- Solicitation number
- GS05P17GBC0003
About this file
Amendment to Solicitation 004 - same as Amendment to Solicitation posted on 8/15/201 and 8/16/2017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment__014.pdf | ||
| Amendment__0013.pdf | ||
| Amendment_0010.pdf | ||
| Amendment_to_Solicitation_009.pdf | ||
| Amendment008.pdf | ||
| Amendment_007_to_Solicitation.pdf | ||
| Amendment_006_to_Solicitation.pdf | ||
| Amendment_to_Solicitation_005.pdf | ||
| Amendment_003.pdf | ||
| Pre-proposal_sheet.docx | DOCX document | |
| Amendment_001.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
5P1QCE-CH
GS-05-P-17-GB-C-0001 -Construction Manager as Constructor, for the John C. Kluczynski Federal Building Tenant Office Buildout, Amendment 004
-Inclusion of pre-proposal meeting minutes and attendee list -Inclusion of contractor questions -Inclusion of second walk through attendee list -Inclusion of additional GSA HR drawings
5P1QCE-CH
Acquisition Management Division 230 S. Dearborn St.
Room 3300 Chicago, IL 60604
Acquisition Management Division 230 S. Dearborn St.
Room 3300 Chicago, IL 60604
GS05P17GBC0003
08/15/2017
07/18/2017
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
JCK CMc Tenant Office Build-out and General Building Modifications Pre-proposal Conference July 31, 2017 at 1:05 pm CST
230 S. Dearborn Street, Floor 18 Chicago, IL 60604
1. Introductions of GSA Team/Welcome/General remarks
2. GSA Recap of agenda, request to write questions down during the walk through so group can also hear it
3. Review of Technical and Price submittal requirements -Past Experience, Management Approach, Key Personnel, Past Performance and what we are looking for -Price proposal 1442 and price worksheet supplement, 527, reps and certs, bonds, etc.
4. RFP due at 3 pm CST -need 1 original and 5 copies the Contracting Officer will accept email but ORIGINAL must be in paper copy. Please send one copy via email to the Contracting Officer, Kathern Williams at kathern.williams@gsa.gov.
-Account for internal JCK building mail processes, MUST be in at 3 pm to floor 33
4.1 -QUESTION: Does the email count if it is in before 3 pm?
-Yes, as long as it is in before 3 pm
5. QUESTION: Does the pricing only want design phase services priced out?
-No, want design phase services and the GMP for construction phase services. We want the lump sum price of all agency work. GMP will be awarded at a later day, but we are evaluating GMP price now.
- Provide two prices. One for design phase services - the other indicating the total gMP
6. QUESTION: What are the general contractor eligibility requirements for the project?
-This is a small business set aside, so you must show that you are a small business. It is a self certification process, but if you have questions you can contact the SBA to inquire about your status. It is a dollar amount and a number of employees that usually make a “small business”
7.1 -QUESTION: What is the dollar amount?
-GSA believes around $30 million over a period of time don’t we need to confirm this dollar value?
mailto:kathern.williams@gsa.gov
7. QUESTION: As the SOW is reading, it seems like the work is “global” for each floor, is that true or is it different on each floor? Example, like what is above the ceiling and what needs to be done?
-It is different for each floor, but we are currently still in design so we are going to work with the CMc to get that information of what is on each floor that needs to be done
8. QUESTION: Is this project going to include energy efficiency? Such as LEED? What is the requirement?
-Yes, there are five (5) agencies (HR, Credit Union, Tax Court, EEOC, Dept. of Ed).
EEOC and Dept. of Ed have LEED requirements and will have separate certifications.
The other 3 agencies do not have LEED requirements.
9. QUESTION: Are there any building standards/building requirement mandates that will have to be considered for systems work?
-Any contractor/sub working on the system need to be certified to work on those systems but there is no required contractor to use. The technicians coming into work on that system must be certified to work on that system.
-There are Building Design Standards (BDS) and systems do require certified technicians.
10. New security clearance process, 2 main changes
1) Once construction contract is awarded, firm will go through a training session to know exactly what has changed in the process
2) If someone is found unfavorable, there is no adjudication, no appeal process
11. As most have contracted with the government before we hope you have a better understand of the process -contract number, zonal clearance contact, need long term clearances, process should run more smoothly, but GSA is not involved once we give you contract number and you work with person who covers the ZONE, after the required training.
-Escort process: if a subcontractor needs to be escorted, they are only allowed up to 15 calendar days per calendar year, and so would need to go through short-term clearance process, and cannot be escorted and in the process of the short-term/long-term clearance
12. QUESTION: Is the security clearance training required from someone from the CMc to manage the contract?
-Yes, the training is required
13. QUESTION: Is there anyone that might be excluded from the firm who could be on their team if they are already on the design team?
There is no exclusion of parties on this contract
14. Review of Wage Rate Requirements, OSHA, staffing requirements, etc.
15. SOW review -EEOC, Dept. of Education, GSA HR, Credit Union, Tax Court
15.1 -Dept. of Education, is the largest tenant in the contract, have a lot of movable partitions that need to come down and go back up
15.2 Pre-alteration assessment happening now, to review if any asbestos or lead based paint is in use
15.3 GOAL for LEED Gold for this project aiming to reuse ceiling and light fixtures, except as indicated on the construction documents.
15.4 EEOC will be moving to the 18th floor. The 18th floor will be a single tenant floor.
The documents indicate reusing ceilings, lights and ventilation grills. A pre-alteration assessment survey has been completed. Information will be provided.
15.5 Relocation of GSA HR office - the existing HR office has already been moved to another floor and will not need to be moved off the 37th floor as part of this project.
There will be some interface work needed when moving HR back to the 37th floor.
15.6 Tax Court ceiling replacement, ceiling only project, replace ceiling tiles and fire protection work to accommodate new ceiling, VAV work, asbestos abatement
15.7 Reconfiguration of Credit Union, is original space from when the building was first built. The work includes demounting walls and re-installing them . HVAC work and electrical work
15. 8 All projects will have a pre-alteration assessment to test for asbestos and lead based paint and containment
16. QUESTION: What floors are tax court?
-39th Floor
17. QUESTION: Existing partitions, will there be an assessment to determine they are in acceptable condition?
-The contractor will perform an assessment prior to construction.
18. QUESTION: Are there any spare parts?
-The GSA will provide demountable partitions and associated doors, frames and hardware that is available from its inventory. The balance of demountable partitions, associated doors and hardware that are not able to be provided from the GSA’s inventory will have to be provided by the Contractor.
19. QUESTION: Will there be an addendum of the asbestos status before proposals are due?
-Yes
20. QUESTION: If the existing furniture glass partitions come down and go back up in the same condition they are in, is that acceptable?
-Yes
21. QUESTION: Can subcontractors come in for a walk through?
-Yes, another walk through will be conducted
22. QUESTION: Mentioned LEED Gold for Dept of Ed, is that also for EEOC?
-Yes, it is a requirement for both
23. QUESTION: Space we are in currently (18th floor of the JCK) will be EEOC, who is moving to this floor, do you want the lights replaced here to meet LEED Gold?
-No, the drawings will show what lights need to be replaced
24. QUESTION: You show materials and carpets to be used, is there an allowance?
-Contractors must match Existing Carpet As Required, C2\C3: Mohawk Group\Starting Over GT316\978 Burst (Color/Style to be selected from full range by Architect)\Brand: Lee
25. QUESTION: Note on floor finish plan for leveling the floors, is that “leveling floors” or “patching floors to accept the goods”?
-It is Patching floors to accept the goods and making sure it looks good at the end, this will be clarified in an amendment.
26. The RFP is made up of the scope of work, drawings, and any amendments that we put out, need to review all of those things.
-If there is anything unclear please submit an RFI or question to Kathern and Lexy and we will respond.
27. Any questions we receive today will be posted on FBO. If we believe something will affect pricing it will be posted as an amendment. If anything significant comes out it will become an amendment to the solicitation.
28. QUESTION: Can we talk about phasing of the project?
-It’s a one phased project, but since we have a lot of agencies on vacant spaces there are a lot of moving parts. It’s up to the contractor to determine the best
“phasing” of the project. There is a small phasing schedule of Tax Courts in the Scope of Work, and GSA HR is already moved. Some floors are occupied by other agencies, so need to take that into consideration.
- Consideration WILL be given to phasing the start of EEOC with work to begin sometime May 2018. The completion date for EEOC will remain as indicated
29. QUESTION: Is fire alarm protection allowed during working hours for this project?
-No, not during business hours, ALL life safety systems must be done after hours, cannot take the building offline during business hours.
30. QUESTION: Elevator use during the day?
-They are very active during the day, the elevators are available, they cannot be isolated for specific project use, but we can look at building projects and coordinate time. There are freight elevators.
31. QUESTION: Can you clarify the design services vs EXPs work?
-The Design services for the CMc is to review the designs and do back-up cost estimating to verify on budget. EXP has milestone dates to produce design documents for CMc to review and insure that the drawings will allow for staying on budget during construction phase
32. QUESTION: Is the CMc doing all the reporting for LEED Gold?
The CMc will make all submittals for this requirement to USGBC.
33. GSA Pricing Requirements:
-Is made up of the 5 agencies under option 1.
-There is a 2nd option and 3rd option and a few alternates. Review the scope of work and pricing worksheet to clarify the pricing requirements.
34. GSA: Does anyone have any questions of what is GMP and what should be included in an option?
-No
35. QUESTION: Bringing CMc on during design but also asking for a GMP, so is it an option?
-The GMP is an option, but as we go through design we will confirm that number.
As we go through design, it requires both parties to come to an agreement to exercise the option. We work the project within the agreed upon budget. It includes, trade costs and general conditions, and contingency pool for CMc, as well as fee are all included in the GMP.
36. QUESTION: What is the contingency percentage?
-3% (Three percent)
37. If there are any questions please email them to Kathern or Lexy so that we can get answers out to you as soon as possible.
38. WALKING THROUGH occupied spaces, so please be respectful of hours
39. Question: Are photos allowed during walk through?
-Not in occupied spaces.
40. Walk through from 1:55 pm CST
41. Please advise if the SF 1442 must be completed by 2 firms partnering to be the CM on the project. Small business majority partner and other CM entity.
42. Will a bid bond be required at this stage of the project submittal.
-A bid bond is required to cover your proposal for pre-construction services. One pre-construction services are awarded, a performance and payment bond will be required. A bond for construction services will not be required until the GMP is awarded later during the project. But construction services proposal will be evaluated and accepted at this time.
43. Will furniture relocation be done by GSA staff.
-Removal of furniture will be done by “others”
44. We will have 3 small business partners on this project. One of the partners is a majority partner. Will each of the 3 firms be required to provide certifications, financials, past performance PPQ and projects?
- We would like to see how the firms work together. Ideally the proposed JV would have worked on previous projects and will submit past experience and past performance as the JV. If not, it is best that all firms submit something to show their past experience and their past performance. Only the lead firm needs to provide certifications and financials.
45. Is the 30 page limit single sided or double sided?
- Double sided
46. Do you want hard copies and submit it electronically as well. Is this a digital submittal only?
-One original hard copy is required for both the technical and price proposal.
JCK CMc Second Walk through Questions
1. How do workers enter the building?
a. Workers will enter through the west side of the building, even with badges, through the clark street entrance, once badged.
2. Demo hours, day or night?
a. Demo can occur during business hours.
b. All HIGH IMPACT demo must be performed demo after hours.
c. Office hours are M-F 6 am to 6 pm.
3. Dumpsters? Leave for next day? How many?
There are locations for dumpsters on P Level, dumpsters are not provided by the building or GSA.
4. Credit Union → window is bullet proof, is the wall also?
Walls are not plated.
5. Sequencing of work?
Only Tax Court has specific schedule but the contractor will get all space and sequence work.
6. Bond, when is it due? How much?
The offeror is required to submit a bid bond with their proposal. A bid bond should cover the amount of the design phase services. A payment and performance bond will be due 10 days after award. The bond will be 100% of the amount of the award for design phase services. Once the GMP option is awarded the bond will have to be increased to cover 100% of the GMP.
7. Freight Elevators?
There are two (2) in the southwest corner with access to every floor, from P level (dock) to 39. They are controlled via push button and will not lock down for the project.
8. Want to confirm the Liquidated Damages Rate of $25,354.39 for the subject contract is correct and firm.
Yes, the Liquidated Damages Rate of $25,354.39 is correct and firm.
9. We request that a CAS be waived during the RFQ-RFP phase and that this audit information be provided if awarded a project. Our accounting system complies with your requirements but we don’t have the CAS audit. There is a fee to perform this specific audit and we would like to do this only if awarded a project. Please advise.
CAS is not a requirement for this contract. Section II.D. Factor #5 Go/No Go CAS requirement of the Solicitation is hereby removed.
10. Page 10 of The Solicitation lists the minimum required key team members as:
• Corporate construction executive
• Project manager
• Architectural review coordinator
• Engineering review coordinators - all disciplines
• Cost estimator(s)
• Project accountant
• Construction superintendent
• Quality control superintendent
• Project engineer
• Construction supervisors
• Full time Occupational Health and Safety Officer (OSHO)
• Industrial Hygienist
• Other key team members as determined by the Offeror with approval from the GSA CO
While page 12 of the SOW lists the minimum as:
● Corporate Construction Executive
● Project Manager
● Cost Estimator
● Construction Superintendent
● Project Engineer
● Safety Program Coordinator
Please confirm the minimum Key Team members that need to be included with our proposal and what roles can be shared.
The Key Team members shall be as follows:
1) Corporate Construction Executive
2) Project Manager
3) Cost Estimator
4) Construction Superintendent
5) Project Engineer
6) Safety Program (OSHA) Coordinator
11. Please confirm who is responsible for low voltage cabling ( AV, Tele/Data, security- card readers and cameras, etc...)
- Contractor is responsible for low voltage cabling for tele/data, and security systems. AV cabling will be by Owner along with the AV system itself except for the EEOC Conference Room 1894 and the DoED RTF 3822-3825 which shall be provided by the Contractor. Owner will provide network equipment, including wireless access points, and patch cables in the telecom room.
12. Are we providing plenum cable for this project - does this project follow National Electric Code or Chicago Code? National electric code allows plenum cable in plenum air spaces and City of Chicago code requires conduit in all plenum air spaces.
- This project follows GSA standards which do not comply with City of Chicago code.
National Electric Code allowances for plenum cabling can be used. All spaces except for EEOC space utilizes the existing underfloor raceway for routing of cabling for all floor-and wall- mounted outlets. EEOC space utilizes above ceiling cable pathways primarily, with limited use of the underfloor raceway.
14. Please confirm who is responsible for hiring the Commissioning Agent for LEED commissioning.
The commissioning agent is contracted by the GSA.
15. Does the GSA intend to publish the list of site visit attendees from the first and second walk-throughs?
Yes, the GSA will publish the list of site visit attendees from the first and second walk through.
16. Who is the fire alarm contractor for the building?
Response: System is Edwards ESP, we have used Convergent Technologies, however, any vendor certified on the system can perform work on the system.
17. Are the Payment and Performance bonds to cover both preconstruction and construction services?
The offeror is required to submit a bid bond with their proposal. A bid bond should cover the amount of the design phase services. A payment and performance bond will be due 10 days after award. The bond will be 100% of the amount of the award for design phase services. Once the GMP option is awarded the bond will have to be increased to cover 100% of the GMP.
18. Please verify that COBie deliverable requirements are only for maintainable and/or depreciable assets. Please provide a list of which assets are required to have completed COBie attributes.
COBie deliverable requirements are defined in the COBie specification 013600, the project BIM Execution Plan (BEP) (specifically section J), and the Region 5 BIM Standards.
Specific assets are that equipment to be integrated into the facility management software which are defined during the preconstruction BIM meeting. Previously it has included light fixtures, mechanical equipment, toilets, motorized shades, etc..
19. Please verify that construction model LOD 400 requirements pertain to only new work, not existing conditions.
Confirmed. The project BIM Execution Plan includes the Model Progression Matrix which lists the LOD requirements for all elements at each stage of design and construction.
GENERAL SHEET NOTES
C B A
4/5
3/4
PHONE
ROOM
PHONE
ROOM
PHONE
ROOM
CONFERENCE
ROOM
OPEN
OFFICE
RECEPTION
STORAGE
CORRIDOR
28' - 0" 28' - 0"
CORRIDOR
SHARED
CONFERENCE
SHARED
COPY/PRINT
A601
TYP.
TYP.
1' - 5"
1'
FURNITURE PLAN KEY NOTES
(KEYNOTES APPLY TO THIS SHEET ONLY)
1. FURNITURE WORKSTATIONS TO BE CONFIGURED BY REUSING TEKNION FURNITURE
COMPONENTS SUPPLIED BY THE GSA.
2. CMC TO CONTRACT WITH A CERTIFIED TEKNION INSTALLER TO PERFORM THIS WORK AS
IDENTIFIED ON THE FURNITURE PLAN.
* CONTACT FRED CRANDALL
* OFFICE DESIGN & FURNISHINGS, LLC
* 1-800-574-3159
3. THE FURNITURE INSTALLER IS RESPONSIBLE FOR DETERMINING THE REQUIRED NECESSARY
COMPONENTS, PARTS AND ACCESSORIES TO MAKE A COMPLETE INSTALLATION.
4. ALL PARTS AND MATERIALS TO BE SUPPLIED BY GSA FROM AVAILABLE INVENTORY ON SITE.
37TH FL AREA OF WORK
KEY PLAN
N.T.S.
0 4' 8'
1/4"=1'-0"
RE
VI
SI
ON
B
LO
CK
CO
NT
RA
CT
DE
SI
GN
ER
ID
EN
TIF
IC
AT
IO
N
ST
AM
P
OR
S
EA
L
OW
NE
R
ID
EN
TIF
IC
AT
IO
N
BU
ILD
IN
G
PR
OJ
EC
T
SH
EE
T
P R
O P
E R
T Y
O F
T H
E U
N
IT
E D
S T
A T
E S
G O
V E
R N
M E
N T
F
O R
O F
F
IC
IA
L U
S E
O N
L Y
D
O N
O T
R E
M O
V E
T H
IS
N
O T
IC
E
P
R O
P E
R L Y
D E
S T
R O
Y D
O C
U M
E N
T S
W H
E N
N O
L O
N G
E R
N E
E D
E D
General Services Administration Public Buildings
Service Great Lakes Region 5
Professional Services Division John C. Kluczynski Federal Building 230 South Dearborn Street Chicago, IL 60604
CONST. CONTRACT NO.
DELIVER ORDER NO.
A/E CONTRACT NO.
BUILDING NAME
ADDRESS
CITY, STATE, ZIP
BUILDING NO.
PROJECT TITLE
GSA PROJECT NO.
SUBMISSION STAGE
SUBMISSION DATE
DRAWN BY
CHECKED BY
FLOOR NO.
DISCIPLINE
PLAN TYPE
SHEET NUMBER
AND FILENAME
KE
Y
PL
AN
GR
AP
HI
C
SC
AL
E
/1
/2
:5 :1
P
M
A102
37TH
2010101
O. ORTEGA
J. STRYKER
230 S. DEARBORN ST.
ARCHITECTURE
FURNITURE PLAN
08/14/2017
GS-05P-15-FA-D-0003
CHICAGO, IL 60604
IL0236FC
JOHN C. KLUCZYNSKI FEDERAL BUILDING
1/4" = 1'-0"1
PARTIAL 37TH FLOOR FURNITURE PLAN
1 CONFERENCE TABLES, CHAIRS, AND FURNITURE PROVIDED BY GSA.
2 (18) - LOCKER / WARDROBES PROVIDED BY GSA.
3 (3) HIGH LATERAL FILES PROVIDED BY GSA.
4 RECONFIGURED BENCH WORKSTATION, FILE CABINETS, AND CHAIRS PROVIDED BY GSA.
5 MANUALLY OPERATED ADJUSTABLE HEIGHT DESK AND CHAIR PROVIDED BY GSA.
6 PHONE ROOM TABLES AND CHAIRS PROVIDED BY GSA.
7 WORKSTATIONS, FILE CABINETS AND CHAIRS PROVIDED BY GSA.
8 MAINTAIN A 1'-0" MIN. CLEARANCE BETWEEN THE EXISTING PERIMETER HVAC INDUCTION UNITS AND ANY FURNITURE
THAT RUNS PARALLEL TO THIS EQUIPMENT.
MARK DATE DESCRIPTION
2010101
08/14/2017
ADDENDUM 1
FLOOR GSA HR
RELOCATION
| Amendment to Solicitation 004 |
| SF30 |
| JCK CMc Preproposal Minutes |
| Pre-proposal attendee list |
| Second walk through |
| GSA-JCK-HR-Relocation-A102_Issued-for-Addendum-01_2017-08-14 |
| Sheets |
| A102 - PARTIAL 37TH FLOOR FURNITURE PLAN |
File details come from the government source that posted it. Updated .