U.S. GENERAL SERVICES ADMINISTRATION
GREATER SOUTHWEST REGION
1BLaredo Convent Bridge 1 &
J&L Bridge 2 Ports of Entry Laredo, Texas
GSA Project No. NTX00007 & NTX00009
2B10 0 % Co ns tru ct i on Do cu m en ts
May 2 3 , 20 1 4
05.23.14
Prepared by: RICHTER ARCHITECTS
201 South Upper Broadway
Corpus Christi, Texas 78401
Telephone: 361-882-1288
SENSITIVE BUT UNCLASSIFIED (SBU)
PROPERTY OF THE UNITED STATES GOVERNMENT
COPYING, DISSEMINATION, OR DISTRIBUTION OF THIS DOCUMENT TO UNAUTHORIZED RECIPIENTS IS PROHIBITED Do not remove this notice. Properly destroy or return documents when no longer needed.
05/23/2014
LAREDO 1 & 2 PORTS OF ENTRY 00 01 10-1
Laredo, Texas TABLE OF CONTENTS
GSA Project Numbers NTX00007 & NTX00009
May 23, 2014
PROPERTY OF UNITED STATES GOVERNMENT –
FOR OFFICIAL USE ONLY
TABLE OF CONTENTS 00 01 10-1
DIVISION – SECTION TITLE PAGES
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 10 - TABLE OF CONTENTS
00 01 15 - LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS (COMBINED PROJECT SECTIONS)
01 14 00 - WORK RESTRICTION
01 29 00 - PAY PROCEDURES ……………………………………………………………………………………………………………………
01 30 00 - ELECTRONIC PROJECT MANAGEMENT AND COORDINATION
01 31 00 - PROJECT MANAGEMENT AND COORDINATION
01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION
01 32 16 - CRITICAL PATH METHOD SCHEDULING
01 32 20 - PHOTOGRAPHIC DOCUMENTATION
01 33 00 - SUBMITTAL PROCEDURES
01 35 29 - SAFETY AND HEALTH
01 35 53 - SECURITY PROCEDURES
01 43 00 - QUALITY ASSURANCE AND CONTROL
01 50 00 - TEMPORARY FACILITIES AND CONTROLS
01 60 00 - PRODUCT REQUIREMENTS
01 70 00 - EXECUTION REQUIREMENTS
01 77 00 - CLOSEOUT PROCEDURES
01 78 22 - OPERATION AND MAINTENANCE DOCUMENTATION
01 78 36 - WARRANTIES
01 78 39 - PROJECT RECORD DOCUMENTS
01 79 00 - DEMONSTRATION AND TRAINING
END OF SECTION 00 01 10
LAREDO 1 & 2 PORTS OF ENTRY 00 01 15-1
Laredo, Texas LIST OF DRAWINGS
LIST OF DRAWINGS 00 01 15-1
DRAWING SHEET INDEX SEQUENCE #
G101 COVER/ TITLE SHEET 001
GENERAL:
G102 OVERALL EXISTING SITE PLAN 002
G103 OVERALL NEW SITE PLAN 003
G104 SITE PLAN - BRIDGE 1 & LOWER PARKING 004
G105 SITE PLAN - BRIDGE 2 - SOUTH 005
G106 SITE PLAN - BRIDGE 2 - NORTH 006
G110 J&L BRIDGE 2 - STEP 1 007
G111 J&L BRIDGE 2 - STEP 2 008
G112 J&L BRIDGE 2 - STEP 3 009
G113 J&L BRIDGE 2 - STEP 4 010
G114 J&L BRIDGE 2 - STEP 5 011
G115 J&L BRIDGE 2 - STEP 6 012
G116 J&L BRIDGE 2 - SCHEDULES 013
G120 CONVENT BRIDGE 1 - STEP 1 & 2 014
G121 CONVENT BRIDGE 1 - STEP 3 015
G122 CONVENT BRIDGE 1 - TEMPORARY BUILDING PLAN 016
G123 CONVENT BRIDGE 1 - CEILING & ROOF PLANS 017
G124 CONVENT BRIDGE 1 - ELEVATIONS - EXTERIOR & INTERIOR 018
G125 CONVENT BRIDGE 1 - SECTIONS & DETAILS 019
G130 CBP BRIDGE 1 & 2 OVERALL EXISTING CAMPUS 020
G131 CONVENT BRIDGE 1 - TEMPORARY BLDG. CONNECTIVITY 021
G132 CONVENT BRIDGE 1 - ONE-LINE DIAGRAM 022
G140 J&L BRIDGE 2 - CAMPUS 023
G141 J&L BRIDGE 2 - ONE-LINE DIAGRAM 024
G142 J&L BRIDGE 2 - AREAS A AND B 025
G143 J&L BRIDGE 2 - AREAS C, D, E, AND F 026
END OF SECTION 00 01 15
LAREDO 1 & 2 PORTS OF ENTRY 01 14 00-1
Laredo, Texas WORK RESTRICTIONS
WORK RESTRICTIONS 01 14 00-1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 - GENERAL
1.1 CONTRACTOR USE OF PREMISES
A. The Government will conduct a pre-construction survey with the Contractor to review and document the existing conditions surrounding the project premises prior to the beginning of any construction activity.
B. During the construction period, the Contractor shall have use of the designated premises for construction operations, including use of the indicated work site, subject to maintaining areas for continuous Government operations and limited by the Government's right to perform work or retain other contractors to perform work on portions of the project.
C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.
1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the
Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain existing buildings in a safe and weather-tight condition throughout the construction period.
Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect buildings and processing areas, their occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one
(1) hour of notice should an emergency occur.
5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.
6. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government. Arrange and gain approval for use of this space through the GSA.
7. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the
Contractor and shall be removed from the site. The Contractor shall make every effort to recycle or salvage those materials and provide the Government salvage/recycling receipts listing details of the transaction. Storage or sale of excess salvageable materials and equipment is not permitted on site.
8. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.
9. No parking will be available on site during working hours of the building occupants. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.
10. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be
“on vibrate” at all times within buildings. If a telephone begins audibly ringing, the building guards will take the cell phone and hold until the end of the working day prior to the con-tractor leaving the property. Cell phones are only permitted in construction area and contractor’s office space.
LAREDO 1 & 2 PORTS OF ENTRY 01 14 00-2
WORK RESTRICTIONS 01 14 00-2
11. No apparatus with an open flame is allowed to be used within existing facilities without the prior receipt of a burn permit. Contact the GSA to obtain burn permits. Burn permits are required for each separate occurrence.
12. City permits and inspections: Some work does occur on city property. For that work, the Contractor is responsible for obtaining any necessary permits and making arrangements for any necessary inspections. The Contractor is hereby alerted that the fee for City inspectors will increase if less than
24 hour notice is given to the City. All fees and payments for permits and inspections shall be the responsibility of the Contractor, at no additional cost to the Government.
13. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.
14. Coordinate with the GSA Building Manager and the COR for site access.
15. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.
16. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.
17. Protect building site from flying debris.
1.2 GOVERNMENT OCCUPANCY
A. The Government will occupy the site and some of the existing buildings during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.
B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the
Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the
Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.
2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.
1.3 WORKING HOURS
A. Government Occupied Hours: Government personnel are scheduled to occupy the site and existing facilities
24 hours / 7 days a week.
B. Government Unoccupied Hours: Not-Applicable
C. Contractor's General Working Hours: 24 hours / 7 days a week.
D. Contractor's Required Working Hours: The following work shall be performed during Government daylight hours:
1. Noisy and/or odor-producing work that may disrupt adjacent residential areas.
LAREDO 1 & 2 PORTS OF ENTRY 01 14 00-3
WORK RESTRICTIONS 01 14 00-3
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01 14 00
LAREDO 1 & 2 PORTS OF ENTRY 01 29 00-1
Laredo, Texas PAYMENT PROCEDURES
PAYMENT PROCEDURES 01 29 00-1
SECTION 01 29 00
PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and process
Requests for Payment.
1.2 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Requests for Payment. The
Agreement provides further details.
B. Request for Payment: Contractor invoice and request for progress payment, with substantiating information consistent with approved schedule of values.
1.3 SCHEDULE OF VALUES
1. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. The Agreement provides further details Submit the schedule of values to
GSA at earliest possible date but no later than 14 days before the date scheduled for submittal of initial Requests for Payment.
B. Format and Content: Use the work breakdown structure from the CPM schedule as a guide to establish work branches for the schedule of values. Provide at least one work branch for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project Name:
b. Project Number:
c. Contract Number:
d. Project Region:
e. Building/Facility Name:
f. Building/Facility Number:
g. Contractor's name and contact information:
h. Date of submittal.
2. Arrange the schedule of values in tabular form with separate columns to indicate the following for each work branch and subordinate line item listed:
a. Related Specification Section.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
LAREDO 1 & 2 PORTS OF ENTRY 01 29 00-2
PAYMENT PROCEDURES 01 29 00-2
e. Name of supplier.
f. Modifications that affect value.
g. Dollar value of the following, as an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent. Adjust the amounts to total to the
Contract Sum and the percentages to total 100 percent.
1) Labor.
2) Materials.
3) Equipment.
3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of
Requests for Payment and progress reports. Provide multiple subordinate line items for work branches with values in excess of five percent of the Contract Sum.
4. Each item in the schedule of values and Requests for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.
5. Schedule Updating: Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the
Contract Sum.
1.4 REQUESTS FOR PAYMENT
A. Requirements for Requests for Payment are governed by the FAR contract clauses included in this Contract.
1. The government will delineate the requirements for Requests for Payment prior to the preconstruction conference.
B. Each Request for Payment following the initial Request for Payment shall be consistent with previous
Requests and payments as paid for by GSA.
1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final
Request for Payment involve additional requirements.
C. Payment Request Times: Submit Request for Payment to GSA by the 22 nd day of the month. The period covered by each Request for Payment is one month, ending on the last day of the month
1. Submit draft copy of Request for Payment along with construction progress report sevendays prior to due date for review by GSA. Provide documentation evidencing the cost of work performed to be included in the Request for Payment. Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment.
2. Request for Payment Forms: The Agreement provides further details.
3. Include project information items required by GSA with each Request for Payment , unless such information is available from the Central Contractor Registration (CCR) database.
D. Request Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. GSA will return incomplete Requests without action.
LAREDO 1 & 2 PORTS OF ENTRY 01 29 00-3
PAYMENT PROCEDURES 01 29 00-3
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.
3. Include amounts of Modifications issued before last day of construction period covered by Request.
E. Stored Materials: Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to GSA, and consent of surety to payment, for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation.
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of effective date of previous
Request for Payment.
b. Value of previously stored materials put in place after effective date of previous Request for
Payment and on or before effective date of current Request for Payment.
c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.
4. Transmittal: The Agreement provides details
F. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (startup if not final).
4. Products list (preliminary if not final).
5. Sustainable design submittal for project materials cost data.
6. Sustainable design action plans.
7. Schedule of unit prices.
8. Submittal schedule (preliminary if not final).
9. List of Contractor's staff assignments.
10. List of Contractor's principal consultants.
11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the
Work.
12. Initial progress report.
13. Report of preconstruction conference.
G. Request for Payment at Substantial Completion: After GSA issues the Certificate of Substantial
Completion, submit a Request for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This Request shall reflect Certificates of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.
H. Final Payment Request: The Agreement provides further details.
LAREDO 1 & 2 PORTS OF ENTRY 01 29 00-4
PAYMENT PROCEDURES 01 29 00-4
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 29 00
LAREDO 1 & 2 PORTS OF ENTRY 01 30 00-1
Laredo, Texas ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM
ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM 01 30 00-1
SECTION 01 30 00
ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM
1.1 GENERAL
A. GSA requires the Contractor to utilize GSA’s electronic Project Management (ePM) system on this project.
The (ePM) system will be provided by GSA to accommodate information exchange needs of the Project as well as training and limited support. GSA’s web-based ePM system is a significantly customized version of
Meridian Systems’ Proliance Construction Management Software.
B. The ePM system will be maintained continuously through completion of the Construction Stage. All communications between the GSA, Contractor, and other entities involved in the execution of the Project shall be captured and recorded in the ePM system. User licenses and training will be provided for GSA and
Contractor members of the Project Delivery Team who will require access to the ePM system.
C. The intended electronic design and construction documents stored in ePM contain various levels of sensitive but unclassified (SBU) information, as defined by PBS Order 3490.1A. The ability of the GSA to provide for the safety and security of persons and property under its charge and control is a major concern of the GSA.
Security procedures are necessary to reduce the risk that project information will be used for dangerous and/or illegal purposes. Most email systems and FTP sites do not meet the necessary security requirements for the transmission of electronic SBU information, therefore the ePM system will be the only acceptable means for electronically transferring SBU project information. *Physical transfer of information following
SBU protocols is still acceptable.
D. Contractor shall use ePM system for communications with GSA and other entities involved in the Project.
Electronic storage and transmission of information via the ePM system shall comply with GSA's Document
Security Requirements.
1.2 PROJECT COLLABORATION AND DOCUMENTATION
A. The Contractor is required to accurately post, review, respond and collaborate with other team members using the following features and/or workflow processes with the ePM system. GSA reserves the right to require the
Contractor to utilize ePM for additional project activities not listed below.
1. Project Team Directory: The Contractor shall provide an updated directory of contact information for all companies, subcontractors and project team members who are engaged on this project to be entered into ePM.
2. Contract Management: The Contractor shall administer applicable contract tasks related to the project within ePM; including maintaining the contract schedule of values, contributing to contract modifications, and invoicing. All supporting documentation related to these processes shall be uploaded as attachments to the source information.
LAREDO 1 & 2 PORTS OF ENTRY 01 30 00-2
ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM 01 30 00-2
3. Pay Application Requests (Invoices): The Contractor shall create invoices for review by GSA in ePM.
Once the invoices are agreed to by GSA then the invoices should be submitted to GSA per the instructions given by the Contracting Officer.
4. Change Management: Cost Events and Change Orders will be managed in the ePM system. The
Contractor shall be responsible for reporting potential Change Orders and logging requested Change
Orders in ePM. All supporting documentation related to these processes shall be uploaded as attachments to the source information.
5. Daily Construction/Progress Reports: The Contractor shall maintain construction progress reports, and daily reports/logs in ePM.
6. Safety/Inspection Reports: The Contractor shall maintain inspection reports on materials and/or workmanship (including fire reports, injury reports and safety notices) in ePM to assure compliance with all contract requirements.
7. Permits and Approvals: The Contractor shall upload and maintain current copies of all project specific permits and agency approvals in ePM.
8. Issue Tracking: The Contractor shall log and respond to issues in ePM that are related and affect other stakeholders within the project team.
9. Punch lists: The Contractor shall manage the punch list process in ePM. NOTE: DEPENDING ON
HOW THE PROJECT IS SET UP IT MIGHT BE BETTER TO USE ePM ONLY AS THE
REPOSITORY OF WORD OR SPREADSHEET PUCHLIST DOCUMENTS
10. Project Correspondence: The Contractor shall manage and maintain all significant incoming and outgoing project correspondence and associated logs in ePM.
11. Drawings and Specifications: The Contractor shall use ePM to record and store all approved specifications and as-built construction documents.
12. Meeting Minutes: The Contractor shall enter or attach meeting agendas and minutes in ePM for all applicable project meetings as designated by the GSA Project Manager.
13. Requests for Information (RFI): The RFI process will be managed in ePM. The Contractor shall utilize ePM to enter all Requests for Information, and respond to those RFI’s directed to the
Contractor.
14. Shop Drawings: The Contractor shall submit all shop drawings in ePM for review by the Project Team.
15. Submittals: The submittal process will be managed in ePM. The Contractor is responsible for uploading submittal documentation and using the system to track the submittal process.
LAREDO 1 & 2 PORTS OF ENTRY 01 30 00-3
ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM 01 30 00-3
16. Schedules: The Contractor shall post, review, and/or respond to CPM schedule updates within the ePM system, as required by the contract.
17. Progress Photos: The Contractor shall upload and maintain all progress photos in ePM.
18. Closeout Documents: The Contractor shall upload any documents pertaining to Closeout into ePM as noted in the ePM Closeout Checklist (i.e. Certificate of Occupancy, Commissioning Report, Environmental Permits, Final Inspections, Final Occupancy Agreements, LEED Scorecard and
Certification, Life Safety and Fire Marshal approval, Operation & Maintenance Manuals, Release of
Claims, Substantial Completion Certificate, and Warranty Certificates).
1.3 EQUIPMENT
A. GSA will not furnish any equipment related to accessing ePM. ePM is web-accessible, and can therefore be accessed via any computer with an Internet connection. Minimum computer requirements for accessing the ePM application include:
Hardware Minimum Requirements
• Intel® Pentium® III 933 MHz or higher (Recommended) Minimum Intel® Pentium® II 300 MHz
• 512 MB RAM or higher
• High Speed Internet Connection (Recommend 1 Mbps or greater)
• 1 GB Storage
Minimum Required Desktop Software
• Microsoft Windows® XP Service Pack 2
• Microsoft® Internet Explorer 6.01 or Microsoft® Internet Explorer 7.0
• Acrobat Reader
• Project Document Manager Client
• Data Dynamics Active Reports Viewer
• Sun Java 2 Runtime (1.4.2)
• Microsoft .NET Framework Version 1.1 Redistributable Package
• Microsoft .NET Framework 3.5 Service Pack 1
• Microsoft® Office 2003 or Office 2007 Professional Edition
• Microsoft Office 2003 / or 2007 Redistributable Primary Interop Assemblies Redistributable
• Primary Interop Assemblies*
• Microsoft Web Services Enhancements 2.0 Service Pack 3 [**Required if using the ePM Office Business
Applications or Desktop Quick Applications]
• Visual Studio 2005 Tools for Office Second Addition Runtime (VSTOR)*
1.4 TRAINING
LAREDO 1 & 2 PORTS OF ENTRY 01 30 00-4
ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM 01 30 00-4
A. GSA will provide training to familiarize team members with the ePM system. All Contractor staff that are key to the execution of ePM protocols are expected to attend these sessions to receive proper training on the system's use.
B. The Contractor to provide a location that can be used for training a group of the required size for the initial training session. This should have internet access, projector, screen, desks, etc. All attendees can bring their own laptops so they can check their system configurations at the same time.
C. GSA will provide ePM system administration and end user support, for the duration of the project.
1.5 PERSONNEL REQUIREMENTS
A. An HSPD-12 security clearance is required to access ePM. Project Team members without an HSPD-12 clearance will need to work with the GSA Project Manager to initiate the clearance process, and request a temporary waiver for ePM access. Once the individual’s HSPD-12 clearance is confirmed, an ePM username and password will be provided.
1.6 DATA OWNERSHIP
A. GSA shall retain ownership of all data entered into the system and shall administer and distribute all information contained therein.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 30 00
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-1
Laredo, Texas PROJECT MANAGEMENT AND COORDINATION
PROJECT MANAGEMENT AND COORDINATION 01 31 00-1
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:
1. General project coordination.
2. Coordination drawings.
3. Conservation.
4. Administrative and supervisory personnel.
5. Conferences and meetings.
6. Utility service interruptions.
7. Cleaning and protection.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the
Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space. Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.
B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
6. Startup and adjustment of systems.
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-2
PROJECT MANAGEMENT AND COORDINATION 01 31 00-2
1.3 COORDINATION DRAWINGS
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
4. Show location and size of all access doors in the structure on both vertical and horizontal surfaces.
5. Coordination Drawing size and submittal requirement are specified in Division 1 Section "Submittal
Procedures."
B. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk. Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.
C. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings: Revit 2012 and / or AutoCAD 2010 as required be each section of the
Specifications.
2. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).
3. GSA will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.
a. GSA makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.
b. Digital Data Software Program: The Drawings are available in Revit and AutoCAD.
c. Execute a data licensing agreement in a form acceptable to the GSA..
1.4 CONSERVATION
A. Coordinate conservation of energy, water and materials in the conduct of construction operation. Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.
B. Waste Management Plan: Establish a program to maximize recycling of waste materials. Program shall include the following:
1. Designation of a waste management coordinator.
2. Identification of recyclable materials.
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-3
PROJECT MANAGEMENT AND COORDINATION 01 31 00-3
3. Identification of available local recycling firms and agencies to receive recyclable materials.
4. Establishment of quantity goals for collection of each recyclable material.
5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.
6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.
7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.
a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.
b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant party of the project, including the Government.
1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.
B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:
1. Scheduling and sequencing of Work.
2. Sharing access to work spaces.
3. Installations.
4. Protection of work.
5. Cutting and patching.
6. Selections for compatibility.
7. Preparation of coordination of drawings.
8. Inspection and tests.
9. Temporary services and facilities.
C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."
D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.
1.6 CONFERENCES AND MEETINGS
A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.
1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-4
PROJECT MANAGEMENT AND COORDINATION 01 31 00-4
a. Government.
b. Architect.
c. Major design consultants.
d. Contractor.
e. Major subcontractors.
f. Major suppliers.
g. Other concerned parties.
2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:
a. Tentative construction schedule.
b. Critical work sequencing.
c. Designation of responsible personnel.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for processing Applications for Payment.
f. Distribution of Contract Documents.
g. Submittal of Shop Drawings, Product Data, and Samples.
h. Preparation of Record Documents.
i. Use of the premises.
j. Parking availability.
k. Office, work, and storage areas.
l. Equipment deliveries and priorities.
m. Safety procedures.
n. First aid.
o. Security.
p. Housekeeping and progress cleaning.
q. Working hours.
r. Energy and resource efficiency / sustainability
s. Waste management
t. Commissioning, if applicable
B. Progress Meetings: The Government or designee shall conduct progress meetings at the Project Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.
1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited;
secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract
Time.
b. Review the present and future needs of each entity present, including but not limited to the following:
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-5
PROJECT MANAGEMENT AND COORDINATION 01 31 00-5
1) Interface requirements.
2) Time.
3) Sequences of operations.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site utilization.
9) Temporary facilities and controls.
10) Hours of work.
11) Hazards and risks.
12) Housekeeping and progress cleaning.
13) Quality and work standards.
14) Change Orders.
15) Documentation of information for payment requests.
16) Updating of Record Documents.
3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.
C. Pre-installation Conferences: Contractor to schedule and conduct pre-installation conferences as required in each section of the specifications. The purpose of these conferences is to discuss critical issues that will effect either submittals or installation of systems. They will help prevent potential quality and/or installation conflicts. Sections requiring Pre-Installation Conferences include but are not limited to:
1. Section 01 40 00 – Quality Assurance and Control, for Exterior Assembly Mock-up.
2. Section 01 70 10 - Airtight Construction (Interior).
3. Section 02 41 00 - Demolition (Pre-demolition).
4. Section 03 35 01 – Concrete Finishing.
5. Section 04 20 00 - Unit Masonry.
6. Section 06 41 00 – Architectural Wood Casework.
7. Section 07 12 50 - Monolithic Membrane.
8. Section 07 41 13 – Metal Roofing.
9. Section 07 54 00 – Thermoplastic Membrane Roofing.
10. Section 08 45 00 – Translucent Panels.
11. Section 08 71 00 – Door Hardware.
12. Section 09 30 00 – Tiling.
13. Section 09 66 23 – Terrazzo
14. Section 32 13 13.1 – Concrete Paving – Vehicular
15. Section 32 13 13.2 – Concrete Paving – Non-Vehicular
16. Section 32 14 00 – Unit Paving – Sand Set
D. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor and Architect, but no later than 90 days prior to the scheduled date of Substantial
Completion.
Attendees: Authorized representatives of GSA, Contractor and its superintendent; major subcontractors;
suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
1. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-6
PROJECT MANAGEMENT AND COORDINATION 01 31 00-6
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for completing sustainable design documentation.
e. Requirements for preparing operations and maintenance data.
f. Requirements for delivery of material samples, attic stock, and spare parts.
g. Requirements for demonstration and training.
h. Preparation of Contractor's punch list.
i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
j. Submittal procedures.
k. Coordination of separate contracts, if any.
l. GSA's partial occupancy requirements.
m. Installation of GSA's furniture, fixtures, and equipment.
n. Responsibility for removing temporary facilities and controls.
2. Minutes: Entity conducting meeting will record and distribute meeting minutes within 3 working days.
1.7 ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM
A. A secure, web-based, electronic project management (ePM) system will be provided by GSA to accommodate information exchange needs of the Project. The ePM system will be maintained continuously through completion of the Construction Stage. All communications between the GSA, Contractor, and other entities involved in the execution of the Project shall be captured and recorded in the ePM system. User licenses and training will be provided for GSA and Contractor members of the Project Delivery Team who will require access to the ePM system.
B. Contractor shall use ePM system for communications with GSA and other entities involved in Project.
Electronic storage and transmission of information via the ePM system shall comply with GSA's Document
Security Requirements.
C. See Section 01 30 00 Electronic Project Management (ePM) System for complete requirements.
1.8 UTILITY SERVICE INTERRUPTIONS
A. Utility Service Interruption Plan: Contractor shall submit a utility service interruption plan for the project.
Plan shall include dates and times of each scheduled interruption, with estimated period of outage, list of existing equipment that will be affected by the interruption, proposed sequence of equipment shut-down and start-up, and responsible personnel.
1. Keep interruptions and periods of interruption to a minimum.
2. Plan must be approved in writing by the GSA. If not approved, consult with the GSA, and revise and resubmit the plan until approved.
3. Some city utility work is required for the project which may result in interruption of service. Any potential interruption shall be coordinated with the City of Laredo.
B. Coordination of Interruptions: Sufficiently in advance of each scheduled utility interruption, the Contractor shall issue a notice to all affected parties, confirming each provision of the interruption, or canceling and rescheduling. Coordinate with the GSA, and confirm that the responsible personnel are prepared to execute the shut-down and start-up of affected existing equipment, prior to each interruption.
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-7
PROJECT MANAGEMENT AND COORDINATION 01 31 00-7
1.9 SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
4. Coordination Drawings: Comply with the shop drawing requirements specified in Division 1 Section
"Submittal Procedures".
B. Waste Management: Within 15 calendar days after commencement of construction, submit the waste management plan, followed by monthly implementation reports.
C. Staff Names: Within 15 calendar days after commencement of construction, submit a list of principal staff assignments, including the superintendent and other primary personnel at the Project site. Identify individuals by name, duties and responsibilities, home address, and business and home telephone numbers.
1. Post copies of this list on ePM, in the project meeting room, temporary field office and at each temporary telephone location.
D. Utility Service Interruptions: No later than 15 calendar days prior to the first planned interruption, submit the utility service interruption plan, followed by confirmed scheduled shut-down notices at least 3 calendar days prior to each interruption.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
LAREDO 1 & 2 PORTS OF ENTRY 01 31 00-8
PROJECT MANAGEMENT AND COORDINATION 01 31 00-8
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light.
10. Radiation.
11. Puncture.
12. Abrasion.
13. Heavy traffic.
14. Soiling, staining, and corrosion.
15. Bacteria.
16. Rodent and insect infestation.
17. Combustion.
18. Electrical current.
19. High-speed operation.
20. Improper lubrication.
21. Unusual wear or other misuse.
22. Contact between incompatible materials.
23. Destructive testing.
24. Misalignment.
25. Excessive weathering.
26. Unprotected storage.
27. Improper shipping or handling.
28. Theft or vandalism.
END OF SECTION 01 31 00
LAREDO 1 & 2 PORTS OF ENTRY 01 32 00-1
Laredo, Texas CONSTRUCTION PROGRESS DOCUMENTATION
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00-1
SECTION 01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain schedules and reports required for documenting the progress of construction during performance of the Work.
B. Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities, and maintain a consistent and logical correlation between updated schedules and reports.
C. All construction progress documentation should be created and transmitted electronically.
1.2 SCHEDULE OF INSPECTIONS AND TESTS
A. Prepare and submit a schedule of inspections, tests and similar services required by the Contract Documents within 10 calendar days after the date established for commencement of the Contract.
B. Coordinate the schedule of inspections and tests with the Contractor's Construction Schedule and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:
1. Specification section number.
2. Description.
3. Identification of applicable standards.
4. Identification of methods to be used.
5. Number of inspections, tests or similar services.
6. Time schedule or time span.
7. Responsible entity.
8. Requirements for taking samples.
9. Unique characteristics.
C. Distribution: Submit electronic copies of the schedule of inspection and tests to the GSA, entities designated by the Contracting Officer, and each party involved in performance of portions of the Work where inspections, tests and similar serviced are required.
1.3 REPORTS
A. Daily Construction Reports: Prepare an electronic daily construction report recording the following information concerning events at the site.
1. List of subcontractors at the site.
2. List of separate contractors at the site.
3. Count of personnel at the site.
LAREDO 1 & 2 PORTS OF ENTRY 01 32 00-2
Laredo, Texas CONSTRUCTION PROGRESS DOCUMENTATION
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00-2
4. High and low temperatures, general weather conditions.
5. Accidents.
6. Meetings and significant decisions.
7. Unusual events (see D. Unusual Event Reports below).
8. Stoppages, delays, shortages, and losses.
9. Meter readings and similar recordings.
10. Emergency procedures.
11. Orders and requests of governing authorities.
12. Change Orders received or implemented.
13. Services connected or disconnected.
14. Equipment or system tests and startups.
15. Partial completions or occupancies.
16. Summary of all work performed.
B. Material Location Reports: At not more than weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include a statement of progress on and delivery dates for materials or items or equipment fabricated or stored away from the site. Submit copies of the list to the Contracting Officer or
Contracting Officer's representative.
C. Field Correction Reports: When the need to take corrective action requires a departure from the Contract
Documents, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Submit a copy to the Contracting
Officer or Contracting Officer's representative for approval.
D. Unusual Event Reports: When an event of an unusual and significant nature occurs at the site, prepare a detailed report. List the chain of events, persons participating, response by the Contractor's personnel, evaluation of the results or effects, and similar pertinent information. Submit a copy to the Contracting
Officer or Contracting Officer's representative immediately. Advise the Contracting Officer or Contracting
Officer's representative in advance when such events are known or predictable.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 01 32 00
LAREDO 1 & 2 PORTS OF ENTRY 01 32 16-1
Laredo, Texas CRITICAL PATH METHOD SCHEDULING
CRITICAL PATH METHOD SCHEDULING 01 32 16-1
SECTION 01 32 16
CRITICAL PATH METHOD SCHEDULING
PART 1 - GENERAL
1.01 SUMMARY
A. Develop a detailed Network Plan using the most current version of any preferred…