluated to determine the number of sprints necessary for the project; the number of sprints can then be included in the Project Management Plan (PMP); requirements are not expected to be complete at this time, but a reasonable scope definition is necessary to proceed
Additional Requirements Reviews may be held until the final requirements are captured
Preliminary Architecture and Design Review
Yes A statement of intentions should be provided with regard to technology, software (open source or commercial off-the-shelf/ Government off-the-shelf [COTS/GOTS]), and high-level design that describe how those technologies shall be applied; identify any interfaces, use of middleware, or other design and technology aspects of the project that are known at this time
Additional Preliminary Architecture and Design Reviews (PADR) may be held until the design becomes well established
Specify in which sprint the finalized design is expected; a Final Architecture and Design Review (FADR) will be scheduled to occur following the specified sprint
Final Architecture and Design Review
Yes The FADR is held when the project team reaches the pre-determined sprint in which the design is expected to be finalized
Design documentation that completely explains the technical intentions and approaches intended by the project team should be submitted and distributed prior to the FADR
Should subsequent sprints require substantial changes to product design or architecture due to unforeseen circumstances, an additional FADR will be held as appropriate
Test Readiness Review
Yes The Test Readiness Review (TRR) will be held at the time of product (or functionally complete sprint) hand-off to independent testing
Requirements specifications included in the following artifacts must be completed and up-to-date prior to the TRR; these artifacts formally determine the test scope and are required to initiate the independent testing process:
System Requirements Document (SRD) Requirements Traceability Matrix (RTM) Data Management Plan (DMP) System Workload Analysis Document (SWAD)
Release Readiness Review
Yes The Release Readiness Review (RRR) will be held prior to deployment
SCRUM 17
3.6 Scrum Testing Types
Exhibit 9 identifies the independent testing efforts associated with this work pattern.
Exhibit 9: Scrum Testing Types
Scrum Testing Types
Test Type To Be Held Rationale
System Acceptance Test Yes All applications will be tested independently Short, SAT-like functional tests may occur for each sprint within the Scrum A final SAT will occur after the final build is delivered
System Security Test Yes All applications will be tested independently
Web Code Review If Necessary
If required by SEB review
Interoperability Testing If Necessary
If system introduces a software or hardware component that potentially conflicts with the existing implementation
Could be a script downloaded to the desktop, a new peripheral device, or other
Performance Testing If Necessary
If system processing speed has a potential impact on business service delivery
If system resource usage potentially impacts other systems or the infrastructure
Section 508 Compliance Testing
Yes All ICE systems with a user interface must be scanned
COTS/GOTS 19
4.0 COTS/GOTS
The COTS/GOTS work pattern supports projects intending to implement a system that is already developed and will not be customized. This work pattern concentrates on documenting the decisions and tasks associated with selecting, acquiring, and implementing the COTS/GOTS product. To use COTS/GOTS, a project must receive approval from ICE Architecture Assurance.
A COTS/GOTS project will typically follow the Waterfall methodology.
Because the system will not need to be developed or customized, Design and Development activities are reduced.
In some cases, the selection of a COTS/GOTS product is determined prior to entering the SLM process. Examples include DHS directives to implement a particular product in the ICE environment and upgrades to products existing in the ICE environment. In cases where the evaluation of available products is unnecessary because the product has already been selected or is an upgrade to an existing product that has already been purchased, elements of this work pattern may be adjusted accordingly.
4.1 COTS/GOTS Project Profile
A project profile is the set of characteristics that ICE Architecture Assurance assesses to determine if a project may use the COTS/GOTS work pattern. These characteristics include size, scope, risk, and context.
Exhibit 10 provides an example of a project that could use the COTS/GOTS work pattern.
Exhibit 10: COTS/GOTS Project Example
COTS/GOTS Project Example
Project X is the implementation of a product selected by DHS as the enterprise standard to serve a particular business function (such as time accounting) that must be deployed within each DHS component.
COTS/GOTS 20
4.2 COTS/GOTS Document Artifacts
Exhibit 11 identifies the SLM document artifacts associated with this work pattern.
Exhibit 11: COTS/GOTS Document Artifacts
COTS/GOTS Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
Project Tailoring Plan
Yes Collaborate with ICE Architecture Assurance to formalize the document deliverables and reviews for the project
Project Management Plan
Yes Include procurement strategy if procurement is necessary Update prior to the Test Readiness Review (TRR) to include activities normally addressed in the Deployment Plan
Acquisition Plan
Yes Ensure Acquisition Plan or Statement of Work (SOW) is on file with Acquisition Management Branch (AMB)
System Requirements
Document
Yes Provide a high-level description of how the system will operate Include the Requirements Traceability Matrix (RTM) Define logical data elements, such as entities and attributes
Requirements Traceability Matrix
No The System Requirements Document includes the required information of this document artifact
System Workload Analysis Document
If Necessary
Include if performance testing will be conducted or if any Office of the Chief Information Officer (OCIO) division raises concern with the application architecture or anticipated workload
Describe the system workload, estimate capacity requirements, and define the impact on the system if system resources are unavailable or if it operates in a degraded mode
Interface Control Agreement
If Necessary
Include if any interfaces with other systems exist
Data Management Plan
No The System Requirements Document includes the required information of this document artifact
Information Technology Change
Request
If Necessary
Submit ITCR and/or Technology Insertions (TI) as appropriate for any new technology not on the ICE TRM or Department TRM respectively
Design Document Yes Identify the architecture, components, and technologies
SEB Service Level Agreements
Yes Collaborate with the production support teams in determining the level of support for system in production
Data Conversion Plan
If Necessary
Required only if data is being converted from one format to another
Training Plan Yes Coordinate with the business owner and the ICE Office of Training and Development (OTD) to provide strategic planning and oversight for training design, development, deployment, and evaluation; and also to provide training project management services
Training Strategies Worksheet
Yes Provide information about how the end users will be trained to operate the system
Development Test Plan
Yes Present the testing strategy, approach, and results from the project team at the TRR
Specify the test environment Define test cases required to verify the requirements and system changes of each release
Development Test Analysis Report
Yes Provide testing results of the requirements and system changes of each release
COTS/GOTS 21
COTS/GOTS Document Artifacts
To Be Document Artifact Tailoring, Justification, and Comments Provided
Version Description Document
Yes Include for each release of any product placed into the production environment
List CCB approved software changes and installation instructions
System Administration and Operations Manual
Yes Provide maintenance personnel and operations staff with the information necessary to maintain the system effectively (Vendor documentation is typically supplied in lieu of a Systems Administration and Operations Manual)
User Guide Yes Provide information that will enable the user to make full use of the system (A quick start guide, frequently asked questions (FAQ) sheet or similar material is frequently provided in lieu of a User Guide)
Deployment Plan No The Project Management Plan includes the required information of this document artifact
Notice of Intent to Release
Yes A Notice of Intent to Release (NIR) required for all Releases
COTS/GOTS 22
COTS/GOTS Document Artifacts
To Be Document Artifact Tailoring, Justification, and Comments Provided
AD Document
If Necessary
Project team will work with Information Assurance Division
COTS/GOTS 23
4.3 COTS/GOTS Gate Reviews
Exhibit 12 describes the SLM gate reviews associated with this work pattern.
Exhibit 12: COTS/GOTS Gate Reviews
COTS/GOTS Gate Reviews
Gate Review To Be Held Tailoring, Justification, and Comments
Planning Review Yes A signed Project Tailoring Plan (PTP), initiated Project Management Plan (PMP), and initial project schedule required before system exits the Planning phase
Requirements Review
Yes
Preliminary Architecture and Design Review
Final Architecture and Design Review
Requirements Review, Preliminary Architecture and Design Review (PADR), and Final Architecture and Design Review (FADR) will be combined; the reviews may be separated if deemed necessary by the Architecture Division
Any Information Technology Change Request (ITCR) associated with the infrastructure must be dispositioned prior to a combined review
Test Readiness Review
Yes Held at the time of product hand-off to independent testing (In many cases, only Interoperability Testing is conducted on commercial off-the-shelf/Government off-the-shelf [COTS/GOTS] products)
Release Readiness
Yes Held prior to deployment
COTS/GOTS 24
4.4 COTS/GOTS Testing Types
Exhibit 13 identifies the independent testing efforts associated with this work pattern.
Exhibit 13: COTS/GOTS Testing Types
COTS / GOTS Testing Types
Test Type To Be Held Rationale
System Acceptance Test If Necessary
Only if COTS/GOTS is customized
System Security Test Yes All applications will be tested independently Uncustomized COTS/GOTS will undergo security scan only
Web Code Review If Necessary
If required by SEB review
Interoperability Testing If Necessary
If system introduces a software or hardware component that potentially conflicts with the existing implementation
Could be a script downloaded to the desktop, a new peripheral device, or other
Performance Testing If Necessary
If system processing speed has a potential impact on business service delivery
If system resource usage potentially impacts other systems or the infrastructure
Section 508 Compliance Testing
INFRASTRUCTURE 25
5.0 INFRASTRUCTURE
The Infrastructure work pattern supports projects intending to implement a customized or non-customized COTS/GOTS product or a hardware product into the infrastructure. To use the Infrastructure work pattern, a project must receive approval from ICE Architecture Assurance.
Infrastructure projects often have unique documentation requirements or have existing documentation that may not obviously map to the ICE SLM conventions. During the tailoring process, the unique documentation requirements of an infrastructure project should be mapped to the appropriate or approximate types of SLM documents. The emphasis is on ensuring that the correct type of data is captured during the SLM process and not on a specific name or format of a document.
An infrastructure-specific pre-defined work pattern document and associated SLM document templates are being developed by ICE OCIO Architecture and Engineering Divisions. Until these are put into place, the interim solution noted in the above paragraph will remain in effect.
An infrastructure project will typically follow the Waterfall or Incremental methodology. (The Incremental methodology should be used particularly with dispersed deployments.)
5.1 Infrastructure Project Profile
A project profile is the set of characteristics that ICE Architecture Assurance assesses to determine if a project may use the Infrastructure work pattern.
These characteristics include size, scope, risk, and context. Exhibit 14 provides examples of projects that could use the Infrastructure work pattern.
INFRASTRUCTURE 26
Exhibit 14: Infrastructure Project Examples
Infrastructure Project Examples
Project X could implement one of the following:
Customization of commercial off-the-shelf/Government off-the-shelf (COTS/GOTS) products implementing ICE Office of the Chief Information Officer (OCIO) operational processes, such as security-related tools, directory services, firewall services, network address management services, and network operating systems (NOS)
Customization of COTS/GOTS products that provide the infrastructure supporting the performance of common business activities, such as e-mail, calendaring, document sharing, and voice and video communications
Configuration and implementation of desktop suites Deployment, operations, and maintenance of local area networks (LAN) and wide area networks (WAN) Configuration and deployment of equipment and hardware (such as desktop computers, servers, cables, routers, and switches) that provide the physical infrastructure for operating and maintaining business applications, OCIO operations-related tools, LANs, and the WAN
Configuration and deployment of satellite circuits and receivers Configuration, implementation, operations, and maintenance of the mainframe, database, E-Gov, and Web environments Configuration and implementation of data warehouses and repositories
5.2 Infrastructure Document Artifacts
Exhibit 15 identifies the SLM document artifacts associated with this work pattern. Note that for infrastructure projects, the emphasis is on ensuring that the appropriate information is captured. Infrastructure projects may have document names and formats that differ from the SLM naming conventions and templates; the tailoring process will document the mapping between documents. A typical example is the Version Description Document (VDD): For an infrastructure project, the VDD will typically detail the necessary build, setup, and configuration instructions to establish the baseline operating capability for the infrastructure component. Separate document artifacts for infrastructure projects will be created before the next version of this document.
In addition to the brief comments below, refer to the appropriate SLM templates to find a full description of the kind of information expected for each document artifact. These templates are available in the ICE Electronic Library (DOCUMENTS.ICE.DHS.GOV) under Governance Documents Home/Templates.
INFRASTRUCTURE 27
Exhibit 15: Infrastructure Document Artifacts
Infrastructure Document Artifacts
Document Artifact To Be Provided Tailoring, Justification, and Comments
Project Tailoring Plan
Yes Collaborate with ICE Architecture Assurance to formalize the document deliverables and reviews for the project
Project Management Plan
Yes To include detailed implementation plan on how the project will progress toward deploying the infrastructure
Acquisition Plan Yes Ensure Acquisition Plan or Statement of Work (SOW) is on file with Acquisition Management Branch (AMB)
System Requirements
Document
Yes Provide a high-level description of the purpose, function and intended operation of the infrastructure
Requirements Traceability Matrix
If Necessary
Case by case determination Typically, the System Requirements Document includes the required information of this document artifact
System Workload Analysis Document
No • Not applicable
Interface Control Agreement
If Necessary
If required per System Requirements Document (SRD)
Data Management Plan
If Necessary
Required if Extract, Transform, and Load (ETL) of data into the new environment will be required
Information Technology Change
Request
If Necessary
Submit ITCR and/or Technology Insertions (TI) as appropriate for any new technology not on the ICE TRM or Department TRM respectively
Design Document Yes Identify architecture, components, and technologies Describe all aspects of the design in full detail as may be applicable for the type of infrastructure
SEB Service Level Agreements
If Necessary
Only if Web or DBA hosting is required (on file with Systems Engineering Branch)
Data Conversion Plan
If Necessary
Required only if data is being converted from one format to another
Training Plan No PMP will include information about vendor knowledge transfer
Training Strategies Worksheet
No PMP will include information about vendor knowledge transfer
Development Test Plan
Yes Present the installation verification strategy and approach from the project team
Define test cases required to verify the requirements and system changes of each release
Development Test Analysis Report
Yes Present the installation verification results Provide testing results of the requirements and system changes of each release
Version Description Document
Yes Typically details the necessary build, setup, and configuration instructions to establish the baseline…