Attachment_2-Estimated_Floor_Measurements-Oki_Custodial-Final-31_Jan_2013.pdf
PDF 155 KB Posted
- Attached to
- DoDDS Okinawa Custodial Services Federal contract opportunity
- Solicitation number
- HE1260-13-R-0001
- Issued by
- Department of Defense Education Activity
About this file
Attachment 2 Estimated Floor Measurements-Oki Custodial-FINAL-31 Jan 2013
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
School Number of Buildings Administrative Office Cafeteria Total Square Meters
DSO 1 2,627.45 0 2,627.45
STO 1 798.69 0 798.69
Amelia Earhart IS 2 207.09 486.86 7,371.64 Bechtel ES 5 122.42 317.92 8,081.53 Bob Hope ES 1 131.65 339.27 7,969.53 Kadena ES 1 234.45 612.32 10,679.43 Kadena HS 3 220.91 701.57 13,110.45 Kadena MS 5 187.15 405.64 6,622.21 Killin ES 5 133.86 329.02 7,270.98 Kinser ES 8 115.92 254 7,529.26 Kubasaki HS 8 145.49 737.94 13,717.35 Lester MS 6 162.39 421.3 7,529.26 Ryukyu MS 5 221.18 533.23 12,018.06 Stearley Heights ES 2 212.85 279.73 6,263.21 Zukeran ES 15 153.17 427.64 6,207.00 Total 68 5,674.67 5,846.44 117,796.05
OKINAWA DISTRICT CUSTODIAL CONTRACT
ESTIMATED Floor Plan Measurements
ESTIMATED Floor Measurements for Okinawa DSO
BLDG AND
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
BLDG 9497
102 15.23 15.23 103 15.67 15.67 104 22.66 22.66 C103 14.24 14.24
STAIR 102 12.84 12.84
105 20.58 20.58 106 21.22 21.22 107 21.6 21.6 108 29.81 29.81
TOILET 109 16.57 16.57
TOILET 110 19.55 19.55
JC111 2.31 2.31
V101 5.58 5.58
STAIR 101 12.22 12.22
C101 63.61 63.61 C102 37.52 37.52 116 23.88 23.88 116A 44.33 44.33 117 13.84 13.84 118 13.75 13.75 119 15.01 15.01 120 10.34 10.34 121 18.78 18.78 122 16.15 16.15 123 10.41 10.41 124 14.25 14.25 125 55.07 55.07 125B 30.2 30.2 127 25.03 25.03 128 18.1 18.1 129 14.81 14.81 130 23.52 23.52 134A 24.61 24.61 134B 6.11 6.11 134C 6.22 6.22 135 13.79 13.79 137 56.67 3.39 60.06 137A 17.07 17.07 139 67.78 67.78 138 59.69 59.69 140 9.09 9.09 141 8.9 8.9 C104 118.48 118.48 146 133.09 3.39 136.48 146A 17.07 17.07 147 14.09 14.09 142 59.69 59.69 202 43.03 43.03 203 17.94 17.94
STAIR202 21.97 21.97
C202 42.59 42.59 205 54.52 54.52 206 42.55 42.55
TOILET 208 16.9 16.9
ESTIMATED Floor Measurements for Okinawa DSO
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
TOILET 209 16.88 16.88
C201 42.88 42.88 212 16.91 16.91
STAIR 201 19.93 19.93
JC213 2.79 2.79
223 14.61 14.61 224 28.18 28.18 215 33.92 33.92 216 16.19 16.19 C205 24.88 24.88 218 19.31 19.31 219 16.34 16.34 220 15.17 15.17 221 15.13 15.13 222 43.94 43.94 225 28.34 28.34 226 28.32 28.32 227 28.01 28.01 228 29.11 29.11 229 84.64 84.64 C203 88.27 88.27 C204 59.06 59.06 230 34.55 34.55 232 66.64 66.64 233 58.82 58.82 234 41.76 41.76 235 103.36 103.36 236 59.68 59.68 235A 14.23 14.23 237 16.32 16.32
STAIR 202 21.97 21.97
TOTAL SM 2114.97 0 399.67 107.71 0 0 5.1 2627.45
ESTIMATED Floor Measurements for Foster STO
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINTED
FL
RUBBER
MAT
ROOM TOTAL
TO BE
CLEANED REMARKS
BLDG 5821
101 136.62 136.62 C101 58.84 58.84 102 11.44 11.44 103 52.4 52.4 106 12.44 12.44 107 13.68 13.68 108 87.72 87.72 110 31.56 31.56 111 9.27 9.27 112 7.31 7.31 113 35.58 35.58 114 276.79 276.79
BW120 65.04 65.04
Total SM 148.06 198.96 130.03 44.85 276.79 798.69
ESTIMATED Floor Measurements for Amelia Earhart IS
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE RUBBER MAT
ROOM TOTAL
TO BE CLEANED REMARKS
BLDG 9481
101 64.77 64.77 Space 102 7.99 7.99 Space 103 8.05 8.05 Space 104 7.92 7.92 Space 105 13.51 13.51 Space 106 15.39 15.39 Space 108 4.59 4.59 Space 109 31.91 31.91 Space 109A 52.96 52.96 Space 110 43.7 43.7 111 90.92 90.92 112 7.96 7.96 113 1.71 1.71 114 10.51 10.51 115 12.84 12.84 116 8.75 8.75 117 5.19 5.19 118 11.04 11.04 119 2.89 2.89 121 9.91 9.91 122 15.51 15.51 123 18.14 18.14 138 18.99 18.99 139A 407.71 407.71 139B 17.41 17.41 140 25.34 25.34 140A 486.86 486.86 Cafeteria 141 17.1 17.1 147 12.58 120.41 132.99 149 9.55 9.55 150 1.06 151 9.49 9.49 170 15.07 15.07 171 14.75 14.75 195 26.52 26.52 202 14.88 14.88 203 14.74 14.74
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE RUBBER MAT
ROOM TOTAL
TO BE CLEANED REMARKS
204 21.89 21.89 205 25.08 25.08 206 14.77 14.77 207 14.83 14.83 234 1.62 1.62 A119 14.61 14.61 A120 14.8 14.8 A125 1.86 1.86 A126 74.8 74.8 A127 32.77 32.77 A128 74.21 74.21 A129 72.73 72.73 A130 74.65 74.65 A134 31.75 31.75 A135 71.94 71.94 A136 75.55 75.55 A137 67.45 67.45 A202 17.24 17.24 A203 68.74 68.74 A205 74.57 74.57 A206 72.36 72.36 A207 74.97 74.97 A211 26.5 26.5 A212 72.1 72.1 A213 75.93 75.93 A214 67.99 67.99 B165 31.36 31.36 B166 68.73 68.73 B167 73.8 73.8 B168 72.83 72.83 B173 32.53 32.53 B174 74.65 74.65 B175 72.55 72.55 B176 74.91 74.91 B177 73.84 73.84 B178 5.11 5.11 B227 31.49 31.49 B228 68.92 68.92
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE RUBBER MAT
ROOM TOTAL
TO BE CLEANED REMARKS
B229 73.34 73.34 B230 72.85 72.85 B235 30.61 30.61 B236 74.71 74.71 B237 72.8 72.8 B238 74.97 74.97 B239 73.27 73.27 B239A 5.19 5.19 C101 320.76 320.76 C102 21.42 21.42 C103 20.65 20.65 C104 27.12 27.12 C105 91.57 91.57 C106 141.83 141.83 C107 61.51 61.51 C108 21.82 21.82 C109 107.17 107.17 C152 103.02 8.48 111.5 C153 7.76 7.76 C154 106.58 13.66 10.02 130.26 C154A 4.49 4.49 C154B 1.27 1.27 C156 123.41 123.41 C156A 2.36 2.36 C156B 18.71 18.71 C157 99.4 99.4 C158 8.48 8.48 C159 8.64 8.64 C160 89.92 89.92 C160B 7.75 7.75 C160C 10.04 10.04 C160D 4.9 4.9 C160E 6.76 6.76 C201 36.99 36.99 C202 64.23 64.23 C203 21.48 21.48 C204 48.58 48.58 C205 12.8 12.8
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE RUBBER MAT
ROOM TOTAL
TO BE CLEANED REMARKS
C206 36.67 36.67 C207 81.21 81.21 C208 21.82 21.82 C209 20.35 20.35 C214 68.07 68.07 C215 70.4 70.4 C216 69.29 69.29 C218 17.69 17.69 C221 39.82 4.58 44.4 C222 76.35 76.35 C223 68.26 68.26 C224 58.33 8.73 67.06 C224A 4.2 4.2 C224B 2.37 2.37 J104 1.89 1.89 J201 1.65 1.65 S101 26.15 26.15 S102 26.29 26.29 S201 25.32 25.32 S202 24.91 24.91
BLDG 9482
101 588.13 588.13 102 11.57 11.57 103 26.58 26.58 104 9.54 9.54 105 15.18 79.92 95.1 106 7.55 7.55 107 1.35 1.35 108 12.87 12.87 109 1.44 1.44 C102 3.28 3.28 C101 26.84 26.84 C103 4.54 4.54 199-1 14.71 14.71 189 6.24 1.14 7.38 190 9.84 9.84 111 9.18 9.18 199 8.12 8.12 C104 21.88 21.88 199-2 9.95 9.95
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE RUBBER MAT
ROOM TOTAL
TO BE CLEANED REMARKS
199-3 6.96 6.96 199-4 17.3 17.3 199-5 40.29 40.29
TOTAL SM 3817.28 2582.7 0 230.13 0 10.02 145.81 588.13 7375.12
ESTIMATED Floor Measurements for Bechtel ES
BLDG AND ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
BLDG 5005:
161 110.07 110.07 162 19.04 19.04 164 15.96 15.96 165 6.44 6.44 170 443.39 443.39
CORRIDOR #2 16.86 16.86
CORRIDOR #1 7.62 7.62
JC167 1.9 1.9
TOILET 166 13.66 13.66
TOILET 169 22.91 22.91
BLDG 5010A
105 29.24 0 Pool 106 31.7 0 Pool 107 1.63 0 Pool 109 4.6 0 Pool
BLDG 5003
121 57.56 18.7 76.26 122 61.01 18.5 79.51 123 57.49 19.12 76.61 128 15.34 15.34
ENTRY #2 8.09 8.09
ENTRY #1 3.86 3.86
TOILET 123A 3.6 3.6
TOILET 123B 1.47 1.47
TOILET 122B 1.23 1.23
TOILET 122A 1.23 1.23
TOILET 121B 1.48 1.48
TOILET 121A 1.38 1.38
JC 127 1.92 1.92
BLDG 5005R Demolished 105 67.77 Demolished 106 68.03 Demolished 107 68.03 Demolished 108 67.77 Demolished 205 76.31 Demolished
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
206 76.57 Demolished 207 75.98 Demolished 208 76.31 Demolished TOILET 106A 15.89 Demolished TOILET 106B 9.97 Demolished
BLDG 5000 0
103 11.62 11.62 Administrative Space 104 12.15 12.15 105 20.12 20.12 107 44.25 44.25 Administrative Space 108 15.11 15.11 Administrative Space 109 17.15 17.15 Administrative Space 110 17.85 17.85 Administrative Space 111 13.06 13.06 Administrative Space 113 5.27 5.27 115 6.52 6.52 116 26.15 26.15 117 13.39 13.39 118 395.18 395.18 132 66.38 9.61 75.99 133 67.41 9.76 77.17 134 64.74 9.4 74.14 135 69.38 9.64 79.02 136 67.41 9.79 77.2 138 67.41 9.76 77.17 139 66.38 9.61 75.99 140 67.12 9.76 76.88 141 67.12 9.76 76.88 144 89.04 89.04 145 8.57 8.57 150 14.83 14.83 155 66.38 9.63 76.01 156 67.41 9.78 77.19 157 66.38 9.65 76.03 158 67.41 9.8 77.21 159 104.97 104.97 160 317.9 317.92 Cafeteria 182 31.46 31.46
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
202 31.92 31.92 203 42.32 6.58 48.9 206 11.55 11.55 209 65.1 10.59 75.69 210 64.07 10.43 74.5 211 62.46 10.18 72.64 212 65.1 10.59 75.69 216 6.18 6.18 221 65.1 10.59 75.69 222 64.79 10.43 75.22 223 64.73 10.54 75.27 224 64.07 10.43 74.5 229 30.59 30.59 230 56.91 56.91 231 57.59 57.59 232 15.7 15.7 233 50.17 50.17 234 20.11 20.11 236 20.01 20.01 237 65.1 10.59 75.69 238 64.07 10.36 74.43 239 63.87 10.39 74.26 240 63.93 10.43 74.36 248 5.22 5.22 118A 77.11 77.11 118B 6.43 6.43 132C 9 9 144A 25.94 25.94 144B 8.66 157C 10.04 10.04 208A 65.49 65.49
CORRIDOR C101 63.82 63.82
CORRIDOR C102 53.06 53.06
CORRIDOR C103 53.97 53.97
CORRIDOR C104 51.03 51.03
CORRIDOR C105 81.18 81.18
CORRIDOR C106 22.25 22.25
CORRIDOR C107 54.77 54.77
CORRIDOR C108 2.69 2.69
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
CORRIDOR C201 91.23 91.23
CORRIDOR C202 16.45 16.45
CORRIDOR C203 109.31 109.31
CORRIDOR C204 20.14 20.14
CORRIDOR C205 28.58 28.58
CORRIDOR C206 36.54 36.54
STAIRWAY S101 3.53 3.53
STAIRWAY S103 3.3 3.3
STAIRWAY S104 3.29 3.29
STAIRWAY S201 9.45 9.29 18.74
STAIRWAY S203 13.75 13.75
STAIRWAY S204 8.13 8.26 16.39
TOILET 105A 4.28 4.28
TOILET 145A 2.27 2.27
TOILET 183 3.38 3.38
TOILET 184 4.25 4.25
TOILET 185 11.1 11.1
TOILET 186 14.59 14.59
TOILET 187 5.78 5.78
TOILET 189 17.71 17.71
TOILET 190 10.82 10.82
TOILET 191 17.59 17.59
TOILET 192 12.77 12.77
TOILET 241 4.26 4.26
TOILET 242 6.56 6.56
TOILET 243 14.36 14.36
TOILET 244 11.6 11.6
TOILET 245 5.56 5.56
TOILETS 246 26.73 26.73
TOILETS 247 25.8 25.8
BLDG5000R Demolished 101 64.61 Demolished 102 64.88 Demolished 103 64.85 Demolished 104 67.77 Demolished 201 70.25 Demolished 202 70.47 Demolished 203 69.94 Demolished
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
204 70.28 Demolished TOILET 15.88 Demolished TOILET 9.97 Demolished
BLDG 5011R
T109 48.67 14.89 63.56 T110 48.89 14.93 63.82 T111 48.79 14.95 63.74 T112 48.79 14.95 63.74 T209 54.24 16.72 70.96 T210 54.59 16.69 71.28 T211 54.59 16.71 71.3 T212 54.59 16.71 71.3
TOILET T108 16.81 16.81
TOILET T107 12.29 12.29
BLDG 5001
103 88.07 88.07 105 37.42 6.23 43.65 106 54.54 54.54 113 38.23 4.85 43.08 114 51.61 20.8 72.41 122 5.95 5.95 203 63.98 23.55 87.53 204 39.32 8.25 47.57 205 36.86 7.62 44.48 206 45.71 15.32 61.03 207 54.74 54.74 212 41.54 70.7 112.24 213 9.3 9.3 214 18.65 18.65 215 15.13 15.13 216 19.2 19.2 303 54.09 16.3 70.39 304 55.19 16.55 71.74 305 54.9 16.48 71.38 306 51.47 16.4 67.87 307 58.88 5.85 64.73 312 54.4 17.61 72.01
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
313 67.76 67.76 103A 14.9 14.9 103B 10.01 10.01 105A 9.65 9.65 106A 14.6 14.6 114A 9.96 9.96 114B 6.6 6.6 203A 12.17 12.17 204A 5.76 5.76 205A 8.66 8.66 207A 5.19 5.19 207B 3.52 3.52 207C 11.47 11.47 213A 1.69 1.69 307A 11.58 11.58 313A 11.44 11.44
CORRIDOR C101 138.29 138.29
CORRIDOR C102 4.72 4.72
CORRIDOR C201 144.89 144.89
CORRIDOR C301 142.05 142.05
JC115 1.67 1.67
JC121 1.82 1.82
JC219 1.98 1.98
JC301 2.78 2.78
STAIRWAY S101 15.7 15.7
STAIRWAY 3FL 11.73 11.73
STAIRWAY 4FL 18.79 18.79
STAIRWAY S201 23.43 23.43
TOILET 101 11.9 11.9
TOILET 102 11.33 11.33
TOILET 106B 6.75 6.75
TOILET 201 17.11 17.11
TOILET 202 15.76 15.76
TOILET 314 19.62 19.62
TOILET 315 21.01 21.01
TOILETS 113A 2.52 2.52
TOILETS 113B 2.52 2.52
TOILETS 114C 14.16 14.16
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE
CLEANED REMARKS
TOTAL SM 6053.86 468.8 1611.1 529.25 553.46 11.47 100.87 8081.53
ESTIMATED Floor Measurements for Bob Hope PS
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 9480-1 Building No Longer Exists
BLDG 9480-2
301 44.26 41.91 86.17 301A 9.12 9.12 300 44.26 41.91 86.17 300A 9.41 9.41 302 44.26 42.2 86.46 302A 8.93 8.93 303 44.26 42.2 86.46 303A 8.93 8.93 304 44.48 42.19 86.67 304A 9.41 9.41 305 44.48 42.19 86.67 305A 9.41 9.41 306 0 Low Traffic Storage C101 56.02 56.02 401 54.82 15.92 70.74 400 54.81 15.91 70.72 400A 10.16 10.16 400B 17.49 17.49
JC400C 2.32 2.32
C201 48.18 48.18 402 35.8 3.18 38.98 402A 2.45 2.45 403 54.55 15.84 70.39 404 54.81 15.91 70.72 405 54.75 15.89 70.64
BLDG 9480
101 65.45 65.45 Administrative Space 102 14.89 14.89 Administrative Space 103 16.7 16.7 Administrative Space 104 7.99 7.99 Administrative Space 105 13.47 13.47 Administrative Space 106 13.15 13.15 Administrative Space 107 39.18 39.18 108 4.57 4.57 109 33.17 33.17 110 43.45 43.45 112 8.15 8.15 114 10.55 10.55 115 13.32 13.32 117 6.24 6.24
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
118 11.09 11.09 118 8.69 8.69 119 2.89 2.89 120 1.91 1.91 121 11.65 11.65 122 15.4 15.4 123 18.87 18.87 124 17.75 17.75 126 53.04 53.04 127 74.02 74.02 128 3.6 3.6 129 74.53 74.53 130 70.9 70.9 131 1.92 1.92 133 14.89 14.89 134 54.5 54.5 135 77.5 77.5 136 76.82 76.82 137 79.32 79.32 138 70.85 70.85 139 16.85 16.85 140 33.73 33.73 141 9.45 9.45 148 87.61 87.61 149 9.52 9.52 150 8.39 8.39 151 53.48 53.48 152 68.03 68.03 153 74.38 74.38 154 71.26 71.26 157 14.89 14.89 158 53.92 53.92 158 53.92 53.92 159 73.54 73.54 160 72.54 72.54 161 74.58 74.58 162 73.79 73.79 165 68.78 21.9 2.39 93.07 165 14.89 14.89 166 66.04 17.04 2.39 85.47 167 65.26 19.94 2.39 87.59 168 66.79 21.3 2.39 90.48 169 63.08 18.51 2.28 83.87 170 66.61 20.2 2.76 89.57
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
171 89.75 89.75 172 24.73 110.94 135.67 175 9.18 9.18 175A 3.09 3.09 177 7.65 7.65 178 8.62 8.62 182/174 337.01 337.01 183 7.56 7.56 184 14.89 14.89 201 4.99 4.99 203 73.44 73.44 204 5.59 5.59 205 74.3 74.3 206 71.61 71.61 207 53.04 53.04 208 14.89 14.89 209 14.89 14.89 210 54.5 54.5 211 74.19 74.19 212 72.82 72.82 213 74.61 74.61 214 58.4 9.81 68.21 215 78.95 6.13 6.31 91.39 218 57.67 57.67 219 69.25 69.25 220 71.9 71.9 221 13.89 13.89 222 2.34 2.34 223 12.73 12.73 224 6.53 6.53 225 8.06 8.06 226 14.18 14.18 227 84.33 84.33 228 69.49 69.49 229 66.64 66.64 230 69.65 69.65 231 53.02 53.02 232 69.2 69.2 233 74.5 74.5 234 70.96 70.96 236 14.89 14.89 237 14.89 14.89 238 5.24 5.24 239 54.5 54.5
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
240 74.11 74.11 241 72.56 72.56 242 74.68 74.68 243 73.64 73.64 107A 14.55 14.55 111A 51.64 51.64 111B 34.55 34.55 115A 25.71 25.71 115B 20.44 20.44 124A 328.1 328.1 124B 18.92 18.92 124C 25.24 25.24 138A 17.87 17.87 138B 289.92 289.92 Cafeteria 138C 41 41 Cafeteria 148A 9.93 9.93 162A 5.5 5.5 174C 1.03 1.03 175A 3.09 3.09 243A 5.47 5.47 C101 133.77 133.77 C102 110.43 110.43 C103 118.12 118.12 C104 44.07 44.07 C105 47.04 47.04 C106 8.35 8.35 Cafeteria C107 81.91 81.91 C108 190.72 190.72 C201 70.2 70.2 C202 67.53 67.53
JC103 1.85 1.85
JC155 1.93 1.93
JC201 1.93 1.93
JC235 1.94 1.94
JC238 5.24 5.24
STAIR201 25.81 25.81
STAIR202 25.66 25.66
STAIR101 25.81 25.81
STAIR102 25.66 25.66
TOTAL SM 4721.57 2443.98 0 258.7 0 9.81 198.46 337.01 7969.53
ESTIMATED Floor Measurements for Kadena ES
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
2514 E WING
E1 67.26 6.99 74.25 E1A 0.6 0.6 E2 67.52 6.81 74.33 E2A 0.6 0.6 E3 68.2 6.81 75.01 E3A 0.6 0.6 E4 67.99 6.68 74.67 E4A 0.6 0.6 E5 67.9 6.65 74.55 E5A 0.6 0.6 E6 68 6.72 74.72 E6A 0.6 0.6 E7 67.8 6.8 74.6 E7A 0.6 0.6 E8 40.67 40.67 E9 18.5 18.5 E10 17.9 17.9
JC 101 2.59 2.59
2514 D WING
D1 71.06 7.39 78.45 D1A 0.6 0.6 D2 70.52 7.49 78.01 D2A 0.6 0.6 D3 70.97 7.48 78.45 D3A 0.6 0.6 D4 68.32 7.71 76.03 D4A 0.6 0.6 D5 69.8 7.41 77.21 D5A 0.6 0.6 D6 71.29 7.49 78.78 D6A 0.6 0.6 D7 69.33 7.48 76.81 D7A 0.6 0.6 D8 18.3 18.3 D8A 20.54 20.54
TOILET 100 17.9 17.9
TOILET 101 18.71 18.71
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
JC 103 2.65 2.65
JC 104 2.6 2.6
D9 70.27 7.83 78.1 D9A 0.6 0.6 D10 70.62 7.44 78.06 D10A 0.6 0.6 D11 75.16 75.16 D11A 0.6 0.6 D12 38.69 38.69 D13 75.72 75.72 D14 18.48 18.48 D15 17.9 17.9 D16 79.32 79.32
JC 106 2.56 2.56
2514 M WING
M1 44.15 43.55 87.7 M1A 10.96 10.96 M2 44.15 43.43 87.58 M2A 10.98 10.98 M3 44.15 43.49 87.64 M3A 10.96 10.96 M3B 18.42 18.42 M4 44.04 41.85 85.89 M4A 9.16 9.16 M5 44.06 41.98 86.04 M5A 9.16 9.16 M6 44.05 41.97 86.02 M6A 9.16 9.16 M7 60.49 14.78 75.27 M8 60.49 14.78 75.27 M9 60.24 13.12 73.36 M10 12.89 12.89 M11 17.44 17.44 C 101 57.87 57.87
2514 C WING
C1 72.67 5.95 78.62 C1A 0.6 0.6
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
C2 72.1 6.08 78.18 C2A 0.6 0.6 C3 72.44 6.15 78.59 C3A 0.6 0.6 C4 71.47 5.58 77.05 C4A 0.6 0.6 C5 70.95 6.13 77.08 C5A 0.6 0.6 C6 72.71 5.99 78.7 C6A 0.6 0.6 C7 70.72 6.13 76.85 C7A 0.6 0.6 C8 39.2 39.2 C9 70.27 6.61 76.88 C9A 0.6 0.6 C9B 3.71 3.71 C10 70.56 7.47 78.03 C10A 0.6 0.6 C11 70.57 7.49 78.06 C11A 0.6 0.6 C12 70.25 7.27 77.52 C12A 0.6 0.6 C13 106.1 9.81 115.91 C13A 0.6 0.6 C14 17.9 17.9 C15 18.86 18.86 C16 17.91 17.91 C17 17.91 17.91
JC 101 2.62 2.62
JC 102 2.59 2.59
2514 B WING
B1 71.41 9.41 80.82 B1A 1.63 1.63 B1B 1.65 1.65 B1C 0.6 0.6 B2 70.62 5.21 75.83 B2A 1.63 1.63 B2B 1.65 1.65
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
B2C 0.6 0.6 B3 70.84 5.16 76 B3A 1.63 1.63 B3B 1.65 1.65 B3C 0.6 0.6 B4 69.89 4.61 74.5 B4A 1.63 1.63 B4B 1.65 1.65 B4C 0.6 0.6 B5 69.96 5.12 75.08 B5A 1.64 1.64 B5B 1.65 1.65 B5C 0.6 0.6 B6 71.23 5.2 76.43 B6A 1.63 1.63 B6B 1.65 1.65 B6C 0.6 0.6 B7 69.47 4.94 74.41 B7A 1.63 1.63 B7B 1.65 1.65 B7C 0.6 0.6 B8 40 40 B4M 17.9 17.9 B4W 18.73 18.73
JC B4D 2.58 2.58
JC B8A 2.62 2.62
2514 L WING
L9 10.37 10.37 L10 78.89 3 81.89 L10A 6.05 6.05 L10B 6.05 6.05 L10C 5.63 5.63 L11 21.61 21.61 L12 49.79 2.54 52.33 L13 1.56 1.56 L14 28.05 28.05 L15 39.9 39.9 C101 13.52 13.52
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
L16 432.46 432.46 L17 39.03 39.03 L18 37.63 37.63 L21 9.7 9.7 L22 6.384 6.384 L23 3.39 3.39
JC 102 1.46 1.46
2514 F WING
F1 80.59 80.59 F2 80.63 80.63 F3 80.79 80.79 F4 80.47 80.47
TOILET F5 11.68 11.68
TOILET F6 11.81 11.81
JC 102 3.61 3.61
2514 G WING
G1 76.03 76.03 G2 74.33 74.33 G3 76.5 76.5 G4 75.81 75.81 G5 75.66 75.66 G6 77.79 77.79 G7 125.59 125.59 G8 15.06 15.06 G9 17.78 17.78
JC 101 3.93 3.93
2514 I WING
I1 76.03 76.03 I2 74.33 74.33 I3 76.5 76.5 I4 76.49 76.49 I4A 9.57 9.57 I5 76.31 76.31 I5A 9.57 9.57 I5B 34.36 34.36 I6 77.79 77.79
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
I7 125.91 125.91 I8 9.08 9.08 I9 9.08 9.08 I10 17.78 17.78 I11 15.06 15.06
JC 102 3.93 3.93
2514 K WING
K1 95.24 95.24 K2 95.45 95.45 K3 17.92 17.92
2514 H WING
H1 54.94 25.01 79.95 H2 55.54 25.34 80.88 H3 54.58 24.7 79.28 H4 56.04 25.01 81.05 H5 56.69 25.34 82.03 H6 54.74 24.7 79.44 H7 17.68 17.68 H8 17 17
JC 101 2.77 2.77
2514 O WING
1ST FLOOR
105 56.18 3.25 59.43 Administrative Space 106 20.99 0.57 21.56 Administrative Space 107 19.34 1.37 20.71 Administrative Space 108 12.88 1.03 13.91 Administrative Space 108A 13.39 13.39 Administrative Space 109 43.06 1.72 44.78 Administrative Space C101 10.62 10.62 Administrative Space TOILET 6A 3.8 3.8 Administrative Space TOILET 6B 3.44 3.44 Administrative Space
2ND FLOOR
1 39.76 3.24 43 1A 28.07 28.07 1B 22.61 22.61 1C 2.6 2.6
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
2 21.07 0.83 21.9 3 27.6 0.8 28.4 4 8.79 8.79 4A 22.3 3.21 25.51 5 26.16 26.16 5A 1.45 1.45 5B 1.45 1.45 6 3.32 3.32 7 3.9 3.9 8 3.84 3.84 9 2.89 2.89 10 6.04 6.04
JC 201 1.04 1.04
2514 J WING
101 279.89 204.48 484.37 101A 123.04 123.04 J1 612.32 612.32 Cafeteria J1A 21.43 21.43 J3 69.1 69.1 J3A 44.2 44.2 J3B 18.89 18.89 C101 22.16 22.16 C102 183.97 183.97 C103 6.46 6.46 C104 6.65 6.65 J8 55.33 55.33 J9 199.04 199.04 J11 23.19 23.19 J11A 11.99 11.99 J12 33.79 33.79 J13 13.23 13.23 J14 13.18 13.18 J15 10.72 10.72 J16 8.84 8.84 J17 7.76 7.76 J18 3.91 3.91 J19 7.86 7.86 J20 3.42 3.42
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
M104 84.36 84.36
JC J114 13.99 13.99
JC 101 1.69 1.69
2514 A WING 0
A1 71.41 4.91 76.32 A1A 1.63 1.63 A1B 1.65 1.65 A1C 0.6 0.6 A2 70.62 5.21 75.83 A2A 1.63 1.63 A2B 1.65 1.65 A2C 0.6 0.6 A3 70.84 5.16 76 A3A 1.63 1.63 A3B 1.65 1.65 A3C 0.6 0.6 A4 69.89 4.61 74.5 A4A 1.63 1.63 A4B 1.65 1.65 A4C 0.6 0.6 A4D 2.58 2.58 A5 52.28 5.12 12.68 70.08 A5A 1.64 1.64 A5B 1.65 1.65 A5C 0.6 0.6 A6 71.23 5.2 76.43 A6A 1.63 1.63 A6B 1.65 1.65 A6C 0.6 0.6 A7 74.4 74.4 A7A 1.63 1.63 A7B 1.65 1.65 A7C 0.6 0.6 A8 27.34 12.85 40.19 Administrative Space A8A 2.62 2.62 Administrative Space A9 17.9 17.9 A10 18.73 18.73
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL
TO BE CLEANED REMARKS
TOTAL SM 6167.58 2874.26 276.53 590.174 402.93 12.68 355.28 10679.43
ESTIMATED Floor Measurements for Kadena HS
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 9495
102 8.74 8.74 103 8.53 8.53 105 12.24 12.24 106 132.86 132.86 107 46.14 46.14 108 183.8 183.8 109 31.04 31.04 110 14.15 14.15 112 12.49 12.49
BLDG 9493 0
A002 8.83 8.83 A003 3.95 3.95 A100 66.09 66.09 A101 24.76 24.76 A101A 4.48 4.48 A101B 2.16 2.16 A101C 3.88 3.88 A102 67.12 67.12 A103 15.38 15.38 A103 75.78 75.78 A104 66.34 66.34 A105 64.94 64.94 A106 65.52 65.52 A108 7.27 7.27 A200 65.77 65.77 A201 64.84 64.84 A202 65.93 65.93 A203 65.78 65.78 A204 66.42 66.42 A205 66.02 66.02 A207 65.26 65.26 A208 65.49 65.49 A208 5.37 5.37 A209 2.08 2.08 A210 7.15 7.15 A211 5.39 5.39 C101 97.63 97.63 C201 95.43 95.43
STAIR101 10.15 10.15
STAIR102 16.18 16.18
V101 10.21 10.21
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 9490 0
101 73.69 73.69 Administrative Space 102 14.69 14.69 Administrative Space 103 10.01 10.01 Administrative Space 104 10.6 10.6 Administrative Space 105 9.85 9.85 Administrative Space 106 10.43 10.43 Administrative Space 107 39.44 39.44 Administrative Space 109 50.21 50.21 110 1.11 1.11 111 2.52 2.52 Administrative Space 112 171.41 271.77 98.22 541.4 113 68.06 68.06 114 161.29 161.29 115 102.37 102.37 116 12.03 12.03 117 71.12 71.12 118 15.33 15.33 119 1.05 1.05 120 13.68 13.68 123 88.33 88.33 124 81.9 81.9 125 69.94 69.94 126 72.9 72.9 127 75.31122 31.29 128 65.21 65.21 129 62.67 62.67 130 75.03 75.03 131 65.78 65.78 132 49.55 49.55 133 60.48 60.48 134 80.3 80.3 135 138.64 138.64 137 72.5 72.5 138 37.03 37.03 139 72.55 72.55 140 701.57 701.57 Cafeteria 141 9.73 9.73 142 596.08 596.08 143 22.1 22.1 144 56.78 56.78 145 33.92 33.92 146 44.67 44.67 147 48.07 48.07
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
148 13.64 13.64 149 60.94 60.94 150 121.72 121.72 151 102.14 102.14 152 52.25 52.25 153 193.57 193.57 154 33.92 33.92 155 35.17 35.17 156 91.91 91.91 157 77.71 77.71 158 56.02 56.02 159 132.82 132.82 160 100.1 20.03 120.13 161 132 0 Low Traffic Storage 162 69.3 69.3 163 63.96 63.96 164 61.37 61.37 165 19.59 19.59 166 3.71 3.71 167 19.28 19.28 168 74.42 1.89 76.31 169 80.11 80.11 172 12.53 12.53 173 20.5 20.5 174 2.36 2.36 176 134.49 134.49 178 16.36 948.64 965 179 130.51 130.51 201 3.95 3.95 202 69 69 203 23.61 23.61 205 21.76 21.76 206 67.43 67.43 207 84.94 84.94 208 89.03 89.03 209 61.01 61.01 210 75.69 75.69 211 75.13 75.13 212 72.48 72.48 213 84.56 84.56 214 66.91 66.91 215 74.87 74.87 216 60.57 60.57 217 79.86 79.86
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
218 68.71 68.71 219 64.72 64.72 220 71.53 71.53 221 71.39 71.39 222 5.96 5.96 103A 8.49 8.49 Administrative Space 108A 7.36 7.36 108B 2.52 2.52 108C 3.13 3.13 112A 2.52 2.52 Administrative Space 113A 4.89 4.89 113B 3.9 3.9 113C 24.06 24.06 113D 3.14 3.14 113E 2.88 2.88 114A 2.5 2.5 114B 11.42 11.42 114C 2.43 2.43 114D 9.56 9.56 114E 5.81 5.81 114F 2.15 2.15 114G 1.86 1.86 114H 2.87 2.87 114I 2.67 2.67 115A 9.88 9.88 115B 2.69 2.69 115C 2.95 2.95 115D 1.85 1.85 115E 2.41 2.41 116A 14.05 14.05 123A 10.81 10.81 125A 10.24 10.24 125B 1.25 1.25 138A 2.23 2.23 138B 3.53 3.53 138C 7.33 7.33 138D 7.28 7.28 140B 2.41 2.41 142A 11.81 11.81 143A 5.73 5.73 147A 15.79 15.79 147B 15.28 15.28 147C 16.36 16.36 147D 8.61 8.61
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
148A 22.73 22.73 148B 22.89 22.89 151A 14.39 14.39 151B 11.14 11.14 151C 10.54 10.54 151D 31.62 31.62 152A 0.63 0.63 152B 1.54 1.54 152C 0.66 0.66 152D 4.1 4.1 154A 3.43 3.43 156A 3.63 3.63 156B 2.46 2.46 156C 8.37 8.37 156D 35 35 159A 15.34 15.34 159B 14.92 14.92 159C 7.03 7.03 159D 21.61 21.61 Administrative Space 160A 7.12 0 Low Traffic Storage 160B 7.12 0 Low Traffic Storage 160C 17.06 17.06 Administrative Space 161A 9.86 0 Low Traffic Storage 161B 9.86 0 Low Traffic Storage 162A 4.14 4.14 162B 4.1 4.1 163A 7.26 7.26 163C 5.38 5.38 163D 1.32 1.32 168A 4.29 4.29 173A 5.48 5.48 173C 1.34 1.34 176A 10.42 10.42 176B 20.18 14.42 34.6 177A 13.36 13.36
177AT 3.9 3.9
177B 13.87 13.87 177C 20.71 20.71 178A 61.84 1.44 63.28 178B 64.5 64.5 178C 63.68 63.68 178D 53.93 53.93 178E 45.44 45.44 179A 12.72 12.72
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
179B 17.82 17.82 179C 21.68 21.68 179D 19.43 11.42 30.85 179E 4.57 4.57 179F 7.17 7.17 206A 10.17 10.17 215A 2.33 2.33 215B 2.53 2.53 215C 3.85 3.85 C101 12.05 12.05 C102 43.52 43.52 C103 98.15 98.15 C105 263.54 263.54 C106 73.48 73.48 C107 121.29 121.29 C108 62.34 62.34 C109 239.9 239.9 C110 45.51 45.51 C114 73.2 1075.72 1148.92 C116 5.57 5.57 C117 6.5 6.5 C201 37.57 37.57 C202 252.31 252.31
JC201A 23.96 23.96
JC204 1.72 1.72
STAIR 101 12.1 12.1
STAIR201 19.4 19.4
T115 10.63 10.63
TOTAL SM 5143.71122 1347.12 1662.06 754.25 1046.86 10.17 2177.12 219.34 13110.45
ESTIMATED Floor Measurements for Kadena MS
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
TO BE
CLEANED REMARKS
Bldg 9397 V101 8.63 8.63 C101 148.07 18.21 166.28 C102 5.71 5.71 156 29.17 29.17 157 21.18 21.18 157A 13.89 13.89 157B 13.78 13.78 157C 5.49 5.49 158 64.21 64.21 160 61.91 61.91 160A 17.95 17.95 161 57.65 57.65 162 55.42 10.82 66.24 162A 3.93 3.93 165 17.58 17.58 165A 16.21 16.21 165B 15.05 15.05 165C 13.47 13.47 166 57.98 57.98 167 52.9 5.53 58.43 168 13.04 13.04 169 1.28 1.28 170 12.98 12.98 173 3.72 3.72 302 2.04 2.04 Administrative Space 303 2.07 2.07 Administrative Space 305 7.73 7.73 Administrative Space 306 19.08 19.08 Administrative Space 306A 2.77 2.77 Administrative Space 308 63.01 63.01 Administrative Space 309 18.58 18.58 Administrative Space 310 13.97 13.97 Administrative Space 311 13.86 13.86 Administrative Space 312 12.78 12.78 Administrative Space 314 11.72 11.72 Administrative Space 315 19.54 19.54 Administrative Space
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
TO BE
CLEANED REMARKS
Bldg 9398 S101 14.66 14.66 S102 13.92 13.92 C101 126.9 12.23 139.13 C102 45.86 45.86 C103 38.04 38.04 C104 126.37 35.2 161.57 102 22.53 38.42 60.95 103 8.01 8.01 104 27 32.64 59.64 105 20.61 38.71 59.32 106 8.05 8.05 107 25.63 33.54 59.17 108 24.24 35.54 59.78 109 7.78 7.78 110 16.32 42.9 59.22 112 5.17 15.7 20.87 113 5.15 15.6 20.75 114 7.89 7.89 115 15.93 15.93 117 5.08 5.08 119 80.46 80.46 120 72.39 72.39 120A 14.21 14.21 123 16.19 16.19 123A 7.6 7.6 124 367.68 367.68 125 63.59 63.59 125A 11.51 11.51 127 13.22 13.22 131 66.42 66.42 132 66.15 66.15 134 55.34 60.59 115.93 136 6.34 139 3.01 140 69.43 69.43 141 65.33 65.33 142 64.92 64.92 143 34.74 3.63 3.86 42.23 147 4.99 15.98 20.97
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
TO BE
CLEANED REMARKS
148 4.95 15.76 20.71 149 11.32 11.32 151 5.57 5.57 152 5.85 154F 8.3 8.3 S201 24.02 24.02 S202 17.93 17.93 S203 6.01 6.01 C201 127.04 13.02 140.06 C202 13.63 13.63 C203 42.04 42.04 C204 13.75 13.75 C205 117.75 29.63 147.38 203 66.23 66.23 204 64.8 64.8 205 65.15 65.15 206 66.23 66.23 207 65.82 65.82 208 65.15 65.15 209 64.8 64.8 210 66.23 66.23 211 4.88 15.88 20.76 212 4.9 15.55 20.45 213 7.92 7.92 214 18.24 18.24 216 4.34 4.34 219 66.26 66.26 220 64.82 64.82 221 65.15 65.15 222 65.67 65.67 223 66.24 66.24 224 65.27 65.27 225 64.81 64.81 226 66.24 66.24 228 4.9 15.96 20.86 229 4.98 15.72 20.7 230 11.32 11.32 232 5.61 5.61 234A 2.13 2.13 234B 2.12 2.12
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
TO BE
CLEANED REMARKS
234C 2.14 2.14 234D 2.17 2.17
Bldg 9399 C101 43.14 43.14 504 2.53 11.9 14.43 505 2.38 2.38 506 3.83 19.17 23 507 101.8 4.79 106.59 508 106.79 106.79 509 405.64 405.64 Cafeteria 511 59.32 59.32 511A 24.76 24.76 512 52.61 52.61
Bldg 9400 100 1.54 1.54 101 10.07 10.07 102 14.19 14.19 103 2.14 2.14 104 3.75 3.75 105 19.28 19.28 106 10.16 10.16 107 19.5 19.5 108 15.02 15.02 109 9.3 9.3 110 13.75 13.75 113 196.95 196.95
Bldg 9401 V101 26.21 26.21 1 25.21 25.21 1A 9.36 9.36 1B 19.35 19.35 2 25.21 25.21 2A 18.2 18.2 3 1.5 1.5 5 5.05 644.75 649.8 6 34.18 34.18 7 33.95 33.95
CERAMIC
TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
TO BE
CLEANED REMARKS
8 6.42 6.42 8A 3.81 3.81 9 6.42 6.42 9A 3.81 3.81 9C 9.36 9.36
TOTAL SM 3816.49 323.9 801.92 437.61 644.75 10.82 115.75 486.17 6622.21
ESTIMATED Floor Measurements for Killin ES
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 370
101 87.15 87.15 101A 11.29 11.29 102 87.76 87.76 102A 11.29 11.29 C103 61.78 61.78 C102 54.03 54.03 303 92.9 92.9 303A 5.16 0 Kiln Room 304A 1.82 1.82 305 Toilets 13.57 13.57 304 Toilets 13.18 13.18 306 17.67 17.67 306A 40.22 40.22 307 390.73 390.73 309 6.08 6.08 309A Toilet 2.59 2.59 310 56.41 56.41 310A 94.8 94.8 311 5.78 5.78 311A Toilet 4.04 4.04 311B 3.84 3.84 322 268.28 268.28 Cafeteria 322A 13.18 13.18 322B 60.74 60.74 Cafeteria 322C 13.33 13.33 323 96.4 96.4 111 51.45 10.18 61.63 110 Toilet 3.51 3.51
BLDG 370G
101 2.32 2.32 102 8.26 8.26 103 13.03 13.03 104 13.03 13.03
BLDG 371
V101 23.65 23.65 102 41.37 41.37 Administrative Space 104 13.66 13.66 Administrative Space 105 6.98 6.98 Administrative Space 106 Toilet 2.8 2.8 Administrative Space
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
107 1.86 1.86 108 Toilet 4.08 4.08 109 21.39 21.39 111 18.87 18.87 Administrative Space 111A Toilet 2.05 2.05 Administrative Space 112 13.35 13.35 Administrative Space 113 13.07 13.07 Administrative Space 114 12.99 12.99 Administrative Space 118 76.48 25.49 4.33 106.3 118A 3.61 3.61 121 67.7 26 3.89 97.59 123 8.84 8.84 124 66.5 26.02 3.9 96.42 126 10.1 10.1 129 42.76 42.76 130 9.15 9.15 131 8.21 8.21 133 Toilet 4.36 4.36 Administrative Space 134 Toilet 4.36 4.36 Administrative Space 135 7.81 7.81 137 357.4 357.4 138 69.09 4.8 73.89 139 68.21 4.8 73.01 140 Toilet 12.74 12.74 141 1.62 1.62 142 Toilet 11.72 11.72 144 64.16 8.9 73.06 145 65.58 8.36 73.94 146 65.07 8.31 73.38 148 69.08 4.8 73.88 149 68.21 4.8 73.01 150 Toilets 12.74 12.74 151 1.62 1.62 152 Toilets 11.72 11.72 154 65.49 8.97 74.46 155 66.46 8.44 74.9 156 48.59 15.42 64.01 156A 5.89 5.89 160 14.97 5.03 20 161 24.5 24.5 162 42.12 17.31 59.43 163 45.18 16.49 61.67 164AB Toilet 3.02 3.02 165 Toilet 12.74 12.74
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
166 1.62 1.62 167 Toilet 11.72 11.72 169 34.97 12.77 47.74 170 35.16 13.41 48.57 171 44.71 16.81 61.52 172 41.71 19.01 60.72 C101 Corridor 71.21 71.21 C102 Corridor 23.45 23.45 C103 Corridor 60.36 60.36 C104 Corridor 184.77 184.77 C105 Corridor 50.62 50.62 C106 Corridor 80.48 80.48 S101 Stairs 29.16 29.16 S102 Stairs 25.06 25.06 S103 Stairs 8.97 8.97 202 19.56 1.31 20.87 203 21.25 3.95 25.2 203A 4.5 4.5 204 Toilet 4.19 4.19 205 3.06 3.06 206 Toilet 4.36 4.36 207 Toilet 4.36 4.36 208 53.95 53.95 209 66.79 4.8 71.59 210 68.21 4.8 73.01 211 Toilet 12.74 12.74 212 1.62 1.62 213 Toilet 11.72 11.72 214 65.67 6.79 72.46 215 65.57 8.36 73.93 216 65.07 8.31 73.38 218 70.3 4.8 75.1 219 68.21 4.8 73.01 220 Toilet 12.74 12.74 221 1.62 1.62 222 Toilet 11.72 11.72 223 64.14 8.9 73.04 224 65.57 8.36 73.93 225 65.07 8.31 73.38 227 70.36 4.8 75.16 228 68.21 4.8 73.01 230 1.62 1.62 231 Toilet 12.74 12.74 232 Toilet 11.72 11.72
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
233 63.37 9.76 73.13 234 64.85 9.18 74.03 235 65.08 8.31 73.39 236 63.36 4.07 67.43 242 58.05 58.05 C201 Corridor 214.54 214.54 C202 Corridor 173.16 173.16
BLDG 370R
501 44.37 41.26 85.63 501A 9.15 9.15 502 44.37 40.99 85.36 502A 9.15 9.15 503 44.37 41.16 85.53 503A 9.15 9.15 504 64.45 8.79 73.24 505 64.71 8.94 73.65 506 64.69 8.83 73.52 507 Toilets 17.92 17.92 508 Toilets 10.37 10.37 508A 3.9 3.9
BLDG 371R
401A 32.33 32.33 401 40.03 40.03 402A 40.34 40.34 402 31.93 31.93 403B Toilet 18.17 18.17 403A Toilet 12.81 12.81 403 72.37 72.37 404 72.99 72.99 405 81.09 81.09 406 80.55 80.55 407 80.74 80.74 408 81.01 81.01
TOTAL SM 4117.53 1960.5 367.7 314.68 455.31 15.42 0 45.07 7270.98
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 1039
1 60.34 32.87 2.6 95.81 1A 6.96 6.96 2 60.34 32.87 2.6 95.81 3 59.41 35.05 2.6 97.06 3A 2.36 2.36 5 1.6 1.6 6 3.97 3.97 7 Toilet 2.99 2.99 C101 Corridor 14.09 14.09
BLDG 1040R
701 44.15 42.21 86.36 701A 9.63 9.63 702 44.13 42.2 86.33 702A 9.63 9.63 703 44.15 42.2 86.35 703A 9.63 9.63 704 44.15 42.21 86.36 704A 9.47 9.47 705 19.43 19.43 706 19.57 19.57 801 59.35 10.2 69.55 802 59.35 10.2 69.55 803 59.35 10.2 69.55 804 32.87 4.66 37.53 804A Toilet 2.41 2.41 805 Toilet 16.55 16.55 806 Toilet 10.52 10.52 807 1.98 1.98
BLDG 1039R
P-1 77.76 2.16 79.92 P-1A Toilets 14.37 14.37 P-1B Toilets 16.51 16.51 P-2 29.41 2.16 31.57 P-3 37.3 2.16 39.46 P-4 37.76 2.16 39.92 P-5 28.53 2.16 30.69
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
P-6 84.31 2.16 86.47 P-7 83.15 2.16 85.31 P-8 82.87 2.16 85.03
BLDG 1041
501 40.11 40.11 502 36.47 36.47 502A 17.97 17.97 503 51.91 51.91 505 75.33 75.33 508 254 254 Cafeteria 508A 11.93 11.93 515 Toilets 14.15 14.15 516 1.68 1.68 517 Toilets 13.91 13.91 V101 6.12 6.12 C101 Corridor 45.99 45.99 S101 Stairs 44.11 44.11 C201 Corridor 18.12 18.12 C202 Corridor 21.14 21.14 601 29.37 29.37 602 30.53 30.53 603 78.95 78.95 604 18.07 18.07
BLDG 1041A
101 69.04 69.04 101A 11.6 11.6 102 12.01 13.01 103 2.28 2.28 104 3.45 3.45
BLDG 1042
A301 53.22 16.27 69.49 A302 85.35 5.28 90.63 A303 53.32 16.29 69.61 A304 87.36 87.36 A304A 9.92 9.92 A305 49.47 4.92 54.39
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
A305A 18.8 6.62 25.42 A306 30.45 30.45 A307 23.46 23.46 A308 22.45 22.45 A309 11.84 11.84 A310 Toilet 9.09 9.09 A311 1.34 1.34 A312 Toilet 8.62 8.62 A313 Toilet 10.44 10.44 A314 1.49 1.49 A315 9.99 9.99 V101 8.56 8.56 C101 Corridor 109.98 109.98 S101 Stairs 35.5 35.5 A401 53.44 16.36 69.8 A402 53.44 16.36 69.8 A403 53.44 16.36 69.8 A404 53.44 16.36 69.8 A405 1.49 1.49 A406 Toilet 9.68 9.68 A407 Toilet 10.12 10.12 C201 Corridor 73.7 73.7
BLDG 1043
100 3.55 402.91 406.46 100A 63.69 63.69 101 19.1 19.1 101A Toilet 3.35 3.35 102 Toilet 18.71 18.71 103 0.97 0.97 104 Toilet 14.54 14.54 105 11.74 11.74 106 8.04 8.04 106A 2.04 1.78 3.82 107 8.04 8.04 107A 2.04 1.78 3.82 108 11.74 11.74 V101 9.4 9.4
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 1040
112 16.64 16.64 Administrative Office 114 26.95 26.95 Administrative Office 115 11.2 11.2 Administrative Office 116 16.31 3.97 20.28 117 49.36 49.36 Administrative Office 118 1.61 1.61 119 12.42 12.42 111 12.06 12.06 122 41.25 41.25 122A 6.82 6.82 122B Toilet 2.32 2.32 122C Toilet 2.32 2.32 123 35.56 35.56 124 33.92 33.92 126 37.57 37.57 127 49.91 5.44 55.35 128 30.44 30.44 120 301.61 301.61 120A 25.52 25.52 120B 11.49 11.49 129 Toilet 10.16 10.16 130 Toilet 8.36 8.36 131 85.75 5.63 91.38 131A 4.97 4.97 132 55.03 55.03 132A 15.41 15.41 132B 13.67 13.67 132C 5.14 5.14 110 8.7 8.7 133 Toilet 3.71 3.71 134 Toilet 3.95 3.95 135 Toilet 4.11 4.11 136 Toilet 8.36 8.36 137 Toilet 10.16 10.16 138 52.91 52.91 138A 6.91 6.91 138B 15.59 15.59 139 62.26 13.67 75.93
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
140 60.11 16.22 76.33 141 60.11 16.22 76.33 142 60.11 16.22 76.33 143 60.11 16.22 76.33 144 60.11 16.22 76.33 145 60.11 16.22 76.33 146 Toilet 10.16 10.16 147 Toilet 8.36 8.36 C101 Corridor 39.47 39.47 C102 Corridor 105.57 105.57 C103 Corridor 134.47 134.47 C104 Corridor 42.48 42.48 S102 17.43 17.43 S101 19.74 19.74 201 62.33 15.01 77.34 202 62.18 13.93 76.11 203 61.83 14.06 75.89 204 61.83 14.02 75.85 204A Toilet 10.11 10.11 204B Toilet 8.36 8.36 205 62.33 14.04 76.37 206 62.33 14.04 76.37 207 61.44 15.01 76.45 208 61.44 15.01 76.45 208A Toilet 10.11 10.11 208B Toilet 8.36 8.36 209 59.9 15.01 74.91 210 60.38 15.01 75.39 211 61.44 15.01 76.45 212 61.44 15.01 76.45 212A Toilet 10.16 10.16 212B Toilet 8.36 8.36 213 61.44 13.68 75.12 214 61.44 13.77 75.21 215 5.5 5.5 216 Toilet 5.49 5.49 217 Toilet 6.15 6.15 218 2.3 2.3 219 Toilet 4.19 4.19
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
C201 Corridor 105.68 105.68 C202 Corridor 143.21 143.21 C203 Corridor 42.49 42.49 C204 Corridor 42.45 42.45
TOTAL SM 4141.1 1313.06 1094.58 384.39 470.16 15.59 109.38 7529.26
ESTIMATED Floor Measurements for Kubasaki HS
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
BLDG 1400
100 737.94 737.94 C101 4.38 4.38 111 16.48 16.48 114 13.57 13.57 107 6.93 6.93 108 60.35 60.35
BLDG 1402
100A 146.77 146.77 100B 2.34 2.34 100C 2.84 2.84 100D 3.13 3.13 100E 4.64 100F 6.1 100G 3.49 3.49 100H 18.36 18.36 100 251.75 461.23 712.98 100J 23.75 23.75 100K 6.15 6.15 100L 217.42 217.42 100M 6.08 6.08 100N 5.67 5.67 C104 9.36 9.36 C105 9.4 9.4 C102 11.79 11.79 C103 8.82 8.82 101 109.55 9.59 119.14 101A 5.02 5.02 102 243.2 243.2 102A 10.47 10.47 102B 10.51 10.51 102C 10.3 10.3 102D 9.13 9.13 103 186.25 186.25 103A 6.62 6.62 103B 6.7 6.7 103C 9 9 104 56.75 56.75 104A 19.07 19.07 104B 29.59 29.59 105 97.17 97.17
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
105A 6.44 6.44 105B 4.69 4.69 106 11.35 11.35 107 113.25 8.16 121.41 107A 5.94 5.94 107B 7.9 7.9 107C 3 3 107D 1.93 1.93 108 36.98 36.98 109 18.9 18.9 110 18.08 18.08 111 15.18 15.18 112 12.56 12.56 112A 10.84 10.84 113 3.07 3.07 114 12.99 12.99 115 15.99 15.99 116 11.19 11.19 117 5.55 5.55 C101 106.53 106.53 V101 12.5 12.5 V102 30.83 30.83 S101 19.28 19.28 213 79.38 79.38 213A 8.47 8.47 214 81.59 81.59 214A 8.47 8.47 215 115.68 115.68 215A 4.37 4.37 216 68.33 68.33 216A 6.9 6.9 216B 6.54 6.54 217 71.03 71.03 218 66.58 66.58 219 41.25 41.25 219A 1.27 1.27 220 56.59 56.59 220A 23.21 23.21 221 37.25 37.25 221A 23.84 23.84 222 36.13 36.13 223 2.43 2.43
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
C201 108.87 108.87 C202 7.87 7.87 C203 5.88 5.88 201 32.51 0 w Traffic Stora 202 24.09 24.09 203 23.17 23.17 203A 2.94 2.94 204 21.01 21.01 204A 2.34 2.34
BLDG 1404
116 32.75 32.75 115 29.61 29.61 S101 28.62 28.62 201 73.96 73.96 202 51.86 51.86 203 72.94 72.94 204 78.17 78.17 205 78.7 78.7 206A 6.09 6.09 206B 6.05 6.05 206 76.13 76.13 S102 27.02 27.02 207 79.48 79.48 207A 8.7 8.7 208 73.92 73.92 209A 21.8 21.8 209 11.61 30.8 42.41 210 79.54 79.54 210A 8.39 8.39 211 79.48 79.48 211A 5.39 5.39 212 72.93 72.93 213 33.6 33.6 213A 9.95 9.95 214 46.63 46.63 214A 11.64 11.64 C101 318.76 318.76 229 23.86 23.86 230 6.32 6.32 231 9.17 9.17 232 20.48 20.48
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
S201 24.83 24.83 215 73.11 73.11 216 73.71 73.71 217 74.32 74.32 218 71.48 71.48 219 91.75 91.75 220 20.03 20.03 220A 7.32 7.32 220B 12.02 12.02 221 96.05 96.05 221A 8.68 8.68 S202 27.76 27.76 222 51.05 51.05 222A 26.26 26.26 222B 12.3 12.3 223 71.53 71.53 224 74.11 74.11 225 73.93 73.93 226 95.48 95.48 227 83.76 83.76 227A 35.27 35.27 227B 5.46 5.46 227C 8.96 8.96 227D 3.89 3.89 228 84.9 84.9 C201 323.4 323.4
BLDG 1406
603 64.34 64.34 604 64.68 64.68 605 64.5 64.5 606 63.47 63.47 S102 25.04 25.04 609 19.16 19.16 608 21.6 21.6 607 22.74 22.74 602 64.88 64.88 601 65.63 65.63 S101 25.75 25.75 C101 80.96 31.68 112.64 622 68.93 68.93 623 69.29 69.29
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
624 64.5 64.5 625 63.47 63.47 S202 35.89 35.89 628 19.16 19.16 630 21.31 21.31 626 22.87 22.87 627 37.97 37.97 627A 18.55 18.55 627B 3.83 3.83 627C 7.18 7.18 621 65.7 65.7 S201 35.95 35.95
BLDG 1408
401 57.26 57.26 402 22.27 22.27 402A 11.63 11.63 403 64.82 64.82 404 65.09 65.09 405 16.31 16.31 406 20.54 20.54 400 503.57 503.57 400A 17.85 17.85 407 33.72 33.72 407A 6.42 6.42 407B 6.55 6.55 407C 3.39 3.39 407D 3.09 3.09 408 45.22 45.22 409 54.37 54.37 410 54.7 54.7 411 19.18 24.88 44.06 413 15.28 15.28 414 15.17 15.17 417 14.81 14.81 418 16.35 16.35 ministrative Sp 419 16.96 16.96 ministrative Sp 420 15.58 15.58 ministrative Sp 421 16.5 16.5 422 16.35 16.35 423 17.1 17.1 424 15.9 15.9
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
425 15.13 15.13 426 11.59 11.59 ministrative Sp 427 14.68 14.68 ministrative Sp 428 14.45 14.45 429 48.41 48.41 ministrative Sp 431 4.74 4.74 432 10.96 10.96 ministrative Sp 433 10.96 10.96 ministrative Sp 434 7.73 7.73 435 9.42 9.42 436 18.24 18.24 437 44.47 44.47 C101 95.25 95.25 C102 45.6 45.6
BLDG 1410
500 42.31 42.31 500A 2.03 2.03 500B 12.35 12.35 501 1302.43 1302.43 502 206.98 206.98 502A 5.93 5.93 502B 41.19 41.19 502C 40.52 0 w Traffic Stora 502D 21.97 21.97 V107 5.69 5.69 505 77.71 77.71 508 28.13 28.13 508A 8.01 8.01 508B 6.6 6.6 508C 10.67 10.67 509 109.02 109.02 510 138.25 138.25 510A 6.04 6.04 511 27.32 27.32 512 138.11 138.11 512A 5.91 5.91 513 112.51 112.51 515 63.82 63.82 515A 9.82 9.82 518 202.11 202.11 518A 5.93 5.93
ROOM # CARPET SRF VCT
CERAMIC
TILE WOOD TATAMI
RUBBER
MAT CONCRETE
PAINT
CONCRETE
ROOM
TOTAL TO
BE
CLEANED REMARKS
518B 13.67 13.67 518C 13.67 13.67 518D 13.81 13.81 518E 13.81 13.81 518F 9.26 9.26 518H 21.91 21.91 V102 4.71 4.71 519 20.24 20.24 522 10.16 10.16 524 20.24 20.24 V106 6.68 6.68 C102 83.52 83.52 V105 7 7 V104 6.97 6.97 C101 68.07 68.07 V103 6.55 6.55
BLDG 1433
V101 10.82 10.82 105 12.29 12.29 103 10.39 10.39 104 100.37 100.37 106 105.41 105.41
BLDG 1437
701 145.92 145.92 702 78.77 78.77 703A 41.49 41.49 703B 35.51 35.51 704 9.3 9.3 705 9.73 9.73 706 11.85 11.85 707 72.54 8.13 80.67 708 9.65 9.65 709 6.59 6.59 710 10.02 10.02 711 9.41 9.41 700 37.63 37.63 C101 67.66 67.66
TOTAL SM 5572.51 737.94 2733.99 1348.01 1796.21 0 109.02 1219.83 283.61 13717.35
ESTIMATED Floor Measurements for Lester MS
ROOM # CARPET SRF VCT/SVF CERAMIC TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 6371
156 29.19 29.19 157 56.18 56.18 158 57.7 57.7 160 58.4 58.4 161 42.3 12.3 54.6 162 54.89 11.03 65.92 165 27.64 27.64 166 57.44 57.44 167 59.12 59.12 168 13.04 13.04
JC169 1.28 1.28
170 14.13 14.13 173 3.72 3.72 302 2.04 2.04 Administrative Space 303 2.07 2.07 Administrative Space 305 5.83 5.83 Administrative Space 306 18.8 18.8 308 52.29 9.29 61.58 Administrative Space 309 18.82 18.82 Administrative Space 310 13.97 13.97 Administrative Space 311 13.86 13.86 Administrative Space 312 12.78 12.78 Administrative Space 314 11.9 11.9 Administrative Space 315 19.54 19.54 Administrative Space 317 2.98 2.98 156A 2.25 2.25 160A 17.95 17.95 161A 2.32 2.32 162A 3.63 3.63 165B 16.55 16.55 165C 13.98 13.98 306A 2.93 2.93 C101 69.44 13.07 82.51 C102 77.44 6.11 83.55 C104 9.1 9.1
BLDG 6375
101 13.63 13.63 102 5.45 5.45 104 194.9 194.9 105 13.32 13.32 106 5.68 5.68 107 19.73 19.73
ROOM # CARPET SRF VCT/SVF CERAMIC TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
108 14.17 14.17 109 10.08 10.08
JC109A 0.76 0.76
107A 2.08 2.08 108A 4.07 4.07
BLDG 6386 0
102 20.34 20.34 103 20.31 20.31
JC106 1.42 1.42
102A 15.53 15.53 102B 14.02 14.02 103A 15.3 15.3 103B 14.04 14.04 V101 8.08 6.24 14.32
BLDG 6388 0
101 3.91 11.64 15.55 103 97.16 97.16 104 109.58 109.58 106 396.1 396.1 Cafeteria 107 58.8 58.8 108 49.1 49.1 103C 4.87 4.87 104A 3.5 3.5 105A 3.84 15.16 19 106A 25.2 25.2 Cafeteria C101 43.37 43.37
JC101 1.38
JC102 2.42 2.42
BLDG 6377 0
102 25.26 25.26 103 6.53 6.53 104 11.33 11.33 106 26.79 26.79 105 649.68 649.68 108 34.38 34.38 109 6.53 6.53 110 25.26 25.26 112 13.41 13.41 102A 9.14 9.14 103A 3.84 3.84 109A 3.84 3.84
ROOM # CARPET SRF VCT/SVF CERAMIC TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
110A 9.14 9.14 C101 26.56 26.56 C102 6 6 C103 6.11 6.11
JC100 1.47 1.47
BLDG 6373 0
102 60.95 60.95 103 7.76 7.76 104 59.65 59.65 105 59.32 59.32 106 59.78 59.78 106 7.8 7.8 107 59.32 59.32 109 7.76 7.76 110 59.22 59.22 112 5.03 15.78 20.81 113 5.01 15.58 20.59 114 4.7 4.7 115 15.93 15.93 119 80.46 80.46 120 73.72 73.72 123 16.19 16.19 124 363.67 363.67 125 24.94 24.94 127 13.22 13.22 128 11.51 11.51 131 66.42 66.42 132 66.15 66.15 134 55.73 59.87 115.6 136 6.13 6.13 139 3.02 3.02 140 65.7 65.7 141 65.33 65.33 142 64.92 64.92 143 34.99 3.57 38.56 144 1.93 1.93 145 1.93 1.93 147 5.01 15.88 20.89 148 4.95 15.68 20.63 149 9.42 9.42 203 66.23 66.23 204 64.8 64.8 205 65.15 65.15
ROOM # CARPET SRF VCT/SVF CERAMIC TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
206 66.23 66.23 207 65.82 65.82 208 65.15 65.15 209 64.8 64.8 210 66.23 66.23 211 5.06 15.7 20.76 212 5.08 15.37 20.45 213 7.92 7.92 214 17.68 17.68 219 66.24 66.24 220 64.82 64.82 221 65.15 65.15 222 65.67 65.67 223 66.24 66.24 224 65.15 65.15 225 64.81 64.81 226 66.24 66.24 228 5.02 15.78 20.8 229 5.09 15.44 20.53 123A 7.8 7.8 125A 38.34 38.34 154F 8.3 8.3 210A 14.21 14.21 C101 70.33 5.05 75.38 C102 57.06 6.78 63.84 C103 83.87 83.87 C104 90.17 33.95 124.12 C105 33.05 33.05 C201 70.28 12.86 83.14 C202 57.06 57.06 C203 13.83 13.83 C204 42.23 42.23 C205 13.75 13.75 C206 62.41 18.01 80.42 C207 51.7 12.51 64.21
JC117 4.98 4.98
JC151 5.57 5.57
JC216 4.34 4.34
JC230 10.24 10.24
JC232 5.61 5.61
STAIR101 14.87 14.87
STAIR102 14 14
STAIR201 23.96 23.96
STAIR202 17.87 17.87
ROOM # CARPET SRF VCT/SVF CERAMIC TILE WOOD TATAMI CONCRETE
PAINT
CONCRETE
ROOM TOTAL TO
BE CLEANED REMARKS
STAIR203 6.01 6.01
TOTAL SM 3598.45 356.06 1237.43 508.74 649.68 11.03 93.26 194.9 6648.17
ESTIMATED Floor Measurements for Ryukyu MS
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE PAINTED FL
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
BLDG 1984
1ST FL
101 10.35 10.35 102 19.05 19.05 103 248.89 248.89 104 6.94 6.94 105 29.91 29.91 106 134.58 134.58 Administrative Space 107 20.25 20.25 Administrative Space 108 14.49 14.49 Administrative Space 109 14.49 14.49 Administrative Space 110 14.93 14.93 Administrative Space 111 22.44 22.44 Administrative Space 112 25.74 25.74 113 8.41 8.41 114 7.13 7.13 115 51.25 51.25 116 11.75 11.75 117 12.19 12.19 118 12.19 12.19 119 12.19 12.19 120 18.16 18.16 121 24.35 24.35 122 29.78 29.78 122A 3.66 3.66 122B 8.77 8.77 122C 4.23 4.23 123 13.07 13.07 124 73.03 73.03 125 20.18 20.18 126 1.65 1.65 127 20.01 20.01 128 12.51 12.51 129 63.91 63.91 130 20.71 20.71 131 7.04 7.04 S10 10.36 10.36 132 75.5 75.5 132A 8.65 8.65 133 3.35 3.35 134 32.09 32.09 135 31.24 31.24 136 27.66 27.66 136A 29.42 29.42 137 86.76 1.42 88.18 137A 18.43 18.43 138 66.55 66.55
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE PAINTED FL
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
138A 13.05 13.05 138B 10.64 10.64 138C 17.74 17.74 139 88.22 2.02 90.24 139A 18.23 18.23 140 58.91 58.91 140A 13.06 13.06 140B 10.72 10.72 141 86.78 2.36 89.14 141A 18.53 18.53 142 2.02 2.02
2ND FL
S10A 25 25 S10B 4.82 4.82 303 262.52 262.52 304 6.94 6.94 305 62.25 1.62 63.87 306 62.37 1.97 64.34 307 61.16 2.02 63.18 308 61.79 1.84 63.63 309 74.6 74.6 309A 18.01 18.01 310 61.79 1.84 63.63 311 28.51 28.51 312 59.05 3.36 62.41 313 30.76 30.76 314 1.67 1.67 315 65.63 65.63 316 5.92 5.92 317 60.07 1.62 61.69 318 63.48 2.17 65.65 319 73.47 73.47 319A 18.38 18.38 320 63.36 1.62 64.98 321 73.47 73.47 321A 18.27 18.27 322 62.18 1.62 63.8 323 61.07 1.85 62.92 324 66.79 1.62 68.41 325 59.3 1.62 60.92 326 61.94 2.21 64.15
BLDG 1985
1ST FL
201 10.25 10.25 202 24.81 24.81 203 355.85 355.85
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE PAINTED FL
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
204 7.04 7.04 205 27.42 27.42 206 62.96 2.03 64.99 207 60.91 1.85 62.76 208 81.84 81.84 208A 15.98 15.98 209 62.78 2.12 64.9 210 85.55 85.55 210A 15.98 15.98 211 62.38 1.85 64.23 212 53.54 2.25 55.79 212A 8.73 8.73 213 62.12 2.12 64.24 214 5.36 5.36 215 31.83 2.27 34.1 215A 5.36 5.36 216 19.88 19.88 217 77.41 77.41 218 32.04 32.04 219 1.75 1.75 220 34.28 34.28 221 58.87 1.85 60.72 222 85.89 85.89 222A 15.39 15.39 223 61.11 2.25 63.36 224 45.48 1.02 46.5 224A 9.02 9.02 225 61.21 2.05 63.26 226 45.48 1.02 46.5 226A 9.02 9.02 227 62.3 2.05 64.35 228 83.25 83.25 228A 16 16 229 62.06 2.05 64.11 230 83.25 83.25 230A 16 16 231 61.04 2.19 63.23 232 45.53 1.3 46.83 232A 10.28 10.28
2ND FL
403 346.22 346.22 404 7.04 7.04 405 64.19 2.03 66.22 406 67.59 1.85 69.44 407 62.43 2.25 64.68 408 66.68 1.62 68.3 409 62.06 2.25 64.31
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE PAINTED FL
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
410 79.55 79.55 410A 15.39 15.39 412 51.42 2.26 53.68 412A 12.51 12.51 413 28.2 28.2 414 5.68 5.68 415 2.09 2.09 416 28.22 28.22 417 67.4 67.4 418 83.2 1.62 84.82 419 44.69 7.3 51.99 419A 11.21 11.21 420 80.56 80.56 420A 15.38 15.38 421 61.26 2.25 63.51 422 62.78 1.62 64.4 423 61.11 2.05 63.16 424 64.95 4.62 69.57 425 62.62 1.82 64.44 426 63.74 2.14 65.88 427 62.09 2.05 64.14 428 84.96 84.96 428A 15.98 15.98 429 61.45 1.97 63.42 230 60.61 1.62 62.23
BLDG 1986
501 39.9 39.9 502 51.29 51.29 503 72.41 72.41 504 76.47 76.47 505 167.05 167.05 506 6.92 6.92 507 200.56 200.56 508 417.68 417.68 508A 82.01 82.01 509 62.58 62.58 510 32.27 32.27 511 29.26 29.26 512 20.24 20.24 513 6.82 6.82 514 223.2 223.2 514A 13.07 13.07 514B 12.73 12.73 514C 7.79 7.79 514D 7.79 7.79 514E 9.85 9.85
ROOM # CARPET SVF VCT
CERAMIC
TILE WOOD TATAMI CONCRETE PAINTED FL
RUBBER
MAT
ROOM TOTAL TO
BE CLEANED REMARKS
514F 9.85 9.85 514G 18.16 18.16 515 533.23 533.23 Cafeteria 516 119.12 119.12 517 16.29 16.29 518 9.56 9.56 519 9.9 9.9 520 14.77 14.77 521 7.86 7.86 530 67.95 67.95 531 17.43 17.43 532 26.02 26.02 532A 3.7 3.7 533 12.19 12.19 534 3.3 3.3 535 20.95 20.95 536 23.97 23.97 537 82.23 82.23 537A 22.17 22.17 538 91.07 91.07 538A 22.89 22.89 539 98.9 98.9 539A 13.2 13.2 539B 9.54 9.54 540 19.88 19.88 541 81.07 81.07 541A 5.71 5.71…