This document contains questions and answers regarding the Defense Information Systems Agency's solicitation for upgrading the security system at the San Antonio data center. The solicitation seeks to replace the existing access control system, including door locks, releases and high-security hardware. It will also upgrade the closed circuit television surveillance system with new cameras, monitors and network video recorders to be installed in three areas. Vendors must estimate cable lengths and will be responsible for cable disposal. DISA will provide cable tray plans and storage for removed equipment. The existing cabling can be reused if tested successfully. All new equipment must be installed, including access control boards. The incumbent contractor is Johnson Controls. The pre-proposal site survey is scheduled for June 7th and responses to vendor questions will be provided after award. A five-day extension may be granted upon request.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I just received some more last minute questions. I apologize for how they have only trickled in when I thought I got them all. Please see the rest below.
Are all currently installed single and dual magnetic locks and electronic strikes in full operating order now? If not, how many are not fully operational? They are all operational.
Are all currently installed egress motion sensors and push-to-exit buttons on doors in full operating order? If not, how many are not fully operational? They are fully operational.
Are all currently installed emergency egress push/crash bars in full operating order? If not, how many are not fully operational? Yes they are all operational.
Can we use existing fiber to cameras in parking lots?
If existing fiber exists, it can be reused as long as it tests good.
Is there 120V power at the pole cameras? The cameras have power going to them but uncertain of voltage.
Can you clarify 6.5.2 Subtask 5.2 – Redistribute Camera Feeds to NVR units? Will there be an NVR in each of those three areas? Yes
What color warning beacons are needed? Blue
Outside portion of the site walk survey:
1. The camera locations are all identified on the documentation, but the cable distances are not. Can DISA provide the cable distances? Drawing are to scale-please estimate lengths.
Inside portion of the site walk survey:
2. Existing Biometrics panels are being removed. Will DISA provide exact paints specifications so that it will match existing wall color? This will be provided after award.
3. Are vendors required to provide Detex in the scope of work or is DISA providing the DETEX. Not sure what DETEX is?
4. Is DISA responsible for disposing of the legacy equipment being replaced? Yes
5. Please describe the specific location in which we need to store the equipment that is being removed? A storage area will be provided.
6. Will we the successful vendor be required to assist with asset tag removal? No
7. Does the successful vendor need to install new asset tags on new DISA Equipment? No
8. Will the old legacy cable also be disposed by DISA? Vendor will be responsible for cable disposal.
9. DISA cables are currently under the floor in the computer room. Will the successful vendor be required to install all cabling in the empty cable racks above? Yes
10. Will DISA be providing the cable tray plans with rack elevations? DISA will provide cable tray plans but not rack elevations. Rack height can be estimated at 7’0”.
11. Who is the current vendor providing maintenance on the current ACS system? Johnson Controls
12. Will DISA be providing the cable path for the new ACS cable runs? DISA will assist cable paths.
13. Will the successful vendor be required to replace everything, including the ACS boards? Yes-All equipment needs to be new.
14. Will plans have a rack elevation? No
15. ACS Cabinet M07 Panel #2 is inaccessible because a key is broken off in the lock. Will DISA be responsible for opening Panel #2? Yes
16. Are larger monitors required in the IT personnel room? If so, what size? Monitor locations are provided in the PWS as well as monitor sizes. Are you referring to security managers office as the IT personnel room?
17. Vendors will require an additional 5 business days after receipt of DISA answer to Vendors questions. Will DISA grant a 5 day extension? To be decided by contracting.
Also, is there an existing access control system in place, or is this new installation including power supplies, wire, and data run? The existing ACS control system will be replaced in full with the exception of existing Cat 5/6, fiber can be reused if tested ok
Are vendors required to provide Detex in the scope of work or is DISA providing the DETEX. Vendors are required to provide.
LKM 7000, and LKM 10000 High security hardware. this hardware has typeI,II,III,IV,VII,IX & X. Do we know specifically which one you want or what the specific application is for the lock. LKM 7000