This solicitation seeks proposals for a Facilities Services Directorate Job Ordering Contract to provide construction services at the Pentagon and other DoD facilities in the National Capital Region. The contract will have a total duration of 5 years with a 1-year base period and four 1-year option periods. The maximum ordering threshold is $100 million and minimum guarantee is $250,000 per period. This procurement is 100% set aside for HUBZone small businesses under NAICS code 236220. Proposals are due by April 22, 2019. A mandatory site visit will be held on February 25, 2019 to tour locations associated with this solicitation. The resultant contract will be an indefinite delivery/indefinite quantity type with requirements being definitized through firm-fixed-price task orders.

Master Answers Sheet

View the file

Other files

File Type Posted
J7_Revised_SOW_for_Paving_of_the_SAL__rev_1_032119.docx DOCX document
J18_Release_Letter.pdf PDF
J4_Past_Performance_Data_Sheet_rev_1.docx DOCX document
J16_VA190134_01-04-2019_Residential.pdf PDF
J13_VA190001_01-04-2019_Heavy_Dredging.pdf PDF
J2_Proposed_Coefficients_v2.xlsx XLSX spreadsheet
J19_JOC_Pre-Bid_Site_Visit_Sign-In_Sheet.pdf PDF
J12_Technical_Approach_Submission_Template_rev_1.docx DOCX document
J15_VA190013_01-04-2019_Building.pdf PDF
J6_Key_Personnel_Qualifications_Sheet_rev_2.docx DOCX document
HQ0034-19-R-0057-0002.pdf PDF
J17_VA190035_02-22-2019_Heavy_Sewer_Water_Line.pdf PDF
J14_VA190103_01-04-2019_Highway.pdf PDF
HQ0034-19-R-0057_0001.pdf PDF
SOW_Attachments.zip ZIP file
J10_DC180002_10-19-2018_Building.pdf PDF
J12_Technical_Approach_Submission_Template.docx DOCX document
J2_JOC_Coefficients_and_Seed_Breakdown.xls.xlsx XLSX spreadsheet
J4_Past_Performance_Data_Sheet.docx DOCX document
J5_Contractor_Performance_Evaluation_Survey.doc DOC document
HQ0034-19-R-0057.pdf PDF
J11_DC180003_08-03-2018_Residential.pdf PDF
J6_Qualifications_Sheet.docx DOCX document
J7_FSD_Statement_of_Work_for_Paving_of_the_SAL.pdf PDF
J9_DC180001_10-19-2018_Heavy_and_Highway.pdf PDF
J1_Const_Mngmnt_Gen_Reqts_V6.pdf PDF
J3_Client_Authorization_Letter.docx DOCX document
J8_Questions_Sheet.doc DOC document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FACILITIES SERVICES DIRECTORATE JOB ORDERING CONTRACT

REQUIREMENT

Questions

HQ0034-19-R-0057

RFP section, paragraph, and page number/Question
Answer
1.
Statement of Work, Page 1 of 12. Item 1.4 Period of Performance: This paragraph establishes a period of work between Friday 1800, and Monday 0500. Can this road be close completely for the asphalt milling, or need to be shut down partially?
Yes, this road can be completely shut down for the asphalt milling. The contractor must submit a Project Coordination Plan (PCP) that includes the dates of the requested shut down.
2.
Statement of Work, page 1 of 12. Project Location: Is the RDF Access Ln, under VDOT’s right of way?
No, it is not under VDOT’s right of way.
3.
Statement of Work, page 1 of 12. Project Background: mentions that “pavement is beginning to show signs of asphalt deterioration”. How will be addressed if the sub base / base is already damaged and needs to be restored before new asphalt is set in place.
Contractor proposal to assume that sub base/base is not damaged and will not require any restoration. Unforeseen site conditions shall be handled through the same process described in Section C, section 1.5.5 Task Orders.
4.
Statement of Work: 2.4 Above Ground Facilities: This paragraph indicates above ground facilities will require coordination for removal and reinstallation. Specific case is the security vehicle barrier. Will this item require to remove the concrete base / supports to complete the work?

Please specify type of security vehicle barrier?

These are mobile security barriers that are placed in the area at the end of the security screening area before the security gate. These devices will be removed by the Pentagon Force Protection Agency before the work starts and returned after the work completes on every weekend the work is being performed. This needs to be reflected in the PCP by the contractor. None of the concrete barriers shall be removed.

5.
Statement of Work, page 4 of 12. Measurements and Quantities: Please confirm that the quantities included under this paragraph are the basis to price the Seed Project.
Yes, the quantities are correct and the basis to price the Seed Project.
6.
Solicitation: Paragraph 1.5.5 task Orders: Is this Seed Project to be considered under 1.5.5.1 Design-Build Construction, or 1.5.5.2 Bid-Build Construction?
This is a bid-build project..
7.
Solicitation: Section H – Special Contract Requirements: Step 4 Contractor Submits Proposal: Price Proposal: This paragraph requests that the price proposal shall be submitted in MS Excel format. ‘Please see Section C -Statement of Work / section 5 for a detailed guidance on developing price proposals”. This section 5 is not included in the Statement of Work.
Section should read “Please See Section C – Statement of work/ section 1.5 Contract Price Book, Coefficient, Task Orders, and Pay Limits for a detailed guidance on developing price proposal.
8.
Do the concrete repairs, at any time during the IDIQ, need to be performed utilizing the Pentagon Concrete Mix Design?

If a Task Order requires historic/specific Pentagon Concrete Mix Design, the individual task order will specify that requirement. Any concrete mix that is specific to the Pentagon will be priced as NPI.

9.
Solicitation Page 78 of 83: Volume IV: Price Proposal. Pricing Sheet and Coefficients page are not included on the FSD Statement of Work for Paving of the SAL
For pricing, use J2_JOC_Coefficients_andSeed_Breakdown.xls in the sheet labeled “Seed Price Breakdown”.
10.
Can an extension on RFI deadline be granted?

Yes, The deadline for the solicitation has been extended to April 22, 2019 by 5 PM EST

11.
Will photos of the areas walked during the pre-proposal meeting be distributed in an amendment?

No photos will be provided. Offerors may price the Seed Project according to the information provided in RFP HQ0034-19-R-0057 and information obtained from the pre-bid site visit.

12.
The seed project location has existing jersey barriers. Do these jersey barriers need to be relocated during the project and re-installed afterword’s?
Refer to section 2.4 A. on Page 3 of J7_FSD_Statement_of_Work_for_Paving_of_theSAL
13.
The road leading to the RDF loading dock needs to be repaved. Will this road need to remain accessible for deliveries during the repaving activities?

The area to be paved is detailed in J7_FSD_Statement_of_Work_for_Paving_of_the_SAL. While the work takes place over a weekend, the SAL will remain shut for commercial traffic. The work schedule and sequencing, and any all other items that require coordination, must be reflected in the PCP by the contractor.

14.
Material deliveries to the building are noted to be directed through the RDF loading dock. Can deliveries for the building be delivered through A&E Drive as well?

No

15.
On page 78 of 83 of the Solicitation, Volume I: Administrative, it says that the cover letter shall identify all enclosures being transmitted and shall be used only to transmit the proposal and shall include no other information; however, we are required to submit our Tax ID number, CAGE Code and DUNS number. Can we include this information in the cover letter? If not, shall we submit this in a separate document entitled Other Administrative Information?

Page 76 of Section C states: “The following are further descriptions of the information that shall be provided with the proposal. Administrative – Cover Letter, Tax Identification Number, CAGE Code and DUNS Number”. Include the Tax Identification Number, CAGE Code, and DUNS Number on the Cover Letter.

16.
This project requires a Bid Bond; however, it does not say where to include this. Should we submit our Bid Bond in Volume I – Administrative?

Each T/O will require pay and performance bonds

17.
On page 81 of 83 of the Solicitation, under Section 2(b), it says that our past performance proposal must address past performance in delivering up to 5 projects . . . concurrently and similar in scope to the effort required by the SOW; however, on page 78 under Volume III: Past Performance, it requires us to use the Past Performance Data Sheet and says that we should submit up to 3 projects. Please clarify whether we can submit up to 3 projects or 5 projects?

Up to 5 projects

18.
When will the list of attendees from the site visit be released?
The list will be release in the amendment
19.
Can you provide information the incumbent and the incumbent contract?
There is no incumbent
20.
In Section M: M-4 Evaluation Factors it states “(b) The Offeror’s past performance proposal must address past performance in delivering up to 5 projects that

could range between $2,001.00 to $499,999.99 concurrently and similar in scope to the effort required by the SOW” but in Volume II: Technical Proposal it states “Offeror shall submit a Past Performance Data Sheet, (Solicitation Attachment Past Performance Data Sheet), for up to three (3) Government or commercial contracts for services directly related or similar to the scope of work described in the SOW.” Please clarify if we need to submit 3 or 5 projects with the proposal.

See answer to RFI# 17

21.
In section 52.228-1 BID GUARANTEE I referenced the bid guarantee information in regard to a 20% bid guarantee being provided in the cost proposal. Please clarify the following: upon award does a blanket bond of $20M need to be provided or will bonds need to be provided on a per task order basis?
See answer to RFI #16
22.
SF1442 (not referenced)

Where should the SF 1442 go?

Completed 1442 should be send to Edgar.L.Moso.civ@mail.mil and Stephanie.a.essiam.civ@mail.mil or see Block 10 of 1442

23.
SOW, Attachment C

Does Past Performance have to reflect experience in SEED SOW (Milling and Paving) or SOW described in Section C (Tenant space renovations and build-outs)?

Past Performance can reflect your overall experience with the Job Ordering Contract.

24.
Section C (page 7)

Section C shows Key Personnel to include PM, DOR, QFPE, SSHO, QCM, Site Super, Scheduler, LEED professional, Mitigation Supervisor. Section L only shows Program Manager. Please clarify which Key Personnel to include.

Program Manager

25.
J4 (Solicitation Attachment)

In Block 12 of Past Performance Data Sheet Attachment J4, it states “Relevance shall address Pentagon Snow and Ice Removal Services”. However, this does not coincide with SOW discussed in Section C or in Statement of Work Attachment J7 for the Seed Project. Please clarify.

Should state: “Facilities Services Directorate Job Ordering Contract”

26.
Section B (page 3)

The CLINS shown on the Section B do not coincide with Attachment J2 JOC Coefficients. Please clarify.

Offerors are not required to submit a completed Section B.

27.
SF 1442 (not referenced)

Please clarify statement "… limited to HUBZone firms in the geographical area serviced by the following states…". Does the home office that counts as the HUBZone qualifier need to be in these states, or can a regional office be in these states?

The office whether home office or regional office has to be certified as a HUBZone to those geographical areas (Maryland, Virginia, Washington DC)

28.
Section B (page 3)

How are the prices for CLINS 0001 - 0005 to be calculated?

See answer to RFI #26

29.
1.5.4 (page 9)

Please verify that engineering and design should be included in the coefficient.

The cost of Engineering and Design, including the LEED Professional and QFPE, shall be applied to the Design Coefficient.

30.
1.6 Key, Personnel Chart (page 10)

Please confirm that the Mitigation Supervisor be an ICD 705 certified installer.

The Mitigation Supervisor no longer needs to be ICD 705 certified installer. .

31.
J2 (Solicitation Attachment)

Contains spaces for JOC coefficients, Base plus Option periods 1-4. The option to extend lists coefficients "equal to …" Option Periods 4-9. Please clarify.

For the purpose of this solicitation, we will assume that your proposal for FAR 52.217-8 clause will be equal to the coefficients in Option Year 4 in our evaluations. The terms under this clause still applies.

32.
Can we have another site visit for the subcontractors
No
33.
Please see the attached Ariel plan.

Do we only Mill/pave where the RED is shown

Yes.

34.
Do we only Mill/pave existing asphalt where the RDF

Is.Just around the Tent and the adjacent parking area

PRK26-01

The area highlighted in A12-Loc of Seed Project 5-23-2018 highlights the area to be milled and paved in red.

35.
Are we to use the existing EXCELL spread sheet

that was provided with the solicitation documents

Offerors should use the revised J2 Excel sheet provided in the RFP.

36.
According to the SOW, WE DO NOT REPLACE

Any existing concrete, unless it is damaged by our operation Concrete work is not included in the scope of work for the Seed Project.

37.
Will the SEED project require design submittals, plans Reference# page#8 of 12, in the SOW section “C.

No .

38.
Will the metal road plate currently in the SAL be removed by the Government prior to the paving work? And what is the existing condition under the road plate?
The metal road plate shall be removed by the Government prior to the start of work. The contractor is to assume that the base/sub-base is a suitable state to receive asphalt. Unforeseen sight conditions shall be handled through the same process described in Section C, section 1.5.5 Task Orders.
39.
Are the asphalt patches within the concrete apron included in the scope?
Asphalt Patches within the Concrete apron are excluded from the scope of work.
40.
Section L, L-3, page 75

Under the Key Personnel heading, the RFP states , “To be eligible for contract award, Offerors must submit resumes, completed qualification sheet, and commitment letters of their key personnel on the proposal due date.” Should this information be included within a specific volume or provided as a separate and distinct document outside and in addition to the four volumes required?

Please provide as a separate and distinct document outside and in addition to the four volumes.

41.
Section L, L-3, page 75

Under the Key Personnel heading, the RFP states that “To be eligible for contract award, Offerors must submit resumes, completed qualification sheet, and commitment letters of their key personnel on the proposal due date.” However, requirements are only provided for one position, Program Manager. Furthermore, M-2 only specifies evaluation criteria for the Program Manager. Are offerors only required to submit a resume, completed qualification sheet, and commitment letter for the Program Manager position?

Yes

42.
Section L, L-3, page 76

Volume I: Administrative requires offerors to include a cover letter: “The cover letter (letter of transmittal) shall identify all enclosures being transmitted and shall be used only to transmit the proposal and shall include no other information.” Additionally, the administrative volume also requires offerors to submit a TIN, DUNS and CAGE. Since this information is not to be included in the Cover Letter, should offerors include this information by submitting a SF1442 with Volume I or is another format preferred?

See RFI Question 15

43.
Section L, L-3, page 76

Should offerors include Representations and Certifications within their proposal response? If so, should they be included within Volume I: Administrative1?

Yes, fill out Section K FAR 52.212-3 ALT I

44.
Section L, L-3, page 76

Volume II: Technical Proposal, paragraph 2) specifies proposal length and format to include ”Each page shall be 8 ½ x 11 inches, double-spaced, no smaller than 12 point font, with one (1) inch margin requirements.” Please confirm that it is acceptable for the headers/footers of Volume II documents to include single-spaced text and a smaller font size than 12 point font.

No

45.
Section L, L-3, page 76

Volume II: Technical Proposal, paragraph 2) specifies proposal length and format to include ”Each page shall be 8 ½ x 11 inches, double-spaced, no smaller than 12 point font, with one (1) inch margin requirements.” Is it acceptable for graphics to be provided as 10 point font and single spaced to aid in legibility?

No

46.
Section L, L-3, Subfactor A, page 77

In regards to Volume II Technical Proposal, Subfactor A – Technical Capability and Approach, should offerors assume the use of J12, Technical Approach Submission Template to respond to this subfactor? If so, is this template required to be double-spaced to match the required formatting of Volume II? Note the attachment J12 provided uses 11 point font and is single-spaced.

Please follow the template and the required formatting. Please change it to 12 point font.

47.
Sections L (page 78) and M (page 81)

The evaluation criteria (Section M) conflicts with submission criteria (Section L) for Volume III Past Performance. Section L states to include a maximum of 3 contracts while Section M references up to 5 total projects for the prime contractor and one (1) for each subcontractors. Please confirm offerors should submit a total maximum of 3 contracts for the prime and subcontractors?

See answer to RFI question #17

48.
Section J (page 68), Section L, L-3, Past Performance (page 78), Section M, M-4 (page 81)

Section L references the Past Performance Data Sheet, shown as Attachment 4 in Section J. Section M references Past Performance Data Sheet (Attachment 7). Please confirm offerors should use Attachment J4.

Confirmed

49.
Attachment J4, Past Performance Data Sheet

Attachment J4 includes reference to Pentagon Snow and Ice Removal Services within block 12. Please confirm this scope of services should be disregarded or removed for this JOC.

See RFI # 25

50.
Section L, L-3, Past Performance (page 78), Attachment J4

Section L states “Offerors shall submit no more than 1 page for each past performance data submission, Solicitation Attachment Past Performance Data Sheet.” However, directions within Attachment J4, block 14 state “Provide a summary description of contract work, not to exceed two pages in length…. Attach the explanation to this form.” Is the page limitation for each contract one total page or one Past Performance Data Sheet PLUS two attachment pages?

Keep the past performance data sheet at 1 page maximum. The summary which is separate from the data sheet, keep it at 2 pages maximum.

51.
Section M, M-4 (page 81), Section J

Paragraph M-4 (2) Past Performance (d) references a Past Performance Questionnaire (Attachment 6) and a Past Performance Data Sheet (Attachment 7). These attachment references do not match Section J. Please confirm these attachment references should be Attachment J5 Contractor Performance Evaluation Survey and J4 Past Performance Data Sheet, respectively?

Confirm Section J Exhibit Attachments J4 & J5 are correct.

52.
Section L, L-3, Volume IV Price (page 78).

Volume IV: Price states to acknowledge all amendments. Should offerors submit the SF1442 along with SF30s in Volume IV to acknowledge amendments or is a different method preferred?

See Block 19 on SF1442 to acknowledge amendments

53.
SF1442 (page 1), Section K (page 69), Attachment J1 - 7.0 Proposal Requirements (page 47 of 61)

Block 13, Item B is marked that an offer guarantee is not required and there is no mention of a bid guarantee in Section L or M of the solicitation. However, Section K - Representations, Certifications and Other Statements of Offerors states, “Bid guarantee shall be submitted electronically as part of Volume IV: Price Proposal, due by the date and time of the proposal submission. Bid guarantee shall be sent to the email address shown below.” Additionally, Attachment J1, paragraph 7.2 references submission of a letter of "bondability" on the Surety's letterhead stating the Offeror(s) has the bonding capacity available is required of each proposer responding to the order. Please clarify—Is a bid guarantee or a letter of bondability required as part of the proposal submission?

Bid quarantee is no longer required.

54.
Section C 1.6 Key Personnel (page 10), Section L – L-3 (page 76), Attachment J1 and J6

The RFP seems to reference the positions of Project Manager and Program Manager interchangeably. For example, RFP paragraph 1.6 Key Personnel (page 10) and Section L (page 76) both reference Program Manager however Attachment J1 and J6 list the position as Project Manager though the Minimum Qualifications Requirements are the same for both positions. Please clarify if this position should be referred to as Project Manager or Program Manager.

Program Manager

55.
Section C, 1.6 Key Personnel (pages 10-11), Section L, L-3 (page 76) and Attachments J1, J6

The licensing requirements for Project/Program Manager and Designer of Record vary between the solicitation, Attachment J6 and Attachment J1. Attachments J1 and J6 state professional registration is acceptable in Pennsylvania but the solicitation document does NOT list Pennsylvania as an acceptable state of professional registration. Please clarify if a Project/Program Manager or Designer of Record licensed in Pennsylvania will meet the minimum qualification criteria.

No, the Project/Program Manager or Designer of Record licensed in Pennsylvania will not meet the minimum qualification criteria.

56.
Section C, 1.6 Key Personnel (page 11) and Attachments J1/J6

Attachment J1 does not reference the Mitigation Supervisor position listed in the solicitation (Section C -page 11) and also in J6 Qualification Summary. Please confirm that offerors are required to include a Mitigation Supervisor as part of the key personnel team for this JOC.

No, the offerors are not required to include a Mitigation Supervisor as part of the key personnel team

57.
Section C, 1.6 Key Personnel (pages 10-11) and Attachments J1/J6

Attachment J1 and the solicitation (Section C, pages 10-11) both reference minimum qualifications requirements for the Qualified Fire Protection Engineer position. However, Attachment J6 does not list this position. Is a Qualified Fire Protection Engineer required to be a part of the key personnel team for this JOC?

They are required as part of the terms and conditions of the IDIQ contract but will not be evaluated for the solicitation of this IDIQ Contract. J6 applies to the Program Manager only.

58.
Attachment J6 Qualifications Sheet

Are offerors expected to complete J6 Qualifications Sheet as part of their proposal response? If so, please clarify where J6 should be included within the proposal submission?

Yes, for the Program Manager only in front of Volume II separate or tab out before each sub-factor

59.
Attachment J6, Section L, L-3 (page 76) and Section M, M-2 (page 80)

In regards to J6 Qualifications Sheet, are offerors expected to provide resumes and commitment letters IN ADDITION to completion of this attachment for ALL positions listed? Please note the positions shown in J6 conflict with the sole position of Program Manager listed in Section L and Section M of the RFP.

J6 was revised to included the following language “ The contractor’s Program Manager should demostrate responsivnesess to project need and load similar to the size and complexity detailed in this SOW as well as ability to effectively manage and execute a program similar to the one detailed in this SOW.

60.
Attachment J6 Qualifications Sheet

If the completion of J6 Qualifications Sheet is required with proposals, please confirm that it will be excluded from page limitations due to the number of positions outlined within the attachment.

It is required and it is excluded from page limitation.

61.
Attachment J6 Qualifications Sheet

If the completion of J6 Qualifications Sheet is required with proposals, does Volume II double-spaced, 12 point font apply to this attachment. Note the attachment J6 provided uses 11 point font with single-spacing.

Yes and we will revise the qualification sheet to reformat.

62.
Attachment J7

Will a laydown area for contractor equipment be provided in close proximity to the SAL work area?

A laydown area will be provided to the contractor but proximity to the SAL cannot be guaranteed.

63.
Attachment J7

Can an aerial work plan be provided for the SAL work area?

For aerial work plans refer to the CD provided during the Pre-Bid Site Visit Attachment A – Project Requirements, A12-Loc of Seed Project 5-23-2018

64.
Attachments J9, J10, and J11 are for wage determinations in Washington, DC. Should the wage determinations be included for Arlington County, VA instead?
Yes, we will revise the solicitation to include Arlington County, VA wage determination.
65.
(2) Past Performance Factor (d), Page 81

Question: May we submit CPARS in lieu of Past Performance Questionnaires (PPQs), and will they be accepted?

Yes

66.
(2) Past Performance Factor (d), Page 81

Question: May we submit previously completed and signed PPQs from other agencies (such as GSA and NAVFAC), and will they be accepted?

No

67.
(2) Past Performance Factor (b), Page 81

Question: May projects that exceed $499,999 be submitted, and will they be accepted?

Yes

68.
(2) Past Performance Factor (b), Page 81

Question: May projects that are slightly over $499,999 (and less than $600,000) be submitted, and will they be accepted?

See RFI question #67

69.
C. SEED Project

Volume III: Past Performance

# 2) Page 78 reads: “… for up to three (3) Government or commercial contracts …SOW.”

(2) Past Performance Factor (b), Page 8 reads: “…delivering up to 5 projects that could range between $2,000.00 to $499,999.99 concurrently…SOW”

And

(2) Past Performance Factor (c), reads: “…for up to five (5) total projects for the prime contractor and may submit one (1) for each subcontractor.”

Question: Please clarify if the prime contractor should submit 3 or 5 projects?

See answer to RFI question #17

70.
Key Personnel, Table – Page 76

Question: May any Bachelor degree be acceptable with all other qualifications? For example, may the candidate have a Bachelor degree in History?

No Bachelor Degree in History does not satisfy the requirements for a BS degree in construction management, architecture, or engineering related field.

71.
Key Personnel, Page 76 reads: “To be eligible for contract award, Offerors must submit resumes … proposal due date.”

Question: In which volume should the Key Personnel package for the Program Manager be placed?

The Program Manager and all supporting documents should be inserting in Volume II separate by a blank sheet before the Technical Sub-Factors

72.
Attachment J12 Technical Approach Submission Template

Question: Is the Technical Approach Submission Template specific to Technical Subfactor C – Seed Project?

No, It is specific to A. Technical Capability and Approach.

73.
Attachment J12 Technical Approach Submission Template &

Instructions to Offerors:

Volume II: Technical Proposal (2) Proposal Length, Page 77 “…double-spaced, no smaller than 12 point font)

Question: Does the Proposal Length requirements for double spacing and 12 point font apply to the content in the Technical Approach Submission Template?

Double spacing and 12 point font requirement applies to the Technical Approach Submission Template.

74.
Attachment J12 Technical Approach Submission Template &

Volume II: Technical Proposal - Technical Subfactor A. Technical Capability and Approach and B. Management Capability and Staffing, Page 77:

Question: Does the Technical Approach Submission Template apply to Volume II, A. Technical Capability and Approach and B. Management Capability and Staffing?

If so, which SOW sections are to be referenced when responding to Technical Subfactor A and Subfactor B?

No,

75.
JOC Coefficients Bid sheet includes “Secure” and “Unsecure” locations. Please advise how these different locations will impact the Bid Coefficient.
Secure Location applies to locations that require an escort. The contractor will need to factor in labor efficiencies that result from the escort requirement as part of the coefficient.
76.
Will any of the TO require security clearances and if so to what level of clearance?
The work at the Pentagon considered for JOC does not require security clearances
77.
From Statement of Work- Item 1.5.1- Please inform how we will invoice any investigation required for pricing a new TO.
Refer to Section C 1.5.4 Contractor Coefficient states: “The Contractor shall provide their coefficient; which shall cover coordination, permits………. and any other expenses not related to performing the work itself”
78.
From Statement of Work- Item1.5.5- This item includes works identified as an Emergency Response/Accelerated Scheduling Project. Please inform on how to proceed when an Emergency Response is required regarding: costs, availability of personnel, secure or unsecured location, escorts, etc, etc.
J2 was revised to include an emergency response coefficient to account for all cost
79.
From JOC Coefficients Bid sheet: Will it be an additional Coefficient for the (7) Emergency Response personnel, will this Coefficient include the cost of the required Response Team, who will be on-call?
See answer to RFI #78
80.
From Statement of Work- Item1.5.6- Since the GOV warranty only “ONE PROJECT FOR THE AMOUNT OF $250K PER YEAR”, please advice how the GOV intent to cover the cost of the required FULL TIME Program Manager.
This contract will have a minimum guarantee of $250K per option year. The Government offers no advice on how to cover the cost of the full time PM.
81.
From Statement of Work- Item1.6.B- Please inform if the Mitigation Supervisor and his crew (total of 7) will be on-call basis and how to include their costs in our JOC Bid Coefficients.
See answer to RFI #78
82.
J7 FSD Statement of Work for Paving the SAL Section. Part 2.4 Above Ground Facilities.

Question: During site visit on 2/25/2019, an existing steel plate was observed within the project area. Please advise what, if any, work is required for this existing steel plate.

See answer to RFI #3

83.
From Statement of Work- Item 1.6.5 states that the Superintendent or the PM may not be the SSHO. Please advise if the same rule applies for Emergency/Accelerated Projects.
Yes
84.
From Statement of Work- Item 1.6.8- Please advise if the LEED Professional can be part of the Design Team.
The LEED Professional may be part of the Design Team, including as a partner/subcontractor if not provided as an in-house service.
85.
From Statement of Work- Item 1-6.9- Please advise what type of Supervision is required for work done by the Mitigation Team.
This work must be supervised in the same manner other construction projects are supervised and in accordance with specific TO requirements, all applicable codes, requirements from HQ0034-19-R-0057, and industry standards.
86.
From Statement of Work- 1.8- Locations- Item e: Other Locations: Please inform the others possible locations and if this cost need to be included in JOC Coefficients. Also, please provide more information to make any additional calculation.
I don’t know the other locations at this time since work is determined by the individual task orders.
87.
From Statement of Work- Item 1.10- In the event of a TO includes Historic Preservation work, please inform how to invoice the additional Design/Construction Effort.
If the work is not covered by one of the coefficients then the final option is to use the NPI clause if the work is not covered in RSMeans and provide a justification for its use.

We will evaluate and identify whether each element is an NPI at that point.

88.
Please provide a complete detailed list of what you are expecting/requiring in the Coefficients?
Refer to section C, 1.5.4 Contractor Coefficient and information provided in this amendment and in attachment J2 JOC Coefficient.
89.
From Statement of Work- Item 2.8.1- Mock-ups: Please inform what Divisions will require Mock-ups and where do we include this cost.
Mock-up cost to be priced through issuance of a Task Order and priced using line items from RSMeans.
90.
Solicitation: Pages 50, 51 and 72 of 83 are blank. Please advise.
Please ignore. It appeared when the document was generated.
91.
Please provide information regarding the TO Price range for the previous JOC.
See answer to RFI #19
92.
Please provide information regarding the expected TO Price range for this Solicitation.
Refer to section C, 2.1.5.1 Task Order Minimums and Maximums
93.
From Statement of Work- Item 1.6.1- PM limitation on number of TO assigned is (5) for projects above $400K. Please advise if any restriction applies for TO below $400K or any other combination.
No
94.
Please inform how many TO can be assigned to one QCM.
Each TO shall detail the requirement for a QCM as well as all other positions and the minimum function/oversight expected.
95.
Please inform how many TO can be assigned to one SSHO.
Each TO shall detail the requirement for a SSHO as well as all other positions and the minimum function/oversight expected.
96.
From Statement of Work- Item 1.6.6- One Superintendent is required each TO. Please inform if this statement applies to $2K TO and provide the exceptions for this rule.
No, the statement does not apply to $2k Task Orders.
97.
Are cost of Design, Mitigation and QFPE included in the JOC Coefficients or if their costs need to be included in the Proposal Breakdown.
98.
The Seed Project includes a Wage Scale. Please inform how to apply the differential Cost of Labor comparing with the UPB Bare Cost.
Refer to section C, 1.5.1 Price Book, 1.5.2 Price Book Set-Up, 1.5.4 Contractor Coefficient, and 1.5.5.2 Bid-Build Construction
99.
J7 FSD Statement of Work for Paving the SAL Section. Part 2.4 Above Ground Facilities.

Question: What is the quantity of existing security vehicle barriers to be removed and re-installed? One (1) vehicle barrier is listed in the SOW; however two (2) vehicle barriers were identified during the site visit on 2/25/2019.

There are two vehicle barriers. These devices will be removed by the Pentagon Force Protection Agency before the work starts and returned after the work completes on every weekend the work is being performed. This needs to be reflected in the PCP by the contractor.

100.
J7 FSD Statement of Work for Paving the SAL Section. Part 2.4 Above Ground Facilities.

Question: The SOW does not mention any Electrical, Security etc - If applicable, please provide the location of the electrical panelboard and controls panelboard for the existing security vehicle barrier to be removed and reinstalled.

Electrical and Security work associated with the vehicle barriers will be by done others.

101.
STATEMENT OF WORK (SOW) 11/30/2018; Part 1.5.5 (Pages 9 and 10 of 83 in PDF file).

Question: Please advise if we should provide separate and different JOC Coefficients for the different project types, as listed below:

a) Design-Build Projects with a Designer of Record (DOR) required.

b) Design-Bid-Build Projects; DOR not required.

c) Emergency Response / Accelerated Scheduling Projects.

Provide coefficients as outlined in revised J2.

The DOR should only be factored into the Design-Build Construction projects’ coefficient.

102.
STATEMENT OF WORK (SOW) 11/30/2018; Part 1.6.3 (Page 12 of 83 in PDF file).

Question: Is the Qualified Fire Protection Engineer (QFPE) to be included on all projects which also includes exterior and site work?

A QFPE shall only be required on projects that specifically require a QFPE.

103.
STATEMENT OF WORK (SOW) 11/30/2018; Part 1.5.5 (Pages 9 and 10 of 83 in PDF file).

Question: Is a separate and different JOC Coefficient to be submitted for projects located outside the National Capital Region, requiring travel, per diems for lodging and meals.

This contract will have no projects outside of the NCR.

104.
J7 FSD Statement of Work for Paving the SAL Section. Part 2.4 Above Ground Facilities.

Question: During site visit on 2/25/2019, an area of asphalt paving was observed within an area of concrete paving. Is any work required at this location?

No, the asphalt sections in the concrete aprons are not included in the cold milling and paving scope of work.

105.
STATEMENT OF WORK (SOW) 11/30/2018; Part 1.6.9 Mitigation Supervisor, and Part 1.7 Response Times (Page 13 of 83 in PDF file)

Question: Is the seven (7) -person team described in Part 1.6.9 to be included in the JOC Coefficient for “Emergency Response / Accelerated Scheduling Projects”?

See answer to RFI #78

106.
J7 FSD Statement of Work for Paving the SAL Section. Part 4.0 ATTACHMENTS (pages 12 and 13 of 14 in PDF file)..

Question: Two (2) different versions of ‘Part 4.0 ATTACHMENTS’ have been issued for this Seed Project RFP; one version is in the initial documents made available on FedBizOpps, and the second version is included on the compact disc given to Contractors by WHS during the site visit on 2/25/2019. Please provide one (1) updated and correct version of ‘Part 4.0 ATTACHMENTS’ The version PART 4.0 ATTACTMENTS provided on the CD during the site visit is the correct version

107.
STATEMENT OF WORK (SOW) 11/30/2018; Section H, Part H-14.d (Pages 46 and 47 of 83 in PDF file).

Question: If personnel with security clearances are required on any project, is the security clearance requirement to be priced by the Contractor as a “Non-Prepriced Item”, per SOW/Part 1.5.3?

See answer RFI #76

108.
Are Key Personnel to be included in the Coefficient or to be included as a Line Item?
Only the Program Manager is required on-site as a full-time employee for the JOC contract. Other Key Personnel requirement will be specified and detailed in each Task Order. The cost of each of the Key Personnel positions should be included in the contractor’s coefficient, except for the DOR who shall be included in the Design coefficient and the Mitigation Supervisor who shall be included in the Emergency Response Coefficient.
109.
Are A/E to be included in the Coefficient or to be included as a Line Item?
A/E to be included in the Design Coefficient.
110.
General – Can site photos of the seed project be provided?
No, photos will not be provided. For pricing purposes refer to section Attachment A – Project Requirements, A12-Loc of Seed Project 5-23-2018 that is in the CD provided during the Pre-Bid Site Visit and section 2.8 Measurements and Quantities in J7_FSD_Statemen_of_Work_for_Paving_of_the_SAL.
111.
Site Visit – Within the security checkpoint there are several locations where the concrete pad was patched with asphalt. Please confirm these areas are included under the statement of work and are to be milled and repaved.
No, the asphalt sections in the concrete aprons are not included in the cold milling and paving scope of work.
112.
Site Visit – Please provide the width dimensions at the narrowest point of the secure access lane.
For pricing purposes, refer to J7_FSD_Statemen_of_Work_for_Paving_of_the_SAL, 2.8 Measurements and Quantities and Attachment A – Project Requirements, A12-Loc of Seed Project 5-23-2018 that is in the CD provided during the Pre-Bid Site Visit.
113.
Site Visit – Please identify any/all items or overhead obstructions that would preclude height/width access to the site.
Warning signs are installed/placed as required by applicable codes.
114.
Site Visit – What is the height of the security checkpoint canopy, cameras, and panels?
We don’t know
115.
Site Visit – Within the secure access lane after the security checkpoint, there is an existing metal plate on the pavement. What is the weight and dimensions of the plate? Is this to remain? If not, what is underneath and what is to be performed underneath the plate?
See answer to RFI #38
116.
SOW pg. 2 – Please confirm that milled surfaces may be opened to traffic prior to paving. Or will all milled areas be required to be paved prior to opening?
Milled surfaces may be opened to traffic prior to paving. The work schedule, sequencing, and all other items that require coordination, must be reflected in the Project Coordination Plan (PCP) submitted by the contractor.
117.
General – What restrictions are there for accessing the site? What badging and/or security requirements are there?
Refer to section C, 2.4 Contract Constraints.
118.
General – What are the requirements for use of the exit gate during construction? Will the contractor have use of the exit gate or will all traffic be required to exit through the entrance to the secure access lane?
The use of the exit gate shall be coordinated in advance with the Pentagon Force Protection Agency (PFPA). Vehicles coming into the work area are required to be screened. Contractor may have use of the exit gate provided it is coordinated in advance with PFPA.
119.
SOW pg. 1/ pg. 5 – section 1.4 indicates that work may only take place on weekends while section 2.9 states that work may take place during off hours and weekends. Please confirm work may take place off hours Monday-Friday and on weekends, for the seed project.
Seed Project work may only take place on weekends.
120.
SOW pg. 5 – Please confirm the existing handicapped parking sign is to remain and the handicapped pavement markings are to be installed per the SOW.
Confirmed
121.
General – Please provide any drawings or details of the seed project.
See answer to RFI # 110
122.
General - Please provide any traffic control requirements associated with this work.
Refer to Addendum A - VDOT RandB Guidelines 2016 found in the CD provided during Pre-Bid Site Visit.
123.
Bonding – Please confirm a bid bond is not required for the seed project or Job Order Contract.
Confirmed
124.
Bonding – Please confirm payment and performance bonds will be required for the seed project.
Confirmed
125.
General - Does the seed project need to be performed in phases? If so, how many?
The contractor is responsible for phasing, if necessary. The contractor shall coordinate sequencing through the PCP.
126.
General - Where and how many spaces are available for the contractor’s personnel vehicles. How many parking permits will be authorized and on what basis?
Refer to section C, 2.4.23 Employee and Commercial Vehicle Parking.
127.
Management - Please confirm a full time Quality Control Manager is required on site for any construction activities associated with the JOC and Seed project.
This work must be supervised in the same manner other construction projects are supervised and in accordance with specific TO requirements, all applicable codes, requirements from HQ0034-19-R-0057, and industry standards.
128.
General - Please confirm no temporary office facilities will be required for the seed project.
Confirmed
129.
General - Please identify any required permits associated with the seed project. Please confirm permits will be ordered, and payed for by the contractor.
The contractor will be responsible for any fees associated with obtaining any permits through Arlington County. Pentagon permits have no fees associated. The contractor should include the time necessary for submission and processing of permits within its coefficient.
130.
SOW pg. 5 - Please confirm all testing will be provided by the contractor at the contractor’s expense.
Yes, testing should be provided by the contractor. Refer to J7_FSD_Statemen_of_Work_for_Paving_of_the_SAL, section 2.11 Testing of Pavement Course.
131.
SOW Pg. 1 – Please confirm the 60-calendar day period of performance includes time for the submission and review period of submittals?
Revision 1 increased the POP from 60 calendar days to 120 calendar days
132.
SOW pg. 8 – Please confirm there is no requirement for dust mitigation for the seed project.
Dust Mitigation Plan is required
133.
SOW pg. 8 – If dust mitigation is required, please provide specifications and requirements.
The Offeror’s mitigation dust plan should discuss specification and requirements see J1 section 1.3.5 Dust Mitigation Plan
134.
General - Please provide the anticipated start date for the seed project.
The offeror should assume this project starting during May-June time period
135.
Solicitation pg. 1 - The solicitation indicates the wage rates for Washington DC only. Please confirm work under the seed project will be performed under the provided wage determinations.
We will also include Arlington Wage Rates.
136.
General - Is work under this solicitation tax exempt?

No

137.
SOW pg. 3 – Please confirm the existing security vehicle barrier is to be removed, stored, and reinstalled by others. If not, please provide the contact information for the product installer. Will the parking barrier need to be reinstalled prior to the facility opening each working day?

If so, who coordinates the barrier relocations?

See RFI answer 4

138.
Solicitation pg. 78 – How will pricing be calculated for work that significantly differs from the RS Means cost data? Ex. If the cost for steel work is significantly higher than RS Means data due to the volatile materials cost, will the contractor be allowed to substitute RS Means pricing with subcontractor quotes?
RSMeans provides quarterly pricing releases that take into consideration market conditions. In the event that a specific item is not covered by a corresponding RSMeans line item, the awarded contractor may refer to section C, 1.5.3 Non-Prepriced Items.
139.
Solicitation pg. 78 – The RS Means labor rates will not include Davis Bacon Wage requirements. How shall the contractor provide labor rates under this solicitation?
“Wage Rate Requirements (Construction)”
140.
Solicitation pg. 78 – The RS Means labor and equipment rates do not include weekend or off hours work. How shall the contractor provide labor and equipment rates for off hours/weekend work under this solicitation?
The weekend hours and off-hours requirement shall be factored into the weekend hours and off-hours coefficients represented in revised J2.
141.
How shall the contractor include pricing for specialty requirements? Ex. Charges for asphalt plants to be open off hours and/or weekends for work under this solicitation.
Specialty items that are not included in RSMeans shall be priced separately as a NPI. Refer to Section C, section 1.5.3 Non-Prepriced Items.
142.
1.5 Contract Price – Will the unit price book (RS Means Online Edition) be updated to reflect the current prices relevant to the year the work is being performed?

RSMeans provides quarterly pricing releases that take into consideration market conditions. In the event that a specific item is not covered by a corresponding RSMeans line item, the awarded contractor may refer to section C, 1.5.3 Non-Prepriced Items.

143.
As every employee will require badging with 24-hour access, is there a limit to the number of personnel the contractor can submit or a limit on how many badges that can be obtained?
Badges are obtained under the task orders
144.
Space Use Permit – Will we be granted a long-standing space use permit, or will each task order be required to have separate permits?
Each TO will be treated as a separate construction project and require its own space use permit.
145.
Please confirm if there are LEED requirements for all task orders.
The Government will specify if there is a LEED requirement in the specific Task Order.
146.
Badging 2.4.19.A – A list of personnel is to be submitted within five calendar days of contract award. If after the first five days, it is discovered that additional personnel are required, will the additional employees be able to be badged?
Yes
147.
3.2 – All submissions received after 1400 hours will be considered (received on) the next business day.

As the contractor is given 7 calendar days to resubmit after a submission is returned, may we consider the same standard, that submissions returned after 1400 hours will be considered received on the next business day?

Yes

148.
Solicitation pg. 1 – The proposed contract is limited to qualifying HubZones [SIC] firms in the geographical area serviced by the following states Maryland, Virginia, and Washington DC.

Please confirm if the contract is limited to firms with their principal office as submitted to the SBA for HubZone certification in the areas of Maryland, Virginia, and Washington DC.

See answer to RFI # 27

149.
How will WHS confirm the eligibility and or certifications for each contractor? Will proof of qualifications be required at time of submission? Does WHS want contractors to provide a confirming letter from the SBA?
WHS will verfied eligibility and or certification for each contractor by going on the List of Qualified HubZone Small Business Concerns site.

http://dsbs.sba.gov/dsbs/search/dsp_searchhubzone.cfm

150.
Contractor Personnel – Please confirm WHS’s intent with respect to the contractor directly employing seven (7) contract required personnel. Does WHS expect the contractor to employ all required personnel full time in support of this contract yet only guarantee $250,000 a year in task orders? These proffers seem exceptionally one sided and disproportionate that we must clarify and confirm WHS’s position. Please address and elaborate on this concern/understanding.
We will not pay for project manager outside of task orders.
151.
Key Personnel – All Contractor key personnel, with the exception of the Designer of Record (DOR) and Mitigation Supervisor, shall be direct employees of the Prime Contractor.

Is WHS prepared to absorb the cost of the full-time employees required for each task order and how is that to be contemplated by RS Means?

Is this to be blended into the coefficient?

Only the Program Manager is required on-site as a full-time employee for the JOC contract. Other Key Personnel requirement will be specified and detailed in each Task Order. The cost of each of the Key Personnel positions should be included in the contractor’s coefficient, except for the DOR who shall be included in the Design coefficient And the Mitigation Supervisior who shall be included in the Emergency Response Coefficient

152.
If no awards or very few awards are issued, how will WHS cover costs of maintaining the direct employee personnel allocated to this contract?
There is a minimum guarantee of $250,000.00 for each period..
153.
Alternate Project Manager- Is it required to provide the resume of the alternate project manager?

No, we will not be evaluating the alternate project manager.

154.
Badging – What type of infractions or issues would prevent an employee from being approved for a badge?
Refer to Section H, H-16 REMOVAL OF CONTRACTOR EMPLOYEES.
155.
Change Orders- If scope is introduced that was not included on the RS Means scope estimate that is necessary for completion of work, will a change order be accepted by WHS?
Yes Response does not address the question. “Will a change order be accepted by WHS?”
156.
Payment Term- Will WHS accept bi-weekly billings? How long is the typical approval time on payment applications?
The Government shall make progress payment monthly or bi-weekly if requested and Contracting Officer approves. See FAR 52.232-5

How long is the typical approval…..? Net 14. Net 10 with prompt payment discount offered

157.
Is this JOC a recompete? If so, who is the incumbent contractor?
See answer RFI #19
158.
If this contract is a recompete, what was the aggregate dollar value on all task orders per year issued for the previous contract?
See answer RFI #19
159.
2.4.30 Work Stoppage: Work may be stopped at any time due to Pentagon Reservation Security Issues. This will not be considered government delay of work, if work is stopped due to security issues.

RS Means does not have pricing for delays for work stoppages, how would those costs be paid?

2.4.30 Work Stoppage now states” Work may be stopped at any time due to Pentagon Reservation Security Issues.

Refer to J1_Const_Mngmnt_Gen_Reqts_V6 found in the CD provided during Pre-Bid Site Visit for details on Government induced work stoppages in section 2.7 Project Schedule Constraints.

160.
2.4.21 Entry: Allow a minimum of fifteen (15) minutes to one (1) hour for processing through the SAL. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

RS Means does not have pricing for delays entering the construction areas, how would those costs be paid?

All costs not related to the work itself should be captured in the offeror’s coefficient.

161.
LEED Professional (Required for projects that are pursuing LEED certification) - Active LEED AP certification - Experience certifying at least 3 LEED projects

RS Means does not have pricing for the hire of LEED Professionals how would their costs be paid?

The LEED Professional cost should be included in the Design coefficient.

162.
1.6 Key Personnel

Qualified Fire Protection Engineer (QFPE) - Registered professional engineer (P.E.)