This is Addendum No. 5 to a solicitation issued by the Town of Glastonbury, Connecticut, for the Center Green Fountain Updates project (GL-2027-10). The addendum revises the original bid due date from September 9, 2026 at 11:00 A.M. to September 10, 2026 at 11:00 A.M. The project encompasses the replacement of an existing fountain, fountain filter, pump system, and electrical equipment currently housed in an underground vault, with relocation of the control and electrical system to an above-ground enclosure to address accessibility, moisture intrusion, and maintenance concerns. The scope includes mechanical, electrical, and plumbing modifications along with site improvements. A non-mandatory pre-bid meeting was held on August 17, 2026 at 10:00 A.M. at the Center Green Fountain location.
The addendum addresses Alternate #3 per Drawing E2.00, requiring bidders to provide a separate "add alternate" price for providing GFI receptacles at existing light poles. The work specified includes removing all existing wiring serving site lighting and providing new wiring (2#10, #10G for light pole receptacles and 2#10, #10G for site lighting utilizing existing conduit), totaling four 20-ampere single-phase receptacle circuits and three 20-ampere single-phase site lighting circuits. Bidders must acknowledge this addendum on the Bid Proposal Page (BP-1). The successful bidder will be required to provide performance and labor and material payment bonds in the full amount of the contract price, with bid security in the form of a Bid Bond certified at not less than 10 percent of the base bid. The project is subject to Connecticut prevailing wage requirements under General Statutes Section 31-53.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
END OF TEXT
TOWN OF GLASTONBURY
GL-2027-10
CENTER GREEN FOUNTAIN UPDATES
ADDENDUM NO. 5
September 9, 2026
Bid Due Date: September 9, 2026 @ 11:00 A.M.
REVISED BID DUE DATE: September 10, 2026
The attention of bidders submitting proposals for the above-referenced project is called to the following Addendum to the specifications. The items set forth herein, whether of omission, addition, substitution or other change, are all to be included in and form a part of the proposed Contract Documents for the work. Bidders shall acknowledge this Addendum on the Bid Proposal Page (BP-1).
NOTIFICATION TO BIDDERS:
Please note: The Bid due date and time have been changed to September 10, 2026 at 11 A.M
Question 1: Please provide direction on how to address Alternate #3 per Drawing E2.00- Provide GFI receptacles at existing light poles.
Answer: Provide separate “add alternate” price for providing GFI receptacles at the existing light poles as shown on drawings. Refer to Add Alternate note on E2.00: “PROVIDE
GFI RECEPTACLE AT EXISTING LIGHT POLES. REMOVE ALL EXISTING WIRING
SERVING SITE LIGHTING. PROVIDE 2#10,#10G FOR NEW LIGHT POLE
RECEPTACLES AND 2#10,#10G FOR SITE LIGHTING UTILIZING EXISTING CONDUIT.
PROVIDE TOTAL OF (4) 20A-1P RECEPTACLE CIRCUITS AND (3) 20A-1P SITE
LIGHTING CIRCUITS.”