HARVARD-LITTLETON-ACTON-CONCORD-611952-134796-A1.pdf

PDF 1 MB Posted

Attached to
611952 HARVARD-LITTLETON-ACTON-CONCORD FAP No. HSI-003S(985)X Guide and Traffic Sign Replacement o
Solicitation number
BD-27-1030-0H100-0H002-130565
Issued by
Middlesex County, Massachusetts

About this file

This is Addendum No. 1 to the contract documents for the Massachusetts Department of Transportation (MassDOT) Highway Division's guide and traffic sign replacement project on Route 2 in Harvard-Littleton-Acton-Concord, Federal Aid Project No. HSI-003S(985)X. The addendum, issued July 17, 2026, transmits revisions to multiple contract documents including updates to the Notice to Contractors (Document 00104, page 3), complete replacements of the prevailing wage and fringe benefits document (Document 00760, 12 pages) and the steel price adjustment document (Document 00813, 4 pages), and revisions to special provisions (Document A00801, page 5). The proposal opening date and time remains Tuesday, July 21, 2026, at 2:00 p.m. Bidders must acknowledge Addendum No. 1 in their Expedite Proposal file before submitting their bids.

The addendum establishes price adjustment provisions for hot mix asphalt, Portland cement, diesel fuel, gasoline, and structural steel, with base prices of $712.50 per ton for liquid asphalt, $452.13 per ton for Portland cement, $3.911 per gallon for diesel fuel, and $3.136 per gallon for gasoline. The Steel Base Price Index is 370.1. Price adjustments for structural and reinforcing steel apply only when variances between base and period prices reach 5% or more and exclude fabrication costs, guardrail panels, handling, transportation, and installation charges. The period price calculation uses the U.S. Department of Labor Bureau of Labor Statistics Producer Price Index (PPI Series ID WPU101702) based on the steel delivery date, with adjustments paid under designated pay items (999.449 for positive structural steel adjustments, 999.457 for credits; 999.466 for positive reinforcing steel adjustments, 999.467 for credits). Additional requirements include compliance with MassDOT Policy Directive P-22-001 for off-site soil stockpiling, implementation of integrated cost and schedule controls through the Contractor Field Completion milestone, and certification that all motor vehicles comply with truck safety device requirements per 540 CMR 4.00, including lateral protective devices, convex mirrors, crossover mirrors, and backup cameras.

View the file

Other files

File Type Posted
611952 - Plan Holders List 7-7-2026.pdf PDF
A00875-611952.pdf PDF
Link to Bid Opening 7-21-2026.pdf PDF
A00801-611952.pdf PDF
A00804-611952.pdf PDF
611952 - Plan Holders List 7-20-2026.pdf PDF
BIDS OPENED - Tuesday - July 21-2026.pdf PDF
611952 - Bid Tabulations.pdf PDF
A00820-611952.pdf PDF
611952 Bid Items List.txt TXT text file
611952 - Notice to Contractors.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ten Park Plaza, Suite 4160, Boston, MA 02116 Tel: 857-368-4636, TTY: 857-368-0655 mass.gov/massdot

July 17, 2026

611952-134796

ADDENDUM NO. 1

To Prospective Bidders’ and Others on:

HARVARD-LITTLETON-ACTON-CONCORD

Federal Aid Project No. HSI-003S(985)X

Guide and Traffic Sign Replacement on a Section of Route 2

THIS PROPOSAL TO BE OPENED AND READ: TUESDAY, JULY 21, 2026, at 2:00 P.M.

Transmitting revisions to the Contract Documents as follows:

DOCUMENT 00104: Revised page 3.

DOCUMENT 00760: Deleted document in its entirety and inserted new document (12 pages).

DOCUMENT 00813: Deleted document in its entirety and inserted new document (4 pages).

DOCUMENT A00801: Revised page 5.

Take note of the above, substitute the revised pages for the originals, delete the documents indicated, insert the new documents in proper order, and acknowledge Addendum No. 1 in your Expedite Proposal file before submitting your bid.

Very truly yours, Eric M. Cardone, P.E.

Construction Contracts Engineer

CD

cc: Stephen Timmins, Project Manager

THIS PAGE IS INTENTIONALLY LEFT BLANK

Massachusetts Department Of Transportation Highway Division Proposal No. 611952-134796

00104 - 3

NOTICE TO CONTRACTORS (Continued)

PRICE ADJUSTMENTS

This Contract contains price adjustments for hot mix asphalt and Portland cement mixtures, diesel fuel, and gasoline. For reference the base prices are as follows: liquid asphalt $712.50 per ton, Portland cement $452.13 per ton, diesel fuel $3.911 per gallon, and gasoline $3.136 per gallon, and Steel Base Price Index 370.1. MassDOT posts the Price Adjustments on their Highway Division’s website at:

https://www.mass.gov/massdot-contract-price-adjustments

This Contract contains Price Adjustments for steel. See Document 00813 - PRICE ADJUSTMENT FOR STRUCTURAL STEEL AND REINFORCING STEEL for their application and base prices.

MassDOT projects are subject to the rules and regulations of the Architectural Access Board (521 CMR 1.00 et seq.)

Prospective bidders and interested parties can access this information and more via the internet at:

WWW.COMMBUYS.COM.

BY: Phillip Eng, Interim MassDOT Secretary Jonathan L. Gulliver, Undersecretary and Highway Administrator

SATURDAY, JUNE 13, 2026

Addendum No.1, Friday, July 17, 2026 https://www.mass.gov/massdot-contract-price-adjustments http://www.commbuys.com/

00760 - 1

Proposal No. 611952-134796 Addendum No. 1, July 17, 2026

Wage rates and fringe benefits.

Provided, Frequently recurring classifications.

Conformance.

00760 - 2

DBAconformance@dol.gov

DBAconformance@dol.gov, Fringe benefits not expressed as an hourly rate.

Unfunded plans.

Provided, Interest.

Withholding requirements.

Priority to withheld funds.

Basic record requirements Length of record retention.

Information required.

00760 - 3

Additional records relating to fringe benefits.

Additional records relating to apprenticeship.

Certified payroll requirements Frequency and method of submission.

Information required.

e.g., https://www.dol.gov/sites/dolgov/files/WHD/ legacy/files/wh347/.pdf

Statement of Compliance.

Use of Optional Form WH–347.

Signature.

Falsification.

Length of certified payroll retention.

Contracts, subcontracts, and related documents.

Required disclosures and access Required record disclosures and access to workers.

00760 - 4

Sanctions for non-compliance with records and worker access requirements.

Required information disclosures.

Apprentices Rate of pay.

Fringe benefits.

Apprenticeship ratio.

Reciprocity of ratios and wage rates.

Equal employment opportunity.

00760 - 5

Withholding process.

Priority to withheld funds.

00760 - 6

00760 - 7

00760 - 8

00760 - 9

00760 - 10

00760 - 11

00760 - 12

Addendum No.1, July 17, 2026

00813 - 1

DOCUMENT 00813

SPECIAL PROVISIONS

PRICE ADJUSTMENTS FOR STRUCTURAL STEEL AND REINFORCING STEEL

July 15, 2026

This special provision applies to all projects containing the use of structural steel and/or reinforcing steel as specified elsewhere in the Contract work. It applies to all structural steel and all reinforcing steel, as defined below, on the project. Compliance with this provision is mandatory, i.e., there are no “opt-in” or “opt-out” clauses. Price adjustments will be handled as described below and shall only apply to unfabricated reinforcing steel bars and unfabricated structural steel material, consisting of rolled shapes, plate steel, sheet piling, pipe piles, steel castings and steel forgings.

Price adjustments will be variances between Base Prices and Period Prices. Base Prices and Period Prices are defined below.

Price adjustments will only be made if the variances between Base Prices and Period Prices are 5% or more. A variance can result in the Period Price being either higher or lower than the Base Price. Once the 5% threshold has been achieved, the adjustment will apply to the full variance between the Base Price and the Period Price.

Price adjustments will be calculated by multiplying the number of pounds of unfabricated structural steel material or unfabricated reinforcing steel bars on a project by the index factor calculated as shown below under Example of a Period Price Calculation.

Price adjustments will not include guardrail panels or the costs of shop drawing preparation, handling, fabrication, coatings, transportation, storage, installation, profit, overhead, fuel costs, fuel surcharges, or other such charges not related to the cost of the unfabricated structural steel and unfabricated reinforcing steel.

The weight of steel subject to a price adjustment shall not exceed the final shipping weight of the fabricated part by more than 10%.

Base Prices and Period Prices are defined as follows:

Base Prices of unfabricated structural steel and unfabricated reinforcing steel on a project are fixed prices determined by the Department and found in the table below. While it is the intention of the Department to make this table comprehensive, some of a project’s unfabricated structural steel and/or unfabricated reinforcing steel may be inadvertently omitted. Should this occur, the Contractor shall bring the omission to the Department’s attention so that a contract alteration may be processed that adds the missing steel to the table and its price adjustments to the Contract.

The Base Price Date is the month and year of the most recent finalized period price index at the time that MassDOT opened bids for the project. The Base Price Index for this contract is the Steel PPI listed in the Notice to Contractors.

Period Prices of unfabricated structural steel and unfabricated reinforcing steel on a project are variable prices that have been calculated using the Period Price Date and an index of steel prices to adjust the Base Price.

The Period Price Date is the date the steel was delivered to the fabricator as evidenced by an official bill of lading submitted to the Department containing a description of the shipped materials, weights of the shipped materials and the date of shipment. This date is used to select the Period Price Index.

The index used for the calculation of Period Prices is the U.S. Department of Labor Bureau of Labor Statistics Producer Price Index (PPI) Series ID WPU101702 (Not Seasonally Adjusted, Group: Metals and Metal Products, Item: Semi-finished Steel Mill Products.) As this index is subject to revision for a period of up to four (4) months after its original publication, no price adjustments will be made until the index for the period is finalized, i.e., the index is no longer suffixed with a “(P)”.

Addendum No.1, July 17, 2026

00813 - 2

Period Prices are determined as follows:

Period Price = Base Price X Index Factor Index Factor = Period Price Index / Base Price Index

Example of a Period Price Calculation:

Calculate the Period Price for December 2009 using a Base Price from March 2009 of $0.82/Pound for 1,000 Pounds of ASTM A709 (AASHTO M270) Grade A36 Structural Steel Plate.

The Period Price Date is December 2009. From the PPI website*, the Period Price Index = 218.0.

The Base Price Date is March 2009. From the PPI website*, the Base Price Index = 229.4.

Index Factor = Period Price Index / Base Price Index = 218.0 / 229.4 = 0.950 Period Price = Base Price X Index Factor = $0.82/Pound X 0.950 = $0.78/Pound

Since $0.82 - $0.78 = $0.04 is less than 5% of $0.82, no price adjustment is required.

If the $0.04 difference shown above was greater than 5% of the Base Price, then the price adjustment would be 1,000 Pounds X $0.04/Pound = $40.00. Since the Period Price of $0.78/Pound is less than the Base Price of $0.82/Pound, indicating a drop in the price of steel between the bid and the delivery of material, a credit of $40.00 would be owed to MassDOT. When the Period Price is higher than the Base Price, the price adjustment is owed to the Contractor.

* To access the PPI website and obtain a Base Price Index or a Period Price Index, go to http://data.bls.gov/cgi-bin/srgate

End of example.

The Contractor will be paid for unfabricated structural steel and unfabricated reinforcing steel under the respective contract pay items for all components constructed of either structural steel or reinforced Portland cement concrete under their respective Contract Pay Items.

Price adjustments, as herein provided for, will be paid separately as follows:

Structural Steel Pay Item Number 999.449 for positive (+) pay adjustments (payments to the Contractor)

Pay Item Number 999.457 for negative (-) pay adjustments (credits to MassDOT Highway Division)

Reinforcing Steel Pay Item Number 999.466 for positive (+) pay adjustments (payments to the Contractor)

Pay Item Number 999.467 for negative (-) pay adjustments (credits to MassDOT Highway Division)

No price adjustment will be made for price changes after the Contract Completion Date, unless the MassDOT Highway Division has approved an extension of Contract Time for the Contract.

Addendum No.1, July 17, 2026

00813 - 3

TABLE

Price per Steel Type Pound

1 ASTM A615/A615M Grade 60 (AASHTO M31 Grade 60 or 420) Reinforcing Steel $0.57

2 ASTM A27 (AASHTO M103) Steel Castings, H-Pile Points & Pipe Pile Shoes (See Note below.)

$0.80

3 ASTM A668 / A668M (AASHTO M102) Steel Forgings $0.80

4 ASTM A108 (AASHTO M169) Steel Forgings for Shear Studs $0.82

5 ASTM A709/A709M Grade 36 / AASHTO M270M/M270 Grade 36 or 250 Structural Steel Plate

$0.86

6 ASTM A709/A709M Grade 36 / AASHTO M270M/M270 Grade 36 or 250 Structural Steel Shapes

$0.81

7 ASTM A709/A709M Grade 50 / AASHTO M270M/M270 Grade 50 or 345 Structural Steel Plate

$0.86

8 ASTM A709/A709M Grade 50 / AASHTO M270M/M270 Grade 50 or 345 Structural Steel Shapes

$0.81

9 ASTM A709/A709M Grade 50WT / AASHTO M270M/M270 Grade 50WT or 345WT Structural Steel Plate

$0.89

10 ASTM A709/A709M Grade 50WT / AASHTO M270M/M270 Grade 50WT or 345WT Structural Steel Shapes

$0.82

11 ASTM A709/A709M Grade 50W / AASHTO M270M/M270 Grade 50W 345W Structural Steel Plate

$0.89

12 ASTM A709/A709M Grade 50W / AASHTO M270M/M270 Grade 50W or 345W Structural Steel Shapes

$0.82

13 ASTM A709/A709M Grade HPS 50W / AASHTO M270M/M270 Grade HPS 50W or 345W Structural Steel Plate

$0.93

14 ASTM A709/A709M Grade HPS 70W / AASHTO M270M/M270 Grade HPS 70W or 485W Structural Steel Plate

$1.00

15 ASTM A514/A514M-05 Grade HPS 100W / AASHTO M270M/M270 Grade HPS 100W or 690W Structural Steel Plate

$1.53

16 ASTM A992/A992M Grade 50S / AASHTO M270M/M270 Grade 50S or 345S Structural Steel Plate

$0.89

17 ASTM A992/A992M Grade 50S / AASHTO M270M/M270 Grade 50S or 345S Structural Steel Shapes

$0.82

18 ASTM A276 Type 316 Stainless Steel $4.61 19 ASTM A240 Type 316 Stainless Steel $4.61 20 ASTM A148 Grade 80/50 Steel Castings (See Note below.) $1.58 21 ASTM A53 Grade B Structural Steel Pipe $1.00 22 ASTM A500 Grades A, B, 36 & 50 Structural Steel Pipe $1.00 23 ASTM A252, Grades 240 (36 KSI) & 414 (60 KSI) Pipe Pile $0.80 24 ASTM 252, Grade 2 Permanent Steel Casing $0.80 25 ASTM A36 (AASHTO M183) for H-piles, steel supports and sign supports $0.84 26 ASTM A328 / A328M, Grade 50 (AASHTO M202) Steel Sheetpiling $1.51 27 ASTM A572 / A572M, Grade 50 Sheetpiling $1.51 28 ASTM A36/36M, Grade 50 $0.86 29 ASTM A570, Grade 50 $0.84 30 ASTM A572 (AASHTO M223), Grade 50 H-Piles $0.86 31 ASTM A1085 Grade A (50 KSI) Steel Hollow Structural Sections (HSS), heat-treated per

ASTM A1085 Supplement S1 $1.00

32 AREA 140 LB Rail and Track Accessories $0.52 NOTE: Steel Castings are generally used only on moveable bridges. Cast iron frames, grates and pipe are not “steel” castings and will not be considered for price adjustments.

END OF DOCUMENT

00813 - 4

THIS PAGE IS INTENTIONALLY LEFT BLANK

A00801 - 5

SOIL STOCKPILING DIRECTIVE P-22-001

Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.

SUBSECTION 8.02 SCHEDULE OF OPERATIONS

Replace this subsection with the following:

An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project. Detailed requirements are provided in Division II, Section 722 Construction Scheduling.

TRUCK SAFETY DEVICES

(Supplementing Subsection 7.04: Motor Vehicles)

All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.

The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540

CMR 4.00.

The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.

Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.

Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.

HARVARD-LITTLETON-ACTON-CONCORD-611952-134796-A1
00104 NTC 11-14-24-A1
NOTICE TO CONTRACTORS
00760 FHWA 1273 Rev 6-25-26
00813 Steel Price Adj. w Base Prices 07-15-2026-A1
A00801 Special Provisions-A1 (page 5)
2026-07-17T11:22:38-0400
Eric M. Cardone

File details come from the government source that posted it. Updated .