About this file
This federal solicitation requests quotes for upgrading video walls at two buildings on an Army base in Germany. The U.S. Army's Washington Headquarters Services seeks to upgrade video walls in the plenaries of Buildings 105 and 106 at the George C. Marshall Center in Garmisch-Partenkirchen, Germany. The work includes installing new equipment that is Trade Agreements Act certified and compatible with the base's existing Crestron environment. All equipment must meet the same standards as current computer and electronic gear and replicate the existing conference room configurations. The firm-fixed price contract requires completing all work by January 25, 2022 and complying with German law. Quotes are due under full and open competition from all responsible sources registered in the System for Award Management and Wide Area Workflow payment systems, with no set-asides applying since the work is overseas.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is the follow ing: Include 'Attachment 10 - OCI Certification'. This attachment is the Organizational Conflict of Interest information and template for an Offeror's use to complete as one of the required documents to submit w ith Volume I of an Offeor's quote. All other terms and conditions remain.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jul-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X HQ084721Q0003
X 9B. DATED (SEE ITEM 11)
08-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Jul-2021
CODE
GCMC
ACQUISITION DIRECTORATE, GERMANY, UNIT 24502,
053-4502
APO AE 09053-4502
HQ0847 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
HQ084721Q0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 SOW_Video Wall
Display_30June2021
30-JUN-2021
Attachment 2a As Built Bldg 105_False Floor
10-JUN-2021
Attachment 2b As Built Bldg 105_Longitudanal C-C
10-JUN-2021
Attachment 2c As Built Bldg 105_2nd Flr Electrical
10-JUN-2021
Attachment 2d As Built Bldg 105_Second Floor
10-JUN-2021
Attachment 2e As Built Bldg 105_Section 1-1, 2-2
10-JUN-2021
Attachment 2f As Built Bldg 105_3rd Floor
10-JUN-2021
Attachment 2g As Built Bldg 106 10-JUN-2021 Attachment 2h As Built Bldg
106_Electrical
10-JUN-2021
Attachment 3 Video Wall Project 10-JUN-2021 Attachment 4 Q&A_Site
Visit_06May2021
10-JUN-2021
Attachment 5 Pricing Template 10-JUN-2021 Attachment 6 Past Performance
Questionnaire
10-JUN-2021
Attachment 7 Questions Template 10-JUN-2021 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 SOW_Video Wall
Upgrade_14 July 2021
14-JUL-2021
Attachment 2a As Built Bldg 105_False
Floor
10-JUN-2021
Attachment 2b As Built Bldg 105_Longitudanal C-C
10-JUN-2021
Attachment 2c As Built Bldg 105_2nd Flr Electrical
10-JUN-2021
HQ084721Q0003
Attachment 2d As Built Bldg 105_Second Floor
10-JUN-2021
Attachment 2e As Built Bldg 105_Section 1-1, 2-2
10-JUN-2021
Attachment 2f As Built Bldg 105_3rd Floor
10-JUN-2021
Attachment 2g As Built Bldg 106 10-JUN-2021 Attachment 2h As Built Bldg
106_Electrical
10-JUN-2021
Attachment 3 Video Wall Project 10-JUN-2021 Attachment 4 Q&A_Site
Visit_06May2021
10-JUN-2021
Attachment 5 Pricing Template 10-JUN-2021 Attachment 6 Past Performance
Questionnaire
10-JUN-2021
Attachment 7 Questions Template 10-JUN-2021 Attachment 8 Vendor Questions & Govt
Answers
14-JUL-2021
Attachment 9
Attachment 10
Plenary 105 Current & Estimated Configuration OCI - Certification
14-JUL-2021
30-JUL-2021
(End of Summary of Changes)