This document is a Statement of Work outlining construction services required for the Capital Security Project at the Clemente Ruiz Nazario U.S. Courthouse and Federico Degetau Federal Building in San Juan, Puerto Rico. The General Contractor will be responsible for 6,200 square feet of new construction, 9,200 square feet of renovation, and 30,000 square feet of site work. Key requirements include construction of a new sally port and prisoner elevator. Optional scope includes an isolation cell and holding cells. The projected schedule is 560 calendar days from NTP to substantial completion. Closeout is required within 60 days thereafter. The General Contractor must adhere to GSA standards and provide CAD as-builts, COBie data, and photographic documentation. Regular progress meetings are required on a bi-weekly basis.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for
General Construction (GC) Contract
PROJECT IDENTIFICATION
Project Name: Capital Security Project
Project Number: 59762
Date: 7/22/2021
Region: Region 2 – Northeast & Caribbean Region
Building Name: Degetau Federal Building & Nazario Courthouse
Building Address: 150 Carlos Chardon Ave., San Juan, PR 00918
TABLE OF CONTENTS
1. PROJECT DESCRIPTION 3
2. PROJECT TYPE 3
3. OBJECTIVE 3
4. PROJECT DELIVERY APPROACH 3
5. REFERENCE MATERIALS 4
6. GENERAL REQUIREMENTS 4
7. SCOPE OF SERVICES 13
7.1 CONSTRUCTION STAGE 13
7.2 CLOSEOUT STAGE 15
8. APPENDIX 17
1. PROJECT DESCRIPTION
This Statement of Work (SOW) is for professional construction services needed to meet the requirements as per the construction documents and supporting documents for the Capital Security Project at the Clemente Ruiz Nazario U.S. Courthouse and Federico Degetau Federal Building at 150 Carlos Chardon Avenue in San Juan, Puerto Rico.
The project consists of the following: 6,200 square feet of new construction; renovation of 9,200 square feet of existing space; and approximately 30,000 square feet of site work. The Nazario U.S. Courthouse and Degetau Federal Building will be fully occupied and work must be performed during non-office hours as such not to interrupt the buildings operations or operation of building occupants. Work that is not disruptive can take place during regular business hours.
The project base scope includes:
● A new sally port to allow secured transportation of prisoners to the Main Detention
Cellblock and to the Nazario Courthouse Courtrooms. This sally port shall be designed to structurally support future equipment as well.
● One (1) new Prisoner Elevator to the Main Detention Cellblock at the Degetau Federal Building.
The following will be provided as options:
● Option 4: One (1) isolation cell at USMS Main Detention Cellblock at Degetau
● Option 5: Three (3) holding cells in Nazario Basement
2. PROJECT TYPE
Renovation and Alteration
3. OBJECTIVE
The GSA intends to construct a project that will address general security deficiencies that affect operations at the Clemente Ruiz-Nazario US Courthouse and Federico Degetau Federal Building in Hato Rey, Puerto Rico.
4. PROJECT DELIVERY APPROACH
a. Design Bid Build - the construction documents, specifications and supplemental materials are included in the RFP.
b. The RFP states the project functional requirements, design and engineering criteria, technical performance specifications, and other supporting documents.
5. REFERENCE MATERIALS
a. Per attached, this project includes:
i. Construction Drawings for
1. 21-0721 - HRCSP Bid Set - Base Scope.pdf
● HRCSP Bid Set - Base Scope
2. 21-0721 - HRCSP Bid Set - Option 4.pdf
● HRCSP Bid Set - Construction Option 4
3. 21-0721 - HRCSP Bid Set - Option 5.pdf
● HRCSP Bid Set - Construction Option 5
ii. Technical Specifications
1. 21-0721 HRCSP Bid Set Specifications Volume 1 of 2.pdf
● HRCSP Bid Set - Specifications Volume 1
2. 21-0721 HRCSP Bid Set Specifications Volume 2 of 2.pdf
● HRCSP Bid Set - Specifications Volume 2
iii. Supplemental Materials
1. HZ Lead Survey HRCSP July2020 Rev. Aug2020.pdf
● Environmental Survey for Lead Based Paint (LBP)
2. HZ ACM Survey HRCSP July2020 Rev. 8-19-2020.pdf
● Environmental Survey for Asbestos Containing Materials (ACM)
3. APPENDIX A_LIGHTING FIXTURE CUTSHEETS.pdf
● Appendix A – Lighting Fixture Cuts
4. 210604-100% Structural Narrative and Calculations.pdf
● Structural Narrative and Design Calculations
5. 2020-05-12 Hato Rey Federal Security Upgrade GES.pdf
● Geotechnical Engineering Study
6. 20-1104 - PAB-1 GPR of Three Areas.pdf
● PAB-1 Underground Survey of Three Areas
b. PBS-P100 Facilities Standards for the Public Buildings Services issued 2018
6. GENERAL REQUIREMENTS
Project requirements are set forth in this Statement of Work (SOW) and in Division 1 included in the Technical Specifications.
a. Contract Parties and Contract Work The parties to this contract are the Contractor, hereinafter referred to as the General Contractor, and the United States Government. For purposes of this contract, the office representing the Government is the General Services Administration (GSA), Region 02, Public Buildings Service, hereinafter referred to as the GSA.
The individual authorized to act on the behalf of the GSA in the administration of this contract is the GSA Contracting Officer (CO). The GSA Contracting Officer may delegate certain of his or her authorities to others, and if so, will notify the General Contractor in writing of the specific authorities delegated to, and limitations placed upon, named authorized representatives. The General Contractor shall not take any direction, or act upon any information, from individuals other than those having the requisite authority as confirmed by the GSA Contracting Officer’s written notification.
This contract includes work which is to be performed by the General Contractor, consultants and or subcontractors.
b. Professional Ethics and Standards of Practice In the conduct of all activities required for or otherwise related to the performance of the contract work, the General Contractor shall conform to and uphold all established ethical principles and professional standards of practice governing the General contractor segment of the construction industry.
c. Project Delivery Team Roles and Responsibilities In the performance of the requirements of this contract, the General Contractor shall work in concert with other parties on the Project Delivery Team. The Project Delivery Team will include the GSA personnel, General Contractor’s team and other stakeholders. The General Contractor will develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities.
The General Contractor is responsible to perform Construction Stage and Closeout Stage services in accordance with the GSA project requirements, schedule, performance objectives, scope of services, and other requirements provided in the contract. The specific activities, tasks, and deliverables required of the General Contractor are further delineated in Division 1.
d. Schedule
Capital Security Project Schedule for Completion
Award Approximately December 2021
NTP to Substantial Completion (includes time for obtaining security clearances)
560 calendar days from Notice to Proceed (NTP)
Contract Closeout Shall be complete within 60 calendar days from Substantial Completion
TOTAL 620 calendar days
i. The Period of Performance is 560 calendar days.
ii. Personnel Requirements: The General Contractor is responsible for obtaining all required long term HSPD-12 clearances. Refer to the specification section “Security Regulations 015930”.
e. General Contractor Team
i. The General Contractor shall provide the necessary staff to perform and complete the required work.
ii. During the performance of the services required under this contract, the General contractor shall obtain the GSA written consent before making any substitution for subcontractors and outside associates or consultants specifically identified and agreed to during negotiations. Refer to the specification section “Substitution Procedures 012500”.
iii. The General Contractor shall abide by all relevant sections in the Federal Acquisition Regulation (FAR), including but not limited to: FAR 52.236-5, Material and Workmanship, regarding removal of any employee deemed incompetent, careless, or otherwise objectionable.
f. Performance Objectives
i. Standards and Criteria Documents
1. Applicability
All services must be conducted in accordance with the documents listed in Reference Materials and other sections of this Statement of Work. The applicable version of each document shall be the version current at the time of award of this contract. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this Statement of Work, the General Contractor shall submit a Request for Information (RFI) to the Government for clarification.
2. Document List
a. P100: The Facilities Standards for the Public Buildings Service (PBS) is the document that provides the design standards and criteria for all new buildings, major and minor alterations, and work in historic buildings for the Public Buildings Service of GSA. This document contains the policy and technical criteria to be used in the programming, design, construction and GC Contract Statement of Work documentation of GSA buildings. All the submission requirements for drawings, specifications and reports are listed in this publication.
b. P120: The Public Buildings Service (PBS) Cost and Schedule Management Policy: establishes the quality and level of cost and schedule management services to be provided during the planning, design and construction phases of projects.
c. CAD Standards: The GSA CAD Standards are composed of several documents. These are the PBS CAD Standards and the PBS Assignment Drawing Guidance, which should be used in conjunction with the BOMA publication. CAD files for layering and title blocks are available on-line at www.gsa.gov
d. BIM Standards: The P100 requires projects to be developed in BIM to the following minimum standards: (1) Accurate Models to represent the proposed construction for design review, constructability clash detection and as-built records; (2) Spatial Data Management to provide the GSA with accurately developed area plans and space names; (3) Track and provide specified building equipment and asset data through the COBie exchange format. More information is provided within Division 1. Also refer to the specification section “Construction Options Building Information exchange 013600”.
e. Specifications: All specifications in GSA projects are performance specifications, with no sole source items allowed. GSA has adopted the AIA MASTERSPEC as the standard specifications to be used on all GSA projects. The specifications are included in the construction documents.
f. Metric Measurements: not applicable
g. National Building Codes: GSA has adopted the following National
Building Codes; which include but are not limited to:
● International Code Council (ICC) family of building codes
● International Building Code (IBC)
● International Fire Code (IFC)
● International Plumbing Code (IPC)
● International Mechanical Code (IMC)
● International Energy Conservation Code (IECC)
● Technical egress requirements of the NFPA Life Safety Code
(NFPA 101) in lieu of the technical egress requirements of the
IBC
● Technical electrical requirements of the NFPA National Electric Code (NFPA 70) in lieu of the technical electrical requirements of the ICC Electrical Code.
h. Minimum Performance Criteria (MPC): GSA MPC includes but is not limited to: Construction Waste Management - Reducing and recycling at least 50% construction waste is a GSA goal and must be accounted for during the construction process. More information is provided within Division 1. Also refer to the specification section “Sustainable Design Requirements 018111”.
i. GSA Controlled Unclassified Information (CUI) Document Security: CUI document security is required to reduce the risk that GSA building information will be used for dangerous or illegal purposes by others. The General Contractor shall comply with PBS order 3490.2, which is titled Document Security for Controlled Unclassified Information (CUI) Paper and Electronic Building Information. This document covers the procedures and labeling requirements for CUI documents during all project phases including design, construction procurement, and construction administration, building commissioning and ongoing building operations. It is meant to reduce the possibility of harm while still respecting GSA’s legitimate business needs to allow access to CUI building information by those with a need to know, such as design professionals, contractors and others. The general principles of this policy are to give CUI project information only to those who have a need to know, to keep records of who received CUI project information, to safeguard CUI project information during use and to destroy it properly after use.
j. Division 1 of the GC Contract Performance Specification: The GSA Division 1 specification sections are combined with the technical sections, these sections are used to describe the project’s general requirements, and they precede the technical specification sections.
g. Project Management Responsibilities
i. Communications Plan
The General Contractor, in consultation with the stakeholders of the project, shall assist the GSA in developing and complying with a project communications plan. This plan will be used and maintained throughout the project and modified as necessary to suit each project phase.
The General Contractor contractual responsibility is to the GSA only and not to other contractors, tenants agencies or local community interests where the project is located. The General Contractor shall direct all questions and requests from tenant agencies and local community interests to the GSA.
Prior to contacting any parties other than the GSA regional personnel, the General Contractor shall confirm all meetings and/or communications with the GSA. The General Contractor shall not release any oral, written or graphic information regarding this project to outside sources without obtaining prior consent from the GSA. All requests for information concerning the project must be referred to the GSA for response.
ii. Detailed Project Schedule Development and Maintenance
Before starting any other work, the General Contractor shall develop and provide a detailed schedule in Microsoft Project® for completion of all tasks, and submissions required herein, leading up to and including final completion. After the General Contractor receives notice to proceed with the Construction Stage work, the General Contractor shall provide and maintain a detailed schedule in Microsoft Project® or equivalent for tasks, and submissions required herein. The schedule must identify a critical path.
The General Contractor shall also provide and maintain the construction schedules as further described in the contract general requirements. After approval by the GSA, the General Contractor schedules will be incorporated into the master project schedule kept by the GSA.
Refer to FAR 52.236-15 Schedules for Construction Contracts and to the Scope of Services Construction Delivery Phase section for additional schedule requirements.
iii. Project Progress Meetings/Presentations
After Notice To Proceed regular weekly meetings shall take place on site until completion of the project. Additional meetings may be required and scheduled at any time.
iv. Meeting Agendas, Attendance, Minutes and Correspondence
The Construction Manager as Advisor (CMa) shall prepare and distribute an agenda at least two days before for each project meeting. GSA may then take the opportunity to add additional agenda items that should be discussed and will share those changes with the CMa. The CMa will then redistribute the revised agenda to all team members.
The General Contractor representation at all meetings shall include those individuals having knowledge of the agenda topics and authority to make decisions and commit resources.
The General Contractor shall review minutes of all project meetings within two
(2) business days before such minutes become official.
General Contractor shall provide supporting documents for regular weekly meetings as required. Supporting documents shall be shared with but not be limited to the GSA PM, COR, CO, and CMa. Supporting documents may include, but not be limited to an updated project schedule, two (2) week look ahead including all tasks requiring assistance from GSA or the building Engineers, important submittals, sketches and pictures as needed and/or RFIs, etc.
h. Computer Aided Design (CAD) Standards General Contractor shall provide as-builts in CAD as per the GSA CAD Standards.
As-builts are required within four (4) weeks of final construction completion for each phase.
i. Construction Options Building Information exchange (COBIe) More information is provided within Division 1. Also refer to the specification section “Construction Options Building Information exchange 013600”.
j. General Contractor Personnel Security Requirements The Contractor and their Contractor Personnel shall comply with the Homeland Security Presidential Directive-12 (HSPD-12).
In accordance with FAR 52.204-9 (Personal Identity Verification of Contractor Personnel):
● The General Contractor shall account for all GSA credentials issued to General
Contractor Personnel in connection with the performance under this contract.
● The General Contractor Personnel shall immediately return credentials issued by
GSA under any of the conditions stipulated in FAR 52204-9.
The Contractor shall incorporate provisions in all applicable subcontracts to comply with the contractor personnel security requirements. More information is provided within Division 1. Also refer to the specification section “Security Regulations 015930”.
k. Document Security Controlled Unclassified Information (CUI) building information will be generated and/or must be disseminated to and stored by various parties in the course of executing this project. CUI building information is information that, if misused, poses a potential security risk to a building, its occupants and visitors, and/or its contents.
The General Contractor shall comply with the following requirements regarding CUI building information.
i. Documents
As used in this section, the term “documents” means any media or devices used to capture, store, and transmit information, including printed images and electronically or optically stored forms of graphic and written information, as well as physical or virtual models.
ii. Identification and Labeling/Marking
Original General Contractor generated documents that contain building information must be reviewed with the GSA to identify any CUI content, before the original or any copies are disseminated to any other parties. If CUI content is identified, the general contractor shall affix CUI document labels/markings to the original documents and all extant copies, as instructed by the GSA, prior to any dissemination
iii. Copying from Labeled/Marked Documents
Any documents containing CUI content copied from CUI labeled/marked documents must have the same CUI labels/markings affixed, unless the copies are redacted and reviewed as provided below.
iv. Redacting
The General Contractor may redact complete or partial copies of CUI labeled/marked documents to remove or completely and unalterably obscure the CUI content. The General Contractor shall review the redacted copies with the GSA to ensure that all CUI content has been removed or obscured. Copies so redacted and reviewed are no longer subject to these requirements regarding CUI building information.
v. Safeguarding and Storage
The General Contractor shall properly safeguard any documents bearing CUI labels/markings at all times while those documents are in General Contractor possession. Access to such documents when in use by the General Contractor must be limited to individuals having a need to know the content in order to perform work required under this contract. When not in use, CUI labeled/marked documents in General Contractor possession must be securely stored such that they can be retrieved only by those individuals having a need to know the content.
vi. Dissemination
Other than within the Project Delivery Team, the General Contractor shall disseminate CUI labeled/marked documents only to parties assigned or authorized to perform a role in the execution of the project and having a resultant need to know the document content. Documents may be disseminated in face-to-face meetings, by courier or secure shipment with evidence of delivery, or by electronic transmission. Electronic transmission of CUI information shall be encrypted as provided in current National Institute of Standards and Technology (NIST) data encryption standards and cryptographic module security requirements for processing CUI information.
vii. Destruction
CUI content that is no longer needed shall be purged from all CUI labeled/marked documents and destroyed, or the complete document shall be destroyed, such that the CUI content is rendered unreadable and incapable of being restored. Data storage devices containing CUI information that is no longer needed shall be destroyed or the CUI content shall be erased using a permanent erase utility or comparable method.
viii. Reporting
The General Contractor immediately shall report to the GSA any known or suspected instances of improper dissemination of CUI information, or other circumstances in which the security of CUI information may be compromised.
ix. Subcontracts
The General Contractor shall incorporate provisions in all applicable subcontracts as necessary to ensure compliance with all requirements provided in this Document Security section.
l. Construction General Requirements Construction general requirements are included in the performance specification.
Additional Construction Stage requirements are provided in the Construction Stage section of the Scope of Services below.
m. Disruptive Work The General Contractor shall work with GSA personnel, US Courts, architect of record, and other stakeholders, during all phases of construction during the project, to coordinate a plan to resolve all issues related to work deemed disruptive.
Refer to specification sections in Division 1.
All shutdowns shall take place during unoccupied hours unless the contractor receives written permission from the GSA CO at least 48 hours prior to the shut down.
n. Building Contractors The contractor is responsible for any and all costs associated with and the coordination of all activities needed to complete the requirements of the contract to include, but not limited to: building system shutdowns; updates, revisions or other changes to the building operating systems; fire watches; sprinklers, fire alarms, security systems.
Coordination shall take place throughout the GSA Building Management team.
o. Sole Source descriptions Any description that gives the appearance that a required product or material is a “sole source” or is otherwise restricted to a particular product or material shall be considered “Brand Name or Equal”. Substitutions for any required product or material and items that are quoted in lieu of Brand Name or Equal items shall have the same salient characteristics of those required by the RFQ. Quotes shall clearly identify if a product or material is a Substitution or is Equal to those required.
7. SCOPE OF SERVICES
7.1 CONSTRUCTION STAGE
a. Construction Delivery Phase Pre-Construction Conference: Participate in the pre-construction conference on site.
b. Hazardous Material Abatement An asbestos report and a lead report report are included in this solicitation. Refer to drawings, specifications and supplemental materials.
c. Construction Administration
i. Schedule of Values
Prepare and submit the schedule of values for the GSA approval, as required in
Division 1.
ii. Construction Safety Program Refer to specification sections in Division 1.
iii. Project Progress Meetings The GSA, General Contractor, Architect of record, Construction Manager as Advisor, and key stakeholders will participate in regular bi-weekly progress meetings. Refer to specification sections in Division 1.
iv. Construction Schedules The General Contractor shall provide and maintain construction schedules in accordance with the requirements provided in Division 1.
The GSA will review the General Contractor schedules for completeness and appropriateness and recommend approval, rejection, or revisions. The General Contractor shall provide monthly project schedule updates showing all tasks needed to complete the project.
The GSA will integrate the approved General Contractor schedules within the master project schedule, incorporating activities of the GSA, General contractor, and other involved parties.
The General Contractor will continuously monitor actual progress against the master project schedule, identify any delays or potential delays and immediately notify the GSA of such delays or potential delays.
v. Submittal Processing Prepare and submit a submittal schedule in accordance with Division 1. In the submittal schedule, identify all submittals requiring review by the GSA. Transmit all required submittals to the GSA. Ensure that all subcontractors understand, agree to, and conform with their respective roles, responsibilities, and timeliness requirements for submittal processing.
Promptly correct and resubmit any submittals returned unapproved, allowing sufficient time for re-review in order to maintain the project schedule.
Upon receipt of submittal approvals, coordinate as necessary with all involved subcontractors.
Refer to FAR 52.236-21, Specifications and Drawings for Construction, for further submittal and shop drawing review requirements.
Expedite the processing of submittals to minimize approval times.
vi. Clarifications/Requests for Information Promptly submit to the GSA a written request for information (RFI) to request clarification of any apparent conflicts, ambiguities, and/or general contract requirements. Each RFI must include a specific description of the issue requiring clarification, citing the specific related contract documents requiring clarification.RFIs should only be submitted after performing due diligence to confirm that the contract requirements in question are in fact unclear or otherwise inadequate. RFIs should also include information as to why the General Contractor needs the RFI answered as it may assist with providing a more accurate answer.
Upon receipt of the response to each RFI submitted, coordinate the response with all involved subcontractors to ensure understanding and appropriate action.
vii. As-Built Drawings and Specifications The General Contractor shall update CAD drawings (as-built drawings) and electronic specifications (as-built specifications), at least monthly, to document changes that occur during construction.
viii. General Contractor Payment Requests Update the construction schedules monthly prior to each payment request.
Provide an advance copy of the construction progress report to the GSA.
Provide documentation evidencing the cost of work to be included in the payment request. Allowability of costs shall be in accordance with FAR 31.105 and 31.2.
Before submitting each payment request, meet with the GSA to review the advance copy of the construction progress report. Ensure that the GSA is in agreement as to the progress of the construction work and the value of the work completed.
Based upon the agreed value of work completed, submit monthly payment requests to the GSA.
All payment requests shall be submitted with certified payrolls.
ix. Substantial completion Prior to substantial completion, conduct a pre-final walk-through and inspection with the GSA
x. Punch-List After the GSA certification that the work of each designated portion thereof is substantially complete, coordinate with the GSA in conducting a final inspection and preparing a punch-list documenting remaining work. The contractor is responsible for compiling the Punchlist and updating the Punch list until all items are completed and accepted by GSA.
xi. Commissioning Refer to specification sections in Division 1.
xii. Warranties, Guarantees and Certificates Prepare and submit warranties, guarantees, and certificates, ensuring that the GSA rights and responsibilities are clearly defined. This includes but is not limited to, all warranty/guarantee/certification necessary to verify that the property meets the standards of the documents listed here within. Additionally, the General Contractor shall provide photographs as discussed in Division 1.
xiii. Final As-Built Drawings and Specifications The General Contractor shall prepare and submit final CAD as-built drawings and electronic as-built specifications for review and approval at the completion of the construction.
7.2 CLOSEOUT STAGE
Upon closeout, the General Contractor must provide all related documents to this project. This includes but is not limited to, the release of all claims, warranty information, payment information, and verification that all deficiencies identified during the pre-design/design/construction stages. All deficiencies shall be remedied to the satisfaction of the GSA. This also includes the operations and maintenance (O&M) and equipment start-up documentation. Additionally, the General Contractor shall provide documentation proving that a certified architect inspected the property verifying that it meets the requirements.
a. Reconciliation The contractor shall provide a final cost breakdown during the closeout stage for each phase as per the P120 breaking out the actual shell and TI costs.
b. Final Project Photographs The General Contractor shall provide before and after photographs of, but not limited to, all deficiencies identified during the pre-design/design/construction stages. Refer to specification sections Division 1.
c. Submittal Review The General Contractor shall review all submittals issued during construction for completeness and accuracy of all documents. The General Contractor shall then submit their comments back to the GSA. The General Contractor shall submit copies of the transmittal cover letters accompanying the comments to GSA. The General Contractor shall keep an accurate log of all submittals. This log shall be cross-referenced to the GSA log for ease of tracking. The General Contractor shall submit their log on a schedule to be set by the respective parties.
d. Review Process The General Contractor and GSA shall maintain a record of all submittals and indicated action taken. The review process will not impose on the reviewer, nor relieve the General Contractor from, the responsibility for errors or omissions, correctness of details or conformity with the construction contract documents. The GSA architect of record shall review all submittals and mark each sheet with one of the following designations:
i. Reviewed: Indicates submittal is in full compliance with contract documents.Work will proceed.
ii. Reviewed as Noted: Indicates submittal has minor corrections, not significant enough to require re-submission. Work will proceed, provided it complies with annotations and corrections.
iii. Resubmit: Indicates another submission is required due to the nature or number of needed corrections. Work will not proceed. Submittal will be revised in conformance with annotations and re-submitted without delay.
iv. No Action: Indicates a submittal is returned for other reasons with an explanation included. No departure from the contract requirements will be made without prior written approval by the CO.
e. Submittals Distribution
i. The distribution of submittals by the General contractor shall be outlined in specification section 01300 -Submittals. The General Contractor will provide the multiple copies required for each submittal for GSA review. The typical distribution of reviewed submittals with related transmittals will be as listed in the chart below. Remaining copies shall go to the General Contractor. A letter of transmittal will be used for this purpose with copies to all parties on the distribution list.
Reviewed Submittal Distribution
AE electronic
GSA COR electronic
GSA PM electronic
CMa electronic
US Courts electronic
USMS electronic
GSA AHJ life safety submittals and shop drawings only electronic
ii. Finish Samples shall be sent to the following parties:
1. US Courts
2. USMS
3. GSA CMa
4. GSA COR
iii. General Contractor Responsibility for Errors and Omissions Per FAR 52.236-23, the (a) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contract shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract, and the Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance of any of the services furnished under this contract. (b) The rights and remedies of the Government provided for under this contract are in addition to any other rights and remedies provided by law. (c) If the Contractor is comprised of more than one legal entity, each such entity shall be jointly and severally liable hereunder.
8. APPENDIX
a. Communication Plan
APPENDIX A - COMMUNICATION PLAN
1. Roles and Responsibilities
1.1. Contractor
The Contractor is solely responsible for the management (planning, supervision and contract coordination), and professional services to meet the requirements of this contract.
A. Management. The Contractor shall provide a single point of contact for interaction with the GSA. This individual shall have legal authority to represent the Contractor.
B. Professional Services. The Contractor shall provide required construction services.
1.2. GSA - Project Manager (PM)
The GSA Project Manager (PM) serves as the primary point of contact for the GSA and client agency. All communication shall be directed through the PM. The GSA PM tracks overall project performance and ensures the project team members know their responsibilities. The PM for this project is:
Melissa Sieg U.S. General Services Administration GSA Caribbean Field Office 150 Carlos F. Chardon Ave, Room 359 Hato Rey, Puerto Rico 00918-1746 o: (787) 274-7476 c: (787) 249-4189 melissa.sieg@gsa.gov
1.3. GSA - Contracting Officer (CO)
The Government's Contracting Officer (CO) has the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The CO will designate to the Contractor in writing the roles and responsibilities of other Government officials as they relate to the execution of this contract. The CO for this project is:
Douglas Tumbrello U.S. General Services Administration Acquisition Management Division Operations Branch C 1 World Trade Center mailto:melissa.sieg@gsa.gov
New York, NY 10007 o: (212) 264-5024 c: (917) 574-3499 douglas.tumbrello@gsa.gov
1.4. GSA - Contracting Officer's Representative (COR)
The Contracting Officer's Representative (COR) may act for the CO within delegated authority limits. Unless otherwise noted, on behalf of the CO, the COR is responsible for the general administration and technical coordination of this project. The COR is the Government's point of contact for post award technical information exchange, design submission reviews, construction inspection/tests, and associated administrative duties. Additionally the COR is the main point of contact for coordination of the security clearance process. The COR for this project is:
Richard Kurrasch U.S. General Services Administration GSA Caribbean Field Office 150 Carlos F. Chardon Ave, Room 359 Hato Rey, Puerto Rico 00918-1746 o: (787) 766-5388 c: (787) 403-7450 richard.kurrasch@gsa.gov
1.5. GSA - Building Manager (BM)
The Building Manager (BM) is the building point of contact for site visits, shutdowns, and other coordination activities that may be required within the building. All coordinations must be reported to the GSA PM, CS, and COR through written correspondence. Any email communications from the contractor to the BM shall cc the GSA PM, CS, and COR.
Vanessa Borges-Arroyo, MPA Building Manager, Hato Rey Complex GSA Caribbean Field Office 150 Carlos F. Chardon Ave, Room 359 Hato Rey, Puerto Rico 00918-1746 c: (646) 455-7195 vanessa.borges-arroyo@gsa.gov
1.6. GSA - Building Manager Supervisor
The Building Manager Supervisor is an additional point of contact for site visits, shutdowns, other coordination activities that may be required within the building.
mailto:douglas.tumbrello@gsa.gov mailto:richard.kurrasch@gsa.gov mailto:vanessa.borges-arroyo@gsa.gov
All coordinations must be reported to the GSA PM, CS, and COR through written correspondence. Any email communications from the contractor to the Building Manager’s Supervisor shall cc the GSA PM, CS, and COR.
Victor Ruiz Senior Property Manager GSA/PBS Caribbean Service Center GSA Caribbean Field Office 150 Carlos F. Chardon Ave, Room 359 Hato Rey, Puerto Rico 00918-1746 o: (787) 274-7467 c: (787) 360-5104 victor.ruiz@gsa.gov
1.7. GSA - Contracting Specialist (CS)
Assists the Contracting Officer in their duties. The CS for this project is:
Erik Lemons U.S. General Services Administration Public Buildings Service, Northeast Region 1 World Trade Center, 54th Floor New York, NY 10007 o: (212) 264-2329 c: (347) 443-4563 erik.lemons@gsa.gov
1.8. GSA - Fire & Life Safety Coordinator
The Fire & Life Safety Coordinator who will be reviewing the submissions for this project is:
Jeffrey Cisney U.S. General Services Administration 1 World Trade Center
NEW YORK NY 10048-0000
o: (212) 264-1446 jeffrey.cisney@gsa.gov
1.9. GSA - Electrical SME
The Electrical SME who will be reviewing the submissions for this project is:
mailto:victor.ruiz@gsa.gov mailto:erik.lemons@gsa.gov mailto:jeffrey.cisney@gsa.gov
Eric Sanchez Regional Chief Architect Office U.S. General Services Administration 1 World Trade Center
NEW YORK NY 10048-0000
o: (212) 264-3576 c: (347) 267-9328 eric.sanchez@gsa.gov
1.10. GSA – Mechanical SME
The Electrical SME who will be reviewing the submissions for this project is:
Robert Wager Regional Chief Architect Office U.S. General Services Administration 1 World Trade Center
NEW YORK NY 10048-0000
o: (212) 264-3520 c: (347) 326-4975 robert.wager@gsa.gov
1.11. GSA Architect (Dattner Architects, PC), Principal-in-Charge
The GSA (Dattner) Architect PIC is the primary point of contact for the architect.
Paul Bauer 1385 Broadway, 15th Floor New York, New York 10018 o: (212) 247-2660 o: (212) 589-7015 c: (917) 757-1834 pbauer@dattner.com
1.12. GSA Architect (Dattner Architects, PC)
The GSA (Dattner) Architect is the primary architect developing the DIDs for the project.
Jon King 1385 Broadway, 15th Floor New York, New York 10018 o: (212) 247-2660 d: (212) 589-7043 pbauer@dattner.com mailto:eric.sanchez@gsa.gov mailto:robert.wager@gsa.gov mailto:pbauer@dattner.com mailto:pbauer@dattner.com
1.13. GSA Construction Manager as Advisor (CMa)
The Construction Manager as Advisor is responsible for scheduling regular bi-weekly meetings as well as formulating the agenda’s, meeting minutes, and action items. The CMa shall assist with reviews for submittals, shop drawings, modifications, close out documents, etc. The CMa will also act as the commissioning advisor (CxA) during facility equipment commissioning.
CBRE/Heery
1.14. GSA Commissioning Agent (Cx)
CBRE/Heery
1.15. Client Agency Point of Contact (POC) - U.S. Courts
Kelly McQuillan Assistant Circuit Executive for Space and Security United States Courts for the First Circuit John Joseph Moakley United States Courthouse One Courthouse Way Boston, MA 02210 o: (617) 748-9327 c: (617) 947-8958 kelly_McQuillan@ca1.uscourts.gov
Michelle Torres-Mora, PMP, LEED AP BD+C Architect & Project Manager US. District Court-District of Puerto Rico t: (787)772-3030 c: (787)306-9206 michelle_torres@prd.uscourts.gov
1.16. Client Agency Point of Contact (POC) - U.S. Marshals Service
George Rodriguez Judicial Security Inspector District of Puerto Rico d: 787-754-4251 c: 939-475-9803 o: 787-766-6000 George.Rodriguez@usdoj.gov
Michael Fanning Senior Program Manager mailto:kelly_McQuillan@ca1.uscourts.gov mailto:michelle_torres@prd.uscourts.gov mailto:George.Rodriguez@usdoj.gov
United States Marshals Service Management Support Division Office of Construction Management Contractor | PSS, Inc.
c: (202) 379-6416 Michael.Fanning@usdoj.gov
Saif B. Syed United States Marshals Service Security Specialist Judicial Security Division Office of Security Systems c: 202-815-4016-Cell o: 703-740-8267– Office said.syef@usdoj.gov
1.17. Client Agency Point of Contact (POC) - Federal Protective Services
Andres Santana Inspector o: (787) 766-5395 c: (787) 930-4353 Andres.Santana@fps.dhs.gov
Wilbur Cesar B Calope Technical Security Program Manager Federal Protective Service, Region 2 U.S. Department of Homeland Security o: (646)589-6035 C: (347)-638-3087 Wilbur.B.Calope@fps.dhs.gov
2. Correspondence
All project correspondence not relating to proposals or contractual issues shall be directed through the GSA Project Manager.
Send the proposal directly to the Contracting Specialist. Original correspondence which addresses changes to the contract, obligation of funds, requests for equitable adjustments and other contracting issues, shall also be sent directly to the Contracting Specialist.
The contractor shall not directly contact the client agency unless permission is granted by the GSA Project Manager.
mailto:Michael.Fanning@usdoj.gov mailto:said.syef@usdoj.gov mailto:Andres.Santana@fps.dhs.gov mailto:Wilbur.B.Calope@fps.dhs.gov
3. Project Meetings
3.1. Preconstruction Meeting after award – half day meeting up to 4 hours - Location
Hato Rey, PR (Core team members required) (CONSTRUCTION).
3.2. ePM Training - Training shall take place over one full day in Hato Rey, PR or via videoconference. Training will take place within 20 business days of contract award. Refer to the specification section “Electronic Project Management (ePM) System 013000”.
3.3. Progress Meetings – Shall take place weekly. On site progress meetings shall take place bi-weekly. Additional on site and virtual meetings shall take place as needed. Location – teleconference/meeting space and Hato Rey, Puerto Rico
3.4. Schedule Update Meetings – Monthly meetings held in conjunction with an on site progress meeting. Location - Hato Rey, PR.
3.5. Security Equipment Coordination Meetings - Refer to the specification section “Summary 011000” part “Work by Others”. Location - Hato Rey, PR.
3.6. Risk Management Review Meetings
3.7. Partnering Session 1 - Shall take place no later than 30 days after Notice to
Proceed. Refer to the specification section “Project Management & Coordination 013100”.
3.8. Partnering Session 2 - Shall take place at mid-construction. Refer to the specification section “Project Management & Coordination 013100”.
3.9. Construction Phase CxA Kick-Off Meeting - Refer to the specification section “General Commissioning Requirements 019113”. Location - Hato Rey, PR.
3.10. Pre Demolition Conference: Conduct conference at Project site - Refer to the specification section “Selective Demolition 024119”. Location - Hato Rey, PR
3.11. Project Closeout Conference(s) - Shall take place no later than 90 days prior to the scheduled date of Substantial Completion. Refer to the specification section “Project Management & Coordination 013100”. Location - Hato Rey, PR
3.12. Reconciliation Meetings – via teleconference and/or meeting space as needed to develop the reconciliation breakdown as per the SOW and P120. The contractor is required to break out the TI/shell costs with their initial bids, at substantial completion, and with the final closeout.