Electrical Questions and Answers 5 Aug 20.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Building 1 Electrical Replacement Contract
Solicitation number
HQ072720R0005
Issued by

About this file

This document contains questions and answers related to a federal solicitation for an electrical replacement contract at a Defense Microelectronics Activity facility. Key details include that the solicitation requires replacement of all electrical systems as shown on technical drawings by August 10, 2020, with the general contractor responsible for design, permitting, and fees. The project scope will be determined during design, though it is expected to include generator, fixtures, and ADA upgrades. Work can be phased concurrently but the facility must remain operational with the exception of scheduled shutdowns. Prevailing wage rates apply and bonds will be required after design completion.

View the file

Other files

File Type Posted
Amendment 0001.pdf PDF
Electrical Questions and Answers 30 Jul 20.xlsx XLSX spreadsheet
HQ072720R0005 Amendment 1.pdf PDF
Site Visit Attendees.docx DOCX document
CA30300007 24 Jul 20.pdf PDF
Electrical Questions and Answers 28 Jul 20.xlsx XLSX spreadsheet
WD 2015-5631.pdf PDF
Site Visit Instructions.docx DOCX document
Contract Data Requirements List.pdf PDF
NDA for Technical Exhibit.docx DOCX document
HQ072720R0005.pdf PDF
PWS 20-0F9 Bldg1 Electrical Upgrade PO Approved.docx DOCX document
EVALUATION FACTORS.docx DOCX document
INSTRUCTIONS TO OFFERORS.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

NumberQuestionAnswer
1Confirm RFP Response due date.Monday 10 August, 2020 at 12:00 PM PST. Please make sure you also acknowledge any amendments to the solicitation.
2Confirm that the General Contractor will be responsible for all required Architectural, Structural, and Electrical design.Yes, this project is for a complete electrical replacement system which will include Architectural and Structural components to complete the electrical work.
3Provide a project scope letter stating any anticipated work beyond the electrical scope shown on E-1 & E-2 - i.e.: generator pad/enclosure, new fixtures, ADA upgrades.A project scope letter will not be issued, but details relating to the scope will be addressed after the design phase. The purpose of the discovery/investigation during the design is to determine the boundaries of the scope for the project.
4Will the General Contractor be responsible for plan review and plan check fees?All fees will be the responsibility of the GC. Historically the County of Sacramento does not recognize this facility as county property so we have not been able to use the county for permitting. The Gov't will determine the AHJ during the design phase.
5Provide anticipated times that shutdowns can occur for cut-over, new equipment tie-ins, testing, and inspections.This is dependent on the type of shut-down/tie-in. The Gov't recognizes that there will be shutdowns due to tie-in's and other activities, but the type, frequency and duration will be developed in the project implementation plan and approved by the Gov't. There are some systems that must remain operational 24-7 like, security, life safety and IT.
6Confirm anticipated wage rates - Prevailing or shop rate?DMEA considers this a nonconstruction contract involving some construction work. Amendment 1 includes Construction Wage Rate Requirements clauses and General Wage Determination CA30300007 for any applicable construction work.
7Will the electrical upgrades be phased or can the installations be scheduled to happen concurrently?Phases can be scheduled concurrently, but the facility must stay operational at all times with the exception of the scheduled shut-downs.
8Project valuation will require the building/site to be fully ADA compliant through Sacramento County, please confirm that the building is fully compliant in current condition.The building is not fully compliant with ADA as it is a federal manufacturing facility. See Question 4 for additional information
9Confirm Sacramento County will be the overseeing jurisdiction for plan review, permitting, inspections, and final approval.See Question 4
10Confirm all work shown on sheets E-1 & E-2 is to be new, none will be existing to remain.In general yes. Most of the equipment is old, but there are a few components that could be re-used. The Gov't would like to re-use those components if they meet the requirements and code for this project.
11Confirm that there will be a due diligence period allowing further investigations between the 'Class 4' and 'Class 1' estimates.Yes, that should be part of the design phase.
12Confirm utility connection fees are to be paid by Owner and excluded by General Contractor.All fees will be the responsibility of the GC. These will be identified after the design.
13Is there an engineer's estimate for the project?Yes, but that will not be available at this time.
14What is the current budget for the project?This will not be answered at this time.
15What is the bonding requirement?Amendment 1 adds clauses for Performance and Payment bonds. These bonds will be required after completion of the Design phase and before replacement work begins. The percentage required will be negotiated in accordance with FAR clause 52.216-5 , Price Redetermination-Prospective.
16Will other electrical drawings be provided at the pre-bid walk or after the bid is awarded? For example, panel schedules, feeder schedules, load calculations, etc.?No additional documentation with the exception of these questions will be provided prior to the due date of the proposals. At the time of award, all documents related to the electrical systems will be shared with the contractor.
17Are all transformers in the building being replaced?Yes
18Is the technical exhibit (E1 & E2) the current as-built drawings of the building?Yes, however there is currently a project underway that will create minor changes the drawings
19Are there any working days or hours restrictions during construction?Yes, general working hours are 0600-1800, Monday-Friday. Work outside of these hours will have to be scheduled and approved by the Gov't
20Is there a maximum outage time, per outage?No, see Question 5
21Is storage space available at the job site for equipment? If not, can shipping containers be kept on-site?Yes, there will be space provided to the contractor for containers. But this space is limited so most major deliveries of equipment will need to be done on the day of installation.
22Are any of the contractor's staff (engineers, admin, construction, etc.) required to be unionized? If so, which staff must be unionized?Because this contract is not considered a Large-scale construction project, there is no requirement for a Project labor agreement.
23Regarding the Item #0001 A/E design, should we include all construction admin/management services and any other qualifiers as needed?Yes, see Question 2
24Most engineering firms are not able to bond an electrical project of this size, so would it be acceptable to have the general contractor possessing the C-10, and subcontractor being the engineering firm?Performance and payment bonds will only be required after completion of the Design phase and before replacement work begins. The percentage required will be negotiated in accordance with FAR clause 52.216-5 , Price Redetermination-Prospective.
25Asbestos?None, but a report can be distributed to the GC at the time of award.
26Is there any redundancy right now?Currently there is no redundancy. It would be ideal to have redundancy but physical space will greatly limit the ability.
27Code upgrades required?This is an old repurposed Air Force flight simulation building. This building was never meant for the manufacturing of semiconductors and other microelectronic engineers efforts. All must meet current codes.
28What is left from old system?To be determined by the GC and the Gov't during the investigation part of the design.
29Additional documents?You get everything we have at award, see Question 16.
30Utility fees part of the projectYes, see Question 12
31Load counts?You get everything we have at award, see Question 16.
32Have we metered any of the load?Yes, you get everything we have at award, see Question 16.
33Escort requirementsNo escorting will be performed by the Gov't. All contractor personnel and their subcontractors must be cleared through a background check.
34Rack cabling?Low voltage wiring is not part of this effort, however the contractor will need to work around the existing cables.
35Contract TypeThe contract type is a fixed-price contract with prospective price redetermination. It provides for a firm fixed price for an initial period of contract deliveries or performance; and prospective redetermination, at a stated time or times during performance, of the price for subsequent periods of performance. The prospective redetermination will occur after completion of the design phase. See clause 52.216-5 in Section I for more information.
36What is the line item for Data?Exhibit A is the Contract Data Requirements List. It lists the data that the Contractor is responsible for delivering to the Government. Line item 0007, not separately priced, is for this data.
37Preferred location for switch gear?The Gov't has set aside some space near the existing switchgear. This should be adequate for the new equipment, but that will need to be verified during the design. Physical space is very limited, and the Gov't does not want transformers near sensitive equipment.
38Cameras after award?No, the Gov't will take any photos needed and provide to contractor after security review.
39Walkie Talkies allowed?Yes, the Gov't recognize the need to communication. Approved walkies will be allowed as well as some cell phones used by main POC. This will be very limited and has additional restriction.
40Specific ManufacturerNo, open for discussion, Eaton and Square-D are used in some of the newer equipment
41Everything replaced?There are newer sections. Some of the Cleans Room have more current equipment. For instance, ARMS IV is 7 years old. Contractor responsible for getting rid of old equipment, see Question 10
42No capacity w/ current switchgearYes, see the single line drawings.
43Site work also included?Yes
44Is one of the SMUD transformers not serviced?Yes. SMUD has used one of the transformer as a "pull-box." This will definitely need to be addressed during the design.
45Is there a second utility?No second utility SMUD services almost all of the Sacramento County. Gov't would ideally like a second generation source, but not part of this project.
46Power monitoring is a big dealPower metering and monitoring will need to be part of the design.
47We have a natural gas generatorCurrent generator is natural gas. There are advantages and disadvantages to this source.
48Want power centralized?Distribution and branch panels should be consolidated as much as possible.
49Are there critical loads?Yes, essentially the entire facility, but security, IT and Life Safety are critical loads.
50Work required in service chassis of clean room?There will be some work required in the clean room services chassis.
51What is the purpose behind line item 0006?The purpose behind line item 6 was to cover the fees needed to get the project started (Permits if needed, bonds, etc.)

The solicitation contains a provision in Section L, FAR 52.204-22, Alternative Line Item Proposal, which states the following:

Alternative Line Item Proposal (Jan 2017)

(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror’s practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.

(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.

52Please, define “data” in items #7If you look at the Performance Work Statement, you will see references to CDRL A0XX. This corresponds to Exhibit A, Contract Data Requirements List (CDRL). This is the data. Because we are asking for this data, we need a contract line item for it.
54Please provide Class 1 and Class 4 Cost Estimate Rate Sheet.There is no specific format required for the Class 1 and Class 4 Cost Estimate Rate Sheet. In addition, it is up to the proposer to propose the rates.
55What forms need to completed?Complete SF 33, Page 1, blocks 12-18.

Complete 52.204-8 (page 45 of SF 33) and 252.204-7007 (page 49 of SF 33) as applicable

Acknowledge receipt of amendment 0001 by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment;

(b) By acknowledging receipt of this amendment on each copy of the offer submitted;

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.

Submit a completed electronic copy of SF 330 Part I Include the firm's DUNS number in SF 330, Part I, Section H.

Submit a completed electronic copy of SF 330 Part II for the firm and all consultants.