U.S. General Services Administration
The Specifications
SOLICITATION NO: GS-01P-15-BZ-C-0004
PROJECT: Houlton Sector Border Patrol HQ, Renovate IFR to Training and Fitness
Room, Hodgdon, Maine
BID DUE:
DATE: March 31, 2015 TIME: 2:00 PM (1400 hrs)
LOCATION: GENERAL SERVICES ADMINISTRATION
ACQUISITION BRANCH, 1PSA
10 CAUSEWAY STREET, ROOM 1100
BOSTON, MA 02222-1077
ATTENTION: Bid Custodian
REFERENCE: GS-01P-15-BZ-C-0004
Volume III of III This procurement is 100% set-aside for Small Businesses
PROPERTY OF THE UNITED STATES GOVERNMENT
COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE
DRAWINGS,PLANS,
OR SPECIFICATIONS TO UNAUTHORIZED USERS IS
PROHIBITED
Do not remove this notice
Properly destroy documents when no longer needed THE INFORMATION COLLECTION REQUIREMENTS CONTAINED IN THIS SOLICITATION/ CONTRACT THAT ARE
NOT REQUIRED BY REGULATION HAVE BEEN APPROVED BY THE OFFICE OF MANAGEMENT AND BUDGET
PURSUANT TO THE PAPERWORK REDUCTION ACT AND ASSIGNED OMB CONTROL NO. 3990-0163
GSA Public Buildings Service U.S. General Services Administration
10 Causeway Street New England Region
Boston, MA 02222 North Service Center www.gsa.gov
47A York Street Portland, ME 04101
(207) 553-7753
Houlton Sector Border Patrol HQ
Renovate IFR to Training and Fitness
Hodgdon, Maine
U.S. General Services Administration
New England Region (Region 1)
North Service Center (1PSK)
AE Contract No. GS-P-01-14-BW-5173
Specifications – Bid Set Submission February 16, 2015
Prepared for:
General Services Administration
New England Region
10 Causeway Street
Boston, MA 02222
PROPERTY OF THE UNITED STATES GOVERNMENT.
COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE
DRAWINGS AND/OR DOCUMENTS WITHOUT THE EXPLICIT
PERMISSION OF THE U.S. GENERAL SERVICES ADMINISTRATION IS
PROHIBITED. DISTRIBUTION TO THOSE WITH OTHER THAN A
NEED TO KNOW IS STRICTLY FORBIDDEN.
HOULTON SECTOR BORDER PATROL HQ RENOVATE IFR FEBRUARY 16, 2015
TO TRAINING AND FITNESS, HODGDON, MAINE
BID SET SUBMISSION
PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
010100 SUMMARY OF THE WORK
010350 OPTIONS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
015050 CONSTRUCTION WASTE MANAGEMENT
015150 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT
015930 SECURITY PROCEDURES
015950 SAFETY AND HEALTH
016000 PRODUCT REQUIREMENTS
016320 PRODUCTS
016350 REQUESTS FOR INFORMATION
017000 EXECUTION REQUIREMENTS
017310 CUTTING AND PATCHING
017320 SELECTIVE DEMOLITION
017350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK
017419 CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017810 PROJECT RECORD DOCUMENTS
017822 OPERATION AND MAINTENANCE DOCUMENTATION
018200 DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
020800 ASBESTOS ABATEMENT
020820 MISCELLANEOUS HAZARDOUS MATERIALS REMOVAL
020900 LEAD REMOVAL
024100 ROOF REMOVAL AND SUBSTRATE PREPARATION
024119 SELECTIVE STRUCTURE DEMOLITION
DIVISION 04 – MASONRY
042000 UNIT MASONRY
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
070150.19 PREPARATION FOR REROOFING
072100 THERMAL INSULATION
075423 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
076200 SHEET METAL FLASHING AND TRIM
079200 JOINT SEALANTS
DIVISION 08 – OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES
085113 ALUMINUM WINDOWS
087111 DOOR HARDWARE (SCHEDULED BY DESCRIBING PRODUCTS)
088000 GLAZING
088300 MIRRORS
DIVISION 09 – FINISHES
092216 NON-STRUCTURAL METAL FRAMING
092900 GYPSUM BOARD
095123 ACOUSTICAL TILE CEILINGS
096519 RESILIENT TILE FLOORING
096813 TILE CARPETING
099123 INTERIOR PAINTING
DIVISION 10 - SPECIALTIES
104416 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
122113 LOUVER BLINDS
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
230500 COMMON WORK RESULTS FOR HVAC
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230523 GENERAL-DUTY VALVES FOR HVAC PIPING
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC
230700 HVAC INSULATION
230800 COMMISSIONING OF HVAC
230900 INSTRUMENTATION AND CONTROL FOR HVAC
232113 HYDRONIC PIPING
232116 HYDRONIC PIPING SPECIALTIES
233113 METAL DUCTS
233300 AIR DUCT ACCESSORIES
237200 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT
238126 SPLIT-SYSTEM AIR-CONDITIONERS
DIVISION 26 - ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262416 PANELBOARDS
262726 WIRING DEVICES
265100 LIGHTING
DIVISION 27 - COMMUNICATIONS
271500 COMMUNICATIONS HORIZONTAL CABLING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
283111 FIRE ALARM SYSTEM
END OF TABLE OF CONTENTS
SUMMARY OF THE WORK 010100 - 1
SECTION 010100 - SUMMARY OF THE WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and conditions of the construction contract, including but not limited to Contract Clauses, and the Special Conditions listed below, apply to work of this section.
1. List of Specifications:
010100 SUMMARY OF THE WORK
010350 OPTIONS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
015050 CONSTRUCTION WASTE MANAGEMENT
015150 CONSTRUCTION INDOOR AIR QUALITY (IAQ)
MANAGEMENT
015930 SECURITY PROCEDURES
015950 SAFETY AND HEALTH
016000 PRODUCT REQUIREMENTS
016320 PRODUCTS
016350 REQUESTS FOR INFORMATION
017000 EXECUTION REQUIREMENTS
017310 CUTTING AND PATCHING
017320 SELECTIVE DEMOLITION
017350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK
017419 CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT
AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017810 PROJECT RECORD DOCUMENTS
017822 OPERATION AND MAINTENANCE DOCUMENTATION
018200 DEMONSTRATION AND TRAINING
020800 ASBESTOS ABATEMENT
020820 MISCELLANEOUS HAZARDOUS MATERIALS REMOVAL
020900 LEAD REMOVAL
024100 ROOF REMOVAL AND SUBSTRATE PREPARATION
024119 SELECTIVE STRUCTURE DEMOLITION
042000 UNIT MASONRY
061000 ROUGH CARPENTRY
070150.19 PREPARATION FOR REROOFING
072100 THERMAL INSULATION
SUMMARY OF THE WORK 010100 - 2
075423 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
076200 SHEET METAL FLASHING AND TRIM
079200 JOINT SEALANTS
081113 HOLLOW METAL DOORS AND FRAMES
085113 ALUMINUM WINDOWS
087111 DOOR HARDWARE
088000 GLAZING
088300 MIRRORS
092216 NON-STRUCTURAL METAL FRAMING
092900 GYPSUM BOARD
095123 ACOUSTICAL TILE CEILINGS
096519 RESILIENT TILE FLOORING
096813 TILE CARPETING
099123 INTERIOR PAINTING
104416 FIRE EXTINGUISHERS
122113 LOUVER BLINDS
230500 COMMON WORK RESULTS FOR HVAC
230513 COMMON MOTOR REQUIREMENTS FOR HVAC
EQUIPMENT
230523 GENERAL-DUTY VALVES FOR HVAC PIPING
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC
230700 HVAC INSULATION
230800 COMMISSIONING OF HVAC
230900 INSTRUMENTATION AND CONTROL FOR HVAC
232113 HYDRONIC PIPING
232116 HYDRONIC PIPING SPECIALTIES
233113 METAL DUCTS
233300 AIR DUCT ACCESSORIES
237200 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT
238126 SPLIT-SYSTEM AIR-CONDITIONERS
260500 COMMON WORK RESULTS FOR ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262416 PANELBOARDS
262726 WIRING DEVICES
265100 LIGHTING
271500 COMMUNICATIONS HORIZONTAL CABLING
283111 FIRE ALARM SYSTEM
SUMMARY OF THE WORK 010100 - 3
2. List of Drawings:
G001 Title Sheet LS101 Life Safety Plan AD101 First Floor Architectural Demolition Plan A101 First Floor Architectural Plan A102 Reflected Ceiling Plan A103 Roof Plan - Base Bid A103A Roof Plan - Option 01 & Option 02 A201 Interior Elevations A501
Architectural Details A502 Roof Details – Option 01 A503 Roof Details – Option 02 A601 Door Details and Schedule A602 Window Details and Schedule M001 Mechanical General Notes and Legend MD101 First Floor Mechanical Demolition Plan M101 First Floor Mechanical Plan - Ductwork M102 First Floor Mechanical Plan - Piping M103 Roof Mechanical Plan M501 Mechanical Details M502 Mechanical Sequences of Operations M601 Mechanical Schedules E001 Electrical General Notes and Legend ED101 First Floor Electrical Demolition Plans EP101 First Floor Power and Systems Plan EL101 First Floor Lighting Plan E601 Electrical Schedules and Details
1.2 PROJECT/WORK IDENTIFICATION
A. Project Name and Location:
Renovate Indoor Firing Range to Training and Fitness Rooms Border Patrol Sector Headquarters 96 Calais Road Hodgdon, Maine 04730
SUMMARY OF THE WORK 010100 - 4
B. Architect: The term "Architect" refers to the professional services contractor listed below. The Architect's status relative to this construction will be fully delineated in writing by the Contracting Officer prior to the pre-award or during the pre-construction conference. The Architect may furnish personnel for site supervision if required by his contract.
Colby Company Engineering 47A York Street Portland, Maine 04101
(207) 553-7753
C. Contracting Officer for this Project is:
Donna Maffeo (CO)
Property Development Division 1PC, Room 1100 Thomas P. O’Neill, Jr. Federal Building 10 Causeway Street Boston, MA 02222-1077
(617) 565-6012 donna.maffeo@gsa.gov
D. Contracting Specialist for this Project is:
Joe Moonan (CS)
Property Development Division 1PC, Room 915 Thomas P. O’Neill, Jr. Federal Building 10 Causeway Street Boston, MA 02222-1077
(617) 565-5027 joseph.moonan@gsa.gov
E. Contract documents indicate the work of contract, and related requirements and conditions that have an impact on the project. Related requirements and conditions that are indicated on the contract documents include, but are not necessarily limited to, the following:
1. Existing site conditions and restrictions.
2. Other work prior to work of contract.
3. Alterations and coordination with existing work.
4. Other work to be performed concurrently by Government.
5. Other work to be performed concurrently by separate contractors.
6. Other work subsequent to work of Contract.
F. Summary by References: Work of Contract can be summarized by reference to the conditions of the contract, Federal Acquisition Regulation clauses, specification sections as listed in the "Index of Specification Sections" bound herewith, drawings as listed in "Schedule of Drawings" bound herewith, addenda and modifications to the contract documents issued subsequent to the initial printing of this project manual, and including but not necessarily limited to printed matter mailto:donna.maffeo@gsa.gov
SUMMARY OF THE WORK 010100 - 5
referenced by any of these.
G. Abbreviated Written Summary: Briefly, and without force and effect upon contract documents, work of contract can be summarized as follows:
This project includes the decommissioning of the existing 1,900 square foot Indoor Firing Range (IFR) at the Houlton Headquarters facility and the renovation of that space to create Training and Fitness Rooms. This work also includes the installation of a new TPO roof system. This project includes the removal of all lead in the existing (IFR).
1.3 CONTRACTOR USE OF PREMISES
A. General: During the entire construction period the Contractor shall have the use of the premises identified at the “LIMIT OF WORK” area for construction operations. The Contractor will also have use of the site only in the area noted as “CONTRACTOR LAYDOWN AREA” All other site area is off limits to the Contractor for any purpose.
1. The Contractor’s use of the premises is limited by the Government's right to perform work or to retain other contractors on portions of the project.
B. General: The Contractor shall limit his use of the premises to the work indicated, so as to allow for Government occupancy and use by the general public.
1. Use of the Site: Confine operations at the site to the areas permitted under the Contract.
Portions of the site beyond areas on which work is indicated are not to be disturbed.
Conform to site rules and regulations affecting the work while engaged in project construction. See Division 01 Section "Project Coordination."
2. Contractor Use of the Existing Building: Maintain the existing building in a safe and weather tight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building and its occupants during the construction period. See "Project Coordination" section.
a. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government's employees, emergency vehicles at all times.
Do not use the areas not identified for use by Contactor for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
3. Working Hours: The normal working hours for this contract shall be from 6:30 a.m. to
6:00 p.m., Monday through Friday, unless otherwise authorized by the Contracting Officer.
4. Utility Interruptions: Utility interruptions, diminished service, or shut-downs will be permitted only after normal working hours, or on weekends, and shall be coordinated with the Contracting Officer.
1.4 GOVERNMENT OCCUPANCY
SUMMARY OF THE WORK 010100 - 6
A. Full Government Occupancy: The Government will occupy the site and adjacent existing building areas during the entire period of construction. Cooperate fully with the Government representative during construction operations to minimize conflicts and to facilitate Government usage. Perform the work so as not to interfere with the Government operations.
1.5 INSPECTION BY REGULATORY AUTHORITIES
A. This project is subject to inspection by the following regulatory authorities:
GSA Fire Protection Engineer Property Development Division 1 PCF 10 Causeway Street, Rm 975 Boston, MA 02222
U.S. Department of Labor Occupational Safety & Health Administration 200 Constitution Avenue Washington, D.C. 20210
B. Notify Contracting Officer when inspections take place. Decision as to action to be taken as a result of inspections by regulatory authorities will be made by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed inside the existing building during normal business working hours of 6:30 a.m. to 6:00 p.m., Monday through Friday, except otherwise indicated.
1. Weekend Hours: Authorized by Contracting Officer.
2. Early Morning Hours: Authorized by Contracting Officer.
3. Hours for Utility Shutdowns: After normal working hours or on weekends, and coordinated with Contracting Officer.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than one week in advance of proposed utility interruptions. Do not proceed with utility interruptions without Contracting Officer's written permission.
1.7 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the
SUMMARY OF THE WORK 010100 - 7
33-division format and CSI/CSC's "MasterFormat" numbering system.
1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
3. The words "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
1.8 MISCELLANEOUS AND GENERAL PROVISIONS
A. Existing Structures: Shall remain in place, except as noted.
B. Outside Electrical Services: Underground and overhead electrical services shall be provided complete to all points of connection to utility and service lines as shown on drawings and specified under other sections of this specification. Any "Limit of Contract" lines or similar general limits that may appear on site or other drawings shall not be deemed to apply to the foregoing electrical work.
C. New Work: Unless otherwise noted on drawings or specified, new work in extension of existing conditions shall correspond in all respects with that to which it connects, or to similar existing conditions, in materials, workmanship, and finish.
D. Alterations to Existing Work:
1. Existing work shall be cut, drilled altered, removed, or temporarily removed and replaced as necessary for performance of work under the contract. Work that is replaced shall match similar existing work. Structural members shall not be cut or altered, except where noted on drawings, without authorization of the Contracting Officer. Work remaining in place which is damaged or defaced during this contract shall be restored to the condition existing at time of award of contract.
2. Discolored or unfinished surfaces exposed by removal of existing work and indicated to be the final exposed surfaces shall be refinished or the material shall be replaced as necessary to make contiguous work uniform and harmonious. Work out of alignment
SUMMARY OF THE WORK 010100 - 8
where exposed by removal of existing work shall be called to the Contracting Officer's attention. Necessary corrective work directed by the Contracting Officer will be subject to adjustment of the contract in accordance with "Differing Site Conditions" clause of the General Conditions.
E. Work Done by Others: This contractor shall cooperate and coordinate with other contractor’s on the site.
F. It is mandatory that the first item of work to be the removal of exterior wall and the installation of a temporary door in the location of the new exterior exit door. This temporary door is to be used during construction as the sole means of entrance for construction staff and construction materials unless otherwise approved by the Owner. The temporary door is to be insulated hollow metal with weather stripping and appropriate hardware to provide a safe and secure facility at all times. All construction demolition materials are to be removed from the existing building through and only through this temporary door.
G. All construction debris material containers are to be covered at all times to avoid the spread of construction material debris around the job site. Also all effort will be required to contain construction material debris, specifically lead dust, from being tracked back into the existing building once removed. See specification Sections 020800, 020820, and 020900 for additional requirements for the removal of hazardous waste materials.
H. The existing lightening protection system must stay active at all times during this project including during the reroofing work.
I. Any and all existing communications systems must stay intact and active (usable) during the entire construction project.
J. All existing electrical, communication, and lightening protection systems grounding protection are to be maintained at all times during this contruction.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 010100
OPTIONS 010350 - 1
SECTION 010350 - OPTIONS
1.1 DESCRIPTION OF REQUIREMENTS
A. Definition: An option is an amount proposed by Bidders and stated on the Bid Form that will be added to Base Bid amount if the Government decides to accept a corresponding change in either scope of work or in products, materials, equipment, systems or installation methods described in Contract documents. If an Option is selected either Option 1 or Option 2 will be selected; not both.
1. Government acceptance of the change shall constitute the “exercise” of the option.
2. The Government shall have sole discretion as to whether to exercise the option or not and shall bear no liability to the bidder for the exercise or non-exercise of the option so long as the decision is made on or before the “Deadline for Acceptance.”
B. Deadline for Acceptance: The options, if exercised, shall be exercised in writing not later than the number of calendar days specified for each Option Period.
C. Performance Period: Should the Government exercise any or all of the options, the work included in each option shall be performed concurrently with the base contract work. There shall be no extension in contact performance time with the exercise of any or all of the options.
D. Coordination:
1. Coordinate related work and modify or adjust adjacent work as required to ensure that work affected by each option is complete and fully integrated into the project.
2. All bidders shall provide a price for each option in the place provided on the Bid form.
3. Include as part of each option, miscellaneous devices, appurtenances and similar items incidental to or required for a complete installation whether or not mentioned as part of the option.
4. Include as part of the price of each option all costs attributable to project Contract Clauses, Division 1 requirements, overhead and profit. No additional payments will be made by the Government for the work of any Option which is exercised beyond the option Price listed, except in accordance with contract provisions related to Changes in the Work.
1.2 SCHEDULE OF OPTIONS:
A. OPTIONS
Option No. 1
OPTIONS 010350 - 2
Perforate (aerate) the existing EPDM roofing. Mechanically attach the re-cover board over the existing roofing or insulation. Provide mechanical attachment to the existing Tectum deck in full accordance with the roofing manufacturer's requirement. The board, the board layout, taper and attachment method shall be approved by the roofing manufacturer. Install a fully adhered TPO roof membrane per specifications and provide a full warranty per specification. Also see requirements of Section 070150.19.
Option No. 2
Remove all existing roof system, down to existing Tectum roof decking, including EPDM roofing, insulation, roof drains, and all existing flashing. Then install a new TPO roof system including new ¼” sloped insulation to new roof drains. This option to include all new roof edge flashing, equipment curb flashing, vent stack flashing. Existing wood blocking to stay in place. R-Value of new roof system shall provide an average R-value of 40. Also see requirements of Section 070150.19.
B. Option Period: The Government shall have 30 calendar days to exercise this option after the
Notice to Proceed for the base contract is received by the Contractor.
C. The work of this option shall be started no later than 3 calendar days after the receipt by the
Contractor of the Government’s exercise of the Option.
1. The Contractor shall coordinate all work of the base bid with the work of the Option so as to expedite the work of the project.
2. An extension of the contract period will be negotiated with the Contractor upon Government acceptance of the Bid Option.
END OF SECTION 010350
REFERENCES 014200- 1
SECTION 014200 - REFERENCES
The following definitions are a partial listing of definitions, and when not found herein are referred.
DEFINITIONS
A. General Explanation: Specification language often includes terms that are defined elsewhere in the Contract Documents, including the Construction Contract Clauses. Certain terms are defined in this section. These definitions or explanations are not necessarily complete or exclusive, but are general for the Work and may be explained more explicitly in other Sections.
B. "General Terms and Conditions" are defined by the Agreement.
C. "Special Conditions" refer collectively to Section 00800 "Supplementary Conditions" and any other sections with numbers starting with 00.
D. "Indicated" refers to graphic representations, notes or schedules on the Drawings, or to requirements elsewhere in the Specifications or other Contract Documents. Terms such as "shown", "noted", "scheduled" and "specified" have the same meaning as "indicated" and are used to further help locate the reference, but no limitation on location is intended
E. .Where "directed", "authorized", "selected", "approved", or a similar term is used in conjunction with the Contractor's submittals, applications, requests and other activities, and the specifications state that an individual other than the Contracting Officer, such as the Contracting Officer's Technical Representative, shall provide this action, it is understood that only the Contracting Officer has this authority unless the individual stated is authorized in writing by the Contracting Officer.
1. When the individual is authorized by the Contracting Officer, the Contractor may still appeal the action to the Contracting Officer.
2. The Contracting Officer's decision will be final.
3. In no case shall the Contracting Officer's action be interpreted as releasing the Contractor from responsibility to fulfill the requirements of the Contract Documents.
F. "Regulations" are found in the FARs, GSAM, and CFR including orders issued by the government.
G. "Project site" refers to the space available to the Contractor for performance of the Work, either exclusively or in conjunction with others performing other work.
H. "Furnish" means to supply and deliver to the Project site, ready for unloading, unpacking, assembling, installation and similar operations.
REFERENCES 014200- 2
I. "Install" describes operations at the Project site, including unloading, temporary storage, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations.
J. "Provide" means to furnish and install, complete in place and ready for full use.
K. "Cutting" refers to removal of material by cutting, sawing, drilling, breaking, chipping, grinding, excavating and similar operations.
L. "Patching" refers to restoration of a surface to its original completed condition by filling, repairing, refinishing, closing and similar operations.
M. "Installer" is the Contractor or another entity engaged by the Contractor, either directly or indirectly through subcontracting, to perform a particular construction operation at the Project site, including installation, erection, application and similar operations. Installers shall be skilled in the operations they perform. Where indicated, installers shall also be Specialists as defined in the Construction Contract Clauses."Testing agency" or "testing laboratory" is an independent entity engaged to perform specific inspections or tests, either at the Project site or elsewhere, and to report the results of those inspections and tests.
N. "Label": This must be provided by a NRTL, or other entity approved by by GSA. The burden of documentation for validation shall be provided by the Contractor.
O. “Superintendent” refers to the Contractor’s on site representative who is responsible for continuous field supervision, coordination, planning, scheduling, and completion of the work and, unless another person is designated by the contract specification, for the prevention of accidents.
P. "Owner" is the Government.
Q. "Government" refers to the General Service Administration (GSA).
R. "Government" refers to the Public Buildings Service (PBS).
S. "Building Manager" is the Government employee responsible for the administration, operation and maintenance of the building.
T. "Notice to Proceed" is the Contracting Officer's notification by letter to the Contractor to proceed with the Contract, activating the time period for construction and establishing the completion date.
U. "Substantial Completion" is defined in the Agreement, with additional provisos in Specification Section 017700 Closeout.
V. "Punch List" is the entire listing of all work including items that must be completed pursuant to Contract Completion.
REFERENCES 014200- 3
1.2 DRAWING SYMBOLS
A. Except as otherwise indicated, symbols used on the Drawings are those symbols recognized in the construction industry.
1. These include graphic symbols defined by "Architectural Graphic Standards", published by John Wiley & Sons, Inc., as well as graphic symbols recommended by ASHRAE, ASME, ASPE, CSI, IEEE and similar technical organizations for the mechanical and electrical Drawings.
2. Refer uncertainties as to meaning of symbols to GSA for clarification before proceeding.
1.3 INDUSTRY STANDARDS
A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect, to the extent referenced, as if bound or copied directly into the Contract Documents. Such standards are made a part of the Contract Documents by reference.
B. Conflicting Requirements. Comply with the most stringent requirement, or the more current edition in case of duplicate requirements with differing dates.
1. Minimum Quantity and Quality: In case of conflict, GSA judgment shall be final.
2. In certain instances, specification text requires that specific work is to be assigned to specialists who must be engaged for performance of that work. Such assignments are special requirements over which the Contractor has no choice or option.
C. Publication dates are those valid in the Contract Documents on the date of the Invitation For Bids. When an applicable standard has been revised in the course of construction, and the contractor is affected by this, a change order proposal shall be submitted. GSA will render a decision for each case.
D. Abbreviations and Acronyms used in the Specifications and other Contract Documents mean the recognized name of a trade association, standards-producing organization, and authority having jurisdiction or other entity applicable to the context of the particular provision. Except as otherwise indicated, refer to the current editions of the following publications for abbreviations:
1. "Encyclopedia of Associations: National Organizations of the U.S.", published by Gale Research.
2. "National Trade and Professional Associations of the United States", published by Columbia Books.
3. "Means Illustrated Construction Dictionary - New Unabridged Edition" published by R.S.
Means Company, Inc.
4. "Abbreviations and Acronyms," paragraphs A through E by MasterSpec Division 0142000.
REFERENCES 014200- 4
E. Abbreviation and Acronyms Listing. The following names are subject to change and are believed, but are not assured, to be accurate and up-to-date as of the date of the Contract Documents.
1. AA- Aluminum Association
2. AABC - Associated Air Balance Council
3. AAMA - American Architectural Manufacturers Association
4. AAN - American Association of Nurserymen (See ANLA)
5. AASHTO - American Association of State Highway and Transportation
6. AATCC - American Association of Textile Chemists and Colorists
7. ABMA - American Bearing Manufacturers Association
8. ABMA - American Boiler Manufacturers Association
9. ACI - American Concrete Institute
10. ACIL - American Council of Independent Laboratories
11. AISET - The Association of Independent Scientific, Engineering, and Testing Firms
12. ACPA - American Concrete Pipe Association
13. ADC - Air Diffusion Council
14. AEIC - Association of Edison Illuminating Companies
15. AFBMA - Anti-Friction Bearing Manufacturers Association (See ABMA)
16. AFPA - American Forest and Paper Association
17. AGA - American Gas Association
18. AGC - Association of General Contractors
19. AHA - American Hardboard Association
20. AHAM - Association of Home Appliance Manufacturers
21. AI - Asphalt Institute
22. AIA - The American Institute of Architects
23. AIA - American Insurance Association
24. AIHA - American Industrial Hygiene Association
25. AISC - American Institute of Steel Construction
26. AISI - American Iron and Steel Institute
27. AITC - American Institute of Timber Construction
28. ALA - American Laminators Association (See LMA)
29. ALI - American Lighting Institute
30. ALCA - Associated Landscape Contractors of America
31. ALI - Associated Laboratories, Inc.
32. ALSC - American Lumber Standards Committee
33. AMCA - Air Movement and Control Association International, Inc.
34. ANLA - American Nursery and Landscape Association
35. ANSI - American National Standards Institute
36. AOAC - Association of Official Analytical Chemists International
37. AOSA - Association of Official Seed Analysts
38. APA - American Plywood Association (see EWA)
39. APA - Architectural Precast Association
40. API - American Petroleum Institute
41. ARI - Air-Conditioning and Refrigeration Institute
42. ARMA - Asphalt Roofing Manufacturers Association
43. ASA - Acoustical Society of America
44. ASC - Adhesive and Sealant Council
45. ASCA - Architectural Spray Coaters Association
REFERENCES 014200- 5
46. ASCE - American Society of Civil Engineers
47. ASHES - American Society for Healthcare Environmental Services - Division of the
American Hospital Association
48. ASHRAE - American Society of Heating, Refrigerating and Air Conditioning Engineers.
49. ASLA - American Society of Landscape Architects
50. ASME - American Society of Mechanical Engineers
51. ASPA - American Sod Producers Association (See TPI)
52. ASPE - American Society of Plumbing Engineers
53. ASQ - American Society for Quality
54. ASSE - American Society of Sanitary Engineering
55. ASTM - American Society for Testing and Materials
56. ATIS - Alliance for Telecommunications Industry Solutions
57. ATS - Automatic Transfer Switch
58. AWCI - Association of the Wall and Ceiling Industries International
59. AWCMA - American Window Covering Manufacturers Association (See WCMA)
60. AWI - Architectural Woodwork Institute
61. AWPA - American Wood-Preservers' Association
62. AWS - American Welding Society
63. AWWA - American Water Works Association
64. BAS - Building Automation System
65. BHMA - Builders Hardware Manufacturers Association
66. BIA - Brick Industry Association
67. BIFMA - The Business and Institutional Furniture Manufacturer's Association International
68. BIM - Building Information Model
69. BOD - Basis of Design
70. CABO - Council of American Building Officials
71. CAGI - Compressed Air and Gas Institute
72. CAUS - Color Association of the United States
73. CBHF - State of California, Department of Consumer Affairs, Bureau of Home Furnishings and Thermal Insulation Technical Information
74. CBMA - Certified Ballast Manufacturers Association
75. CC - Construction Contractor
76. CE - Construction or Consulting Engineer
77. CEx - Contract Executive
78. CCC - Carpet Cushion Council
79. CDA - Copper Development Association Inc.
80. CE - Corps of Engineers (U.S. Department of the Army)
81. CFFA - Chemical Fabrics & Film Association, Inc.
82. CFR - Code of Federal Regulations (Publications available from the Government Printing
Office)
83. CGA - Compressed Gas Association
84. CGSB - Canadian General Standards Board
85. CISCA - Ceilings and Interior Systems Construction Association
86. CISPI - Cast Iron Soil Pipe Institute
87. CLFMI - Chain Link Fence Manufacturers Institute
88. CLP - Certified Landscape Professional
89. CLT-E - Certified Landscape Technician-Exterior
90. CLT-I - Certified Landscape Technician - Interior
REFERENCES 014200- 6
91. CLPA – California Lathing and Plastering Association
92. CMPM - CM Project Manager
93. CM - Construction Manager
94. CO - Contracting Officer
95. COLP - Certified Ornamental Landscape Professional
96. CORPS - Army Corps of Engineers
97. COTR - Contracting Officer's Technical Representative
98. COBIE - Construction to Operations Building Information Exchange
99. CPA - Composite Panel Association
100. CPPA - Corrugated Polyethylene Pipe Association
101. CPSC - Consumer Product Safety Commission
102. CRI - Carpet and Rug Institute
103. CRSI - Concrete Reinforcing Steel Institute
104. CS - Commercial Standard (U.S. Department of Commerce)
105. CSI - Construction Specifications Institute
106. CSSB - Cedar Shake and Shingle Bureau
107. CTI - Ceramic Tile Institute of America
108. CTI - Cooling Tower Institute
109. CTP - Certified Turfgrass Professional
110. DHI - Door and Hardware Institute
111. DIPRA - Ductile Iron Pipe Research Association
112. DLPA – Decorative Laminate Products Association
113. DOC - Department of Commerce (Publications available from the Government Printing
Office)
114. DOJ - Department of Justice
115. DOT - Department of Transportation
116. DP - Design Professional
117. ECSA - Exchange Carriers Standards Association (See ATIS)
118. EIA - Electronic Industries Association
119. EIMA - EIFS Industry Members Association
120. EJMA - Expansion Joint Manufacturers Association
121. EPA - Environmental Protection Agency
122. EPAct 2005 -
123. EWA - Engineered Wood Association
124. FAA - Federal Aviation Administration
125. FCC - Federal Communications Commission
126. FCI - Fluid Controls Institute
127. FCICA - Floor Covering Installation Contractors Association
128. FDA - US Food and Drug Administration
129. FGMA - Flat Glass Marketing Association (See GANA)
130. FHA - Federal Housing Administration (U.S. Department of Housing and Urban
Development)
131. FM - Factory Mutual System
132. FMR - Federal Management Regulation
133. FPE - Fire Protection Engineer
134. FPS - Federal Protective Service
135. FPT - Functional Performance Test
136. FS - Federal Specification (Publications available from GSA)
REFERENCES 014200- 7
137. FSC – Forest Stewardship Council
138. FTI – Facing Tile Institute
139. GA - Gypsum Association
140. GANA - Glass Association of North America
141. GRI - Geosynthetic Research Institute
142. GSA - General Services Administration
143. HEI - Heat Exchange Institute
144. HFES - Human Factors and Ergonomics Society
145. HI - Hydraulic Institute
146. HI - Hydronics Institute - Division of Gas Appliance Manufacturers Association
147. HMA - Hardwood Manufacturers Association
148. HPVA - Hardwood Plywood and Veneer Association
149. IALD - International Association of Lighting Designers
150. IAS - International Approval Services - Division of Canadian Standards Association
151. ICEA - Insulated Cable Engineers Association
152. IEC - International Electrotechnical Commission (Publications available from ANSI)
153. IES - Illuminating Engineering Society
154. IEEE - Institute of Electrical and Electronics Engineers
155. IESNA - Illuminating Engineering Society of North America
156. IGCC - Insulating Glass Certification Council
157. IIDA - International Interior Design Association
158. ILI - Indiana Limestone Institute of America
159. IMSA - International Municipal Signal Association
160. INCE - Institute of Noise Control Engineering
161. ISA - International Society for Measurement and Control
162. ISC - Interagency Security Committee
163. ISEA - Industrial Safety Equipment Association
164. ISS - Iron and Steel Society
165. KCMA - Kitchen Cabinet Manufacturers Association
166. LEED - Leadership in Energy and Environmental Design
167. LGSI - Light Gage Structural Institute
168. LIA - Lead Industries Association, Inc.
169. LMA - Laminating Materials Association
170. LPI - Lightning Protection Institute
171. MBMA - Metal Building Manufacturers Association
172. MCAA - Mechanical Contractors Association of America
173. MFMA - Maple Flooring Manufacturers Association
174. MFMA - Metal Framing Manufacturers Association
175. MHIA - Material Handling Industry Association
176. MIA - Marble Institute of America
177. MIA - Masonry Institute of America
178. MIL - Military Standardization Documents (U.S. Department of Defense)
179. MILCON - Military Construction
180. ML/SFA - Metal Lath/Steel Framing Association
181. MSS - Manufacturers Standardization Society of the Valve and Fittings Industry
182. NAA - National Arborist Association
183. NAAMM - National Association of Architectural Metal Manufacturers
184. NAAMM - North American Association of Mirror Manufacturers (See GANA)
REFERENCES 014200- 8
185. NACE - National Association of Corrosion Engineers International
186. NAGDM - National Association of Garage Door Manufacturers (See DASMA)
187. NAIMA - North American Insulation Manufacturers Association
188. NAMI - National Accreditation & Management Institute, Inc.
189. NAPA - National Asphalt Pavement Association
190. NBHA - National Builders Hardware Association (See DHI)
191. NBIMS - National Building Information Model Standards
192. NBGQA - National Building Granite Quarries Association, Inc.
193. NBS – National Bureau of Standards
194. NIBS - National Institute of Building Sciences
195. NIST - National Institute of Standards and Technology
196. NCAC - National Council of Acoustical Consultants
197. NCCA - National Coil Coaters Association
198. NCMA - National Concrete Masonry Association
199. NCPI - National Clay Pipe Institute
200. NCRPM - National Council on Radiation Protection and Measurements
201. NCSPA - National Corrugated Steel Pipe Association
202. NEBB - Natural Environmental Balancing Bureau
203. NEC - National Electrical Code
204. NECA - National Electrical Contractors Association
205. NEI - National Elevator Industry
206. NEMA - National Electrical Manufacturers Association
207. NETA - InterNational Electrical Testing Association
208. NFPA - National Fire Protection Association
209. NFPA - National Forest Products Association (See AFPA)
210. NFRC - National Fenestration Rating Council Incorporated
211. NGA - National Glass Association
212. NHLA - National Hardwood Lumber Association
213. NIA - National Insulation Association
214. NIAC - National Insulation and Abatement Contractors Association (See NIA)
215. NIST - National Institute of Standards and Technology (U.S. Department of Commerce)
216. NKCA - National Kitchen Cabinet Association (See KCMA)
217. NPCA - National Paint and Coatings Association
218. NRCA - National Roofing Contractors Association
219. NRMCA - National Ready Mixed Concrete Association
220. NRTL - Nationally Recognized Testing Laboratory
221. NSA - National Stone Association
222. NSF - National Sanitation Foundation International
223. NTMA - National Terrazzo and Mosaic Association
224. NVLAP - National Voluntary Laboratory Accreditation Program (via NIST)
225. NUSIG - National Uniform Seismic Installation Guidelines
226. NWFA - National Wood Flooring Association
227. NWMA - National Woodwork Manufacturers Association (See NWWDA)
228. NWWDA - National Wood Window and Door Association
229. O & M - Operations & Maintenance
230. OSHA - Occupational Safety and Health Administration (U.S. Department of Labor)
231. P100 - GSA Facilities Standards for the Public Building Service
232. PATMI - Powder Actuated Tool Manufacturers' Institute
REFERENCES 014200- 9
233. PCA - Portland Cement Association
234. PCI - Precast/Prestressed Concrete Institute
235. PDCA - Painting and Decorating Contractors of America
236. PDI - Plumbing and Drainage Institute
237. PDS - Program Development Study
238. PEI - Porcelain Enamel Institute
239. PLANET - Professional Landcare Network
240. PMO -
241. POR - Program Of Requirements
242. PPFA - Plastic Pipe and Fittings Association
243. PPI - Plastics Pipe Institute (The Society of the Plastics Industry, Inc.)
244. PS - Product Standards of the National Bureau of Standards (U.S. Department of
Commerce)
245. QAQC - Quality Assurance Quality Control
246. RCSC - Research Council on Structural Connections
247. RFCI - Resilient Floor Covering Institute
248. RFP - Request For Proposal
249. RFQ - Request For Qualifications
250. RIEI - Roofing Industry Education Institute
251. RMA - Rubber Manufacturers Association
252. SAE - Society of Automotive Engineers International
253. SAMA - Scientific Apparatus Makers’ Association
254. SDI - Steel Deck Institute
255. SDI - Steel Door Institute
256. SEFA - Scientific Equipment and Furniture Association
257. SEGD - Society for Environmental Graphic Design
258. SFPE - Senior Fire Protection Engineer
259. SGCC - Safety Glazing Certification Council
260. SHLMA - Southern Hardwood Lumber Manufacturers Association (See HMA)
261. SIGMA - Sealed Insulating Glass Manufacturers Association
262. SJI - Steel Joist Institute
263. SMA - Screen Manufacturers Association
264. SMACNA - Sheet Metal and Air Conditioning Contractors' National Association
265. SPI - The Society of the Plastics Industry, Inc.
266. SPIB - Southern Pine Inspection Bureau
267. SSINA - Specialty Steel Industry of North America
268. SSPC - Steel Structures Painting Council - The Society for Protective Coatings
269. SSPMA - Sump and Sewage Pump Manufacturers Association
270. STI - Steel Tank Institute
271. SWI - Steel Window Institute
272. SWPA - Submersible Wastewater Pump Association
273. SWRI - Sealant, Waterproofing and Restoration Institute
274. TAB - Testing, Adjusting, and Balancing Bureau
275. TCA - Tile Council of America
276. TIMA - Thermal Insulation Manufacturers Association (See NAIMA)
277. TPI - Truss Plate Institute
278. TPI - Turfgrass Producers International
279. TRB - Transportation Research Board - National Research Council
REFERENCES 014200- 10
280. UFAC - Upholstered Furniture Action Council
281. UL - Underwriters Laboratories Inc.
282. USDA - U.S. Department of Agriculture]
283. USGBC – U.S. Green Building Council
284. USITT - U.S. Institute of Theater Technology - The American Association of Design and
Production Professionals in the Performing Arts
285. USMS - U.S. Marshal Service
286. USP - U.S. Pharmacopeia
287. USPS - U.S. Postal Service
288. VOC – Volatile Organic Compound
289. WA - Wallcoverings Association
290. WASTEC - Waste Equipment Technology Association
291. WCMA - Window Covering Manufacturers Association
292. WEF - Water Environment Federation
293. WMMPA - Wood Moulding & Millwork Producers Association
294. WPCF - Water Pollution Control Federation (See WEF)
295. WRI - Wire Reinforcement Institute
296. WSC - Water Systems Council
297. WSFI - Wood and Synthetic Flooring Institute (See MFMA)
298. WWPA - Western Wood Products Association
299. W.W.P.A. - Woven Wire Products Association
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 014200
TEMPORARY FACILITIES AND CONTROLS 015000- 1
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
1.1 SUMMARY
A. This section includes requirements for temporary utilities, support facilities and protection.
1. Temporary utilities include but are not limited to the following:
a. Temporary water service and distribution.
b. Temporary electric power and lighting.
c. Temporary heat and ventilation.
d. Temporary telephone service.
e. Temporary sanitary facilities, including drinking water.
f. Storm and sanitary sewer.
2. Support facilities include but are not limited to the following:
a. Field offices, storage sheds and fabrication shops.
b. Temporary lifts and hoists.
c. Project identification and other temporary signs.
d. Waste disposal services.
e. Other construction aids and miscellaneous services and facilities.
3. Protection includes but is not limited to the following:
a. Temporary fire protection.
b. Barricades, warning signs, and lights.
c. Enclosure fence.
d. Environmental protection.
e. Enclosure partitions.
B. Provide temporary facilities and controls required for construction activities except, for facilities and controls indicated as existing or provided by the Government or others.
1.2 UTILITY USE CHARGES
A. Unless otherwise specified, Contractor shall pay utility service use charges for temporary utilities used by all entities engaged in construction activities at the Project site. Costs for these services are included in the Contract price.
TEMPORARY FACILITIES AND CONTROLS 015000- 2
B. Water Service: The Contractor may use water from the Government's existing water system, without metering and without payment of use charges.
C. Sewer Service: Contractor may use the Government's existing sewer system, without payment of use charges.
D. Electric Power Service: Contractor may use electric power from the Government's existing electric power system, without metering and without payment of use charges.
1.3 SUBMITTALS
A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.
B. Reports: Submit reports of tests, inspections, meter readings and similar procedures for temporary utilities.
C. Implementation and Termination Schedule: Within 15 calendar days after the date established for the submittal of the Contractor's Construction Schedule, submit a schedule indicating implementation and termination of each temporary utility.
D. Weather Protection:
1. Provide protection for work areas affected by moisture and thermal change. Including building floor areas, masonry scaffolds and fabrication areas. Covering, enclose and heat to maintain a relatively dry work area with a minimum temperature of 40°F at the working surface. Weather protection is not required for excavation, pile driving, steel erection, and similar operations normally completed in the open.
2. Submit weather protection plan to GSA for approval. Future changes must be approved by GSA.
3. Provide accurate Fahrenheit thermometers for every 2,000 square feet of floor space located as directed.
1.4 QUALITY ASSURANCE
A. Standards and Regulations: In temporary facilities, comply with industry standards, applicable laws, and regulations of authorities having jurisdiction, including but not limited to the following:
1. Building code requirements.
2. Health and Safety regulations.
3. Utility company regulations.
4. Police, fire department and rescue squad rules.
5. Environmental protection regulations.
6. For temporary egress, ABAAS regulations.
7. NFPA 241 "Standards for Safeguarding Construction, Alterations and Demolition
Operations".
TEMPORARY FACILITIES AND CONTROLS 015000- 3
8. ANSI-A10 Series standards for "Safety Requirements for Construction and Demolition".
9. NECA Electrical Design Library "Temporary Electrical Facilities", NFPA 70, and
NEMA, NECA and UL standards and regulations for temporary electric…