HHES Painting Question and Answers.pdf
PDF 123 KB Posted
- Solicitation number
- S-P30001-00016285
- Issued by
- Union County, Oregon
About this file
This is a Question and Answers document for Invitation to Bid 2026-02 issued by Hermiston School District 8R for comprehensive interior and exterior painting services at Highland Hills Elementary School located at 450 SE 10th St, Hermiston, Oregon. The project scope includes exterior power washing and surface preparation, interior and exterior door painting, metal awning and roof coating, gymnasium metal rafter painting, and interior wall preparation and painting throughout the facility. Key clarifications from the questions include confirmation that all exterior classroom doors will be painted, modular classrooms must be bid as separate line items with both interior and exterior options, preparatory work may begin upon Notice to Proceed (tentatively June 13 at the earliest for onsite work), and exterior painting should proceed in morning hours following the district's noise ordinance guidelines. The document specifies that FRP walls and existing utility boxes will not be painted, plexiglass roof overhang panels will remain unpainted, and the district will remove items from walls to enable full painting coverage. Sealed bids are due by 2:00 PM Pacific Daylight Time on April 22, 2026, with a mandatory pre-bid conference scheduled for April 3, 2026, at 8:00 AM at the school site. The Notice of Intent to Award is anticipated for April 23, 2026, with board approval on May 11, 2026, and Notice to Proceed on May 12, 2026. Substantial completion is required by July 15, 2026, with final completion by August 1, 2026.
All bidders must use only Sherwin-Williams paint and coatings with no alternatives permitted, including specified primers and top coats with quantities varying by surface type (one primer and three top coats for roofs and metal awnings, two coats for concrete and CMU surfaces). Interior walls require painting only without primer, while exterior doors require proper surface preparation before painting over existing finishes. Bidders must submit bids in person or via postal services, provide bid security equal to 10 percent of the bid amount, and submit first-tier subcontractor disclosure forms within two business hours of bid closing for subcontractors exceeding five percent of the total bid or $15,000, whichever is larger, or $350,000 regardless of percentage. The successful contractor must execute a Performance Bond equal to 100 percent of the contract cost and comply with Oregon prevailing wage requirements. Liquidated damages are assessed at $300 per day for failure to achieve substantial completion by the July 15, 2026, deadline. Nonresident bidders will have a percentage increase applied to their bids equal to the preference their state of residency would receive under Oregon Administrative Rule 137-046-0310.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hermiston School District – Highland Hills Elementary Painting 2026-02
ITB: Question & Answers Page 1
1) Can you include the wall elevations for a TYP classroom? Are the as-builts from 2023 remodel available?
2) The district has posted the drawings from the 2023 construction project to OregonBuys for all bidders to review.
3) Admin trailers off the SE side are not to be painted y/n
a) Please bid modular classrooms as a separate line item/alternate bid, so that the district can determine if it will be painted now depending on costs. An official bid amendment will be released with details.
4) What is the planned phasing for the HVAC work.
a) Only one wall will be affected by the HVAC project (this should not slow down painting).
All the interior walls should be painted first, then move to the exterior. This will allow all teachers to move into classroom spaces as soon as possible.
5) The exterior metal utility boxes on North side of school near HVAC work to be done that are currently a greenish color are not to be painted y/n
a) No, the metal utility boxes are not to be painted.
6) Summer time exterior painting works best in the morning, is there any AM time work restraints or conditions? i.e. can my crews work in the early AM hours?
a) The painted schedule needs to be communicated ahead of time with the district’s Facility
Supervisor. The district has no issues with painting occurring in the early AM hours, so long as the contractor is operating within the city’s noise ordinance, if applicable, and operating within all applicable ORS 279C.
7) The plastic overhang panels on the roof edge are to not be painted y/n
a) The plexiglass is not to be painted
8) Would weekend painting work prior to June 15 be allowed, as in could my guys get going on some of the interior spaces, like the rafters, that are out of the staff and students way.
a) It may be possible for onsite work to begin June 13, but that would be the earliest possible date the district would consider. The successful bidder will coordinate with the district’s facility supervisor to develop a work schedule. Keep in mind this is a public works project, subject to Oregon prevailing wage laws.
9) Preparatory work may begin on date of Notice to Proceed. Preparatory work includes but is not limited to submittals, field verification, exploratory work, equipment procurement, scheduling, and any work not impacting school operations. What is allowed under this clause?
a) This clause allows procurement of supplies and offsite prep work to begin so that the successful bidder is ready to begin onsite work once students and staff are out of the building for the summer. It is the district’s intent that a construction schedule will be developed between the successful bidder and the district’s facility supervisor during this preparatory time.
10) Is the bid going to be submitted in person or can it be turned in through email?
a) Bids can be submitted in person or via postal services, but there is not an option to submit virtually.
11) Bid Documents state that “No exterior doors will be painted” but during the jobwalk it was stated that
“We are painting the exterior doors (Inside and Out). Can you please confirm which option to include in bid?
a) All exterior classroom doors are getting painted. The four exterior doors under the awning in the CMU wall will be painted. An amendment to the bid document will be released soon.
12) Are the Exterior Doors Getting Primed? Or just painting over?
a) Painted over, with proper prep
13) At the job walk it was mentioned that the painting contractor could choose what material to use for the door numbers, is this correct? Or are they staying as is?
a) Yes, all numbers will need to be put back with like material.
Hermiston School District – Highland Hills Elementary Painting 2026-02
ITB: Question & Answers Page 2
14) For the exterior “Effervenscence” is this the CMU behind the gymnasium? If not can you please identify what area this is going to?
a) Yes, that is behind the Gym
15) During the job walk, it was stated to exclude the modular building next to the basketball court, is this correct?
a) Please bid modular classrooms as a separate line item/alternate bid, so that the district can determine if it will be painted now depending on costs. An official bid amendment will be released with details.
16) Are the exterior Louvers getting primed and painted? Or leaving as is?
a) Primed and painted
17) Are we to estimate 2 coats to be applied to all concrete/CMU surfaces?
a) Yes
18) Is the entire roof of each building getting primed? Or are we only putting paint over the existing?
a) Primer and Paint
19) Is the Roof getting 3 coats of paint?
a) 1 primer and 3 top coat, may need a 4th with how dark the color is.
20) Is the bottom part of the metal awnings getting primed and 3 coats of paint? Or only paint? And how many coats?
a) 1 primer and 3 top coat, may need a 4th with how dark the color is.
21) Is the School removing all the whiteboards, posters, and everything that is currently on the walls so we can paint behind it? OR are we painting around these areas?
a) HSD will remove everything we want to paint behind. If it's left on the wall paint around it
22) Are the interior walls needed to get primed? Or only Painted?
a) Painted only
23) Are the Wall and Base cabinets getting primed and painted?
a) No cabinets are getting painted
24) Are the interior doors getting primed and painted?
a) Painted over, with proper prep
25) The classroom restrooms have FRP walls, are these walls getting primed and painted? Or only the ceilings?
a) FRP will not be painted
26) Is the dishwasher station room behind door 88 getting painted?
a) Yes, the whole kitchen is getting painted
27) Gymnasium: Multi-Purpose room: are the Peg Board walls getting primed & painted?
a) Primed and painted primer is going to be Prep Rite pro block primer
28) At the walk it was discussed that painting the metal rafters in the gym would be added. Do you have a coating specified for that?
a) PI Precat eg K45W01151 is the coating spec to use.
29) The non-collusion affidavit just below the signature says "State of Oregon". We are getting this notarized in Washington. Do you want the notary to just cross out Oregon and put Washington? I am doing an amendment to the bid document, so I will remove Oregon, and put a line so each notary can just fill in the State.
30) If no subcontractors will be used do we just put NA on the first-tier subcontractor disclosure form? Just write "None" in the name box of line 1 and then complete the signature and contact information section at the bottom. The form will still need to be submitted in a separate envelope though.
31) Is the option for the portable classrooms only the interior or both interior and exterior?
a) Please bid the modular as internal and external.
BIDDERS ARE REMINDED THAT THE REQUIRED SPECIFIED SHERWIN-WILLIAMS PAINT AND
COATINGS MUST BE USED AND NO ALTERATIVES WILL BE ALLOWED.