HIGH PERFORMANCE GREEN BUILDING MODERNIZATION FOLLOW‐ON PROJECT
FEDERICO DEGETAU FEDERAL OFFICE BUILDING
CONSTRUCTION DOCUMENTS OVERVIEW
PRE‐BID MEETING – JUNE 15TH, 2016
DEGETAU FEDERAL OFFICE BUILDING
BID DOCUMENTS BID FORM
BASE SCOPE BASE
BID ALTERNATE 1 OPTION N1
BID OPTION A1 OPTION N2a
BID OPTION A2 OPTION N2b
BID OPTION 1 OPTION N3a
BID OPTION 2a OPTION N4
BID OPTION 2b OPTION N5
BID OPTION 3 OPTION N6a
BID OPTION 4 OPTION N6b
BID OPTION 5 OPTION N6c
BID OPTION 6
BID OPTION 7
ALTERNTE MAGISTRATE
COURTS BID PACKAGE
CERTAIN PORTIONS
OF BID DOCUMENT
BASE SCOPE,
ALTERNATE 1 AND
BID OPTION 1 ARE
ALSO
INCORPORATED
INTO BID FORM
BASE SCOPE
PROJECT OVERVIEW
PROJECT SCOPE CONSISTS OF:
MAGISTRATES COURTS RENOVATION (4TH FL) BID PACKAGE
RE‐ROOFING OF FOB
BASE SCOPE
REPLACEMENT/REPAIR OF FOB LIGHTNING PROTECTION
SIGNAGE PACKAGE FOR USCH, LINK AND FOB FLOORS 4‐7
COMPLETION OF USCH AND LINK MODERNIZATION, AND
FOB SIGNAGE FLOORS B‐3 ARE A SEPARATE CONTRACT,
HOWEVER DUE TO SHARED CHILLER PLANT, ELECTRICAL
AND BUILDING ACCESS, SOME INTERFACE REQUIRED.
DEGETAU FEDERAL OFFICE BUILDING
OPTION N1
CONNECTION OF USDC THERMAFUSERS
OPTION N2a & N2b 2a – RAINHARVESTING CISTERN FOR CT MAKE‐UP 2b – COMPLETE SUPPLEMENTAL MAKE‐UP WELL
OPTION N3a
OPTION N4
COMPLETE GRID‐TIE SOLAR PV SYSTEM AT FOB ROOF
RENOVATION OF EAST RESTROOMS FLOORS 5‐7
OPTION N5
6a – INSTALL NEW 7TH FLOOR MECH. EQUIP. AND ASSOC. WORK
OPTIONS N6
6b – NEW AIR RISERS FLOORS 4‐7 6c – RENOVATION AND VAV CONVERSION OF 7TH FLOOR
4TH FLOORROOF1st FLOOR
USDC
7thFL MERs & cores SWING 2nd and 3rd
SWING 1st and 3rd
E. BASEMENT MER
4‐6th floor cores
PROJECT OVERVIEW ‐ BASE SCOPE
• RENOVATION OF 4 COURTROOMS
• RENOVATION OF 4 CHAMBER SUITES AND
ASSOCIATED SPACES
• RENOVATION OF JURY ROOMS
• RENOVATION OF PUBLIC CORE AND
CORRIDORS & SUPPORT SPACES
• RENOVATION OF 4TH FLOOR EAST RESTROOM
• NEW MER, MECHANICAL UPGRADES AT E.
BASEMENT, RISERS UPGRADES TO AC‐FOW‐B‐3
• RELOCATION OF FCC (MINIMAL SPACE RENOV.)
FLOORS B ‐3,
INCLUDING BASEMENT
MERs RENOVATED IN
PREVIOUS PROJECT –
COURTS TO SWITCH OVER FROM
OLD 7TH FLOOR CAV SYSTEMS TO
NEW BASEMENT VAV SYSTEM
REMOVE CEILINGS
INSTALL NEW HVAC, FP
AND INFRASTRUCTURE
INSTALL NEW CEILINGS
AND LIGHTING FIXTURES
OTHER INTERIOR
RENOVATIONS SUCH AS
DOORS, HARDWARE,
PAINT, RAILINGS AND
SOME FLOORING
COURTS RENOVATION SCOPE:
DEMOLITION/ABATEMENT
PHASED PROJECT & TURNOVER – REMAINDER OF BUILDING WILL REMAIN
CONTINOUSLY OCCUPIED AND IN USE THROUGHOUT CONSTRUCTION
HIGH PERFORMANCE GREEN BUILDING MODERNIZATION FOLLOW‐ON PROJECT
DEGETAU FEDERAL OFFICE BUILDING
• JUDGE’S CHAMBER SWING SPACE
• RE‐ROOF FOB
• REPLACE/REPAIR LIGHTNING PROTECTION
PROJECT OVERVIEW ‐ PHASING
PHASED PROJECT SUGGESTED WORK SEQUENCE:
INSTALL TEMPORARY HVAC AT 4TH FLOOR RESTROOM
PHASE 1 (Completion Milestone 210 days from NTP):
RENOVATE 1ST FLOOR OFFICES AND RELOCATE FCC (NOT SHOWN HERE)
TENANT MOVES – JUDGE TO SWING CHAMBER, SHUTDOWN
COURTROOM
RETURN JUDGE TO RENOVATED SPACE, REOPEN COURTROOM
CONSTRUCT MAGISTRATE SWING SPACE AT 3RD FLOOR
DEGETAU FEDERAL OFFICE BUILDING
PHASES 3A–3D (Comp. Milestone 730 days from NTP):
RENOVATE CHAMBER SUITE, COURTROOM, JURY ROOM (AS
APPLICABLE) & ASSOCIATED MER UPGRADES AT PHASE 3A
RENOVATE CORE & RESTROOM AND COMPLETE RISER
SWITCHOVER AT LAST SUBPHASE 3D, REMOVE TEMPORARY HVAC
REPEAT (3) TIMES FOR EACH CHAMBER/CR PAIR
PHASE 2 ‐ SKIPPED
REROOF AND REPLACE LIGHTNING PROTECTION AT
ANY POINT (CONCURRENTLY, NOT SHOWN HERE)
DEFINED IN BID DOCUMENTS “ALTERNATE
MAGISTRATE COURTS BID PACKAGE”
ROOF: “BID OPTION 6”
LIGHTNING PROTECTION: “BID OPTION 7”
PROJECT OVERVIEW ‐ OPTION N1
DEGETAU FEDERAL OFFICE BUILDING
SCOPE: CONNECT APPROXIMATELY 110
VAV DIFFUSERS INSTALLED IN PREVIOUS
PROJECT TO EXISTING BUILDING DDC BAS
LOCATED IN 1ST FLOOR USDC SPACE – WILL BE
OCCUPIED SO ALL WORK AT NIGHT AND CLEANED
EACH DAY.
INSTALL HEATERS, CONTROLLERS @ DIFFUSERS,
CONTROL WIRING, ADDITIONAL BAS
CARDS/PANELS AND (2) POINTS PER DIFFUSER.
PROGRAM INTO EXISTING BAS – SEE DIV. 23 BAS
SPEC FOR MORE INFORMATIONDEFINED IN BID DOCUMENTS AS “BID OPTION 5”
PROJECT OVERVIEW ‐ OPTION N2a & N2b
DEGETAU FEDERAL OFFICE BUILDING
OPTION N2a: CONSTRUCT A CONCRETE
RAINWATER HARVESTING CISTERN NEAR
SOUTHEAST ENTRANCE (SITE/LAWN AREA)
SITE WORK – AREA PROTECTION, CLEARING AND
GRADING, EXCAVATION, SHORING/SHEET PILING.
CONCRETE CAST‐IN PLACE CISTERN APPROX. 30’ X
20’ – TWO COMPARTMENTS (ONE WET ONE DRY)
INSTALL PLUMBING BOOSTER PUMP, FILTRATION
SYSTEM, AND COMPLETE INTERIOR NPW PIPING –
TIE‐IN TO COOLING TOWER MAKE‐UP SYSTEM –
REQUIRES OPENING OF SHAFT FROM 4‐7 FL.
STORES RAINWATER FROM ROOF STORMWATER
SYSTEM FOR RE‐USE IN COOLING TOWER MAKE‐UP
COMPLETE TEST‐WELL (SCREEN CASING AND CAP)
TO PROVIDE FUNCTIONING WELL TO PROVIDE
SUPPLEMENTAL MAKE‐UP WATER TO CISTERN
SUBMERSIBLE PUMP, METER VAULT, PIPING, CONTROL
PANEL, ADJUSTMENT OF TOWER TREATMENT
OPTION N2b: IN ADDITION TO OPTION N2a (CISTERN) COMPLETE
A MAKE‐UP WATER WELL
DEFINED IN BID DOCUMENTS AS
“BID OPTION 2a AND 2b”
PROJECT OVERVIEW ‐ OPTION N3a
DEGETAU FEDERAL OFFICE BUILDING
COMPLETE SOLAR PHOTOVOLTAIC SYSTEM
ARRAY TO BE MOUNTED ON EXISTING STEEL
SUPPORT STRUCTURE.
BASIS OF DESIGN SYSTEM PROVIDED –
CONTRACTOR TO HIRE A SOLAR INTEGRATOR TO
COMPLETE INSTALLATION ACCORDING TO
PERFORMANCE SPECIFICATION
PROVIDE ARRAY, WIRING, INVERTERS – GRID TIE
TO EXISTING SUBSTATIONS VIA BUS DUCTS
GRID‐TIE 105 kW SOLAR PV SYSTEM
INCLUDE PERMITTING AND INTERCONNECTION
COORDINATION WITH PREPA
STRING SIZING AND ANY STRUCTURAL
CONNECTION OF ARRAY TO SUPERSTRUCTUREDEFINED IN BID DOCUMENTS AS “BID OPTION 3”
PROJECT OVERVIEW ‐ OPTION N4
DEGETAU FEDERAL OFFICE BUILDING
BUILDING SIGNAGE ON FOB FLOORS 4 ‐ 7
NOTE: SIGNAGE WORK ON FLOORS B‐3 ARE PART OF THE ONGOING WORK FOR THE NAZARIO
CONSTRUCTION CONTRACT. THE WORK OF THIS OPTION SHALL BE COORDINATED WITH THE B‐3 SIGNAGE.
PROVIDE WAY‐FINDING AND BUILDING LOBBY SIGNAGE IN PUBLIC CORES AND CORRIDORS ON FOB FLOORS 4 ‐ 7
PROJECT OVERVIEW ‐ OPTION N5
DEGETAU FEDERAL OFFICE BUILDING
RENOVATION OF THE EAST RESTROOMS ON FLOORS 5, 6 AND 7
DEMOLISH CEILINGS FOR 5TH 6TH AND 7TH FLOOR RESTROOMS AND REPLACE WITH
NEW CEILINGS AND LIGHTING. THIS WORK IS DEFINED UNDER “BID ALTERNATE 1”
FOR THE 5TH AND 6TH FLOORS AND “BASE SCOPE” FOR THE 7TH FLOOR IN THE BID
DOCUMENTS.
DEMOLISH AND REPLACE PLUMBING FIXTURES, TOILET PARTITIONS, TILING AND
FINISHES AT THE 5TH, 6TH AND 7TH FLOOR EAST RESTROOMS. PLUMBING FIXTURE
AND FINISH WORK IS DEFINED UNDER “BID OPTION 1” IN THE BID DOCUMENTS.
A DUCTWORK ALLOWANCE IS PROVIDED UNDER SECTION “UNIT PRICES” TO
ACCOMMODATE ADAPTING EXISTING EXHAUST DUCTWORK TO THE NEW CEILING
LAYOUT.
NOTE: RENOVATIONS FOR THE 4TH FLOOR EAST RESTROOM IS NOT
PART OF OPTION N5 (TO BE DONE WITH MAGISTRATE COURTS, SEE
BASE SCOPE ABOVE. RENOVATIONS FOR THE 7TH FLOOR WEST
RESTROOM IS NOT PART OF OPTION N5 (OPTION N6a BELOW).
PROJECT OVERVIEW ‐ OPTIONS N6a,b,c
DEGETAU FEDERAL OFFICE BUILDING
OPTION N6a: INSTALL OF NEW 7TH FL MECH. EQUIP. AND ASSOC.WORK
DUCTWORK MODIFICATIONS IN 7TH FLOOR TENANT AREAS TO ADAPT CAV
DISTRIBUTION TO NEW HVAC EQUIPMENT. NEW CHW PIPING.
REQUIRES TEMP UNITS FOR AREAS TO REMAIN OCCUPIED ON 5TH AND 6TH FLOORS
RENOVATION OF 7TH FLOOR PUBLIC CORES AND CORRIDOR
CONSTRUCTION OF 8,000 SF OF SWING SPACE ON THE 2ND AND 3RD FLOORS –
RECONFIGURE PARTITION LAYOUT (RENVOATED IN BDB)
CONSTRUCTION OF 1,200 SF SWING SPACE AT 6TH FLOOR
RELOCATION OF SWING TENANTS
DEMOLITION OF EXISTING, INSTALLATION OF NEW HVAC EQUIPMENT AT 7TH
FLOOR MERS AND ROOF. INCLUDES AHUS, HRUS, RTU, PENTHOUSE A/C.
RENOVATION OF 7TH FLOOR WEST PUBLIC RESTROOM
INSTALLATION OF REHEAT COILS AND DUCT MODS AT 4TH, 5TH AND 6TH FLOOR
LOCATIONS TO ADAPT NEW EQUIPMENT TO EXISTING DISTRIBUTION
MISC. WORK INCLUDING REPLACEMENT OF FIRE PUMP AND CONTROLLER,
ELECTRICAL DISTRIBUTION AND TRANS. REPLACE, COMPLETE BAS
OPTION N6b: NEW AIR RISERS 4‐7 FLOORS
IN ADDITION TO ABOVE, INSTALL NEW RISERS AND COMPLETE 4W, 5 & 6 CORES
COMPLETE SCDW SYS., VENTILATION TIE‐IN AT BASEMENT MERS, SOLAR HW SYS.
HVAC SYSTEM WILL BE RUN AS CAV
SYSTEM AT UPPER HOUSE
OPTION N6c: COMPLETE 7TH FLOOR VAV
CONVERSION AND RENOVATION
HVAC SYSTEM WILL BE RUN AS VAV
SYSTEM AT 7TH FLOOR, CAV FOR
REST OF UPPER HOUSE –INSTALL
CAV BOXES
PROJECT OVERVIEW ‐ PHASING ‐ OPTIONS N6a,b,c
DEGETAU FEDERAL OFFICE BUILDING
PHASE 1 (210 DAYS FROM NTP)
“HEAD START” CONSTRUCTION IN CENTER AREA OF 7TH FLOOR – N6a & N6b MISC.
DUCTWORK MODIFICATIONS FOR NEW HVAC, CHW PIPING, N6c INSTALL VAVs AND
RENOVATE TENANT SPACES, 7TH AND 6TH FLOORS (525 DAYS FROM NTP)
CLOSE EAST RESTROOMS, CONSTRUCT TEMP MERS AND INSTALL ADDITIONAL TEMP
UNITS ON 5TH AND 6TH FLOORS – TOP OF HOUSE ON TEMP UNITS
RENOVATION OF 7TH FLOOR PUBLIC CORES AND CORRIDOR, 7TH FL RISERS (OPT. N6b).
COMPLETE 7TH FLOOR TENANT AREA RENOVATIONS (OPTION N6c)
CONSTRUCT SWING SPACE ON THE 2ND AND 3RD FLOORS
CONSTRUCT 6TH FLOOR SWING SPACE (FBI)
RELOCATION OF SWING TENANTS, CLOSE CAFETERIA (180 – 210 DAYS FROM NTP)
RENOVATION OF 7TH FLOOR WEST PUBLIC RESTROOM
INSTALL NEW RISERS ATH 5TH AND 6TH FLOORS, AND COMPLETE 5TH & 6TH FL CORES (OPT. N6b) COMPLETE SCDW SYS., VENTILATION TIE‐IN AT BASEMENT MERS, SOLAR HW SYS. (N6b) MISC. HVAC WORK AT BASEMENT (ALL OPTs.)
HVAC SYSTEM WILL BE RUN AS VAV
SYSTEM AT UPPER HOUSE
PHASE 2
MOVE TENANT AND COMPLETE 6TH FL WEST TEMP MER (285 DAYS FROM NTP)
PHASE 3 (495 (N6a) OR 525 (N6b/c) DAYS FROM NTP)
DEMOLITION OF EXISTING, INSTALLATION OF NEW HVAC EQUIPMENT AT 7TH FLOOR MERS
AND ROOF. INCLUDES AHUS, HRUS, RTU, PENTHOUSE A/C.
4TH FLOOR WEST MISC. HVAC MODIFICATIONS, RISERS (OPT. N6b)
PHASE 4 (570 (N6a) OR 715 (N6b/c DAYS FROM NTP)
RETURN TENANTS TO 7TH FLOOR, REOPEN
RETURN TEMP MER TENANTS FROM SWING SAPCE
LEED PROJECT REQUIREMENTS – GOAL OF LEED SILVER
SELECT PROJECT SYSTEMS (HVAC, CONTROLS, LIGHTING, ELECTRICAL) WILL BE
COMMISSIONED UNDER 3RD PARTY COMMISSIONING AGENT (CONTRACTED BY
GOVERNMENT). COMMISSIONING AGENT WILL WITNESS FUNCTIONAL TESTING
PERFORMED BY CONTRACTOR. SUCCESSFUL COMMISSIONING IS A CONDITION OF
ACCEPTANCE OF THE WORK. REFERENCE DIVISION 1, AND TECHNICAL COMMISSIONING
SPECIFICATION SECTIONS FOR SPECIFIC REQUIREMENTS.
HIGH PERFORMANCE GREEN BUILDING MODERNIZATION FOLLOW‐ON PROJECT
DEGETAU FEDERAL OFFICE BUILDING
FINAL PROJECT CLOSEOUT BY:
IF OPTIONS n6a,b,c ARE EXERCISED: 865 DAYS FROM NTP, OTHERWISE: 820 DAYS FROM NTP
SUBMITTALS FOR EQUIPMENT AND OTHER ITEMS NOT DEPENDENT ON TURN OVER OF A SPACE
ARE TO BE SUBMITTED AT THE START OF THE PROJECT – NO LATER THAN 120 DAYS FROM NTP
READ THE DIVISION 1!!
PROJECT AND EXISTING CONDITIONS REQUIRE SOME SPECIFIC GENERAL REQUIREMENTS AND
COORDINATION.
THESE ARE SUMMARIZED IN THE DIVISION 1 “SUMMARY” SECTION.
DETAILED ELSEWHERE IN THE DIVISION 1 AND TECHNICAL SPECIFICATION SECTIONS
SPECIAL REQUIREMENTS ARE HERE FOR A SUCCESSFUL PROJECT BASED ON LESSONS LEARNED.
THE DOCUMENTATION AND SUBMISSION PROCESS IS A CRITICAL PART OF THE EXECUTION PLAN.
GENERAL REQUIREMENTS
RELOCATION OF TENANTS AND MOVING OF FURNITURE:
• CONTRACTOR IS RESPONSIBLE TO HIRE A QUALIFIED MOVER. SPECIFIC MOVING REQUIREMENTS
ARE OUTLINED IN SECTION “SUMMARY”
• SELECTED FURNITURE TO BE RELOCATED TO TENANT SWING SPACES.
• REMAINING FURNITURE, INCLUDING ALL COURTROOM FURNITURE, TO BE TAKEN TO SECURED
OFF‐SITE CLIMATE CONTROLLED STORAGE. MUST SUBMIT FOR GOVERNMENT APPROVAL, AND
GOVERNMENT SHALL INSPECT.
• PHOTODOCUMENT ALL EXISTING CONDITIONS (FURNITURE, SPACES, ETC.)
WORK BY OTHERS/COORDINATION WITH OTHER PROJECTS AT THE SITE:
WORK OF THIS PROJECT MUST BE COORDINATED WITH OTHER IN PROCESS AND PLANNED WORK:
• PROBATION/PRE‐TRIAL CONSOLIDATION AT FOB 2ND FLOOR.
• EXPANSION OF US MARSHALS SPACE AT FOB 2ND FLOOR WEST.
• MAGISTRATE COURTS WAITING ROOM RENOVATION.
• CONNECTION OF FBI CHILLED WATER SYSTEM TO MAIN BUILDING CHILLED WATER SYSTEM.
• FOLLOW‐ON RENOVATIONS AT THE USCH AND LINK.
• OTHER PROJECTS – GSA TO ADVISE AND COORDINATE.
• REFERENCE DIVISION 1 SPECIFICATIONS FOR ADDITIONAL DETAILS
EQUIPMENT REUSE – GOVERNMENT FURNISHED PROPERTY:
• THIS PROJECT CONTINUES THE WORK OF AN EXISTING PROJECT. EQUIPMENT PURCHASED BY
THE GOVERNMENT FROM THIS PROJECT IS AVAILABLE AS GOVERNMENT FURNISHED PROPERTY.
• (2) SCHEDULES:
• SCHEDULE A – GOVERNMENT FURNISHED PROPERTY THAT MUST BE REUSED. INCLUDES
DOOR HARDWARE, VAV BOXES, LIGHTING CONTROL AND ELECTRICAL COMPONENTS.
• SCHEDULE B – GOVERNMENT FURNISED PROPERTY THAT MAY BE REUSED AT THE
GOVERNMENT’S OPTION. INCLUDES AIR‐HANDLING UNITS, VFDs AND OTHER ITEMS. THE
CONTRACTOR SHALL PROVIDE A DEDUCT ALTERNATE PRICE FOR INSTALLATION AND
WARRANTY OF THESE GOVERNMENT PROVIDED ITEMS REVIEW. REFERENCE SECTION
“ALTERNATES” AND “SUMMARY” FOR SPECIFIC REQUIREMENTS AND INVENTORY.
EXISTING PROJECT CONDITIONS:
• CONTINUATION OF PREVIOUS PROJECT TO COMPLETE THE ORIGINAL BRIGING INTENT
• WORK OF THIS PROJECT INTERFACES WITH THAT OF PREVIOUS, ESPECIALLY:
• HVAC SYSTEMS – DOAS/HRUS FEEDING AHUS – (2) PARTIALLY COMPLETE SYSTEMS, EAST AND WEST BASEMENT, IN PLACE ARE RUNNING INTERIM, USING EXISTING BUILDING EXHAUST. DEPENDING ON OPTIONS/ALTERNATES SELECTED, VARIOUS
MODIFICATIONS AND CONNECTION TO NEW EQUIPMENT WILL BE NEEDED.
• NEW CENTRAL CHILLER PLANT HAS BEEN INSTALLED – CERTAIN PORTIONS OF THIS SYSTEM, SUCH AS SECONDARY CONDENSER
WATER SYSTEM, WILL NEED TO BE COMPLETED AND COMMISSIONED.
• CONTROLS SYSTEM – PARTIALLY INSTALLED – FINAL PROGRAMMING OF COMPLETE BUILDING SYSTEM NEEDED
• LIGHTING AND LIGHTING CONTROL SYSTEM – SOME LIGHTING CONTROL HUBS IN PLACE – NEW LIGHTING TO BE ADDED
• ELECTRICAL DISTRIBUTION AND METERING
• BAS BACKBONE
• FINAL HVAC BALANCING
• SOLAR PHOTOVOLTAIC SYSTEM – SUPERSTRUCTURE INSTALLED – MODULES AND BALANCE OF SYSTEM TO BE COMPLETED
• SOLAR HOT WATER SYSTEM AND CISTERN PIPING
• CONTRACTOR WILL BE RESPONSIBLE TO PROVIDE A COMPLETE OPERATIONAL USCH AND LINK BUILDING AT THE CONCLUSION OF THE
PROJECT
EXISTING CONDITIONS – UNIT PRICES AND RELOCATIONS:
• EXISTING BUILDING WITH EXTENSIVE EXISTING ABOVE CEILING INFRASTRUCTURE
• SELECTED RELOCATIONS CALLED OUT ON DRAWINGS TO ALLOW NEW DUCTWORK TO BE
INSTALLED
• ADDITIONAL ALLOCATION FOR CONCEALED, OR UNFORESEEN UTILITY RELOCATIONS TO BE
ACCOUNTED IN BASE BID IN FORM OF UNIT PRICE WITH SPECIFIC QUANTITY. SEE SECTION “UNIT PRICES”. THESE ARE NON‐SPECIFIC IN LOCATION, FOR USE AS ABOVE CEILING CONFLICTS ARE
ENCOUNTERED. INCLUDES ELECTRICAL, FIRE PROTECTION AND PLUMBING.
EXISTING CONDITIONS – PROJECT COORDINATION:
• ABOVE CEILING COORDINATION IS CRITICAL.
• DETAILED MEASUREMENT AND SURVEY TO COORDINATE DESIGN WITH FIELD CONDITIONS.
• COORDINATION DRAWINGS SHALL REFLECT FIELD CONDITIONS AND PROPOSE
RESOLUTION/ALTERNATE ROUTING WHERE REQUIRED. COSTS SHALL BE INCLUDED IN BID.
• CONTRACTOR SHALL PROVIDE ADEQUATE RESOURCES AND ALLOWANCE IN SCHEDULE TO
PERFORM THIS COORDINATION
• RETAIN PROFESSIONAL STAFF TO PERFORM COORDINATION
EXISTING CONDITIONS – CEILINGS AND NOISE:
• U.O.N. CEILINGS TO BE INSTALLED AT SAME HEIGHT AS EXISTING. SOFFITS OR LOWERING NOT
PERMITTED.
• AMBIENT NOISE LEVEL BASELINE TESTING SHALL BE PERFORMED IN COURTROOMS. AMBIENT
NOISE LEVEL SHALL NOT BE INCREASED IN ANY COURTROOM.
DELEGATED DESIGN – COORDINATION AND SHOP DRAWING REQUIREMENTS
• COORDINATION DRAWINGS MUST BE DONE USING BUILDING INFORMATION MODELING (BIM)
3D SOFTWARE. INTERDISCIPLINARY COORDINATION DRAWINGS TO BE PREPARED UNDER THE
SUPERVISION OF A LICENSED PROFESSIONAL ENGINEER. DETAILED INTERDISCPLINARY
COORDINATION DRAWINGS GENERATED FROM BIM COORDINATION MODEL.
• SEE DIVISION 1 SECTIONS “SUMMARY” AND “PROJECT MANAGEMENT AND COORDINATION”
• HVAC SHOP DRAWINGS SHALL BE PERFORMED UNDER THE SUPERVISION OF A LICENSED PE.
THE SAME PE SHALL VERIFY THE INSTALLATION CONFORMS TO THE SHOP DRAWINGS.
DELEGATED DESIGN – COORDINATION AND SHOP DRAWING REQUIREMENTS
• CONTRACTOR SHALL PERFORM LASER SCANNING OF SPACES ONCE CEILINGS ARE REMOVED TO DOCUMENT EXISTING CONDITIONS. THE LASER SCANNING POINT CLOUD SHALL BE USED FOR ABOVE CEILING COORDINATION.
DELEGATED DESIGN – CONTROLS SYSTEM DESIGN
• PROFESSIONAL ENGINEER WITH MINIMUM OF (5) YEARS OF EXPERIENCE DESIGNING CONTROLS
SYSTEMS.
• PREPARE COMPLETE CONTROLS SUBMITTAL PACKAGE.
• DETAILED POINTS, SEQUENCES, WIRING DIAGRAMS, PROCESS AND INSTRUMENTATION
DIAGRAMS.
• COMPLETE OPERATIONS DDC SYSTEM FOR WHOLE BUILDING – MUST INTERFACE WITH SYSTEM
INSTALLED IN PREVIOUS PROJECT.
WORK RESTRICTIONS – WORKING HOURS
• GENERAL WORKING HOURS ARE DURING UNOCCUPIED HOURS – 6 PM TO 7 AM
• SELECTED NON‐DISRUPTIVE WORK MAY BE PERFORMED DURING OCCUPIED HOURS WITH
GOVERNMENT APPROVAL.
• SEE SECTION “WORK RESTRICTIONS” FOR ADDITIONAL REQUIREMENTS.
SPECIAL INSPECTIONS & TESTING REQUIREMENTS
• CONTRACTOR SHALL HIRE SPECIAL INSPECTORS FOR INSPECTIONS AS REQUIRED BY IBC
• QUALITY ASSURANCE REQUIREMENTS OF DIVISION 1
• ADDITIONAL INSPECTION REQUIREMENTS, SUCH AS INSPECTION OF COMPLETED DUCTWORK,
ARE PART OF TECHNICAL SPECIFICATIONS.
TEMPORARY FACILITIES AND CONDITIONING REQUIREMENTS
• TEMPORARY SPACE CONDITIONING TO BE PROVIDED BY CONTRACTOR DURING CONSTRUCTION
• PROTECTION OF MILLWORK
• TEMPERATURE AND HUMIDITY CONTROL
• SIGNIFIFICANT PORTIONS OF THE PROJECT AS WELL AS BUILDING AREAS OUTSIDE THE PROJECT
UNDER CERTAIN OPTIONS WILL REQUIRE TEMPORARY AIR‐CONDITIONING SO THAT THEY MAY
REMAIN ACTIVE DURING THE CONSTUCTION WHEN HVAC SYSTEMS SERVING THESE SPACES ARE
DEMOLISHED
STAFFING REQUIREMENTS
• DELEGATED DESIGN – PROFESSIONAL SUPPORT
• BIM SUPPORT AND LASER SCANNING
• FULL‐TIME PROJECT COORDINATOR
• FULL‐TIME MEP COORDINATOR
• FULL‐TIME QAQC MANAGER
• COMMISSIONING COORDINATOR
• ADDITIONAL REQUIREMENTS FOR STAFF AND KEY PERSONNEL OUTLINED IN DIVISION 1
SPECIFICATIONS