Hoover Renovation and Addition Furniture Bid Package 1 Addendum 2.pdf
PDF 157 KB Posted
- Solicitation number
- RFP LPP 200000001436 5
- Issued by
- Wayne County, Michigan
About this file
This is an addendum to a furniture and equipment bid package issued by Lincoln Park Public Schools for the Hoover Elementary School Renovation and Addition project in Lincoln Park, Michigan. The addendum, issued on March 30, 2020, addresses modifications and clarifications to the bidding documents prior to bid receipt. The project involves the procurement of furniture and equipment for the school renovation and addition, with bidders required to acknowledge receipt of this addendum on their bid forms.
The addendum contains three substantive clarifications. First, recognizing current business environment restrictions, the addendum permits bidders to obtain performance bonds after bid submission rather than prior to bid due dates. Second, Item C17 upholstery (Momentum Eon Epu grade) has been rejected for use by Ideon, and bidders are instructed to price for this upholstery grade with replacement selections to be made after bid awards. Third, clarifications are provided regarding two furniture items: Tag S1 is confirmed as a single-sided bookcase and Tag S2 is confirmed as a double-sided bookcase, resolving discrepancies between product descriptions and manufacturer item number references.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 02
Issue Date: March 30, 2020
Project Name: Lincoln Park Public Schools
Hoover Elementary School Renovation and Addition Furniture and Equipment Bid Package 01 Lincoln Park, Michigan
IDS Project No.: 17146-1000
This Addendum is issued prior to receipt of bids in order to modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections. Bidders are to indicate receipt of this Addendum in the space provided on the Bid Form.
NEW OR REVISED DOCUMENTS ISSUED WITH THIS ADDENDUM
Project Manual Documents: None
Drawings: None
Sketches: None
PROJECT MANUAL DOCUMENTS DELETED OR REVISED BUT NOT ISSUED
Item No. 1 Clarification:
Due to the current environment and restrictions on businesses, if bonds cannot currently be obtained, they can be attained at a later date, after bids are due.
Item No. 2 Clarification: Item C17, Upholstery Momentum Eon Epu has been rejected for use by Ideon.
Please price for this grade of upholstery, replacement upholstery will be selected after bid awards.
Item No. 3 Questions:
1. Tag S1 - The description calls for single sided unit, but the Media Tech Item number referenced is for a double-sided bookcase, please advise if this is supposed to be a single sided unit.
2. Tag S2 – The description calls for a double-sided unit, but the Media Tech Item number references is for a single sided bookcase. Please advise if this is supposed to be double sided.
Answer: Item S1 – Is a single sided bookcase. Item S2 – Is a double-sided bookcase.