This is a Preliminary Construction Cost Estimate document prepared for the Grissom Parkway Widening Project in Florida, which involves widening an existing two-lane arterial roadway to a four-lane divided facility with a median. The project spans approximately 1.48 miles and is divided into three primary sections: a Suburban Section, a Rural Section, and an Urban Section extending from Port St. John Parkway to north of Fay Boulevard. The scope of work includes roadway widening, closed drainage system installation, traffic signal implementation in the Urban Section, sidewalk construction, turn lane development, and various ancillary improvements such as lighting, signage, and environmental controls. The estimate encompasses detailed line-item costs for clearing and grubbing, excavation, embankment work, asphalt paving, drainage infrastructure including pipes and inlets, curb and gutter installation, concrete sidewalk construction, utility conduit placement, and roadway signalization. The document is dated November 20, 2022, and reflects preliminary cost projections intended for design phase planning purposes.

The total preliminary construction cost for the project is $13,927,870, comprising a subtotal of $11,606,558 with an additional 20 percent contingency allowance of $2,321,312. Cost breakdowns by section are as follows: Suburban Section at $3,534,972, Rural Section at $1,221,516, Urban Section (including two traffic signals) at $4,287,082, Turn Lanes at $903,461, and Sidewalk costs at $1,659,528. The estimate was developed using FDOT long-range estimating methodologies and includes comprehensive unit pricing for labor, materials, and equipment across multiple construction disciplines. The document explicitly notes that costs will be updated as design progresses and drainage evaluations are completed, indicating this estimate serves as a baseline for budget planning and phased construction approach considerations aligned with the project's anticipated two-phase minimum implementation schedule.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX FIVE:

PRELIMINARY CONSTRUCTION

COST ESTIMATE

Date: November 20, 2022

Suburban Section $3,534,972

Rural Section $1,221,516

Urban Section (includes 2-signals) $4,287,082

Turn Lanes $903,461

Sidewalk Cost $1,659,528

Subtotal Cost $11,606,558

Contingency 20% $2,321,312

Total Cost $13,927,870

FDOT long range of estimate was utilized to perform a preliminary cost estimate for this phase of the project

Cost Estimate will be updated as we move forward with the design and the drainage has been evaluated

Preliminary Construction Cost Estimate

Grissom Parkway Widening Project from Port St. John Parkway to North of Fay Blvd.

102-1 MAINTENANCE OF TRAFFIC 1.00 LS $448,456.46 $448,456.46

101-1 MOBILIZATION 1.00 LS $493,302.11 $493,302.11

104-10-3 SEDIMENT BARRIER 10,560.00 LF $1.70 $17,952.00

104-11 FLOATING TURBIDITY BARRIER 250.00 LF $8.90 $2,225.00

104-12 STAKED TURBIDITY BARRIER- NYL

REINF PVC

250.00 LF $7.50 $1,875.00

104-15 SOIL TRACKING PREVENTION

DEVICE

1.00 EA $2,400.00 $2,400.00

104-18 INLET PROTECTION SYSTEM 53.00 EA $114.00 $6,042.00

107-1 LITTER REMOVAL 1.20 AC $22.00 $26.40

107-2 MOWING 1.20 AC $35.00 $42.00

110-1-1 CLEARING & GRUBBING 7.06 AC $19,000.00 $134,140.00

120-1 REGULAR EXCAVATION 9,680.00 CY $7.10 $68,728.00

120-6 EMBANKMENT 81,040.18 CY $8.50 $688,841.53

160-4 TYPE B STABILIZATION 21,800.53 SY $5.30 $115,542.81

285-709 OPTIONAL BASE,BASE GROUP 09 18,773.33 SY $19.00 $356,693.27

327-70-8 MILLING EXIST ASPH PAVT,2 1/2"

AVG DEPTH

18,773.33 SY $2.40 $45,055.99

334-1-54 SUPERPAVE ASPH CONC, TRAF D,

PG76-22

3,097.60 TN $100.00 $309,760.00

337-7-83 ASPH CONC FC,TRAFFIC C,FC-

12.5,PG 76-22

3,003.74 TN $110.00 $330,411.40

425-1-351 INLETS, CURB, TYPE P-5, 36.00 EA $5,200.00 $187,200.00

425-1-451 INLETS, CURB, TYPE J-5, 10.00 EA $7,000.00 $70,000.00

425-1-521 INLETS, DT BOT, TYPE C, 5.00 EA $4,100.00 $20,500.00

425-1-541 INLETS, DT BOT, TYPE D, 1.00 EA $4,400.00 $4,400.00

425-2-41 MANHOLES, P-7, 5.00 EA $5,000.00 $25,000.00

425-2-71 MANHOLES, J-7, 1.00 EA $8,600.00 $8,600.00

430-175-112 PIPE CULV, OPT MATL, ROUND,

12"S/CD

2,328.00 LF $83.00 $193,224.00

430-175-130 PIPE CULV, OPT MATL, ROUND,

30"S/CD

208.00 LF $120.00 $24,960.00

430-175-142 PIPE CULV, OPT MATL, ROUND,

42"S/CD

5,056.00 LF $170.00 $859,520.00

430-175-154 PIPE CULV, OPT MATL, ROUND,

54"S/CD

200.00 LF $480.00 $96,000.00

430-515-100 STRAIGHT CONC ENDW 15",

SINGLE, 0 ROUND

1.00 EA $3,200.00 $3,200.00

430-530-100 STRAIGHT CONC ENDW 30",

SINGLE, 0 ROUND

1.00 EA $4,600.00 $4,600.00

430-542-100 STRAIGHT CONC ENDW 42",

SINGLE, 0 ROUND

2.00 EA $8,300.00 $16,600.00

430-554-100 STRAIGHT CONC ENDW 54",

SINGLE, 0 ROUND

2.00 EA $12,000.00 $24,000.00

520-1-10 CONCRETE CURB & GUTTER,

TYPE F

21,120.00 LF $24.00 $506,880.00

Description: Widen 2 Lane Rural Arterial to 4 Lane Divided Urban Arterial and

Closed Drainage System

Grissom Parkway Preliminary Cost Estimate for Urban Section section from the beginning of

Bridge Road to north of Fay Blvd. Approximate length 0.55 miles

522-1 CONCRETE SIDEWALK AND

DRIVEWAYS, 6"

2,933.33 SY $42.00 $123,199.86

550-60-234 FENCE GATE,TYP

B,SLIDE/CANT,18.1-20'OPEN

1.00 EA $4,300.00 $4,300.00

570-1-1 PERFORMANCE TURF 384.00 SY $1.20 $460.80

570-1-2 PERFORMANCE TURF, SOD 18,365.60 SY $2.80 $51,423.68

630-2-11 CONDUIT, F& I, OPEN TRENCH 5,280.00 LF $8.80 $46,464.00

630-2-12 CONDUIT, F& I, DIRECTIONAL

BORE

689.00 LF $22.00 $15,158.00

635-2-11 PULL & SPLICE BOX, F&I, 13" X 24" 21.00 EA $750.00 $15,750.00

700-1-11 SINGLE POST SIGN, F&I GM, 24.00 AS $350.00 $8,400.00

700-1-12 SINGLE POST SIGN, F&I GM, 12-20

SF

2.00 AS $1,000.00 $2,000.00

700-2-14 MULTI- POST SIGN, F&I GM, 31-50

SF

2.00 AS $4,700.00 $9,400.00

700-2-15 MULTI- POST SIGN, F&I GM, 51-100

SF

2.00 AS $6,400.00 $12,800.00

706-1-1 RAISED PAVMT MARK, TYPE B W/O

FINAL SURF

405.00 EA $4.10 $1,660.50

710-11-101 PAINTED PAVT

MARK,STD,WHITE,SOLID,6"

8.00 GM $1,000.00 $8,000.00

710-11-131 PAINTED PAVT

MARK,STD,WHITE,SKIP, 6"

4.00 GM $470.00 $1,880.00

715-1-13 LIGHTING CONDUCTORS, F&I,

INSUL, NO.4-2

17,907.00 LF $2.00 $35,814.00

715-4-13 LIGHT POLE COMPLETE, F&I- STD,

40'

21.00 EA $5,500.00 $115,500.00

715-500-1 POLE CABLE DIST SYS,

CONVENTIONAL

21.00 EA $580.00 $12,180.00

711-15-131 THERMOPLASTIC, STD-OP, WHITE,

SKIP, 6"

2.00 GM $1,600.00 $3,200.00

715-1-13 LIGHTING CONDUCTORS, F&I,

INSUL, NO.4-2

19,284.00 LF $2.00 $38,568.00

715-4-13 LIGHT POLE COMPLETE, F&I- STD,

40'

35.00 EA $5,500.00 $192,500.00

715-500-1 POLE CABLE DIST SYS,

CONVENTIONAL

35.00 EA $580.00 $20,300.00

999-999-9 SIGNALIZATION 2.00 EA $680000.00 $1,360,000

$7,145,136.81

For project length 0.55 miles $4,287,082.09

Pay Item Description Total Quantity Unit Weighted Avg.

Unit Price

Total Amount

102-1 MAINTENANCE OF TRAFFIC 1.00 LS $265,662.41 $265,662.41

101-1 MOBILIZATION 1.00 LS $292,228.65 $292,228.65

104-10-3 SEDIMENT BARRIER 13,728.00 LF $1.70 $23,337.60

104-11 FLOATING TURBIDITY BARRIER 350.00 LF $8.90 $3,115.00

104-12 STAKED TURBIDITY BARRIER- NYL

REINF PVC

350.00 LF $7.50 $2,625.00

104-15 SOIL TRACKING PREVENTION

DEVICE

1.00 EA $2,400.00 $2,400.00

107-1 LITTER REMOVAL 2.40 AC $22.00 $52.80

107-2 MOWING 2.40 AC $35.00 $84.00

110-1-1 CLEARING & GRUBBING 14.12 AC $19,000.00 $268,280.00

120-1 REGULAR EXCAVATION 19,360.00 CY $7.10 $137,456.00

120-6 EMBANKMENT 54,493.51 CY $8.50 $463,194.84

160-4 TYPE B STABILIZATION 25,813.33 SY $5.30 $136,810.65

285-704 OPTIONAL BASE,BASE GROUP 04 6,253.87 SY $15.00 $93,808.05

285-709 OPTIONAL BASE,BASE GROUP 09 14,467.20 SY $19.00 $274,876.80

327-70-1 MILLING EXIST ASPH PAVT, 1" AVG

DEPTH

5,866.67 SY $2.40 $14,080.01

327-70-15 MILLING EXIST ASPH PAVT,2 3/4"

AVG DEPTH

14,080.00 SY $2.40 $33,792.00

334-1-53 SUPERPAVE ASPH CONC, TRAF C,

PG76-22

2,968.54 TN $100.00 $296,854.00

334-1-54 SUPERPAVE ASPH CONC, TRAF D,

PG76-22

2,323.20 TN $100.00 $232,320.00

337-7-25 ASPH CONC FC,INC BIT,FC-5,PG76-

1,188.36 TN $130.00 $154,486.80

425-1-541 INLETS, DT BOT, TYPE D, 1.00 EA $4,400.00 $4,400.00

425-2-71 MANHOLES, J-7, 1.00 EA $8,600.00 $8,600.00

430-174-124 PIPE CULV, OPT MATL,

ROUND,24"SD

800.00 LF $98.00 $78,400.00

430-175-130 PIPE CULV, OPT MATL, ROUND,

30"S/CD

168.00 LF $120.00 $20,160.00

430-175-142 PIPE CULV, OPT MATL, ROUND,

42"S/CD

56.00 LF $170.00 $9,520.00

430-175-154 PIPE CULV, OPT MATL, ROUND,

54"S/CD

200.00 LF $480.00 $96,000.00

430-530-100 STRAIGHT CONC ENDW 30",

SINGLE, 0 ROUND

2.00 EA $4,600.00 $9,200.00

430-542-100 STRAIGHT CONC ENDW 42",

SINGLE, 0 ROUND

2.00 EA $8,300.00 $16,600.00

430-554-100 STRAIGHT CONC ENDW 54",

SINGLE, 0 ROUND

2.00 EA $12,000.00 $24,000.00

430-984-129 MITERED END SECT, OPTIONAL

RD, 24" SD

40.00 EA $1,800.00 $72,000.00

546-72-1 GROUND-IN RUMBLE STRIPS, 16" 2.00 GM $610.00 $1,220.00

Grissom Parkway Preliminary Cost Estimate for Rural Section from the beginning of the Project to Souh of Port St Johns Parkway

Description: Widen Existing 2 Lane Arterial to 4 Lane Divided; Resurface Existing 2 Lanes; 5' Paved

Shoulders.

550-10-220 FENCING, TYPE B, 5.1-6.0',

STANDARD

1,180.00 LF $21.00 $24,780.00

550-60-234 FENCE GATE,TYP

B,SLIDE/CANT,18.1-20'OPEN

1.00 EA $4,300.00 $4,300.00

570-1-2 PERFORMANCE TURF, SOD 22,117.34 SY $2.80 $61,928.55

700-1-11 SINGLE POST SIGN, F&I GM, 12.00 AS $350.00 $4,200.00

700-1-12 SINGLE POST SIGN, F&I GM, 12-20

SF

34.00 AS $1,000.00 $34,000.00

700-1-50 SINGLE POST SIGN, RELOCATE 2.00 AS $190.00 $380.00

700-1-60 SINGLE POST SIGN, REMOVE 12.00 AS $34.00 $408.00

700-2-14 MULTI- POST SIGN, F&I GM, 31-50

SF

4.00 AS $4,700.00 $18,800.00

700-2-60 MULTI- POST SIGN, REMOVE 2.00 AS $700.00 $1,400.00

706-1-1 RAISED PAVMT MARK, TYPE B W/O

FINAL SURF

540.00 EA $4.10 $2,214.00

710-11-101 PAINTED PAVT

MARK,STD,WHITE,SOLID,6"

4.00 GM $1,000.00 $4,000.00

710-11-131 PAINTED PAVT

MARK,STD,WHITE,SKIP, 6"

2.00 GM $470.00 $940.00

711-15-101 THERMOPLASTIC, STD-OP, WHITE,

SOLID, 6"

4.00 GM $4,600.00 $18,400.00

711-15-131 THERMOPLASTIC, STD-OP, WHITE,

SKIP, 6"

2.00 GM $1,600.00 $3,200.00

$3,214,515.16

For project length 0.38 miles $1,221,515.76

Pay Item Description Total Quantity Unit Weighted

Avg.

Total Amount

102-1 MAINTENANCE OF TRAFFIC 1.00 LS $410,960.71 $410,960.71

101-1 MOBILIZATION 1.00 LS $452,056.78 $452,056.78

104-10-3 SEDIMENT BARRIER 13,728.00 LF $1.70 $23,337.60

104-11 FLOATING TURBIDITY BARRIER 250.00 LF $8.90 $2,225.00

104-12 STAKED TURBIDITY BARRIER- NYL

REINF PVC

250.00 LF $7.50 $1,875.00

104-15 SOIL TRACKING PREVENTION

DEVICE

1.00 EA $2,400.00 $2,400.00

107-1 LITTER REMOVAL 1.90 AC $22.00 $41.80

107-2 MOWING 1.90 AC $35.00 $66.50

110-1-1 CLEARING & GRUBBING 14.62 AC $19,000.00 $277,780.00

120-1 REGULAR EXCAVATION 24,200.00 CY $7.10 $171,820.00

120-6 EMBANKMENT 96,444.09 CY $8.50 $819,774.77

160-4 TYPE B STABILIZATION 51,226.56 SY $5.30 $271,500.77

285-704 OPTIONAL BASE,BASE GROUP 04 6,253.87 SY $15.00 $93,808.05

285-709 OPTIONAL BASE,BASE GROUP 09 36,541.12 SY $19.00 $694,281.28

334-1-13 SUPERPAVE ASPHALTIC CONC,

TRAFFIC C

6,217.79 TN $97.00 $603,125.63

337-7-25 ASPH CONC FC,INC BIT,FC-5,PG76-

1,663.79 TN $130.00 $216,292.70

425-1-351 INLETS, CURB, TYPE P-5, 36.00 EA $5,200.00 $187,200.00

425-1-451 INLETS, CURB, TYPE J-5, 10.00 EA $7,000.00 $70,000.00

425-1-521 INLETS, DT BOT, TYPE C, 5.00 EA $4,100.00 $20,500.00

425-1-541 INLETS, DT BOT, TYPE D, 1.00 EA $4,400.00 $4,400.00

425-2-41 MANHOLES, P-7, 5.00 EA $5,000.00 $25,000.00

425-2-71 MANHOLES, J-7, 1.00 EA $8,600.00 $8,600.00

430-175-112 PIPE CULV, OPT MATL, ROUND,

12"S/CD

2,328.00 LF $83.00 $193,224.00

430-175-130 PIPE CULV, OPT MATL, ROUND,

30"S/CD

208.00 LF $120.00 $24,960.00

430-175-142 PIPE CULV, OPT MATL, ROUND,

42"S/CD

5,056.00 LF $170.00 $859,520.00

430-175-154 PIPE CULV, OPT MATL, ROUND,

54"S/CD

200.00 LF $480.00 $96,000.00

Description: Widen 2 Lane Rural Arterial to 4 Lane Divided Urban Arterial with 22' Median, and

Closed Drainage System

Grissom Parkway Preliminary Cost Estimate for Urban Section section from Port St

Johns Parkway of Bridge Road to north of Fay Blvd. Approximate length 0.55 miles

430-515-100 STRAIGHT CONC ENDW 15",

SINGLE, 0 ROUND

1.00 EA $3,200.00 $3,200.00

430-530-100 STRAIGHT CONC ENDW 30",

SINGLE, 0 ROUND

1.00 EA $4,600.00 $4,600.00

430-542-100 STRAIGHT CONC ENDW 42",

SINGLE, 0 ROUND

2.00 EA $8,300.00 $16,600.00

430-554-100 STRAIGHT CONC ENDW 54",

SINGLE, 0 ROUND

2.00 EA $12,000.00 $24,000.00

520-1-10 CONCRETE CURB & GUTTER,

TYPE F

21,120.00 LF $24.00 $506,880.00

522-1 CONCRETE SIDEWALK AND

DRIVEWAYS, 6"

2,933.33 SY $42.00

550-60-234 FENCE GATE,TYP

B,SLIDE/CANT,18.1-20'OPEN

1.00 EA $4,300.00 $4,300.00

570-1-1 PERFORMANCE TURF 384.00 SY $1.20 $460.80

570-1-2 PERFORMANCE TURF, SOD 18,365.60 SY $2.80 $51,423.68

630-2-11 CONDUIT, F& I, OPEN TRENCH 5,280.00 LF $8.80 $46,464.00

630-2-12 CONDUIT, F& I, DIRECTIONAL

BORE

689.00 LF $22.00 $15,158.00

635-2-11 PULL & SPLICE BOX, F&I, 13" X 24" 21.00 EA $750.00 $15,750.00

700-1-11 SINGLE POST SIGN, F&I GM, 24.00 AS $350.00 $8,400.00

700-1-12 SINGLE POST SIGN, F&I GM, 12-20

SF

2.00 AS $1,000.00 $2,000.00

700-2-14 MULTI- POST SIGN, F&I GM, 31-50

SF

2.00 AS $4,700.00 $9,400.00

700-2-15 MULTI- POST SIGN, F&I GM, 51-100

SF

2.00 AS $6,400.00 $12,800.00

706-1-1 RAISED PAVMT MARK, TYPE B W/O

FINAL SURF

405.00 EA $4.10 $1,660.50

710-11-101 PAINTED PAVT

MARK,STD,WHITE,SOLID,6"

8.00 GM $1,000.00 $8,000.00

710-11-131 PAINTED PAVT

MARK,STD,WHITE,SKIP, 6"

4.00 GM $470.00 $1,880.00

715-1-13 LIGHTING CONDUCTORS, F&I,

INSUL, NO.4-2

17,907.00 LF $2.00 $35,814.00

715-4-13 LIGHT POLE COMPLETE, F&I- STD,

40'

21.00 EA $5,500.00 $115,500.00

715-500-1 POLE CABLE DIST SYS,

CONVENTIONAL

21.00 EA $580.00 $12,180.00

711-15-131 THERMOPLASTIC, STD-OP, WHITE,

SKIP, 6"

2.00 GM $1,600.00 $3,200.00

715-1-13 LIGHTING CONDUCTORS, F&I,

INSUL, NO.4-2

19,284.00 LF $2.00 $38,568.00

715-4-13 LIGHT POLE COMPLETE, F&I- STD,

40'

35.00 EA $5,500.00 $192,500.00

715-500-1 POLE CABLE DIST SYS,

CONVENTIONAL

35.00 EA $580.00 $20,300.00

$6,427,221.57

For project length 0.55 miles $3,534,971.86

Pay Items

Unit Price

Total Amount

102-1 MAINTENANCE OF TRAFFIC 1.00 LS $3,060 $3,060

101-1 MOBILIZATION 1.00 LS $15,605 $15,605

110-1-1 CLEARING & GRUBBING 1.25 AC $19,000.00 $23,750

120-1 REGULAR EXCAVATION 322.66 CY $7.10 $2,291

522-1 CONCRETE SIDEWALK AND

DRIVEWAYS, 6"

11,640.00 SY $45.00 $523,800

570-1-1 PERFORMANCE TURF 3,121.07 SY $1.20 $3,745

$572,251

$1,659,528

Description: Sidewalk construction; 8' one side, 6 inch depth

Grissom Parkway Sidewalk, from Port St. John to Fay Blvd, approximately2.48 mile length.

Sidewalk Cost (per Mile)

Sidewalk Estimated Cost

Unit Price

Total Amount

102-1 MAINTENANCE OF TRAFFIC 1.00 LS $114,177.08 $114,177.08

101-1 MOBILIZATION 1.00 LS $125,594.79 $125,594.79

120-6 EMBANKMENT 20,417.62 CY $8.90 $181,716.82

160-4 TYPE B STABILIZATION 7,040.00 SY $5.30 $37,312.00

285-709 OPTIONAL BASE,BASE GROUP 09 7,427.20 SY $19.00 $141,116.80

334-1-54 SUPERPAVE ASPH CONC, TRAF D,

PG76-22

1,161.60 TN $100.00 $116,160.00

337-7-83 ASPH CONC FC,TRAFFIC C,FC-

12.5,PG 76-22

563.20 TN $110.00 $61,952.00

430-175-124 PIPE CULV, OPT MATL, ROUND,

24"S/CD

216.00 LF $97.00 $20,952.00

706-1-1 RAISED PAVMT MARK, TYPE B W/O

FINAL SURF

132.00 EA $4.10 $541.20

For 1.13 miles total length for turn lanes along the corridor $903,461

( Refer to LTG traffic Study for turn lanes length

Description: Construction cost of turn-lanes along the corridor

Turn Lane Total Cost (per Mile) $799,523

Turn Lane Estimated Cost

File details come from the government source that posted it. Updated .