Scope of Work
Department of Energy Project Areas 5, 7,8 & 9
Office and Hallway Renovation 825 Jadwin Avenue
Richland, WA 99352
17 March 2015
1.1 Project Description:
A. The Contractor shall provide all labor, materials, tools and equipment necessary to provide space renovations on the Richland Federal Building’s fourth floor and restoration of the fourth and fifth floor Heating, Ventilation, and Air Conditioning (HVAC) systems in accordance with these specifications and the attached drawings, sheets and other attachments listed in Attachments section 1.14 below.
B. An overview of the projects’ phasing follows. Projects are listed in order of required phased performance.
1. Phase 1, Project Area 5.
a. Project 5 is intended to demolish and rebuild the fourth floor’s Project Area 5 as shown on the Project’s drawing A101. Department of Energy (DoE) will relocate this area’s staff to swing space elsewhere within the building to allow the contractor access to this area. Staff relocation will be accomplished by DoE’s support contractor.
b. DoE will move their staff back to the renovated area once the Contractor completes work, freeing the Project Area 7 & 9 for the Contractor’s work.
2. Phase 2, Project Areas 7 & 9. This phase consists of two separate activities in the same project area.
a. Project 7 is intended to demolish and rebuild the fourth floor’s Project Area 7 as shown on drawing A101. Department of Energy (DoE) will relocate this area’s staff to swing space elsewhere within the building to allow the contractor access to this area.
b. Project 9 is intended to restore the (HVAC flow to the Project 7 area. The in-floor perimeter floor duct penetrations on the fourth and fifth floors, in this area, were disconnected and the penetrations capped with sheet metal for security reasons several years ago. Under this scope of Work (SOW), the Contractor shall remove the sheet metal caps, clean the duct interior, and reconnect the floor penetrations to the building’s HVAC infrastructure with new insulated sheet metal medium pressure duct work, restoring balanced air flow to the Project 7 area. See paragraph 1.3 C Mechanical for additional details.
3. Phase 3, Project Area 8. Project Area 8 consists of renovating the hallways bordering
Project Areas 5 and 7. The Contractor may work in these hallway areas during the two week gap between work in Project Areas 5 and Project Areas 7 & 9, when DoE is moving the affected areas’ staffs to and from swing space. Alternatively, the
Contractor may elect to treat the hallway area as a totally separate project, pursing the work from beginning to end, with no breaks. The Contractor shall address Project
Area 8 work in the construction schedule. The Contractor shall conduct hallway
Office and Hallway Renovation 825 Jadwin Avenue renovations in such a manner that DoE personnel are able to transit the hallway areas during day time hours. The Contractor will have exclusive access to the hallway areas after normal work hours.
1.2 Performance Period:
A. The performance period for this contract shall be 240 calendar days from contract award to substantial completion. This performance period includes two, two week transition periods when DoE will relocated their staffs between the construction areas and swing space. The Contractor shall commence all non-physical construction requirements to include submittal of bonds and/or insurance documents, background investigation documents (as applicable), and material submittals -- within 10 calendar days of contract award. Notice to Proceed will be issued by the Contracting Officer upon acceptance by the GSA of all required documents, submittals and receipt of Security clearances.
Physical work shall only be allowed after the issuance of Notice to Proceed.
B. Final completion shall occur no later than 30 days after substantial completion. Final completion includes, all site cleanup activities, punch list items, and closeout documents
(see 1.5 Submittals).
1.3 Work Specifications:
A. Demolition. Refer to Attachments 1 and 3, Project Area 5 and Project Area 7
Demolition Drawings respectively.
1. The Contractor shall remove the existing walls, doors, and door frames as shown on demolition drawings, and all associated electrical devices within the walls. The existing ceiling grid and light fixtures shall remain, and shall require temporary support. The Contractor shall salvage locksets for reuse, and turn the lock cores over to the GSA Project Manager.
2. The Contractor shall temporarily support the fire alarm devices during construction and permanently affix the devices when the final walls are in place, where walls are scheduled to be removed that contain fire alarm devices. Adding additional fire alarm devices or modifying the Richland Federal Building’s fire alarm system is beyond the scope of this contract.
3. The Contractor shall remove all electrical wiring back to the electrical distribution panel in Room 4082, or to the nearest junction box on that electrical circuit, if the wire will not be reused. Data/telephone wiring shall be removed back to its point of origin. The building maintenance contractor will remove all monument outlets and patch the holes leading to the Walker Duct prior to the contractor beginning demolition work. The Contractor shall run all new power, data, and voice circuits above the suspended ceiling grid.
Office and Hallway Renovation 825 Jadwin Avenue
4. The existing ceiling tiles shall be removed and disposed of in accordance with local, state and federal regulations for material that may contain spray on asbestos fire proofing residue. See paragraph 1.5 and Attachment 10 for additional information.
The Contractor shall provide temporary support of the ceiling grid as required.
5. The Contractor shall remove the existing carpet and cove base and recycle off site as indicated in Attachments 1 (Project Area 5 Demolition Drawing A101), Attachment 3
(Project 7 Demolition Drawing A101), and Attachment 5 (four drawings depicting the hallway area renovation, numbered A102 A104, A105, and A107). The flooring beneath the existing carpet in Project Areas 5, 7 and 8 is covered with vinyl asbestos tile (VAT) held in place with mastic that also contains asbestos.
a. The contractor shall notify the GSA Project Manager if any of the VAT beneath the carpet tiles is loose or broken.
b. Removal/abatement of the VAT and mastic is beyond the scope of this project.
6. The Contractor shall remove and dispose of, off site, the existing large HVAC wall/floor registers located beneath each window throughout the project area and replace them with new low profile registers. See Attachment 15 for a photo depicting the diffuser to be removed and a photo of the diffuser style to be used as a replacement. See paragraph C,5,C,4 for the replacement diffuser’s salient features.
B. Wall and Ceiling Construction. Refer to the Attachment 2, Project Area 5 Architectural
Drawing A102; and Attachment 4, Project Areas 7 Architectural Drawing A102.
1. The contractor shall furnish and install new walls as indicated -in Attachment 2, Project Area 5 Architectural Drawings A102; and Attachment 4, Project Area 7
Architectural Drawing A102. The walls shall be constructed of 3–5/8” metal studs, installed 16 inches on center, with 5/8” type X fire rated gypsum wall board (GWB) on each side. The GWB shall be taped and finished. The finish shall be level 5 as defined by the Association of Wall and Ceiling Industries International (AWCI). The contractor shall provide and install 3-5/8” R11 glass-fiber sound attenuation, bat insulation in the wall cavities.
2. The contactor shall provide and install new 3 foot x 7 foot solid core wood doors
(type plain sliced maple) and metal door frames with hinge butts and door stops at locations shown in Attachment 2, Project Area 5 Architectural Drawings A102; and
Attachment 4, Project Area 7 Architectural Drawing A102. . Each door shall contain a metal framed 21 inch (wide) x 63 inch (high) tempered glass window, centered in the door to match building standard. The door shall be stained. GSA will provide the
Contractor a stained wood control sample for the Contractor to match. The
Office and Hallway Renovation 825 Jadwin Avenue
Contractor shall install salvaged locksets. The Contractor shall furnish and install wall mounted door stops at the lockset handle level.
3. The Contractor shall furnish and install 70-3/4” (high) x 22-3/4” (wide) tempered glass sidelights as shown in Attachment 2, Project Area 5 Architectural Drawings
A102; and Attachment 4, Project Area 7 Architectural Drawing A102. . The sidelights shall have a metal frame matching the adjacent door frames. The door and sidelight frames shall be painted with a primer and two finish coats of paint. Top of window frame and door frame shall be at the same height above the finished floor.
4. The existing ceiling grid in Project Areas 5, 7 and 8 shall remain in place. The
Contractor shall paint the grid white and install new government furnished acoustical ceiling tile, existing florescent light fixtures, and existing ceiling mounted thermostats. The Contractor shall move the government furnished ceiling tiles from the storage areas within the Richland Federal Building, transporting them to the work area. Refer to paragraphs 1.5 (Asbestos Requirements), 1.6 (Submittals), and
Attachment 10, Asbestos Control Procedures for additional information and requirements regarding work in the above ceiling areas.
C. Mechanical.
1. The Contractor shall restore, following procedures below, the HVAC system supplying air to the fourth and fifth floor, southeast areas shown in the red boundary on Attachment 6, Project Overview, Sheet A 108. The plenum above the ceiling in all Project Areas contains spray on asbestos fire proofing on deck, overspray on piping and equipment, and hard asbestos trawled on beams. The Contractor shall make every effort to avoid disturbing this fire proofing material. Abatement, other than spot abatement for installation of new terminal units and missing duct work, and removal of sheet metal duct covers is beyond the scope of this contract.
a. The Contractor shall provide line item costs for the following activities:
1. Replacement and installation of a missing core terminal box, to include 10 feet of duct work on either side of the terminal box.
2. Restoration of an existing core terminal box.
3. Replacement and installation of a missing perimeter terminal box, to include
10 feet of duct work on either side of the terminal box.
4. Restoration of an existing perimeter terminal box.
Office and Hallway Renovation 825 Jadwin Avenue
b. The attached drawings depict the anticipated disposition of the core and perimeter terminal boxes above the third and fourth floors. For bidding purposes the assumed disposition of each floor’s core and terminal boxes is shown in this table:
Building Area Core Terminal Box Status Perimeter Terminal Box Status
Above Third Floor Ceiling
Not Applicable.
(Core boxes in this area do not supply air to the floor above.)
Eight Boxes Missing
Above Fourth Floor Ceiling Four Boxes Missing
Four Boxes Require Restoration
Four Boxes Missing
Four Boxes Require Restoration
c. The core and perimeter units that remain were disconnected and abandoned during a previous renovation project. Recommissioning and restoration shall consist of the following activities. See Attachments 15, Figure 1 which depicts an existing, operational terminal box.
1. Remove interior controls, actuators, dampers, etc. in terminal units to allow free air flow. Provide and install new direct digital control (DDC) damper assemblies and discharge air temperature sensors, and connect the new DDC device to the Johnson Controls Metasys panel located in the Fourth Floor Fan
Room. Reprogram the Johnson Controls Metesys System to receive data from the new DDCs and control air flow at each terminal. Do not disturb asbestos overspray on ductwork, insulation or terminal units without following asbestos procedures.
d. Replacement shall consist of the following activities:
1. Provide a suitable terminal box and DDCs, connect the new terminal units to the existing duct work, and insulate.
i. Missing third and fourth floor perimeter terminal units shall have a 522 cubic foot per minute (CFM) or higher rating.
ii. Missing fourth floor core terminal units shall have a 700 CFM or higher rating.
iii. The original mixing boxes were of the Connor Engineer Corporation
Series 45 P product line. The Contractor shall provide new terminal units matching the construction and performance specification of the original
Connor 45P Series units. Brand name or equal.
2. Provide and install new wall mounted DDC thermostats to control the replaced terminal units through the Johnson Controls Metasys system. Submit the proposed thermostat locations to the GSA Project Manager for approval.
Office and Hallway Renovation 825 Jadwin Avenue
3. Connect new DDC terminal unit controls to the Johnson Controls Metasys system and program.
e. In addition to replacing the missing boxes, the Contractor shall accomplish the following.
1. Remove the covers on the above ceiling ductwork where the duct penetrates the fourth and fifth floors. Figures 2 and 3 in Attachment 15, Photos to
Accompany SOW, depict examples of capped ductwork. Connect new metal duct work to the cleared floor penetrations and wrap with new insulation.
Figure 4 in Attachment 15, Photos to Accompany SOW, depicts a perimeter terminal unit and original duct work that are intact and functional.
2. The Contractor shall seal all gaps between the ductwork and concrete floor with an approved fire-caulking. Fire-caulking salient points follow:
i. Underwriters Laboratory Listed for use as fire and smoke barrier
ii. Low or no Volatile Organic Components (VOCs), less than 15 grams per liter.
iii. Color: Red
3. Connect the both the new and refurbished terminal unit’s DDCs to the
Johnson Metasys panel located in the Fourth Floor fan room.
f. The Contractor shall remove and dispose of the abandoned air conditioning air handler from Room 478’s ceiling to include the following. Refer to Attachment 4, Project Area 7 Architectural Drawings 102 for Room 478’s location.
1. The air handler.
2. The electrical conduit and wire to the nearest junction box.
3. Refrigerant piping to the limits of the renovation area.
g. The Contractor shall notify the GSA Project Manager of any other abandoned
HVAC equipment located above the Project Area 7 suspended ceiling. Removal of this abandoned equipment is beyond the scope of this contract.
h. The Contractor shall design and install a new supply air duct for Room 478 in accordance with the requirements in Attachment 16, Room 478 HVAC Schematic.
1. The Contractor shall submit to the GSA Project Manager for review and approval his air supply design for Room 478.
Office and Hallway Renovation 825 Jadwin Avenue
2. The Contractor shall inform the GSA Project Manager if Room 478’s existing exhaust duct work does meet the design requirements shown in Attachment
16, Room 478 HVAC Schematic.
2. The Contractor shall utilize a Johnson Controls certified technician to reprogram the
Richland Federal Building’s Metasys System to recognize and control the new DDC controllers on both the new and retrofitted terminal units. Salient points for the DDC
Controllers follow:
a. Internal Pressure Transmittal with Dead Ended Input Ports
b. Range of 0.0 to 1.5 inches of Water Column (WC) input pressure
c. No warm up period
d. Capacitive sensor for long-term stability and accuracy
e. Output span: 0 – 4 Volts DC.
f. Power requirement: 15 volts DC
g. Overpressure Limit: 15 inches WC
3. The Contractor shall retain the services of a National Environmental Balancing
Bureau (NEBB) certified technician to test and balance the fourth and fifth floor’s
HVAC systems at the project’s completion, and all ceiling tiles have been replaced.
The intent of the testing and balancing is:
a. To ensure the new and restored terminal unites are functioning as intended, and being monitored and controlled by the Johnson Controls Metasys System.
b. To restore balanced airflows throughout the building’s fourth and fifth floors once perimeter and core area air flows in the Project 7 area have been restored. See
Paragraph 6 below.
4. The Contractor shall notify the GSA Project Manager immediately of any deviation between the missing and disconnected terminal units and duct work shown on the attached drawings, and what the Contractor discovers when he removes the ceiling tiles. Adjustments to this contract required to fully restore the HVAC system shall be made on the basis of the line item prices provided in paragraph 1.3C1a.
5. Mechanical Phasing.
a. The Contractor shall undertake all above-the-ceiling fourth floor mechanical work in the Project 7 area during this project’s demolition and reconstruction phase.
The Contractor may remove portions of the suspended ceiling grid in order to replace the missing terminal units and associated duct work. The Contractor shall reuse the existing suspended ceiling support wires to minimize spot abating the
Office and Hallway Renovation 825 Jadwin Avenue asbestos spray on fire proofing in order to attach new acoustical ceiling support wire.
b. The contractor shall also undertake the after-hours access to the third floor above-ceiling-areas for HVAC restoration at the same time work is being performed on the fourth floor.
1. Duration of the above ceiling third floor work is envisioned to last no more than two weeks. The Contractor shall notify the GSA Project Manager during the Contractor’s planning phase if he envisions the duration of work in this area lasting longer. The Contractor shall not commence the HVAC restoration work until all required equipment is on site. If required, the GSA
Project Manager will coordinate with DoE and GSA Property Management to find additional swing space options.
2. Much of the third floor area beneath the fourth HVAC restoration site is used for drawing and map storage. DoE will leave the flat files in place during work above the third floor ceiling, and relocate their staff to other areas of the
Richland Building. The Contractor shall cover the flat files and furniture remaining in the third floor work area to protect them from possible asbestos contamination and facilitate Contractor cleanup when the HVAC system restoration above this ceiling area is complete.
c. Afterhours access to the fifth floor offices areas for removal of the large registers and replacement with the smaller units shall be accomplished by the Contractor one office at a time. DoE will not relocate the fifth floor tenants to swing space to facilitate the floor penetration restoration. Work involved in each of the eight fifth floor office consists of the following actions.
1. Move the office furniture to allow access to the existing HVAC air diffuser cabinet.
2. Remove and dispose of the cabinet off site.
3. Seal the duct from below until the new terminal units are installed and the missing ductwork is replaced and reconnected. The penetrations between the fourth and fifth floors shall be sealed at the end of each shift. Intent is to block possible asbestos fiber migration from the area above the fourth floor’s ceiling to the fifth floor offices.
4. Replace the HVAC air diffuser cabinet with a floor mounted register. See
Figure 5 in Attachment 15, HVAC Photos, to Accompany SOW, for pictures of a typical HVAC air diffuser cabinet. Attachment 15, Photo 6 depicts the replacement register whose salient points follow.
i. All steel construction
ii. Length: Four feet.
Office and Hallway Renovation 825 Jadwin Avenue
iii. White enamel finish
iv. Removable face
v. Dual valves
vi. Equal air distribution over length of diffuser
5. Clean the individual office area of debris and dust, and replace the office furniture to its original configuration.
6. Restoration of the offices’ walls, where the original HVAC air distribution cabinet sat, will be accomplished by others in follow on restoration projects.
The Contractor shall take reasonable care to avoid damage to the fifth floor office’s walls during grout removal operations.
6. Testing and Balancing.
a. The Contractor shall test and balance the Richland Federal Building’s fourth and fifth floor HVAC systems upon completion of the HVAC restoration. The
Contractor shall coordinate the HVAC testing and balancing with the GSA Project
Manager. The GSA Project Manager will coordinate with both Property
Management and the building’s maintenance contractor for access to tenant space and maintenance contractor support. The HVAC testing and balancing shall be conducted after hours to avoid impact to tenant operations and allow access to the terminal units above the suspended ceiling. Access to the areas above the suspended ceiling for testing and balancing will accomplished in accordance with the Attachment 10. Asbestos Control Procedures .
b. The intent of the Contractor’s testing and balancing is to restore air flow on the fourth and fifth floors to their original flow values as shown on Attachment 8, Fourth Floor Plan; and Attachment 9, Fifth Floor Plan.
c. The heating and cooling load, as well as the floor configuration in these areas, remains similar to the building’s original design. It is anticipated that the restoration the Contractor accomplishes under this SOW will provide similar air flows to those shown on the attached drawings.
1. Further restoration of the HVAC system to meet the original airflow requirements is beyond the scope of this contract. The Contractor shall submit his testing and balancing report to the GSA Project Manager with recommendations to return the floors’ airflows to the original specifications in the event the resorted system does not meet the flows shown on these two sheets.
Office and Hallway Renovation 825 Jadwin Avenue
D. Electrical. Refer to the attached Attachment 2, Project 5 Architectural Drawings A102;
Attachment , Project Area 7 Architectural Drawing A102; and Attachments 5’s Drawings
A105 and A107.
E. The Contractor shall revise the existing light switching configuration and the light fixture locations in each office to provide an individual switch to control each room’s overhead lights and uniform lighting throughout each office area. The light switch shall be located adjacent to each office’s door, as indicated in Attachment 2, Project 5 Architectural
Drawing A102; and Attachment 4, Project Area 7, Architectural Drawing A102 drawings A 102 and A 104. The plenum above the ceiling in all project areas contains spray on asbestos fire proofing. Refer to paragraphs 1.5 (Asbestos Requirements), 1.6
(Submittals), and Attachment 10. Asbestos Control Procedures for additional information and requirements regarding work in the above ceiling areas.
1. The Contractor shall provide and install wall mounted 120 volt duplex receptacles, wall mounted RJ 45 jacks, and all associated conduit and fittings as shown in in
Attachment 2, Project 5 Architectural Drawing A102; and Attachment 4, Proejct Area
7, Architectural Drawing A102. The Contractor shall confirm the exact location of all power and data outlets with the GSA Project Manager prior to installation. New plenum rated Cat 6 data cable shall extend back to the punch down blocks located in the telephone closet, Room T418. Data wire shall be punched down or terminated at each end. Data cable shall not be spliced.
2. The Contractor shall test all data cable and RJ45 terminations in accordance with
ANSI/TIA/EIS - 568 - B.1 (Commercial Building Telecommunications Cabling
Standard), and submit final test reports to the GSA Project Manager.
3. The Contractor shall label both ends of each data cable with machine printed labels.
Hand written labels will not be accepted.
4. All new cable – for both voice and data, and the Johnson Controls Metasys System --shall be Cat 6 cable, plenum rated with blue insulation jacket, meeting the following specifications.
a. ANSI/TIA/EIA-568-B Category 6 unshielded twisted pair (UTP)
b. Gauge: 24 AWG
c. Number of pairs: 4
d. Maximum DC resistance: 28.6 ohm/ 1000 ft.
e. Maximum DC resistance unbalanced: 5 percent
f. Nominal mutual capacitance at 1 kHz: 14pF/ 1000 ft.
g. Tested to 350 MHz.
Office and Hallway Renovation 825 Jadwin Avenue
5. The building’s existing 120 volt power and 277 volt lighting circuits may be used for
120 volt outlet and light installation. All electrical work shall be performed in accordance with the National Electrical Code.
6. The Contractor shall reinstall all existing fire alarm devices in the new wall configurations in accordance with NFPA, PBS P-100, and GSA Region 10 Policy.
7. Modification of either the Richland Federal Building’s existing fire sprinkler system or fire detection and alarm system is beyond the scope of this contract.
1.4 Finish Work
A. The contractor shall install carpet tile in each office, bay area, and hallway as shown in
Attachment 2, Project Area 5 Architectural Drawing A102; Attachment 4, Project Area 7
Architectural Drawing A 102; and Attachment 5’s four Project Area 8 Architectural
Drawings, numbered A102, A104, A105, and A107.. The Government will provide the carpet tile. The Contractor shall be responsible for providing quick release carpet adhesive and all tools and equipment required to install the carpet tile. The Contractor shall move the carpet tiles from a storage located in the Richland Federal Building’s basement to the applicable Project Area.
B. Clean, patch and repair existing surfaces in accordance with the paint manufacturer’s recommendations. The Contractor shall prime all patched wall areas as necessary.
C. The Contractor shall provide and install one coat of primer, and one coat of finish paint at all new wall locations. All remaining, existing walls shall require one coat of finish paint. GSA will provide the contractor with a color pallet not exceeding 10 colors, which the contractor shall use for painting the individual office areas. Tenants will be allowed no more than two colors per office. Each office's walls will be painted a solid color, with door and window frames to match their adjacent walls as will each window inset area.
The hallway (Project Area 8) will be painted one color to match the color used in the hallway areas recently renovated under other contracts. The building’s brushed aluminum exterior windows frames shall not be painted. The ceiling grid throughout
Project Areas 5, 7 and 8 shall be painted white.
D. Use of a premium grade, low VOC waterborne interior alkyd wall paint and primer is required.
E. There shall be no skips, runs or holidays on the finished paint surface. The finished product shall provide a uniform surface.
Office and Hallway Renovation 825 Jadwin Avenue
F. The Contractor shall apply paint to the walls and other surfaces in accordance with the paint manufacturer’s recommendations.
G. Protect work from paint droppings and spattering by use of masking, drop cloths, removal of items or by other approved methods.
H. Upon completion, clean paint from hardware, glass and other surfaces and items not required to be painted of paint drops or smears.
I. Paints and primer coatings shall meet Green Seal Standard GS-11: http://www.
Aqmd.gov/rules/reg/reg11/r1168.pdf
J. Application of paint via brush, roller or airless spray is acceptable.
K. Adhesives and Sealants:
1. Reduce the quantity of indoor air contaminants that are odorous, irritating, and or harmful to the comfort and well-being of installers and occupants.
2. All adhesives and sealants used in interior of building shall comply with South Coast
Air Quality Management District (SCAQMD) Rule #1168 and Green Seal (GS)
Standard for Commercial Adhesives GS-36.
3. Adhesives, sealants and solvents shall be no to very low VOC and environmentally preferred.
L. The contractor shall provide and install four inch rubber cove base throughout Project
Areas 5, 7 and 8. GSA shall provide the required rubber base color to successful contractor.
1.5 Asbestos Requirements:
A. This scope of work does not address comprehensive asbestos abatement activities.
However, the contractor shall be required to remove asbestos debris from the existing ceiling tiles prior to disposal. The contractor shall not remove any spray on fireproofing from the protected surfaces above the suspended ceilings, except as required to install new terminal units and replace missing duct work. Cleanup of all visible asbestos fibers or debris shall occur as soon as possible and not later than the end of the work shift in which the asbestos debris was discovered. Reference Attachment 10. Asbestos Control
Procedures for additional information. The Contractor shall reapply non asbestos fire proofing to the building’s protected areas when the existing asbestos fire proofing is abated as part of this contract. The contractor shall submit for approval the manufacture’s literate for the replacement fire proofing. Salient features for the replacement spray on fire proofing follow.
1. UL 263 Listed
2. Water based
3. Comply with ASTM E84 for surface burning
Office and Hallway Renovation 825 Jadwin Avenue
4. Comply with ASTM D2240 for Durometer Hardness
5. Comply with ASTM D2794 for Impact Resistance
6. Comply with ATSM D4060 for Abrasion Resistance
B. All areas above the ceiling contain asbestos sprayed on fire proofing, and it is anticipated that asbestos residue has settled on all above ceiling surfaces as well as the ceiling tiles in the years following application. All ceiling tiles shall be properly cleaned prior to disposal. The Contractor shall submit an asbestos work plan for approval. The work plan shall be approved by GSA prior to issuing Notice to Proceed (NTP). The work plan shall include, as a minimum,
1. How the contractor plans on minimizing contact with asbestos containing materials
(ACM) during the demolition and renovation work
2. What steps the contractor will take if ACM fire proofing is disturbed.
3. Detailed description of how the contractor will approach the demolition and renovation work.
C. All contractor employees and subcontractors performing work above the ceiling grid shall comply with WISHA (Washington State Industrial Safety and Health Act) requirements for training.
D. The Contractor shall coordinate all asbestos related work with the building mechanical staff to ensure the building’s HVAC system is off when the contractor is working in an asbestos protected area. Asbestos related work shall be performed after 6 pm and before
4 am Monday through Friday or on the weekends from 6 pm Friday evening to 4 am
Monday morning. All asbestos related work shall be completed, to include clearance air testing, prior to 4am. Air sample test cassettes shall be read on site and the clearance results shall be posted on the building Operations and maintenance (O&M) contractor supervisor’s office door prior to 5 am. Clearance samples shall meet WISHA requirements.
E. The Contractor shall perform all required asbestos containment and in accordance with
EPA (Environmental Protection Agency) Asbestos Laws and Regulations and WISHA
Standards contained in Washington State Department of Labor and Industries WAC 296-
62-07712 and WAC 296-65.
F. The Contractor shall perform air sampling at the end of each work shift where spot abatement or ceiling tile removal and disposal activities occurred.
G. The floor surfaces beneath the existing carpeting in all three project areas are tiled with vinyl asbestos tile (VAT), held in place with mastic containing asbestos. The contractor shall not disturb these materials. The Contractor shall immediately notify the GSA
Project Manager should the Contractor discover during carpet removal that the VAT beneath the carpet is loose from the mastic or the VAT is broken and deteriorating.
Office and Hallway Renovation 825 Jadwin Avenue
1.6 Submittals:
A. Material submittals shall be provided to the Government no later than (NLT) 10 calendar days after award of contract. All submittals shall be accompanied by a completed GSA
Submittal Transmittal Form (see attached). Clearly mark material submittals to identify which products and options are applicable to this contract (this is especially important with product data in which multiple items and/or optional items are provided for on the same sheet). The rejection of a submittal by the GSA COR (General Services
Administration Contracting Officer’s Representative) is not sufficient reason to extend the contract performance period. Upon GSA COR acceptance of submittals, the GSA
Contracting Officer (CO) will issue notice to proceed (NTP) to the Contractor. The actual
Construction Period available to the Contractor will vary depending on the amount of time taken to complete the bonds, background investigations, and material submittal process. Allow 10 (ten) calendar days for review and approval of all submittals.
Contractor shall provide submittals and receive approval prior to ordering materials.
1. Project schedule addressing the overall project phasing.
2. Schedule of values by Project Area
3. Dust containment plan
4. Asbestos work plan
5. Hollow Metal Door and Door Frame: Product information
6. Releasable carpet glue manufacture’s technical data and Material Safety Data Sheets
(MSDS)
7. Paint draw downs and manufacture’s technical data and MSDS.
8. Door assembly and hardware manufacture’s product data sheets
9. Sound insulation manufacture’s product technical data sheet
10. Rubber base manufacture’s technical data and samples
11. Manufacturer’s technical data on DDC Controllers
12. Manufacturer’s technical data on replacement core and perimeter terminal units
13. Manufacturer’s technical data for replacement flush HVAC floor diffusers.
14. Manufacturer’s technical data for fire caulk.
15. Manufacture’s data for spray on fire proofing
16. Contractor’s proposed design for Room 478’s Supply Duct Work
17. The fourth and fifth floor HVAC balancing reports.
18. Manufacture’s technical data for Cat 6 cable and RJ 45 jacks.
19. Cat 6 Cable certification and testing report.
20. Closeout documents upon completion to include:
a. General waste disposal documentation
b. Asbestos waste disposal documentation
c. Warranties
d. Payroll Documentation (certified payrolls, SF1413s, etc.)
e. Final invoice and payment support documents.
f. Release of Claims
Office and Hallway Renovation 825 Jadwin Avenue
1.7 Security:
A. All workers shall pass a background screen prior to the start of the work.
1. The GSA Project Manager will provide the successful offeror with a partially completed electronic Contractor Information Worksheet (CIW) and OF 306 (samples attached). Paper copies of CIW’s will not be accepted. The CIW is required in MS
Word document (Version 4 12/2010), and encrypted. Scanned pdf documents will not be accepted.
a. Submit the CIW and OF 306 electronically to: r10securityem@gsa.gov. CIW’s shall be completed entirely including the GSA sponsor and all contract information. (Vendor name, contract number, award date, and end date)
b. Form OF 306 shall be completed and submitted
2. Contractor fingerprints will be taken electronically at any of the USAccess/Managed
Service Office shared credentialing centers. The information from the CIW will be entered into GSA’s database, and the contractor will be sponsored after GSA’s security office receives a validated and legible CIW. Once sponsored, the contractor will be able to go on-line and make an appointment at any shared service credentialing office to have their fingerprints taken. Use the following website to locate shared credentialing centers: http://www.fedidcard.gov/centerlocator.aspx
3. All security information shall be submitted no later than 7 calendar days after contract award notice.
4. All workers shall display at all times the ID badge issued to contractors by the GSA.
5. All workers shall confine operations to areas permitted.
B. Contractor personnel shall complete HSO training for the Hanford site, in order to access
DoE space. DoE space is considered the 4 th through the 7 th floor of the Tower.
1.8 Specification Compliance Requirements:
A. Code and Design Standards:
1. The Contractor shall securing all needed permits, certifications and for ensuring compliance with federal, state, and local codes and design standards, latest editions, including, but not limited to the following as applicable:
a. International Building Code (IBC, International Code Council)
b. National Electrical Code, NFPA 70 (National Fire Protection Association)
c. ABA (Architectural Barriers Act) Standards.
d. Occupational Safety and Health Administration (OSHA) Code of Federal
Regulations Part 1910 and Part 1926.
e. Facility Standards for the Public Building Service, PBS/P-100 (2010):
http://gsap100.wbdg.org/
f. Washington State Department of Labor and Industry asbestos requirements:
http://www.lni.wa.gov/wisha/rules/asbestos/Default.htm mailto:r10securityem@gsa.gov http://www.fedidcard.gov/centerlocator.aspx http://gsap100.wbdg.org/ http://www.lni.wa.gov/wisha/rules/asbestos/Default.htm
Office and Hallway Renovation 825 Jadwin Avenue
g. EPA asbestos standards:
http://www2.epa.gov/asbestos/asbestos-laws-and-regulations
h. OSHA safety regulations:
https://www.osha.gov/law-regs.html
1.9 Material Compliance Requirements:
A. The Contractor shall reduce the quantity of indoor air contaminants that are odorous, irritating, and or harmful to the comfort and well-being of installers and occupants.
1. All adhesives and sealants used in interior of building used under this contract shall comply with South Coast Air Quality Management District (SCAQMD) Rule #1168 and Green Seal (GS) Standard for Commercial Adhesives GS-36.
2. Adhesives, sealants and solvents shall be no to very low VOC and environmentally preferred.
3. Use of a Premium Grade Low or No VOC Waterborne Interior Alkyd Wall Paint is required.
4. Paints and coatings shall not exceed Green Seal Standard GS-11:
http://www.aqmd.gov/rules/reg/reg11/r1168.pdf
B. No asbestos containing materials shall be installed in the performance of this work.
1.10 Recycling Requirements:
A. Maximum recycling of all construction & demolition debris required.
1. Divert demolition recyclable / reusable items and materials from landfills and incineration facilities to appropriate reusable material sites. Provide documentation of compliance to COR.
1.11 Additional Project Requirements:
A. The building tenants shall have no functional disruptions resulting from the Contractor’s planning and execution of project work and requirements
B. Contractor use of premises:
1. Contractor shall supply their own dumpster. No waste shall be put in building dumpsters or containers.
2. On-site storage is not available except in area of work.
3. Deliveries of products by vendors shall be coordinated with the GSA COR at least 24 hours in advance.
4. On-site parking is available in the west parking lot.
5. All persons working for or under a General Contractor or Sub-Contractor shall maintain safely marked areas of work.
6. The building tenants shall have no functional disruptions resulting from the contractor’s planning and execution of project work.
1.12 Work Hours:
http://www2.epa.gov/asbestos/asbestos-laws-and-regulations https://www.osha.gov/law-regs.html http://www.aqmd.gov/rules/reg/reg11/r1168.pdf
Office and Hallway Renovation 825 Jadwin Avenue
A. All work, with the exception of asbestos related activities, shall be performed after the normal working hours of the building occupants which are 6:00 am to 5:30 pm Monday through Friday unless approved otherwise by GSA. Weekend work shall be approved in advance by the GSA Project manager.
B. All painting shall be performed after 6:00 PM and before 3:00 AM, Monday through
Friday, or on weekends. The contractor shall provide 24 hours (minimum) notice in advance of painting
C. Refer to Section 1.5 (Asbestos Requirements) for asbestos work hours. These work hours are slightly more restrictive due to the need to ensure the Building’s air handling units are off while the asbestos activities are underway, and the contractor suspends asbestos work prior to the air handlers resuming operation the next duty day.
1.13 Clean-up:
A. The contractor shall install protective measures to protect existing conditions and to contain dust and debris during construction to ensure a safe and irritant free work environment for building occupants.
1. Work shall provide for protection of all finishes and furnishings, and shall include cleanup of work site during and after work performed. Work shall include removal of all unused material, refuse and debris from the work area.
a. Dispose of all construction debris according to Federal, State and Local requirements.
b. Work areas shall be free of debris and cleaned to a dust free environment prior to the end of the contractor’s work day.
B. If equipment or building surfaces are damaged, contractor shall repair to original specification.
1. Material used for touchup and repairs shall blend with the color and texture of surrounding surface and be applied in accordance with the manufacture's recommendations.
1.14 Attachments:
1. Project 5 Demolition Drawing, A 101
2. Project 5 Architectural Drawing, A 102
3. Project 7 Demolition Drawing, A 103
4. Project 7 Architectural Drawing, A 104
5. Project 8 Architectural Drawings, A 102, A 104, A 104-2, A 105, and A 107.
6. Project Overview, A 108
7. Sheet 9-V-AC-10
8. Sheet 9-V-AC-12
Office and Hallway Renovation 825 Jadwin Avenue
9. Fifth Floor Plan 9-V-AC-13
10. Asbestos Control Procedures
11. Not Used
12. Submittal Transmittal Form
13. CIW sample form
14. OF306 sample form
15. HVAC Photographs
16. Room 478 HVAC Duct Details.