This is a Memorandum for Record from the Air Force Sustainment Center (AFMC) Operating Location at Robins Air Force Base, Georgia, establishing contract requirements for hazardous material abatement services focused on asbestos and lead-based paint (LBP) removal and remediation.

The contractor must provide all resources and personnel necessary to perform asbestos and lead-based paint abatement work while ensuring maximum safety for personnel and property. Work must comply with current federal regulations including OSHA 29 CFR 1926.1101 (asbestos), OSHA 29 CFR 1926.62 (lead), EPA 40 CFR Part 61 Subpart M (Asbestos NESHAP), EPA 40 CFR Part 745 (Lead RRP Rule), and EPA 40 CFR Parts 260-272 (RCRA), along with applicable DoD and Air Force directives. The contractor must submit separate, site-specific Asbestos Abatement Plans and Lead Compliance Plans for approval by the Contracting Officer (CO) and Contracting Officer's Representative (COR) at least 10 business days before work commences. All asbestos supervisors and workers must be state and federally accredited and licensed, while lead supervisors must be EPA Certified Renovators with workers trained per applicable regulations. Upon work completion, each area must pass final clearance by an independent third party. The contractor bears full responsibility for cradle-to-grave waste disposal and must provide all disposal manifests and certificates to the CO and COR within 10 business days of disposal completion.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE SUSTAINMENT CENTER (AFMC) OPERATING LOCATION

ROBINS AIR FORCE BASE GEORGIA

Deliver and Support Agile War-Winning Capabilities

MEMORANDUM FOR RECORD:

FROM: AFSC/PZIOB

SUBJECT: HAZARDOUS MATERIAL ABATEMENT: ASBESTOS AND LEAD-BASED PAINT

C.5.8.1 General: The Contractor shall furnish all resources for asbestos and lead-based paint (LBP) abatement, ensuring maximum safety for personnel and property. Work must adhere to all governing federal, state, local, and Air Force directives, with the most stringent requirement prevailing in any conflict.

C.5.8.2 Governing Directives: The Contractor must comply with the current versions of all governing directives, including:

• Federal:

o OSHA 29 CFR 1926.1101 (Asbestos) o OSHA 29 CFR 1926.62 (Lead) o EPA 40 CFR Part 61, Subpart M (Asbestos NESHAP) o EPA 40 CFR Part 745 (Lead RRP Rule) o EPA 40 CFR Parts 260-272 (RCRA)

• DoD/Air Force:

o AFI 32-7040 (Air Quality) o AFI 91-203 (Occupational Safety) o USACE EM 385-1-1 (Safety and Health)

C.5.8.3 Abatement Plans: At least 10 business days before work, the Contractor must submit separate, site-specific abatement plans for approval from the CO and COR

• a. Asbestos Abatement Plan (AAP): Must detail procedures for controls, air monitoring, PPE, and waste handling.

• b. Lead Compliance Plan (LCP): Must detail procedures for removal, containment, waste characterization, PPE, and decontamination.

C.5.8.4 Personnel Qualifications:

• a. Asbestos: All supervisors and workers must be accredited and licensed as required by state and federal law.

• b. Lead: Supervisors must be EPA Certified Renovators; workers must be trained per 29 CFR 1926.62.

C.5.8.5 Final Clearance: Upon completion, each work area must pass a final clearance conducted by an independent third party.

C.5.8.6 Waste Management: The Contractor is responsible for cradle-to-grave waste disposal and must provide all manifests and certificates to the CO and COR within 10 business days of disposal.