About this file
This represents Amendment 0001 issued against the above referenced solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FBO Award Synopsis.pdf | ||
| 67 0449.pdf | ||
| Amendment 0005.pdf | ||
| 70 0164.pdf | ||
| 93 0262.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003 language.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002 language.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Charleston_Facilities_Engineering_-_Electronic_Offer_Sheet.xlsx | XLSX spreadsheet | |
| SOL__GS-03P-11-CD-D-0004.pdf | ||
| Bidders_Library.zip | ZIP file | |
| Pre-Proposal_Invite.pdf | ||
| Roanoke_Equipment_List.xlsx | XLSX spreadsheet | |
| Preproposal Meeting Information.pdf | ||
| Pre-Proposal Invite.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this amendment is to revise the minimum and maximum Order Limitations as prescribed in FAR Clause 52.216-19 in the above solicitation. The minimum and maximum limitations are hereby revised as stated in the below clause:
52.216-19 -- Order Limitations.
As prescribed in 16.506(b), insert a clause substantially the same as follows:
Order Limitations (Oct 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $250.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor --
(1) Any order for a single item in excess of $50,000,000.00;
(2) Any order for a combination of items in excess of $50,000,000.00; or
(3) A series of orders from the same ordering office within 10 days that together call for quantities exceeding the limitation in subparagraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216- 21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within five days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of Clause)
All other terms and conditions remain unchanged.