Contract Agreement

View the file

Other files

File Type Posted
Amendment II_West.pdf PDF
C301.doc DOC document
Amendment I_West.pdf PDF
Sol_Asbestos_Abatement_and_Mold_Remediation_Services_West 1 .doc DOC document
Question Answer.doc DOC document
Percentage factor agreement_West.doc DOC document
SF 1442_West.pdf PDF
Document Security Notice.doc DOC document
UNIT PRICE SCHEDULE NOTES AND DRAWINGS.doc DOC document
Abatement IDIQ line Items Updated Feb 22 2012.xls XLS spreadsheet
SF 24(2).pdf PDF
GSA 527.pdf PDF
Specifications.doc DOC document
Sol_Asbestos_Abatement_and_Mold_Remediation_Services_West 1 .doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Asbestos Abatement and Mold Remediation Services Contract-Region 7 West – The Agreement

Construction Contract for Asbestos Abatement and Mold Remediation Services, Region 7 West GSA Contract No. GS-07P-12-HHD-0009A The Agreement

Table of Contents

I.

Project Information

A.

Project Summary

B.

The Contract

C.

Period of Performance

D.

Work Conditions/Site Requirements

E.

Authorized Representative

F.

Contract Liquidated Damages Rate

G.

Buy American Exceptions

H.

Statements of Work, Specifications, Drawings, Exhibits and Other Attachment

II.

Prices

Basis of Pricing

Contract Price Form

III.

Terms and Conditions

General Terms and Conditions

Contract Clauses

I Project Information

I.A Project Summary

Provide all asbestos abatement and mold remediation services; to include site surveys, confirmation of asbestos/mold scope of work on-site, bulk samples of suspected asbestos containing materials (i.e. ACM), and prepare reports on the results of the site surveys. Projects will primarily involve asbestos abatement and mold remediation, but may also include selective demolition.

I.B The Contract

I.B.1 The Contract consists of the SF 1442, the Agreement, Specifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.

I.B.2 The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.

I.C Period of Performance

The period of performance of this contract will commence on or about April 2012 and remain in effect for a period of one (1) year, with four (4) one(1) year options for a total contract term not to exceed five (5) years from that date; except that task orders placed prior to the expiration date shall remain in full force and effect until deliveries have been completed and payments have been made.

I.C.1 Commencement. Commence work under this contract as stated in the task order after the Contractor receives the Notice to Proceed.

I.C.2 Substantial Completion. Complete the entire work, ready for use, not later than the time shown on the task order. The time stated for completion shall include final cleanup of the premises.

I.C.3 Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 60 calendar days of Substantial Completion.

I.D Work Conditions/Site Requirements

See individual task orders I.E Authorized Representative I.E.1 This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the authorized GSA representative under this Contract:

Contract Specialist

Name: Trevor A. Simon

Address: 819 Taylor St, 12B01

Telephone: 817-7-978-0122

Email: trevor.simon@gsa,gov

I.E.2 GSAR 552.236-71, Authorities and Limitations, is incorporated by reference in this Contract.

I.F Contract Liquidated Damages Rate (If applicable)

The performance times in calendar days and liquidated damages will be stated on each individual task order.

The liquidated damages will vary and will be established per individual delivery order. The liquidated damage rate will be established by the Contracting Officer and at a minimum, cover the estimated cost of inspection, depending on if the inspection is to be made by a Government if the inspection is to be made by a Government Official or other Government contracted sources, and will vary depending on the use of the space and how critical its occupancy is to the affected agencies and the cost of travel to and from the site. Whenever the Government will suffer other specific losses due to the failure of the Contractor to complete the work on time, the rate(s) shall include an amount for additional items as:

(a) The cost of substitute facilities

(b) The rental of buildings and/or equipment.

Liquidated damages will be assessed in accordance with FAR 11.5.

If the ordering official and the Contractor cannot agree on time of performance or the liquidated damages rate for any task order, the matter shall be resolved by the base contract CO.

I.G Buy American Exceptions

For the purpose of determining Buy American requirements set forth in the Buy American Clause of the Agreement, the following construction materials and components are excepted:

None

I.H Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments

The following document is incorporated into this Contract.

Specifications for Contract No. GS-GS-07P-12-HHD-0009A, Dated February 29, 2012

II

Prices

II.A

Basis of Pricing

II.A.1

Task Orders: Scheduled Line Items Percentage Factor and Scheduled Line Items Percentage Factor (using RS Means Guides)

The Government furnished line item listing and the RS Means Guides in this contract are the primary ordering source. A non-scheduled line item is a line item that is not listed in the Government furnished line item listing or the RS Means Guides; therefore, a non-scheduled line item shall be negotiated.

1. Government Furnished Scheduled Line Items.

The unit pricing in the scheduled line items is based on national averages taken from the most current RS Means Facilities Construction Cost Data guide and in-house estimating. The scheduled line items are a combination of components that represent a “compact effect”. The line items were developed in this manner for the Indefinite Quantity Contract as a tool to provide a faster performance time to meet our customer needs. The unit price listed in the scheduled line items already includes a reasonable overhead and profit for the installing contractor.

The offeror shall submit one percentage factor for all scheduled line items. The percentage factor submitted for the scheduled line items shall be proposed as: plus, minus or net. This percentage factor will apply to the base period of one year and will include all markup, labor and materials. The offeror shall also submit one percentage factor for each option period, (option period one, option period two, option period three, and option period four) which take into account any changes in the costs of labor and materials.

2. Scheduled Line Items (using RS Means Guides)

The unit price in the RS Means Facilities Construction Cost Data guide already includes a reasonable overhead and profit for the installing contractor; however, it has not been adjusted for a particular geographic area. The offeror shall submit one percentage factor for all scheduled line items (using RS Means Guides). The percentage factor submitted for the scheduled line items (using

RS Means Guides) shall be proposed as: plus, minus or net. (See Scheduled Line Items using RS Means Guide – Solicitation, Offer and Award – SF 1442). This percentage factor will apply to the base period of one year and will include all markup, labor and materials. The offeror shall also submit one percentage factor for each option period, (option period one, option period two, option period three, and option period four) which take into account any changes in the costs of labor and materials. The scheduled line items (using RS Means Guides) portion of the task orders will use the most current RS Means Guides. The percentage factor submitted will be a ceiling percentage.

SAMPLE

An example of how the Scheduled Line Items (using RS Means Guides) will be utilized is as follows:

Item #: 161 105 8800 Description: Conductor, 15KV, aluminum shielded-ungrounded, #1 with PVC jacket, 350 MCM Reference: 1997 Means Electrical Cost Data, pg. 136

Unit Price: $21.00/LF

Company A’s Percentage Factor: -10%

Company A’s Price: $21.00/LF X 10% = $ 2.10 $21.00 - $2.10 = $18.90/LF

Do not include the Gross Receipts Tax for the State of New Mexico in your percentage Factor. Do not include premiums for bonds in your percentage factors.

The gross receipts tax and premiums for bonds will be a separate line item when applicable. Premiums for bonds will be restricted to the actual bond fee only. No additional factors will be added.

The awardee will be required to submit schedules on all projects in Microsoft Project. The Contracting Officer (CO) and designated Contracting Officer Representative (COR) may negotiate, at their discretion, special circumstances pertaining to the project.

Price Schedule. The current issues of the RS Means Guides are incorporated in this contract by reference. (See below). The Contractor will be required to comply with the current issues of the RS Means Guides for the duration of the contract. These publications, to include all revisions, must be maintained by the contractor, at no cost to the Government.

“The current issues of the following data books are incorporated into this contract by reference annually.”

RS Means Facilities Construction Cost Data

RS Means Building Construction Cost Data

RS Means Mechanical Cost Data RS Means Electrical Cost Data

RS Means Site Work & Landscape Cost Data

RS Means Plumbing Cost Data

III

Terms and Conditions

III.A

General Terms and Conditions

III.A.1

Commencement, Prosecution, and Completion of Work FAR 52.211-10, Commencement, Prosecution, and Completion of Work, is supplemented as follows:

The Contractor shall not commence the Work until the Contracting Officer has issued NTP. The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion, as defined in III.A.8(a), of the Work within the time specified in Paragraph I.C of the Agreement. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.

III.A.2

Contractor Responsibilities

III.A.2(a) For the purposes of FAR 52.236-1, Performance of Work by the Contractor, the Contractor shall perform at least 51 percent of the Work.

III.A.2(b) Unless otherwise expressly stated in the Contract, the Contractor shall be responsible for all means and methods employed in the performance of the Contract.

III.A.2(c) The Contractor shall be responsible for providing professional design services in connection with performance of the Work or portions of the Work only if this responsibility is expressly stated and the Contract Documents provide the performance and design criteria that such services will be required to satisfy. In the performance of such work, the Contractor shall be responsible for retaining licensed design professionals, who shall sign and seal all drawings, calculations, specifications and other submittals that the licensed professional prepares. The Contractor shall be responsible for, and GSA shall be entitled to rely upon, the adequacy and completeness of all professional design services provided under this Contract.

III.A.2(d) The Contractor shall be responsible for coordinating all activities of subcontractors. This responsibility includes coordination of: preparation of shop drawings produced by different subcontractors where their work interfaces or may potentially conflict or interfere and the installation of such work; scheduling of work by subcontractors; and use of the Project site for staging and logistics.

III.A.2(e) Where installation of separate Work components as shown in the Contract Documents will result in conflict or interference between such components or with existing conditions, including allowable tolerances, it is the Contractor's responsibility to bring such conflict or interference to the attention of the Contracting Officer and seek direction before fabrication, construction, or installation of any affected work. If the Contractor fabricates, constructs, or installs any work prior to receiving such direction, the Contractor shall be responsible for all cost and time incurred to resolve or mitigate such conflict or interference.

III.A.2(f) Where drawings show work without specific routing, dimensions, locations, or position relative to other work or existing conditions, and such information is not specifically defined by reference to specifications or other information supplied in the Contract Documents, the Contractor is responsible for routing, dimensioning, and locating such work in coordination with other work or existing conditions in a manner consistent with Contract requirements.

III.A.2(g) It is not the Contractor's responsibility to ensure that the Contract Documents comply with applicable laws, statutes, building codes and regulations. If it comes to the attention of the Contractor that any of the Contract Documents do not comply with such requirements, the Contractor shall promptly notify the Contracting Officer in writing. If the Contractor performs any of the Work prior to notifying and receiving direction from the Contracting Officer, the Contractor shall assume full responsibility for correction of such work, and any fees or penalties that may be assessed for non-compliance.

III.A.2(h) The Contractor shall immediately bring to the Contracting Officer's attention any hazardous materials or conditions not disclosed in the Contract Documents discovered by or made known to the Contractor during the performance of the Contract

III.A.2(i) The Contractor must submit a safety plan before commencing work.

III.A.3

Contractor Management and Personnel

FAR 52.236-6, Superintendence by the Contractor, is supplemented as follows:

III.A.3(a) The Contractor shall employ sufficient management and contract administration resources, including personnel responsible for project management, field superintendence, change order administration, estimating, coordination, inspection, and quality control, to ensure the proper execution and timely completion of the Work. The Contractor shall designate a principal of the firm or other senior management official to provide executive oversight and problem resolution resources to the Project for the life of the Contract.

III.A.3(b) The Contractor shall employ, and require its subcontractors to employ, qualified personnel to perform the Work. The Government reserves the right to exclude, or remove from the site or building, any personnel for reasons of incompetence, carelessness, or insubordination, who violate rules and regulations concerning conduct on federal property, or whose continued employment on the site is otherwise deemed by the Government to be contrary to the public interest.

III.A.3(c) Repeated failure or excessive delay by the Contractor to provide qualified personnel shall be deemed a default for the purposes of the Termination for Default clause.

III.A.4

CPM Project Schedule

III.A.4(a) The Contractor shall use a Critical Path Method ("CPM") Project Schedule to plan, coordinate, and perform the Work. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance.® For example, compatible software includes Microsoft Project,® Primavera SureTrak,® and Primavera Project Planner.®

III.A.4(b) The Project Schedule shall be a rational, reasonable and realistic plan for completing the Work, and conform to requirements specified in this clause and elsewhere in this Contract.

III.A.4(c) The Contractor understands and acknowledges that the preparation and proper management of the Project Schedule is a material component of the Work, and that the Contract price includes all costs of compliance with Project Schedule requirements.

III.A.4(d) The Project Schedule shall depict all activities necessary to complete the Work, including, as applicable, all submittal and submittal review activities, all procurement activities, and all field activities, including mobilization, construction, start-up, testing, balancing, commissioning, and punchlist. Activities shall be sufficiently detailed and limited in duration to enable proper planning and coordination of the Work, effective evaluation of the reasonableness and realism of the Project Schedule, accurate monitoring of progress, and reliable analysis of schedule impacts.

III.A.4(e) Within thirty (30) days of NTP, or such other time as may be specified herein, the Contractor shall submit its Project Schedule to the Contracting Officer, together with a written narrative describing the major work activities, activities on the critical path, and major constraints underlying the sequence and logic of the Project Schedule. The Contractor shall submit the Project Schedule in both electronic and hardcopy print format.

III.A.4(f) The Contractor should anticipate that its initial submittal of the Project Schedule shall be subject to review and revision as contemplated by Paragraph III.A.4(k), and the Contractor shall devote sufficient resources for meetings, revisions, and resubmissions of the Project Schedule to address exceptions taken by the Contracting Officer to the initial submittal. The Contractor understands and acknowledges that the purpose of the initial review and resolution of exceptions is to maximize the usefulness of the Project Schedule for the Parties during Contract performance.

III.A.4(g) Activity durations shall be based upon reasonable and realistic allocation of the resources required to complete each activity, given physical and logistical constraints on the performance of the Work. All logic shall validly reflect physical or logistical constraints on relationships between activities. Except for the first and last activities in the Project Schedule, each activity shall have at least one predecessor and one successor relationship to form a logically connected network plan from NTP to the Contract Completion date.

III.A.4(h) The Project Schedule shall incorporate milestone events specified in the Contract, including, as applicable, NTP, Substantial Completion, and milestones related to specified work phases and site restrictions. The Project Schedule shall also include Contractor-defined milestones to identify target dates for critical events, based upon the Contractor's chosen sequence of work.

III.A.4(i) Unless a shorter period for updates is specified elsewhere, the Contractor shall update the Project Schedule monthly to reflect its actual progress in completing the Work, and submit the updated Project Schedule to the Contracting Officer within five (5) working days of the end of each month or other specified period.

III.A.4(j) If the Contractor revises the Project Schedule after initial submission, the Contractor shall provide in writing to the Contracting Officer a narrative describing the substance of the revision, the rationale for the revision, and the impact of the revision on the projected Substantial Completion date and the available float for all activities. The Contractor shall only revise prospective activities, durations and logic, but addition of detail to prospective activities shall not be deemed a revision if the overall duration of the detailed activity does not change.

III.A.4(k) If at any time the Contracting Officer finds that the Project Schedule does not comply with any Contract requirement, the Contractor shall, upon written notice of exceptions taken by the Contracting Officer, revise the Project Schedule, adjust activity progress, or provide sufficient information demonstrating compliance. Regardless of whether the Contracting Officer takes any such exception, the Contractor shall not be relieved of its responsibility for the rationality, reasonableness or realism of the Project Schedule, or its responsibility to achieve Substantial Completion within the time specified by this Contract.

III.A.4(l) If the Contractor fails to sufficiently address the Contracting Officer's exceptions to the Project Schedule within thirty (30) calendar days of written notice of same, the Contracting Officer may withhold retainage until the Project is Substantially Complete or until such time as the Contractor has complied with Project Schedule requirements.

III.A.4(m) The Contracting Officer shall be entitled, but not required, to rely upon the Project Schedule to evaluate the Contractor's progress, evaluate entitlement to extensions of time and determine the criticality or float of any activities described in such Project Schedule.

III.A.5

Extensions of Time

FAR 52.211-13, Time Extensions, is supplemented as follows:

III.A.5(a) If the Contractor requests an extension of the time for Substantial Completion, the Contractor shall base its request on analysis of time impact using the Project Schedule as its baseline, and the new Substantial Completion date projected by the Project Schedule as revised to account for the impact. The Contractor's request must be submitted to the Contracting Officer in writing, and set forth facts and analysis in sufficient detail to enable the Contracting Officer to evaluate the Contractor's entitlement to an extension of time.

III.A.5(b) The Contractor shall only be entitled to an extension of time to the extent that Substantial Completion of the Work is delayed by causes for which the Contractor is not responsible under this Contract and to the extent that the actual or projected Substantial Completion date is later than the date required by this Contract for Substantial Completion.

III.A.5(c) The Contractor shall not be entitled to an extension of time if the Contractor has not updated the Project Schedule in accordance with this Contract.

III.A.5(d) The Government shall not be liable for any costs to mitigate time impacts incurred by the Contractor that occur less than 30 calendar days after the date the Contractor submits a request for extension of time complying with this clause.

III.A.6

Interpretation of Specifications and Drawings

FAR 52.236-21, Specifications and Drawings for Construction, and GSAR 552.236-77, Specifications and Drawings, are supplemented as follows:

III.A.6(a) Different requirements within the Contract Documents shall be deemed inconsistent only if compliance with both cannot be achieved.

III.A.6(b) Unless otherwise noted, the drawings shall be interpreted to provide for a complete construction, assembly, or installation of the Work, without regard to the detail with which material components are shown in the drawings.

III.A.7

Submittals

FAR 52.236-21, Specifications and Drawings for Construction, GSAR 552.236-78, Shop Drawings, Coordination Drawings, and Schedules, and GSAR 552.236-79, Samples, are supplemented as follows:

III.A.7(a) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract. If particular submittal requirements are not specified for a component of the Work, the Contractor shall prepare submittals for such Work as directed by the Contracting Officer.

III.A.7(b) The Contractor shall not proceed with work or procure products or materials described or shown in submittals until the Contracting Officer has indicated approval of the submittal. Any work or activity undertaken prior to approval shall be at the Contractor’s risk; should the Contracting Officer subsequently determine that the work or activity does not comply with the Contract, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination. The Contracting Officer shall have the right to order the Contractor to cease execution of work for which submittals have not been approved. The Government shall not be liable for any cost or delay incurred by the Contractor attributable to the proper exercise of this right.

III.A.7(c) The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty (20) working days.

III.A.8

Substantial Completion and Contract Completion

FAR 52.211-10, Commencement, Prosecution, and Completion of Work, FAR 52.211-12, Liquidated Damages (Construction), and GSAR 552.246-72, Final Inspection and Tests, are supplemented as follows:

III.A.8(a) For the purposes of FAR 52.211-10, Commencement, Prosecution and Completion of Work, and FAR 52.211-12, Liquidated Damages (Construction), the Work shall be deemed complete when it is “Substantially Complete.” The Work shall be deemed "Substantially Complete" if and only if the Contractor has completed the Work and related Contract obligations in accordance with the Contract Documents, such that the Government may enjoy the intended access, occupancy, possession, and use of the entire Work without impairment due to incomplete or deficient work, and without interference from the Contractor's completion of remaining work or correction of deficiencies in completed work. In no event shall the Work be deemed Substantially Complete if all fire and life safety systems are not tested and accepted by the Authority Having Jurisdiction, where such acceptance is required under the Contract.

III.A.8(b) At the appropriate time, the Contractor shall submit to the Contracting Officer a written notice specifying a proposed Substantial Completion date (Notice of Substantial Completion). The Contracting Officer shall conduct inspections and make a determination of Substantial Completion within a reasonable time. If the Contracting Officer takes exception to the Notice of Substantial Completion, the Contractor shall be entitled to a written notice of conditions precluding determination of Substantial Completion.

III.A.8(c) The Contractor shall be entitled to an extension of time to address such conditions if, and to the extent that, the Contracting Officer provides notice of such conditions more than thirty (30) calendar days from receipt of the Notice of Substantial Completion.

III.A.8(d) Substantial Completion shall be established by the Contracting Officer's issuance of a written determination specifying the date upon which the Work is Substantially Complete.

III.A.8(e) The Contract is complete (Contract Completion) if and only if the Contractor has completed all Work and related Contract obligations, corrected all deficiencies, and complied with all conditions for final payment.

III.A.8(f) Unless otherwise specifically noted, or otherwise clear from context, all references in this Contract to "acceptance" shall refer to issuance of a written determination of Substantial Completion.

III.A.8(g) The Contractor shall not be entitled to final payment or release of any retainage held by the Government until after Contract Completion. If the Contractor does not achieve Contract Completion within the time required by this Contract, the Government shall be entitled, after providing notice to the Contractor, to complete any work remaining unfinished. The Contractor shall be liable to the Government for all costs incurred by the Government to complete such work.

III.A.9

Use and Possession Prior to Substantial Completion FAR 52.236-11, Use and Possession Prior to Completion, is supplemented as follows:

Exercise of the right conferred by FAR 52.236-11 shall not relieve the Contractor of responsibility for completing any unfinished components of the Work.

III.A.10

Finality of Contract Modifications

As set forth elsewhere in this Contract, the Contractor is entitled to additional consideration under certain conditions, including the issuance of change orders. It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing such consideration, adjustments to the Contract price or time agreed upon therein shall be deemed to provide all compensation to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to compensation on account of the change or other condition giving rise to the modification.

III.A.11

Liquidated Damages

FAR 52.211-12, Liquidated Damages (SEP 00), is supplemented as follows:

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount to be shown on each task order issued against this contract, for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

III.A.11(a) The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work within the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Paragraph I.F for each calendar day following the required completion date that the Work is not Substantially Complete.

III.A.11(b) If the Contract requires different completion dates for different phases or portions of the Work, the Contractor shall be liable for liquidated damages at the specified rate for each calendar day following the required completion date that the phase or portion of Work is not Substantially Complete. If a single rate is specified, the specified rate shall be apportioned between the different phases or portions of the Work.

III.A.11(c) If the Government elects to accept any portion of the Work not specifically designated as a phase or portion of Work with its own required completion date, the liquidated damage rate shall be apportioned between accepted work and uncompleted work, and the Contractor's liability for liquidated damages shall be computed accordingly.

III.A.12

Insurance Requirements III.A.12(a) The Contractor shall obtain, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation.

III.A.12(a)(i) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $100,000. If occupational diseases are not covered by workers' compensation insurance, Employers' liability coverage shall include occupational diseases.

III.A.12(a)(ii) Broad form comprehensive commercial general liability insurance in the amount of at least $500,000 per occurrence. Such insurance shall include, but not be limited to, contractual liability, bodily injury and property damage.

III.A.12(a)(iii) Comprehensive automobile liability covering the operation of all automobiles used in connection with performing the Contract in the amount of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

III.A.12(b) The Contractor shall provide to the Contracting Officer proof that it is has obtained insurance required by the Contract in the form of certificates of insurance. The Contractor shall submit to the Contracting Officer all renewal certificates issued during the life of this Contract immediately upon issuance.

Note: Corrections are required to the cancellation block in the lower right-hand corner. The statement must read as follows: “Should any of the policies described herein be cancelled before the expiration date thereof, the insurer affording coverage will mail 30 days written notice to the certificate holder named to the left.” A letter from your insurer stating they will provide a 30 day written notice will suffice in lieu of marking the certificate itself in accordance with FAR 52.228-5.

The certificate(s) should also cite the contract number and must name GSA as additional insured.

III.A.13

Order of Precedence Different requirements within this Contract shall be deemed inconsistent only if compliance with both cannot be achieved. In case of inconsistency between Contract Documents, the following order of precedence shall apply:

(1) Construction Contract Clauses (Section III.B of the Agreement)

(2) Other Provisions of the Agreement (Sections I, II, and III.A of the Agreement)

(3) The Statement of Work

(4) The Specifications

(5) The Drawings

(6) Exhibits and Other Attachments

III.A14

Administrative Matters

III.A.14(a) Project Meetings. The Contractor shall attend a preconstruction conference and shall participate in regularly scheduled Project meetings.

III.A.14(b) Schedule of Values. The Contractor shall prepare and submit for approval a detailed cost breakdown of the Contract price, to be referred to as the Schedule of Values, assigning values to each component of the Work. Values must include all direct and indirect costs, although a separate value for bond costs may be established. The Schedule of Values must contain sufficient detail to enable the Contracting Officer to evaluate applications for payment. If this Contract requires that the Project Schedule be cost loaded, the Schedule of Values will be derived from the Project Schedule.

III.A.14(c) Payments. FAR clause 52.232-5, Payments under Fixed-Price Construction Contracts, is supplemented as follows:

III.A.14(c)(i) Before submitting a request for payment, the Contractor shall attend pre‑invoice payment meetings each month, as scheduled, with the designated Government representative for the purpose of facilitating review and approval of payment requests. Payment meetings may be conducted in person or by telephone. The Contractor shall provide documentation to support the prospective payment request.

III.A.14(c)(ii) The Contractor shall submit its invoices to the representative designated in Paragraph I.E.1. Separate payment requests shall be submitted for progress payments, payments of retainage, and partial or final payments.

III.A.14(c)(iii) If the invoice does not meet the requirements of FAR Clause 52.232‑27 (a)(2) and the requirements specified in Subparagraphs III.A.14(c)(i), (iv), (v), and (vi), the Contracting Officer may be return the invoice to the Contractor without payment for correction. If the Contracting Officer disputes the requested payment amount, the Government may pay the portion of the requested payment that is undisputed.

III.A.14(c)(iv) Invoices shall be submitted in an original and two (2) copies to the designated billing office specified in this Contract or in individual delivery/work orders.

III.A.14(c)(v) Invoices must include the Account Document Number (ADN) assigned at award.

III.A.14(c)(vi) The Contractor shall submit the following information or documentation with each invoice:

III.A.14(c)(vi)(A) GSA Form 184A and/or 184B - Construction Progress Report (Construction Phases Only) or AIA Form G702, including the updated Schedule of Values upon which the payment request is based;

III.A.14(c)(vi)(B) GSA Form 2419 - Certification of Progress Payments Under Fixed-Price Construction Contract;

III.A.14(c)(vi)(C) The payment terms that apply for the particular services rendered;

III.A.14(c)(vi)(D) Additional documentation: Certified Payrolls III.A.14(c)(vii) GSA will not be obligated to issue final payment unless the Contractor has furnished to the Contracting Officer a release of claims against the Government relating to this Contract, and submitted all required product warranties, as-built drawings, operating manuals, and other items as specified in the Contract. The Contractor may reserve from the release specific claims only if such claims are explicitly identified with stated claim amounts. All release forms must bear the original signature of the signer and must be affixed with the Contractor’s corporate seal or the seal of a Notary Public.

III.A.14(d) Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:

(i) Progress Payments: 14 days

(ii) Subsequent Subcontractor Payments: 7 days

III.A.14(e) Payment Information. The General Services Administration (GSA) makes information on contract payments available electronically at http://www.finance.gsa.gov.

The Contractor may register at the site and review its record of payments. This site provides information only on payments made by GSA, not by other agencies.

III.A.14(f) Security Clearances. Contractor shall comply with the following requirements pertaining to security clearances.

III.A.14(f)(i) All personnel performing work under the Contract on the Project site must obtain an Enter on Duty (EOD) determination before they will be granted access to the site.

III.A.14(f)(ii) To obtain an EOD determination, Contractor shall submit for all such personnel fingerprints on Form FD258 and a completed Contractor Information Worksheet (CIW).

III.A.14(f)(iii) In addition, all such personnel who will be on site 6 months or longer must apply for and receive clearance in accordance with Homeland Security Presidential Directive 12 (HSPD-12).

III.A.14(f)(iv) Information concerning these requirements can be found at:

http://www.gsa.gov/portal/category/26757 III.A.14(g) Sensitive But Unclassified (SBU) Building Information. The following requirements apply to information contained in this Contract that has been designated as Sensitive But Unclassified (SBU) building information:

III.A.14(g)(i) The Contractor shall submit to GSA all Contractor-generated documents that may contain SBU building information before the original or any copies are disseminated to any other parties. If GSA identifies SBU content in such documents, the Contracting Officer may direct the Contractor to imprint or affix SBU document markings to the original documents and all copies prior to dissemination.

III.A.14(g)(ii) The Contractor shall protect SBU building information by strictly limiting access to those individuals having a need to know such information acting on behalf of Federal, State, and local government entities, nongovernment entities engaged in the conduct of business on behalf of or with GSA, and firms currently registered as “active” in the Central Contractor Registration (CCR) database at www.ccr.gov. If a subcontractor is not registered in the CCR and has a need to possess SBU building information, the subcontractor shall provide to the Contractor its DUNS number or its tax ID number and a copy of its business license. This clause shall not be construed to encumber the dissemination of SBU building information to public safety entities.

III.A.14(g)(iii) The Contractor shall use session or file encryption when transmitting SBU building information electronically outside of the GSA firewall and network. The Contractor shall encrypt sessions or files with an approved NIST algorithm, such as Advanced Encryption Standard (AES) or Triple Data Encryption Standard (3DES), in accordance with Federal Information Processing Standards Publication (FIPS PUB) 140-2, Security Requirements for Cryptographic Modules. Encryption tools that meet FIPS 140-2 are referenced on the NIST web page found at the following URL:

http://csrc.nist.gov/groups/STM/cmvp/documents/140-1/1401vend.htm All encryption products used to satisfy the FIPS 140-2 requirement should have a validation certificate that can be verified at the following URL:

http://csrc.nist.gov/groups/STM/cmvp/validation.html#02 (Note that not all vendors of security products that claim conformance with FIPS 140-2 have validation certificates.)

III.A.14(g)(iv) When transmitting SBU building information contained in any physical media, including hardcopy and portable electronic data storage devices, the Contractor shall only use methods of shipping that provide services for monitoring receipt such as track and confirm, proof of delivery, signature confirmation, or return receipt. Portable electronic data storage devices include but are not limited to CDs, DVDs, and USB drives.

III.A.14(g)(v) The Contractor shall maintain a list of the entities and the firms to which it has disseminated SBU building information. This list must include at a minimum (1) the name of the entity or firm; (2) the name and contact information of the individual at the entity or firm who is responsible for protecting the SBU building information; and (3) a description of the SBU building information provided. Upon completion of the Work, the Contractor shall collect all lists maintained in accordance with this clause, including those maintained by any subcontractors and/or suppliers, and submit them to the Contracting Officer. The Contracting Officer may withhold final payment until the lists are received.

III.A.14(g)(vi) This Contract requires that the Contractor retain beyond the period of performance certain records that may contain SBU building information. With the exception of such records, upon completion of the Work, the Contractor shall either destroy all records containing SBU building information or return them to the Contracting Officer, as directed by the Contracting Officer. The Contractor shall destroy electronically stored SBU building information by deleting it or otherwise rendering it unreadable and incapable of being restored, in accordance with guidelines provided for media sanitization within Appendix A of NIST Special Publication 800-88, Guidelines for Media Sanitization, available at http://csrc.nist.gov/publications/nistpubs/800-88/NISTSP800-88_rev1.pdf. Examples of acceptable destruction methods for SBU building information are: burning or shredding hardcopies; physically destroying portable electronic storage devices; deleting and removing files from electronic recycling bins; and removing material from computer and hard drives using a permanent-erase utility such as bit-wiping software or disk crushers.

III.A.14(g)(vii) The Contractor shall verify to the Contracting Officer in writing that SBU building information has been disposed of as required in Subparagraph III.A.14(g)(vi). The Contracting Officer may withhold final payment until written verification is received.

III.A.14(g)(viii) The Contractor shall immediately report to the Contracting Officer all improper disclosures of SBU building information. If the Contractor fails to comply with any provision of this clause, the Contracting Officer may withhold approval of progress payments until the Contractor provides a corrective action plan explaining how it will rectify any noncompliance and prevent future improper disclosures of SBU building information.

III.A.14(g)(ix) The Contractor shall insert the substance of this clause in all subcontracts.

III.A.15 Non-Compliance with Contract Requirements

In the event the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this contract, fails to initiate promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the Contracting Officer shall have the right to order the Contractor to stop any or all work under the contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.

III.A.16

Options and Allowances

The General Services Administration (GSA) has included an option to extend the term of this contract in order to demonstrate the value it places on quality performance by providing a mechanism for continuing a contractual relationship with a successful Offeror that performs at a level which meets or exceeds GSA’s quality performance expectations as communicated to the Contractor, in writing, by the Contracting Officer or designated representative. When deciding whether to exercise the option, the Contracting Officer will consider the quality of the Contractor’s past performance under this contract in accordance with 48 CFR 517.207.

III.A.17

Additional Terms and Conditions

PAYMENT BY CREDIT CARD

The Government reserves the right to pay vendors by use of the Government Commercial credit card. The contractor must be equipped to accept payments via credit card upon award and/or notice to proceed of the contract. Currently, Citibank Government Card Services is under contract with General Services Administration to provide payment services to vendors through the VISA card. The provisions of this paragraph are applicable to any card issued by any succeeding credit card service vendor. For purposes of this solicitation, the clearinghouse identifies the nationally accepted credit card payment network being used by the Government Commercial credit card contractor.

Contractor shall not process a transaction for payment through the credit card clearinghouse until the purchased supplies have been shipped or services performed. Unless the cardholder requests corrections or replacement of a defective or faulty item in accordance with other contract requirements, the contractor shall immediately credit the cardholder’s account for items or services returned as defective or faulty or services performed in an unsatisfactory manner.

FAR 52.217-9 - Option to Extend the Term of the Contract (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within the schedule; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed five (5) years.

(End of clause)

FAR 52.217-5 - EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

FAR 52.216-22 - INDEFINITE QUANTITY (OCT 1995)

(a) This is an indefinite quantity contract for the supplies or services specified, and effective for the period stated in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum". The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum".

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after the date specified in the individual work order.

ORDERING

FAR 52.216-18 - ORDERING (OCT 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from approximately April 2012 through March 2013.

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

FAR 52.216-19 - TASK-ORDER LIMITATIONS (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $500.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under this contract.

(b) Maximum order. The Contractor is not obligated to honor --

(1) Any order for a single (unit priced) item in excess of $1,000,000

(2) Any order for a combination of (unit priced) items in excess of $1,000,000;

(3) A series of orders from the same ordering office within five (5) days that together call…