Attachment 4 – Project Schedule
Project Schedule for CCA and CCM Office Renovation and Remodel
A week is defined as Monday -Friday
Week 1: Contractors: Removal and disposal of CCA Office equipment ONLY. PROPOSED
Week 2: Military only: Paint CCA office. NEED
Week 3: Contractors: Delivery and installation of furniture for CCA Office ONLY. PROPOSED
Week 4: Military only: Vacate CCM office. NEED
Week 5: Contractors: Removal and disposal of CCM Office equipment ONLY. PROPOSED
Week 6: Military only: Paint CCM office. NEED
Week 7: Contractors: Delivery and installation of furniture for CCM Office ONLY. PROPOSED