This memorandum from the Director of Operational Test and Evaluation establishes guidelines for using production-representative systems in Initial Operational Test and Evaluation (IOT&E). It specifies that IOT&E should utilize Low Rate Initial Production systems assembled with the parts, tools, manufacturing processes, software, logistics systems, and maintenance manuals intended for full-rate production. When using LRIP systems is impractical, the system must at least incorporate the same hardware, software, and manufacturing processes defined in critical design reviews and intended for full-rate production. The Director must be provided details on any process differences to independently evaluate their acceptability. Adherence to these guidelines will be assessed as part of reviewing and approving Test and Evaluation Master Plans and Test Plans, and proposals to use non-LRIP systems must demonstrate compliance with the criteria.
The related solicitation seeks Test, Evaluation, and Certification services for the Joint Interoperability Test Command to ensure systems, networks and platforms meet interoperability, information assurance and cybersecurity requirements. The Defense Information Systems Agency is the contracting agency.
View the file
Other files for this federal contract opportunity
Show all 50
TEC II Services RFP has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OFFICE OF THE SECRETARY OF DEFENSE
1700 DEFENSE PENTAGON
WASHINGTON, DC 20301-1700
OCT 1 8 2010
OPERATIONAL TEST
AND EVALUATION
MEMORANDUM FOR COMMANDER, ARMY TEST AND EVALUATION
COMMAND
COMMANDER, OPERATIONAL TEST AND EVALUATION
FORCE
COMMANDER, AIR FORCE OPERATIONAL TEST AND
EVALUATION CENTER
DIRECTOR, MARINE CORPS OPERATIONAL TEST AND
EVALUATION ACTIVITY
COMMANDER, JOINT INTEROPERABILITY TEST
COMMAND
DEPUTY UNDER SECRETARY OF THE ARMY, TEST &
EVALUATION COMMAND
DEPUTY, DEPARTMENT OF THE NAVY TEST &
EVALUATION EXECUTIVE
DIRECTOR, TEST & EVALUATION, HEADQUARTERS,
U.S. AIR FORCE
TEST AND EVALUATION EXECUTIVE, DEFENSE
INFORMATION SYSTEMS AGENCY
SUBJECT: Use of Production-Representative Test Articles for Initial Operational Test and Evaluation (IOT&E)
Consistent with Title 10 USC 2400, Department of Defense (DoD) Directive
5000.01 and DoD Instruction 5000.02 state production-representative articles should be used for test and evaluation. This memorandum expands upon the discussion of production representative systems contained in the Defense Acquisition Guidebook, Section 9.4.3. DOT&E will use the following criteria in evaluating whether systems are production-representative.
Wherever practicable, 101'&E will be conducted using low-rate initial production (LRIP) systems assembled using the parts, tools, and manufacturing processes intended for use in full-rate production. The system will also utilize the intended production versions of software. In addition, the logistics system and maintenance manuals intended for use on the fielded system should be in place.
When the use ofLRIP articles is impractical, the system used in 101'&E should, at a minimum, incorporate the same parts and software to be used in LRIP articles. In particular, the hardware and software should be as defined by the system-level Critical o
Design Review, Functional Configuration Audit, and System Verification Review, including correction of appropriate major deficiencies identified during developmental testing. Manufacturing processes to be used in full-rate production should also be adhered to as closely as possible. DOT&E must be provided detailed infonnation describing any process differences in order to independently evaluate whether the differences are acceptable.
DOT&E will assess adherence to the above guidelines as part of its responsibility for reviewing and approving Test and Evaluation Master Plans and Test Plans. Proposals to use articles not from LRIP to conduct lOT&E will be considered for approval by DOT&E using the criteria stated above as part of those reviews.