Volume I Specs

View the file

Other files

File Type Posted
GROUP4-10-R-J041_Revision_0002.pdf PDF
15-043_Capron_Shoal_3ft_ALL.xyz XYZ file
GROUP4-10-R-J041_Revision_0001.pdf PDF
5304-29_FT_PIERCE_1FT_DATA.xyz XYZ file
113090_Fort_Pierce_FY18_20170921.pdf PDF
Ft_Pierce_SPP_FY17_GDR-final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GROUP4-10-R-J041

Jacksonville District

Fort Pierce Shore Protection Project, Beach Renourishment 2018

St. Lucie County, Florida

Construction Solicitation and Specifications

28 SEPTEMBER 2017

Fort Pierce Shore Protection Project GROUP4-10-R-J041 Beach Renourishment 2018

DESIGN AUTHENTICATION

This project was designed by the Jacksonville District, U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.

JEFF E. BERGEN, P.E.

CHIEF, WATERWAYS SECTION, DESIGN BRANCH

ENGINEERING DIVISION

DENNIS J. ZEVENEY, P.E.

CHIEF, GEOTECHNICAL BRANCH

DAVID DUDLEY, P.E.

CHIEF, DESIGN BRANCH

LAUREEN A. BOROCHANER, P.E.

CHIEF, ENGINEERING DIVISION

GROUP4-10-R-J041 SF 1442-A1

ADDENDUM TO THE STANDARD FORM 1442

Fort Pierce Shore Protection Project, Beach Renourishment 2018, St. Lucie County, Florida

SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING

CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER

W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc.

(W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005);

Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);

Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);

Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015) PROPOSALS WILL NOT BE

CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS

INCLUDED IN THE Group 4 Dredging MATOC Pool.

TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:

(1) Availability of technically acceptable dredge(s).

(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Contractor Performance Assessment Reporting System (CPARS) records contained in the US Army Corps of Engineers CPARS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).

SUBMISSION REQUIREMENTS: Contractors are required to submit the following:

(1) A letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.

(2) Completed Bid Schedule (see Section 00010A)

(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC

(4) Completed “Addendum to the Standard Form 1442 with the latest revision”.

(5) Revisions – Offers must acknowledge receipt of this Revision by completing “Notice to Offerors--Blocks 14, 15 and 20” of each revision.

THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:

Block 9 -- For additional information contact:

Claurice M. Dingle 904-232-1387 Claurice.m.dingle@usace.army.mil.

Block 10 -- Magnitude of Construction is between $5,000,000.00 and $10,000,000.00.

GROUP4-10-R-J041 SF 1442-A2

Block 11 -- The Contractor shall begin performance within 45 calendar days and complete it within 110 calendar days after receiving notice to proceed. This performance period is mandatory. NOTE: If there are optional line items, refer to FAR 52.211-10 for breakdown of period of performance.

Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.

Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than 14 Nov 2017 at 2:00 P.M. Local Time.

USA Engineer District, Jacksonville Contracting Division 701 San Marco Blvd

Jacksonville, Florida 32207-8175

NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:

Block 14 -- Name and Address of Offeror (including Zip Code):

DUNS: ___________________ CAGE: _______________

Block 15 -- Telephone No. (include area code): _____________________

Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):

Type/Print ________________________________________________

Signature: ________________________________________________ e-Mail: ________________________________________________

Offer Date: _______________________________________________

Block 26 -- This Task Order will be administered by:

South Florida Area Office 4400 PGA Blvd Suite 203

Palm Beach, FL 33410

Block 27 -- Payment will be made by:

USACE Finance Center 5722 Integrity Drive

ATTN: CEFC-AO-P

Millington, TN 38054-5005

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

FORT PIERCE SHORE PROTECTION PROJECT

BEACH RENOURISHMENT 2018

ST. LUCIE COUNTY, FLORIDA

GROUP4-10-R-J041 00010A-1

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

BASE (R-34 TO R-38)

0001 MOBILIZATION AND DEMOBILIZATION JOB $______________

0002 BEACH FILL (ESTIMATED QUANTITY, SEE NOTE 2) 385,000 CUBIC YARD $______________ $______________

0003 SCREENING (ESTIMATED QUANTITY, SEE NOTE 2 ) 385,000 CUBIC YARD $______________ $______________

0004 BEACH TILLING (ESTIMATED QUANTITY, SEE NOTE 2) 12 ACRE $______________ $______________

0005 REMEDIATION OF NONCOMPLIANT MATERIAL 0.8 ACRE $______________ $______________

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0006 TRANSPORTATION AND DISPOSAL OF 6 CUBIC YARD $_____________ $______________

UNACCEPTABLE MATERIAL

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0007 CONSTRUCTION/VIBRATION CONTROLS & MONITORING JOB $______________

0008 ENVIRONMENTAL SPECIES MONITORING JOB $______________

0009 TURBIDITY MONITORING JOB $______________

0010 MOBILIZATION AND DEMOBILIZATION, FOR JOB $______________

NON-CAPTURE SEA TURTLE TRAWL SWEEPING

(HOPPER DREDGE ONLY)

0011 SEA TURTLE NON-CAPTURE TRAWL SWEEPING 3 DAY $______________ $______________

(HOPPER DREDGE ONLY) (SEE NOTES 3 AND 5)

0012 STANDBY TIME (SEE NOTES 3 AND 4) 24 HOUR $______________ $______________

TOTAL BASE (LINE ITEMS 0001 THROUGH 0012) $______________

OPTION A (R-38 TO R-39A)

0013 BEACH FILL (ESTIMATED QUANTITY, SEE NOTE 2) 100,000 CUBIC YARD $______________ $______________

0014 SCREENING (ESTIMATED QUANTITY, SEE NOTE 2 ) 100,000 CUBIC YARD $______________ $______________

0015 BEACH TILLING (ESTIMATED QUANTITY, SEE NOTE 2) 4 ACRE $______________ $______________

0016 REMEDIATION OF NONCOMPLIANT MATERIAL 0.1 ACRE $______________ $______________

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0017 TRANSPORTATION AND DISPOSAL OF 2 CUBIC YARD $_____________ $______________

UNACCEPTABLE MATERIAL

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0018 CONSTRUCTION/VIBRATION CONTROLS & MONITORING JOB $______________

0019 ENVIRONMENTAL SPECIES MONITORING JOB $______________

0020 TURBIDITY MONITORING JOB $______________

TOTAL OPTION A (LINE ITEMS 0013 THROUGH 0020) $______________

TOTAL BASE PLUS OPTION A (LINE ITEMS 0001 THROUGH 0020) $______________

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

FORT PIERCE SHORE PROTECTION PROJECT

BEACH RENOURISHMENT 2018

ST. LUCIE COUNTY, FLORIDA

GROUP4-10-R-J041 00010A-2

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

OPTION B (R-39A TO R-41)

0021 BEACH FILL (ESTIMATED QUANTITY, SEE NOTE 2) 75,000 CUBIC YARD $______________ $______________

0022 SCREENING (ESTIMATED QUANTITY, SEE NOTE 2 ) 75,000 CUBIC YARD $______________ $______________

0023 BEACH TILLING (ESTIMATED QUANTITY, SEE NOTE 2) 4 ACRE $______________ $______________

0024 REMEDIATION OF NONCOMPLIANT MATERIAL 0.1 ACRE $______________ $______________

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0025 TRANSPORTATION AND DISPOSAL OF 2 CUBIC YARD $_____________ $______________

UNACCEPTABLE MATERIAL

(ESTIMATED QUANTITY, SEE NOTES 2 AND 3)

0026 CONSTRUCTION/VIBRATION CONTROLS & MONITORING JOB $______________

0027 ENVIRONMENTAL SPECIES MONITORING JOB $______________

0028 TURBIDITY MONITORING JOB $______________

TOTAL OPTION B (LINE ITEMS 0021 THROUGH 0028) $______________

TOTAL BID (LINE ITEMS 0001 THROUGH 0028) $______________

NOTES: (1) OFFERORS MUST BID ON ALL LINE ITEMS.

(2) ACTUAL QUANTITIES MAY VARY.

(3) THIS LINE ITEM IS NOT SUBJECT TO VARIATION IN ESTIMATED QUANTITY CLAUSE, AND PAYMENT WILL ONLY BE MADE FOR ACTUAL EXECUTION OF THIS LINE ITEM AS APPROVED BY THE CONTRACTING OFFICER.

(4) STANDBY TIME IS DEFINED AS WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE CONTRACTING OFFICER OR ADMINISTRATIVE CONTRACTING OFFICER. STANDBY TIME SHALL BE UTILIZED ONLY DUE THE THE PRESENCE OF ENDANGERED SPECIES IN THE IMMEDIATE AREA OF THE DREDGING OPERATIONS, DIFFERING SITE CONDITIONS, SECURITY OPERATIONS OR OTHER CONDITIONS AS DETERMINED BY THE CONTRACTING OFFICER. STANDBY TIME IS NOT AFFORDED FOR DELAYS CAUSED BY ADVERSE WEATHER CONDITIONS. THIS LINE ITEM IS NOT SUBJECT TO THE VAIRATION IN ESTIMATED QUANTITY CLAUSE, AND PAYMENT WILL ONLY BE MADE FOR ACTUAL STANDBY TIME REQUIRED BY THE CONTRACTING OFFICER. SEE SECTION 01 22 00 MEASUREMENT AND PAYMENT AND SECTION 01 57 20 ENVIRONMENTAL PROTECTION.

(5) SEA TURTLE NON-CAPTURE TRAWL SWEEPING IS REQUIRED WHEN DIRECTED BY THE CONTRACTING OFFICER.

SEE SECTION 01 57 20 ENVIRONMENTAL PROTECTION, PARAGRAPH "SEA TURTLE NON-CAPTURE TRAWL SWEEPING

(FOR HOPPER DREDGE ONLY)".

SECTION 00010A, Attachment A

INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 25 October 2017, Close of Business. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on the FedBizOps in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are all finalized.

The Solicitation Number is: GROUP4-10-R-J041

The Bidder Inquiry Key is: BNGW2E-WVCH2B

Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:

1. Identify the Agency. This should be marked as USACE.

2. Email. Enter the email address you would like to use for communication.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret

Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. Identify the Agency. This should be marked as USACE.

3. Email. Enter the email address you used to register previously in ProjNet.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

THE FOLLOWING PAGES CONTAIN ADDENDUMS TO SPECIFIC SECTIONS OF THE

ORIGINAL SOLICITATION NUMBER W912EP-10-R-0026

THESE ADDENDUMS ARE ONLY APPLICABLE TO THIS

SPECIFIC TASK ORDER

REQUEST FOR PROPOSAL NUMBER: GROUP4-10-R-J041

TASK ORDER PROJECT TITLE:

Fort Pierce Shore Protection Project, Beach Renourishment 2018, St. Lucie County, Florida

NOTICE TO OFFERORS: The information on the following pages is provided for the various clauses and/or paragraphs which require information to be filled in (when applicable) on each Request for Proposal for Task Orders issued under the awarded contracts. All applicable clauses, terms and conditions contained in the original solicitation and subsequently awarded contracts become part of each Task Order.

GROUP-10-R-J041 Clause Addendum-1

ADDENDUM TO SECTION 00100, INSTRUCTIONS TO OFFERORS

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00100 ARE HEREBY PROVIDED:

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

30.4% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is St. Lucie County, Florida.

(End of provision)

GROUP4-10-R-J041 00100-A1

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) (ALTERNATE I) (FEB 1995) (CESAJ

ADAPTATION)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for – 11 Oct 2017 at 11:00 AM Local Time.

(c) Participants will meet at -- (Location will be provided by the contract administration office via telephone. See (d) below.)

(d) Participants should call Cecilia Muzi at 561-472-3500 on or before 06 Oct 2017 to make arrangements.

(e) Core borings are available. (If available, follow the instructions in the Physical Data paragraph in Section 00 11 00 and 00 31 32 of individual request for proposals issued for task orders under this contract to make arrangements to inspect the borings. Failure to follow the instructions may result in a delay ranging in duration from one hour to 4 days.)

(f) After the site visit, a memorandum summarizing the visit may be posted to the appropriate website under the solicitation number. This posting will be strictly for informational purposes only.

The memorandum will not become a part of the solicitation. If the solicitation needs to be changed as a result of information obtained during the site visit, a written amendment will be made available to all registered vendors. Questions regarding any information given in the memorandum must be directed to the person whose name appears in item 9 of the Addendum to the Standard Form 1442.

(End of provision)

GROUP4-10-R-J041 00100-A2

ADDENDUM TO SECTION 00700, CONTRACT CLAUSES

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00700 ARE HEREBY PROVIDED:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 45 calendar days after the contractor receives the notice to proceed, (b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than * 110 calendar days after the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

* The total completion time of 110 calendar days includes the following:

Base 90 calendar days

Option A 12 calendar days

Option B 8 calendar days

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,442.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

GROUP4-10-R-J041 00700-A1

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general—

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing Index No.

Fort Pierce SPP Beach GROUP4-10-R-J041 G-02 Renourishment 2018, St. Lucie County, FL

GROUP4-10-R-J041 00700-A2

ADDENDUM TO SECTION 00800, SPECIAL REQUIREMENTS

THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00800 ARE HEREBY PROVIDED:

LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR

SUBCONTRACTORS

The award decision for this contract was based, in part, on an evaluation of the personnel and/or subcontractors the Contractor included in its proposal for the positions and/or items of subcontracted work identified at the end of this paragraph. The Contractor agrees these personnel and/or subcontractors will be employed as described in its proposal and no substitutes will be employed without prior written approval of the Contracting Officer or Administrative Contracting Officer. The Contractor further agrees that any proposed substitutes shall meet or exceed the qualifications of the original personnel and/or subcontractors. If the Contractor’s proposal did not name a subcontractor for an identified item of work, the Contractor will not be allowed to subcontract that item of work without prior approval of the Contracting Officer or Administrative Contracting Officer. The limitations described herein shall apply to the following:

plant and equipment.

(End of paragraph number 999.215-4001)

GROUP4-10-R-J041 00800-A1

NOTE NOTE NOTE

THIS PROJECT INCORPORATES STATEWIDE HEAVY DREDGING AND HOPPER

DREDGING WAGE DETERMINATIONS AS WELL AS THE HEAVY CONSTRUCTION

WAGE DETERMINATION FOR ST. LUCIE COUNTY, FL

THE HEAVY CONSTRUCTION WAGE DECISION MAY ONLY BE APPLIED TO

OPERATIONS OCCURRING ON LAND

EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE OF

$10.20 FOR 2017 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE DAVIS-

BACON ACT FOR ALL HOURS PERFORMED ON THE CONTRACT IN CALENDAR

YEAR 2017

IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE WAGE

DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:

FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY

CORPS OF ENGINEERS AT 904-232-3761

00800A-i

SECTION 00800A

WAGE DETERMINATIONS & OTHER ATTACHMENTS

LIST OF CONSTRUCTION CONTRACT ATTACHMENTS

NO. TITLE DATE NO. OF PAGES

1 NOTE 1

2 General Decision Number FL170002 02/03/2017 5 3 General Decision Number FL170003 01/06/2017 4 4 General Decision Number FL170179 08/04/2017 6

FL170002.txt[9/6/2017 12:12:17 PM]

General Decision Number: FL170002 02/03/2017 FL2

Superseded General Decision Number: FL20160002

State: Florida

Construction Type: Heavy Dredging

Counties: Florida Statewide.

Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 02/03/2017

* ENGI0025-002 10/01/2016

Rates Fringes

Dredging : (Hydraulic Dredges Over 20") CLASS A.....................$ 37.25 13.28+a CLASS B1....................$ 32.21 12.88+a CLASS B2....................$ 30.33 12.73+a CLASS C1....................$ 29.50 12.41+a CLASS C2....................$ 28.54 12.33+a CLASS D.....................$ 23.71 11.70+a Hydraulic Dredges Under 20" Cook........................$ 8.11 1.73+b Deckhand....................$ 7.77 1.73+b Engineer....................$ 9.59 1.73+b Launchman...................$ 8.19 1.73+b Leverman....................$ 10.03 1.73+b Mate........................$ 8.82 1.73+b Mess Cook...................$ 7.71 1.73+b Messman & Janitor...........$ 7.53 1.73+b Oiler & Fireman.............$ 8.11 1.73+b

Shoreman....................$ 7.82 1.73+b Spider Barge Operator.......$ 8.68 1.73+b Spill Barge Operator........$ 8.68 1.73+b Welder......................$ 9.79 1.73+b

CLASSIFICATIONS:

CLASS A: Leverman, Operator.

CLASS B1: Licensed Tug Operator over 1000 HP, Derrick Operator, Spider/Spill Barge Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician.

CLASS B2: Licensed Boat Operator, Certified Welder.

CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill Placer, Steward.

CLASS C2: Boat Operator.

CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor.

PREMIUMS: Additional 20% for hazardous material work

FOOTNOTE APPLICABLE TO ABOVE CRAFTS:

a. New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.

b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.

INCENTIVE PAY : (Add to Hourly Rate)

Operator (NCCCO License/Certification) $0.50; Licensed Tug Operator over 1000 HP (Assigned as Master) USCG licensed Master of Towing Vessels (MOTV) $1.00; Licensed Boat Operator (assigned as lead boat captain) USCG licensed boat operator $0.50; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $0.50; Oiler QMED and Tankerman endorsement (USCG) $0.50; All classifications Tankerman endorsement only (USCG) $0.50; Deckhand or Mater AB w/Lifeboatman only (USCG) $0.25; Welder (ABS certification) $0.50

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

FL170003.txt[9/6/2017 12:13:04 PM]

General Decision Number: FL170003 01/06/2017 FL3

Superseded General Decision Number: FL20160003

State: Florida

Construction Types: Heavy Dredging

Counties: Florida Statewide.

HOPPER DREDGE CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017

SUFL1993-010 05/24/1993

Rates Fringes

Self-Propelled Hopper Dredge Drag Tenders................$ 8.21

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

�

FL170179.txt[9/6/2017 12:13:26 PM]

General Decision Number: FL170179 08/04/2017 FL179

Superseded General Decision Number: FL20160179

State: Florida

Construction Type: Heavy

County: St Lucie County in Florida.

HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 08/04/2017

* ELEC0728-006 03/01/2017

Rates Fringes

ELECTRICIAN......................$ 30.50 11.43

ENGI0487-014 07/01/2013

Rates Fringes

OPERATOR: Crane All Tower Cranes Mobile, Rail, Climbers, Static- Mount; All Cranes with Boom Length 150 Feet & Over (With or without jib) Friction, Hydraulic, Electric or Otherwise;

Cranes 150 Tons & Over;

Cranes with 3 Drums (When 3rd drum is rigged for work); Gantry & Overhead Cranes; Hydraulic Cranes

Over 25 Tons but not more than 50 Tons;

Hydraulic/Friction Cranes;

& All Types of Flying Cranes; Boom Truck..........$ 29.05 8.80 Cranes with Boom Length Less than 150 Feet (With or without jib); Hydraulic Cranes 25 Tons & Under, & Over 50 Tons (With Oiler);

Boom Truck..................$ 28.32 8.80 OPERATOR: Drill.................$ 25.80 8.80 OPERATOR: Oiler.................$ 22.99 8.80

IRON0402-003 10/01/2015

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 22.34 10.15

LABO1652-004 06/01/2013

Rates Fringes

LABORER: Grade Checker..........$ 14.50 4.92

PAIN0452-007 08/01/2014

Rates Fringes

PAINTER: Brush, Roller and Spray............................$ 19.50 8.83

SUFL2009-175 06/24/2009

Rates Fringes

CARPENTER, Includes Form Work....$ 15.50 0.00

CEMENT MASON/CONCRETE FINISHER...$ 16.46 0.00

LABORER: Common or General......$ 10.52 0.00

LABORER: Landscape..............$ 7.25 0.00

LABORER: Pipelayer..............$ 13.93 0.00

LABORER: Power Tool Operator (Hand Held Drills/Saws, Jackhammer and Power Saws Only)............................$ 10.63 2.20

OPERATOR: Asphalt Paver.........$ 11.59 0.00

OPERATOR: Backhoe Loader Combo............................$ 16.10 2.44

OPERATOR: Backhoe/Excavator.....$ 21.70 0.00

OPERATOR: Bulldozer.............$ 16.07 0.00

OPERATOR: Grader/Blade..........$ 16.00 2.84

OPERATOR: Loader................$ 14.11 0.00

OPERATOR: Mechanic..............$ 14.32 0.00

OPERATOR: Roller................$ 11.25 0.00

OPERATOR: Scraper...............$ 11.00 1.74

OPERATOR: Trackhoe..............$ 20.92 5.50

OPERATOR: Tractor...............$ 10.54 0.00

TRUCK DRIVER, Includes Dump Truck............................$ 10.60 0.00

TRUCK DRIVER: Lowboy Truck......$ 12.73 0.00

TRUCK DRIVER: Off the Road Truck............................$ 12.21 1.97

TRUCK DRIVER: Servicer..........$ 12.00 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

General Decision Number: FL170002 02/03/2017 FL2

Superseded General Decision Number: FL20160002

State: Florida

Construction Type: Heavy Dredging

Counties: Florida Statewide.

Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 02/03/2017

* ENGI0025-002 10/01/2016

Rates Fringes

Dredging : (Hydraulic Dredges Over 20") CLASS A.....................$ 37.25 13.28+a CLASS B1....................$ 32.21 12.88+a CLASS B2....................$ 30.33 12.73+a…