Solicitation No. GS-10F-12-LP-R-0002 SECTION I Dial-tone Infrastructure Procurement System (DIPS)
AMENDMENT A02
SECTION I – CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses.
(a) Federal Acquisition Regulation: https://www.acquisition.gov/far/
(b) General Services Acquisition Manual: https://www.acquisition.gov/GSAM/gsam.html
FAR
CLAUSE NO.
CLAUSE TITLE AND DATE
| 52.202-1 |
| DEFINITIONS (JUL 2004) |
| 52.203-3 |
| GRATUITIES (APR 1984) |
| 52.203-5 |
| COVENANT AGAINST CONTINGENT FEES (APR 1984) |
| 52.203-6 |
| RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006) |
| 52.203-7 |
| ANTI-KICKBACK PROCEDURES (OCT 2010) |
| 52.203-8 |
| CANCELLATION, RESCISSION, AND RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997) |
| 52.203-10 |
| PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997) |
| 52.203-12 |
| LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT 2010) |
| 52.203-13 |
| CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (APR 2010) |
| 52.204-4 |
| PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011) |
| 52.204-7 |
| CENTRAL CONTRACTOR REGISTRATION (APR 2008) |
| 52.204-9 |
| PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011) |
| 52.204-10 |
| REPORTING EXECUTIVE COMPENSATION AND FIRST TIER SUBCONTRACT AWARDS (JUL 2010) |
| 52.209-6 |
| PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH CONTRACTS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (DEC 2010) |
| 52.210-1 |
| MARKET RESEARCH (APR 2011) |
| 52.215-2 |
| AUDIT AND RECORDS – NEGOTIATION (OCT 2010) |
| 52.215-8 |
| ORDER OF PRECEDENCE – UNIFORM CONTRACT FORMAT |
| 52.215-11 |
| PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA – MODIFICATIONS (AUG 2011) |
| 52.215-13 |
| SUBCONTRACTOR CERTIFIED COST OR PRICING DATA – MODIFICATIONS (OCT 2010) |
| 52.215-21 |
| REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OTHER THAN CERTIFIED COST OR PRICING DATA – MODIFICATIONS (OCT 2010) |
| 52.217-8 |
| OPTION TO EXTEND SERVICES (NOV 1999) |
FILL-IN:30 days
| 52.219-4 |
| NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS CONCERNS (JAN 2011) |
| 52.219-8 |
| UTILIZATION OF SMALL BUSINESS CONCERNS (JAN 2011) |
| 52.219-9, Alt II |
| SMALL BUSINESS SUBCONTRACTING PLAN (JAN 2011), ALTERNATE II (OCT 2001) |
| 52.219-16 |
| LIQUIDATED DAMAGES – SUBCONTRACTING PLAN (JAN 1999) |
| 52.219-28 |
| POST-AWARD SMALL BUSINESS PROGRAM REPRESENTATION (APR 2009) |
FILL-IN: 51170, GS-10F-12-LP-D-0002
| 52.222-1 |
| NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997) |
| 52.222-3 |
| CONVICT LABOR (JUN 2003) |
| 52.222-4 |
| CONTRACT WORK HOURS AND SAFETY STANDARDS ACT – OVERTIME COMPENSATION (JUL 2005) |
| 52.222-21 |
| PROHIBITION OF SEGREGATED FACILITIES (FEB 1999) |
| 52.222-24 |
| PREAWARD ON-SITE EQUAL OPPORTUNITY COMPLIANCE EVALUATION (FEB 1999) |
| 52.222-35 |
| EQUAL OPPORTUNITY FOR VETERANS (SEP 2010) |
| 52.222-36 |
| AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES (OCT 2010) |
| 52.222-37 |
| EMPLOYMENT REPORTS VETERANS (SEP 2010) |
| 52.222-40 |
| NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) |
| 52.222-41 |
| SERVICE CONTRACT ACT OF 1965 (NOV 2007) |
| 52.222-43 |
| FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT ACT – PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS) (SEP 2009) |
| 52.222-50 |
| COMBATING TRAFFICKING IN PERSONS (FEB 2009) |
| 52.222-54 |
| EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2009) |
| 52.223-2 |
| AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS |
| 52.223-5 |
| POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011) |
| 52.223-17 |
| AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS (MAY 2008) |
| 52.223-18 |
| ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (AUG 2011) |
| 52.225-1 |
| BUY AMERICAN ACT – SUPPLIES (FEB 2009) |
| 52.225-13 |
| RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008) |
| 52.227-1 |
| AUTHORIZATION AND CONSENT (DEC 2007) |
| 52.227-2 |
| NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (DEC 2007) |
| 52.227-3 |
| PATENT INDEMNITY (APR 1984) |
| 52.227-14 |
| RIGHTS IN DATA – GENERAL (DEC 2007) |
| 52.227-17 |
| RIGHTS IN DATA – SPECIAL WORKS (DEC 2007) |
| 52.228-5 |
| INSURANCE – WORK ON GOVERNMENT INSTALLATION (JAN 1997) |
| 52.229-3 |
| FEDERAL, STATE AND LOCAL TAXES (APR 2003) |
| 52.232-1 |
| PAYMENTS (APR 1984) |
| 52.232-8 |
| DISCOUNTS FOR PROMPT PAYMENT (FEB 2002) |
| 52.232-11 |
| EXTRAS (APR 1984) |
| 52.232-17 |
| INTEREST (OCT 2010) |
| 52.232-23 |
| ASSIGNMENT OF CLAIMS (JAN 1986) |
| 52.232-25 |
| PROMPT PAYMENT (OCT 2008) |
| 52.232-33 |
| PAYMENT BY ELECTRONIC FUNDS TRANSFER – CENTRAL CONTRACTOR REGISTRATION (OCT 2003) |
| 52.233-1, ALT I |
| DISPUTES (JUL 2002), ALTERNATE I (DEC 1991) |
| 52.233-3 |
| PROTEST AFTER AWARD (AUG 1996) |
| 52.233-4 |
| APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004) |
| 52.237-2 |
| PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION (APR 1984) |
| 52.237-3 |
| CONTINUITY OF SERVICES (JAN 1991) |
| 52.239-1 |
| PRIVACY OR SECURITY SAFEGUARDS (AUG 1996) |
| 52.242-13 |
| BANKRUPTCY (JUL 1995) |
| 52.243-1, ALT II |
| CHANGES – FIXED PRICE (AUG 1987), ALTERNATE II (1984) |
| 52.243-7 |
| NOTIFICATION OF CHANGES (APR 1984) |
FILL-IN: 10 (ten), 30 (thirty)
| 52.244-6 |
| SUBCONTRACTS FOR COMMERCIAL ITEMS (DEC 2010) |
| 52.246-20 |
| WARRANTY OF SERVICES (MAY 2001) |
| 52.246-25 |
| LIMITATION OF LIABILITY – SERVICES (FEB 1997) |
| 52.249-2 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (MAY 2004) |
| 52.249-8 |
| DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) |
| 52.253-1 |
| COMPUTER GENERATED FORMS (JAN 1991) |
| GSAM CLAUSE NO. |
| CLAUSE TITLE AND DATE |
| 552.203-71 |
| RESTRICTION ON ADVERTISING (SEP 1999) |
| 552.215-70 |
| EXAMINATION OF RECORDS BY GSA (FEB 1996) |
| 552.216-74 |
| TASK-ORDER AND DELIVERY-ORDER OMBUDSMAN (AUG 2010) |
| 552.219-75 |
| GSA MENTOR-PROTÉGÉ PROGRAM (SEP 2009) |
| 552.232-23 |
| ASSIGNMENT OF CLAIMS (SEP 1999) |
I2. Clauses incorporated by full text 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Jan 2011)
(a) The Contractor shall update the information in the Federal Awardee Performance and Integrity Information System (FAPIIS) on a semi-annual basis, throughout the life of the contract, by posting the required information in the Central Contractor Registration database at http://www.ccr.gov.
(b)(1) The Contractor will receive notification when the Government posts new information to the Contractor’s record.
(2) The Contractor will have an opportunity to post comments regarding information that has been posted by the Government. The comments will be retained as long as the associated information is retained, i.e., for a total period of 6 years. Contractor comments will remain a part of the record unless the Contractor revises them.
(3)(i) Public requests for system information posted prior to April 15, 2011, will be handled under Freedom of Information Act procedures, including, where appropriate, procedures promulgated under E.O. 12600.
As required by section 3010 of Public Law 111-212, all information posted in FAPIIS on or after April 15, 2011, except past performance reviews, will be publicly available.
(End of clause) 52.216-18 Ordering (Oct 1995)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from the date of contract award through the end date of either the base period of performance or the last option period exercised.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) If mailed, a delivery order or task order is considered “issued” when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.
(End of clause) 52.216-19 Order Limitations (Oct 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,500.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor—
(1) Any order for a single item in excess of $500,000.00;
(2) Any order for a combination of items in excess of $500,000.00; or
(3) A series of orders from the same ordering office within thirty (30) days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within seven (7) days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of clause) 52.216-22 Indefinite Quantity (Oct 1995)
(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”
(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after the end date of either the base period of performance or the last option period exercised. (End of clause) 52.217-9 Option to Extend the Term of the Contract (Mar 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 138102 months.
(End of clause) 52.222-42 Statement of Equivalent Rates for Federal Hires (May 1989) In compliance with the Service Contract Act of 1965, as amended, and the regulations of the Secretary of Labor (29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5332.
This Statement is for Information Only:
It is not a Wage Determination
| Employee Class |
| Employee Description |
| Monetary Wage – Fringe Benefits |
| _23921_______ |
| _Telecommunications Mechanic I__ |
| $27.36 |
| _23932_______ |
| _Telecommunications Mechanic II_ |
| $28.21 |
| _23160_______ |
| _Electrician, Maintenance_________ |
| $31.22 |
(End of clause)