Attachment X11
Questions and Answers
2/11/2022 – Q: Can subcontractors submit PPQs? A: Yes, information for a subcontractor that is performing on a contract that you are the prime contractor may be included. Also, work that the subcontractor that you are planning on using and has performed may also be submitted.
If a PPQ for a subcontractor is submitted, it will be used in your evaluation.