HOTD_Tour_Handout_Oct2024.pdf

PDF 70 KB Posted

Attached to
GSA PBS - Heating Operation & Transmission Division (HOTD)- RFI
Solicitation number
RFI47HAA022
Issued by

About this file

This document is a Request for Information (RFI) issued by the General Services Administration (GSA) Public Buildings Service for the Heating Operations and Transmission Division (HOTD) in Washington, DC. The RFI seeks to gather industry feedback on various ownership and operational alternatives for the HOTD system to enhance its value, efficiency, and environmental impact. Key objectives include identifying parts of the HOTD heating and chilled water systems that can be privatized cost-effectively, ensuring continued economical service to buildings connected to the HOTD system, informing long-term strategy for GSA to deliver maximum electrification by 2030 and reduce operating costs, and decarbonizing the HOTD distribution system. The RFI outlines the HOTD's current plant facilities, annual output, and staffing, as well as ongoing and planned projects. It provides opportunities for industry engagement through question submissions, a Q&A webinar, and optional tours of the HOTD Central Plant and the adjacent DC Water wastewater thermal energy system. The information gathered through this RFI may be used in the preparation of a subsequent Request for Proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HOTD Tour Fact Sheet October 2024

Plant Facilities

Type/Brand Year Installed Quantity Total Installed Nameplate Capacity

Unit of Measure

Steam Boilers

Water Tube/Erie City

1933, majority of tubes replaced

2 360,000

Lbs/hr Water Tube/Zurn

Industries 1973 2 760,000

Water Tube/Zurn Industries

1977 1 200,000

HRSG/Zurn Industries

1977, modified to HRSG in 2000

1 240,000

Chillers

Condensing Steam Turbine

2000 2 4386

Tons Induction Motor 2000 4 8340

Induction Motor 2000 1 2185

Induction Motor 2000 1 2200

Electricity Solar Turbines 2000 2 11 MW

Plant Output Annual FY23

Type Unit of Measure Total Annual Plant Output

Steam Mlb 989,108 (sold)

Chilled Water Ton HR 24.7 million

Electricity MWH 62,892(FY21)

Peak FY23

Type Unit of Measure Total Annual Plant Output

Steam Mlb/Hr 650

Chilled Water Ton 12,166

Electricity MW 8.5

Physical Plant Data

Service Max. Sendout Pressure (PSI)

Max. Sendout Temperature (F)

Return Temperature (F)

Percent Return

Steam 250 400 180 70%

Chilled Water 125 41 51 99.5%

Staff

Job Category Full-Time GSA Employees Contract Employees

Plant Operation 12 11

Plant Maintenance 11 1

Distribution 7 -

Engineering & Energy 3 3

Environmental 4 -

Financial Management 7 1

Mission Support 1 3

Total 45 19

Projects Currently Underway or Funded

- Boiler #6 Upgrade to comply with new RACT emission standard

- General Boiler Repairs

- General Steam Plant Repairs

- Steam Distribution Repairs

- Steam Tunnels Concrete Repairs

- Repair to Cooling Towers

- Replace 17th Street steam & condensate lines from MH# 9 to MH#11

- Boiler #3 Upgrade to comply with new RACT emission standard

- PIV Security Locks – follow-up from CISA Audit

Projects Identified but not currently funded

- Repair to Structural Deficiencies: $2.2M

- Feedwater Pumps relocation: $2.5M

- Hot well Repair: $1.5M

- Install intrusion ramp barriers: $1.7M

- Add NOx Control to Boilers #1 & #2: $7.9M

- Replace Heating Plant Roof: $2M

- Replace Ellipse Steam and Condensate Lines: $2.4M

File details come from the government source that posted it. Updated .