This document contains a price list for a federal contract with the United States Special Operations Command for the provision of concrete targets. The price list covers five ordering periods from award to day 1,825 and includes pricing for the manufacture, delivery, and placement of eight concrete clumps as well as the retrieval and disposal of concrete clumps and the placement of additional clumps on an as-needed basis. Pricing will be determined by the date of task order issuance and corresponding ordering period. No unit prices are listed but will be negotiated at the task order level. The pre-solicitation opportunity seeks these concrete target services.

View the file

Other files

File Type Posted
Attachment 1 - Statement of Work (SOW) Updated 26 Sept 2023.docx DOCX document
Attachment 3 - Initial Task Order SOW Updated 26 Sept 2023.docx DOCX document
H9224023R0012-0001.pdf PDF
Attachment 4 - SCA Wage Determination.txt TXT text file
Attachment 3 - Initial Task Order SOW.docx DOCX document
Attachment 1 - Statement of Work (SOW).docx DOCX document
Attachment 2 - ELIN Price List.xlsx XLSX spreadsheet
H9224023R0012 Released.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attach 2

ORDERING PERIOD 1AWARD - DAY 365
ORDERING PERIOD 2DAY 365 - DAY 730ELINS REVISE TO B
ORDERING PERIOD 3DAY 730 - DAY 1,095ELINS REVISE TO C
ORDERING PERIOD 4DAY 1,095 - DAY 1,460ELINS REVISE TO D
ORDERING PERIOD 5DAY 1,460 - DAY 1,825ELINS REVISE TO E
**APPLICABLE PRICING IS BASED ON THE DATE OF TASK ORDER ISSUANCE.
Ordering Period One:ELIN ITEM#DescriptionU/IQTYUnit PriceTotal Evaluated Price (All Periods)
A001Manufacture, Delivery & Placement of Eight (8) Concrete ClumpsEA1$0.00
A002Concrete Clumps Retrieval & DisposalEA1
A003Manufacture, Delivery & Placement of One (1) Additional Concrete ClumpsEA1
A004Other Services as Negotiated at the Task Order LevelTBNTBNTo Be Negotiated (TBN)
Ordering Period Two:ELIN ITEM#DescriptionUOMQTYUnit Price
B001Manufacture, Delivery & Placement of Eight (8) Concrete ClumpsEA1
B002Concrete Clumps Retrieval & DisposalEA1
B003Manufacture, Delivery & Placement of One (1) Additional Concrete ClumpsEA1
B004Other Services as Negotiated at the Task Order LevelTBNTBNTBN
Ordering Period Three:ELIN ITEM#DescriptionUOMQTYUnit Price
C001Manufacture, Delivery & Placement of Eight (8) Concrete ClumpsEA1
C002Concrete Clumps Retrieval & DisposalEA1
C003Manufacture, Delivery & Placement of One (1) Additional Concrete ClumpsEA1
C004Other Services as Negotiated at the Task Order LevelTBNTBNTBN
Ordering Period Four:ELIN ITEM#DescriptionUOMQTYUnit Price
D001Manufacture, Delivery & Placement of Eight (8) Concrete ClumpsEA1
D002Concrete Clumps Retrieval & DisposalEA1
D003Manufacture, Delivery & Placement of One (1) Additional Concrete ClumpsEA1
D004Other Services as Negotiated at the Task Order LevelTBNTBNTBN
Ordering Period Five:ELIN ITEM#DescriptionUOMQTYUnit Price
E001Manufacture, Delivery & Placement of Eight (8) Concrete ClumpsEA1
E002Concrete Clumps Retrieval & DisposalEA1
E003Manufacture, Delivery & Placement of One (1) Additional Concrete ClumpsEA1
E004Other Services as Negotiated at the Task Order LevelTBNTBNTBN