This is a Geotechnical Report prepared by Larry M. Jacobs & Associates, Inc. for Escambia County, Florida, regarding the Beulah Road Widening and Resurfacing project. The report, signed and sealed by Principal Engineer Keith V. Jacobs on May 10, 2025, was prepared for HDR, Inc. (Michael Collins, PE) and documents subsurface conditions, pavement analysis, and construction recommendations for approximately 1.4 miles of Beulah Road and a portion of Kingsfield Road in Escambia County. The investigation included pavement condition assessments, soil borings to a depth of 6 feet, and groundwater evaluations to inform design and construction planning for the road rehabilitation project that will include full depth pavement asphalt rebuild, turn lane widening, shoulder additions, ditch reconstruction, and the installation of five 60-inch pipes under Beulah Road.
The geotechnical investigation revealed that Beulah Road is in poor condition with extensive rutting, alligator cracking, and widespread pavement distress, indicating structurally inadequate base and subgrade materials for current traffic loading. Subsurface conditions consist of variable base materials (sand-clay, graded aggregate base, or no discernable base) ranging from 3 to 19 inches thick, overlying silty and clayey sands with medium dense to dense soil conditions in the upper portions transitioning to loose soils at depth. Groundwater was not encountered in Beulah Road borings but was present at 2 feet depth in Kingsfield Road borings. The report recommends full depth asphalt rebuild for Beulah Road due to poor subgrade conditions and heavy traffic loading, with mill and overlay acceptable for Kingsfield Road. Critical construction recommendations include removal and replacement of wet, uncompactable soils (Strata 3 and 5) with Type B stabilized materials, removal of clayey Stratum 7 soils from the top 18 inches of subgrade in widening areas, and phased construction of widening sections to manage moisture conditions and allow adequate compaction during anticipated rainfall periods.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This document has been electronically signed and sealed by Keith V. Jacobs (license # 66577) on May 10, 2025. Printed copies of this document are not considered signed and sealed, and the signature must be verified on any electronic copies.
Beulah Road Widening and Resurfacing Escambia County, Florida LMJ File 24-372 May 10, 2025
Prepared for
Mr. Brad Collins, PE
Michael.Collins@hdrinc.com
Prepared by
Larry M. Jacobs & Associates, Inc.
328 East Gadsden Street, Pensacola, Florida 32501 FL Certificate of Authorization #2184
Keith V. Jacobs, PE Principal Engineer FL Reg. #66577 mailto:Michael.Collins@hdrinc.com
Beulah Road Widening and Resurfacing LMJ Project 24-372 E May 10, 2025
Roadway Conditions Summary ▼ Beaulah Road appeared to be in generally poor condition with rutting, widespread alligator cracking, and regular longitudinal and block cracking. Pop outs, edge failures, and patching were also observed in some areas. A summary of the pavement conditions is here.
▼ Kingsfield Road appeared to be generally in good condition, and we understand that Kingsfield Road was recently overlain. Edge cracking and minor rutting was observed near B-27, and the existing asphalt was worn near the intersection with Beulah Road.
▼ Standing water was present near the intersection of Beulah Road and Kingsfield Road and on the sides of the road south of B-14 at the time of our site visits.
▼ The asphalt cores were 3-12 inches thick with most cores between 3-4 inches thick.
Borings B-9, B-13, B-17, B-19, and B-21 had 6¾-12 inches of asphalt.
Subsurface Conditions Summary ▼ The base material under the existing asphalt varied and included sand-clay type base
(Stratum 1), Graded Aggregate Base (Stratum 2), or no discernable base (Strata 3 and 4).
The base thickness also varied between 3-19 inches.
▼ Directly below the pavement materials or topsoil, most of the borings encountered slightly silty and silty sand (Strata 3 and 4) and clayey silty sand (Stratum 5) to the bottom of the borings at 6 feet.
▼ Layers of clayey sand and sandy clay (Stratum 7) were encountered in B-10 through B-20, B-22, and B-29 beginning at 1.5-2 feet below the pavement or existing grade in most of these borings except B-10, B-16, and B-20 where these layers were in the top foot.
▼ Traces of iron rock, mica, and gravel were encountered in the borings, and B-23 had a 3-inch layer of iron rock on the bottom.
▼ The soil density under the roadway was typically medium dense to dense in the upper 2-4 feet over loose and medium dense and some dense soils to the bottom of the borings at 6 feet. Boring B-29 had a very loose layer from 4 feet to the bottom of this boring at 6 feet.
▼ The soil density in the widening areas was generally loose in the upper 2 feet over medium dense and loose conditions or medium stiff to very hard conditions.
Groundwater Conditions Summary ▼ Groundwater did not appear to be encountered in the 6-foot borings drilled on Beulah Road at the time of drilling, although determining an accurate groundwater level in firm clayey and clay soils is not practical without piezometers.
▼ Groundwater was encountered in B-29 and B-30, drilled on Kingsfield Road, at a depth of 2 feet below existing grade, and the other Kingsfield borings did not encounter water.
▼ The borings encountered conditions that could trap or perch groundwater on the firm Strata 5 and 7 soils where overlain by the better draining Stratum 4 soils.
▼ Groundwater and perched water levels will vary with local rainfall and changes in site grading or drainage characteristics and may be different at other times.
Conditions Summary
Pavement Recommendations for Beulah Road ▼ The existing asphalt is in poor condition and the alligator cracking and rutting indicates that the base and subgrade are structurally inadequate for the loading on Beulah Road.
▼ Several options were considered including milling and overlaying, which has proven to be ineffective, full rebuild, Full Depth Reclamation (FDR), and full depth asphalt rebuild.
▼ Given the heavy traffic loading, poor subgrade soils in a portion of the project, and the benefit of speed (temporary lane can be avoided), full depth asphalt rebuild appears to be the best option for this project.
Pavement Recommendations for Kingsfield Road ▼ Kingsfield Road had been recently overlain and was in good condition at the time of our evaluation with 3½-3¾ inches of Asphaltic Concrete within the project limits.
▼ It appears that Kingsfield Road can be milled and overlain.
Widening Recommendations ▼ Strata 3 and 5 soils drain slowly, retain excess moisture, and are difficult to dry and compact if they are too wet, and this is a concern for earthwork.
▼ If construction occurs during a rainy period, widespread removal, and replacement of wet, uncompactable Strata 3 and 5 soils may be needed.
▼ We recommend constructing widening areas in sections that can be managed and paved in a timely manner when rainfall is anticipated.
▼ Strata 3 and 5 soils (>15% fines) are suitable for subgrade if they are not overly wet. Since time and space needed for drying these soil types is not expected to be available, soils that are too wet to be compacted will need to be removed and replaced with Type B soils.
▼ Stratum 7 (clayey) soils are normally not desirable as pavement subgrade because when exposed to water, they can lose strength and have the potential to swell.
▼ We recommend removing Stratum 7 soils where present in the top 18 inches of subgrade in widening areas and replacing them with Type B stabilized subgrade.
▼ Stratum 4 soils (<15% fines) should be relatively easy to work and are suitable for subgrade.
Note: The above summary is an overview of the report and should not be used by itself for planning, design, and/or construction. See the relevant sections for further details.
Recommendations Summary
Project Information The site is Beulah Road in Escambia County, Florida from roughly 600 feet north of the north landfill entrance and south to roughly 900 feet south of the intersection with Kingsfield Road.
The project also includes Kingsfield Road from the intersection at Beulah Road south and east for roughly 1,610 feet. Based on the provided information, the project includes widening the existing 10-foot lanes to 12-foot lanes with a paved shoulder. The paved shoulder on Beulah Road is planned to be 5 feet, except for the south end of the project (Station 137+18 to 142), which has an existing curb and gutter. The paved shoulder on Kingsfield Road is planned to be 2 feet wide. Most of the project is planned to match existing grade, but some cuts and fills generally 1-2 feet are planned mostly to cut new swales or fill in existing ones. A portion of the roadway at the 90-curve is planned to be overbuilt up to 7½ feet to provide superelevation.
Pavement Evaluation Our engineering staff performed a visual evaluation of the existing pavement conditions. The asphalt was cored at 19 locations, and the cores were collected and measured in our laboratory for thickness and were photographed. Standard Penetration Test (SPT) borings were drilled at each of the core locations in the roadway and on alternating sides in the widening areas to a depth of 6 feet. We also saw cut the existing roadway at random locations to collect samples of the base and subgrade for laboratory LBR testing. Photos of the cores can be found here, and the boring logs can be found here.
Existing Pavement Conditions
Beaulah Road appeared to be in generally poor condition with rutting, widespread alligator cracking, and regular longitudinal and block cracking. Pop outs, edge failures, and patching were also observed in some areas. The asphalt thickness was erratic and varied between 3- 12 inches thick with most cores between 3-4 inches. The asphalt consisted of multiple overlays with layers of sand asphalt in some of the cores. Borings B-9, B-13, B-17, B-19, and B-21 had 6¾-12 inches of asphalt (including sand asphalt). The pavement was generally in worse condition for the northbound lane south of the landfill and for the southbound lane north of the landfill which is to be expected. The pavement was in worst condition between borings B-9 and B-22, and this area had more intense cracking, and the cracks appeared to be full depth, wider, and worn more at the surface indicating water being trapped in these cracks. Most of the pop outs and patching was observed in this area.
We noted a section of the northbound lane that had been rebuilt near B-19, and LMJ performed work in this area in 2015 after the pavement had been recently overlain. In 2015, in the area near B-19 and toward B-20, LMJ observed signs of shoving, likely due to poor tack coat on the original milled surface. The contractor elected to rebuild this area using 12 inches of total asphalt that consisted of 5½ inches of asphaltic concrete and 6½ inches of sand asphalt, and this section was the only section of Beulah Road where significant cracking was not observed.
Kingsfield Road appeared to be generally in good condition, and we understand that Kingsfield Road was recently overlain. Edge cracking and minor rutting was observed near B-27, and the existing asphalt was worn near the intersection with Beulah Road.
The above project information is the basis of our recommendations. If this information changes or is incorrect, our office should be notified, and changes to our report may be needed.
Asphaltic Materials* Thickness Summary Table
Boring Total Asphalt
Thickness (in)
Boring Total Asphalt
Thickness (in)
B-1 3½ B-21 7½
B-3 3½ B-23 3⅜
B-5 3¾ B-24 3½
B-7 3¼ B-25 3¾
B-9 7¼ B-27 3¾
B-11 5 B-29 3¼
B-13 6¾ B-30 4
B-15 3 B-31 2¾
B-17 8 B-32 3⅛
B-19 12
*See photos for layer thickness and composition and core condition
Kingsfield Road
Kingsfield Road
Kingsfield Road near Beulah Road Intersection.
Standing Water.
Beulah Road near B-22.
Alligator cracking, patching, and rutting.
Worse in NBL (bottom).
Beulah Rd near B-19 looking south. Repaired section. Transverse cracks stop at CL.
North end of pavement repair.
Pothole and patching near B-14.
SBL between B-10 and B-11. Sawcut trench deflection and cracking.
Earthwork Concerns and Comments ▼ Strata 3 and 5 soils drain slowly, retain excess moisture, and are difficult to dry and compact if they are too wet, and this is a concern for earthwork.
▼ If construction occurs during a rainy period, widespread removal, and replacement of wet, uncompactable Strata 3 and 5 soils may be needed.
▼ We recommend constructing widening areas in sections that can be managed and paved in a timely manner when rainfall is anticipated.
▼ Strata 3 and 5 soils (>15% fines) are suitable for subgrade if they are not overly wet. Since time and space needed for drying these soil types is not expected to be available, soils that are too wet to be compacted will need to be removed and replaced with Type B soils.
▼ Stratum 7 (clayey) soils are normally not desirable as pavement subgrade because when exposed to water, they can lose strength and have the potential to swell.
▼ We recommend removing Stratum 7 soils where present in the top 18 inches of subgrade in widening areas and replacing them with Type B stabilized subgrade.
▼ Stratum 4 soils (<15% fines) should be relatively easy to work and are suitable for subgrade.
Site Preparation ▼ The proposed widening areas should be cleared, grubbed, and stripped of all trees, vegetation, major roots, topsoil, and any other deleterious materials.
▼ Stripped vegetation, topsoil, and organic materials should be hauled offsite, or suitable topsoil could be stockpiled for use in sodded areas after final grading.
▼ Grades in widening areas should be sloped to run stormwater away from the widening area and existing roadway.
▼ Widening areas should be graded to top of subgrade elevations and the subgrade soils should be evaluated by LMJ to determine if the soils are suitable for subgrade (Strata 3, 4, or 5) and not overly wet.
▼ Widening areas should be proof rolled with a fully loaded on-road dump truck under the observation of LMJ staff. Proof rolling should occur when subgrades are not overly wet.
▼ Any areas that pump, yield, or rut during proof rolling should be evaluated by the geotechnical engineer or his representative.
▼ If the subgrade soils are determined to be unsuitable (Stratum 7) or overly wet Strata 3 and 5 soils, they should be undercut 18 inches (or less if suitable material is encountered) and backfilled in compacted lifts using Type B material.
▼ After proof rolling, the top of subgrade and fill in widening areas should be compacted to the requirements in the table below for a minimum depth of 12 inches.
Earthwork Recommendations
Fill Material ▼ All fill material should meet the current requirements of FDOT Index 120-001.
▼ Native soils that meet the requirements of FDOT Index 120-001 can be used as fill.
▼ Fill for the top 18 inches under the shoulder and pavement should be Type B material with a minimum LBR value of 40.
▼ All fill should be free of significant organic materials, debris, or other deleterious materials.
▼ Samples of any imported fill material, if needed, should be submitted to the geotechnical engineer for testing and evaluation prior to shipment to the site.
Compaction ▼ Soils should be moisture conditioned to within 2% of their optimum moisture content prior to compaction.
▼ We recommend using 6-inch lifts (loose thickness) for filling. Thicker lifts could be allowed if the requirements in FDOT Section 120-8.2.1.2 are met.
▼ Fill or backfill (for removal of unsuitable or uncompactable soils) should be compacted to the requirements in the following table. Compaction under pavement should extend 5 feet beyond edges where practical.
▼ Traffic sized rubber-tired rollers are the preferred compaction equipment for the native silty/clayey sand soils (Strata 3 and 5). Large vibratory rollers could be used for Strata 4.
▼ Large vibratory rollers have the potential to draw up shallow groundwater and disturb or damage nearby structures and are not recommended within 50 feet of existing structures or where shallow groundwater is present.
▼ We recommend that LMJ remain involved during construction to evaluate the suitability of subgrade soils, document the removal of unsuitable or uncompactable soils, provide compaction testing, and help resolve other issues.
▼ LMJ can also provide additional recommendations if the contractor is having difficulty achieving compaction.
Compaction Recommendations
Site Element Minimum
Compaction
(ASTM D1557)
Minimum Compaction Testing Frequency Per 12-inch lift
Fill/Backfill 98%* 1 per 300 LF
Top 12 inches of Pavement Subgrade 98% 1 per 300 LF
*Escambia County Requirement
Earthwork Recommendations pavement Recommendations Pavement Recommendations
Beulah Road General Comments The existing asphalt is in poor condition and the alligator cracking and rutting indicates that the base and subgrade are structurally inadequate for the loading on Beulah Road. A portion of the project between B-9 and B-22 had clay soils (Stratum 7) that are considered poor subgrade. The borings did not appear to encounter any perched water, but several of the borings encountered conditions that could trap or perch infiltrating stormwater. The clay soils were generally firm and dry in the borings indicating they had not been recently wetted.
Because the clay was drier and based on the laboratory results, it has swell potential, which is a concern for the roadway because the clay could be wetted in the future from cracks in the pavement.
Option 1: Milling and Overlaying
Milling and overlaying the roadway would not address the underlying base/subgrade issues and would therefore only provide a relatively short-term improvement. In addition, reflective cracking and premature failure of the overlay is very likely since the road was overlain just over a decade ago and is in poor condition (reflective cracking showed up within the first few years).
Milling and overlaying was therefore not considered an option.
Option 2: Full Rebuild
A full rebuild with GAB was considered by the design team, but the existing roadway elevation needed to be maintained, and this would require removing the poor Stratum 7 soils to a significant depth below the existing pavement. Considering the depth of excavation required for a full rebuild and the time needed to remove and replace Stratum 7 soils, compact the subgrade, and place and compact the base, this option would require a temporary lane to manage traffic and was not further considered.
Option 3: FDR
Full Depth Reclamation (FDR) was considered by the design team, but there were several concerns with this method including the erratic asphalt and base types and thicknesses which would produce an inconsistent FDR base, and areas with thicker asphalt would present challenges. There were also significant concerns with shrinkage cracking with a cement added base product, which could allow wetting of the clay subgrade soils. This option was considered to involve too much risk and was not further considered.
Option 4: Full Depth Asphalt
Given the heavy traffic loading, poor subgrade soils in a portion of the project, and the benefit of speed (night closure and no temporary lane), full depth asphalt pavement appears to be the best option for this project. Multiple attempts have been made over the years to repair sections of Beulah Road including rebuilds using GAB, sand asphalt, mill and overlay, etc., but these have empirically proved to be inadequate given the base and subgrade conditions and traffic loading. A full depth asphalt rebuild was done for a portion of the road (to repair construction deficiencies) and has empirically proven to withstand the traffic loading over the clayey (Stratum 7) soils. In areas where milling for the new full depth section does not remove all the existing asphalt, we recommend that the remaining asphalt surface be cleaned and swept/brushed and a tack coat applied prior to placing asphalt.
Pavement Recommendations
Kingsfield Road General Comments Kingsfield Road had been recently overlain and was in good condition at the time of our evaluation with 3½-3¾ inches of Asphaltic Concrete within the project limits and suitable base and subgrade soils. It appears that Kingsfield Road can be milled and overlain. We recommend the following:
▼ Any significant cracks in the milled surface should be carefully and completely cleaned before sealing because most sealant failures occur due to poor adhesion.
▼ Cracks should be cleaned with high-pressure compressed air blasting to remove loose pavement, debris, and dirt to a depth of at least twice the crack width.
▼ Inspect cracks before sealing to ensure that they are clean, dry, and free of dirt, debris, or other contamination.
▼ Seal existing cracks before overlaying using hot applied sealant and place immediately after crack cleaning and drying.
▼ Crack sealing should take place when temperatures are warmer and large swings in temperature are not anticipated.
▼ Seal reflective cracks when they appear in the new overlay using routine maintenance.
▼ Routine maintenance should also include control of vegetation along pavement edges.
▼ We recommend placing a tack coat on the milled surface prior to overlaying, and the milled surface should be carefully cleaned and swept/brushed prior to tack application.
Asphalt Recommendations We recommend paving with FDOT structural and friction course Superpave Asphaltic Concrete.
FC-12.5 is preferred for surface course, and SP-19 is preferred for structural courses, because it can be placed in thicker lifts. Asphalt should meet the requirements of FDOT Section 334.
We recommend limiting the amount of Recycled Asphalt Pavement (RAP) to no more than 25% of the mixture since mixtures over 25% RAP have a higher potential for quality and performance issues. The asphalt should be compacted to a target of 92% of the laboratory maximum specific gravity (Gmm or Rice Specific Gravity) as determined by FM 1-T 209. We recommend that LMJ review the contractor’s proposed asphalt mix designs.
Quality Control Testing All compaction should be verified using in-place density testing in accordance with current FDOT Standard Specifications. Asphalt temperature at the time of placement is critical to achieving good compaction of the asphalt, and we recommend documenting and verifying asphalt temperatures at the time of placement. After compaction, the asphalt should be cored to determine the thickness and compaction. Cores should be taken at the FDOT recommended frequency. The bulk specific gravity (Gmb) of the cores should be determined in accordance with FM 1-T 166 (if the road is overlain, the overlay should be saw cut from older layers to evaluate compaction of overlay).
Boring Locations
STANDARD PENETRATION TEST BORING
ALL BORING LOCATIONS ARE APPROXIMATE
Boring Locations
STANDARD PENETRATION TEST BORING
ALL BORING LOCATIONS ARE APPROXIMATE
Boring Logs
N
B-1
GNE
02-04-25
N
B-2
GNE
02-04-25
N
B-3
GNE
5*
02-04-25
2 0 N
B-4
GNE
02-04-25
N
B-5
GNE
02-04-25
N
B-6
GNE
02-04-25
6 0 N
B-7
GNE
02-04-25
N
B-8
GNE
02-03-25
4 TRACE IRON ROCK
ASPHALT (3 12")
3 5
3 4
ASPHALT (3 14")
WITH PLASTIC WATER
BOTTLE LABEL
w=6.7 -200=14.5 w=10.0 -200=15.0 w=7.8 -200=17.0 w=6.1 -200=10.2 w=9.8 -200=19.2 w=5.4 -200=18.6 w=13.1 -200=34.2 w=5.6 -200=12.2 w=8.0 -200=15.6 w=8.2 -200=12.9 w=7.4 -200=14.2
(5")
(3")
(7")
2-4 FT SAMPLE: 7/3/2/2
*HAMMER BLOWS:
(3")
TRACE IRON ROCK
(4") (3") (2")
ASPHALT (3 12")
1 38" 1 18" 1"
ASPHALTIC CONCRETE
SAND ASPHALT
ASPHALTIC CONCRETE
ASPHALT (3 34")
3 34" ASPHALTIC CONCRETE
3 14" ASPHALTIC CONCRETE
1 34" ASPHALTIC CONCRETE
1 34" ASPHALTIC CONCRETE
ORANGE/RED SILTY SAND, SOME
TRACE CLAY (BASE)(A-2-4)
LIGHT GRAY CRUSHED LIMESTONE; GRADED
AGGREGATE BASE (BASE)(A-1-a, A-1-b)
TAN/BROWN, TAN/ORANGE SLIGHTLY SILTY
SAND AND SILTY SAND (-200<15%)(A-3)(A-2-4)
2 4
ORANGE, TAN, BROWN SILTY SAND,
TRACE CLAY (A-2-4)
TAN/ORANGE SLIGHTLY CLAYEY SILTY SAND
AND CLAYEY SILTY SAND (A-2-4)(A-2-6)(A-4)5
DARK BROWN/BROWN SLIGHTLY SILTY SAND
AND SILTY SAND WITH ROOTS (TOPSOIL)(A-2-4)6
LIGHT GRAY/TAN/ORANGE MOTTLED AND DARK GRAY CLAYEY
SAND AND SANDY CLAY WITH IRON ROCK (A-6)(A-7-6)7
B-9
GNE
02-04-25
N
B-10
8*
GNE
02-03-25
N
B-11
GNE
02-03-25
N
B-12
GNE
02-03-25
ASPHALT (7 14")
ASPHALT (5")
TRACE IRON ROCK
TRACE MICA
w=14.1 -200=25.3 w=17.4 -200=42.1 w=12.6 -200=5.2 w=20.8 -200=46.9 c ~ 3500 w=2.4 -200=18.7 w=12.6 -200=28.8
0-2 FT SAMPLE: 2/2/6/16
*HAMMER BLOWS:
(3")
(7") c ~ 3500
(2") w=18.9
LL=38
PL=18
PI=20
LI=-0.04
-200=64.4c ~ 3500
1" 1" 1" 1"
ASPHALTIC CONCRETE
SAND ASPHALT2"
ASPHALTIC CONCRETE1 14"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
1 34" 1 12" 1 34"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
N
B-13
GNE
7*
01-31-25
N
B-14
GNE
01-30-25
N
B-15
GNE
01-30-25
N
B-16
GNE
01-30-25
ASPHALT (6 34")
TRACE IRON ROCK (5 14")
TRACE IRON ROCK, DARK GRAY
VERY FINE AT 2 FEET, TRACE
ORGANICS/WOOD
TRACE IRON ROCK
WITH GRAVEL
WITH THIN CLAY LAYER
WITH IRON ROCK
WITH IRON ROCK
ASPHALT (3")
WITH ROOTS
TRACE IRON ROCK
TRACE MICA
w=17.1 -200=41.6 O.C.=3.7 w=17.8 -200=45.1 w=14.8 -200=48.3 c ~ 1500-4500+
0.5-2 FT SAMPLE: 11/29/35
*HAMMER BLOWS:
2-4 FT SAMPLE: 8/4/3/5
c ~ 3750
NOTE: ENCOUNTERED OBSTRUCTION
(SUSPECTED IRON ROCK LAYER) AT 2 FT.
OFFSET BORING FOR 4-6 FT
c ~ 3000
(3") c ~ 4000
(2")
(4")
(6") w=16.9
LL=47
PL=21
PI=27
LI=-0.14
-200=60.2 c ~ 3400 w=18.6
LL=41
PL=18
PI=23
LI=0.02
-200=79.0 c ~ 3750 w=21.7
LL=41
PL=21
PI=20
LI=0.04
-200=55.1 c ~ 1000 w=20.0
LL=53
PL=24
PI=29
LI=-0.14
-200=67.4 c ~ 3500
3" ASPHALTIC CONCRETE
1 34"
SAND ASPHALT1 34"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
1 12" ASPHALTIC CONCRETE
1 34"
LIGHT GRAY CRUSHED LIMESTONE; GRADED
AGGREGATE BASE (BASE)(A-1-a, A-1-b)
TAN/BROWN, TAN/ORANGE SLIGHTLY SILTY
SAND AND SILTY SAND (-200<15%)(A-3)(A-2-4)
2 4
ORANGE, TAN, BROWN SILTY SAND,
TRACE CLAY (A-2-4)
TAN/ORANGE SLIGHTLY CLAYEY SILTY SAND
AND CLAYEY SILTY SAND (A-2-4)(A-2-6)(A-4)5
DARK BROWN/BROWN SLIGHTLY SILTY SAND
AND SILTY SAND WITH ROOTS (TOPSOIL)(A-2-4)6
B-17
GNE
18*
01-30-25
1 0 N
B-18
GNE
01-30-25
N
B-19
23*
GNE
01-30-25
N
B-20
GNE
01-30-25
N
B-21
GNE
01-30-25
1 0 N
B-22
GNE
01-30-25
N
B-23
GNE
01-30-25
N
B-24
GNE
01-29-25
VERY SILTY WITH ROOTS
TRACE IRON ROCK
ASPHALT (12")
SAND ASPHALT (SEPARATED
FROM CORE)
TRACE MICA 2-4 FT
SANDY CLAY (6")(CL)
7 TRACE MICA
ASPHALT (7 12")
SAND ASPHALT (SEPARATED
FROM CORE, PIECES)
5 WITH IRON ROCK (4-6 FT)
WITH IRON ROCK
ASPHALT (3 38")
TRACE IRON ROCK
1-2 FEET
IRON ROCK (3")
ASPHALT (3 12")
TRACE IRON ROCK
SOME MOTTLING 4-6 FT
w=9.6 -200=19.9 w=10.9 -200=21.1 w=16.1 -200=29.8 w=18.0 -200=37.8 w=8.8 -200=18.2 w=17.8 -200=29.1 w=31.9 -200=56.9 w=17.6 -200=15.0 w=16.5 -200=29.3 w=12.6 -200=24.2 w=8.3 -200=18.5 w=9.9 -200=7.7 w=6.0 -200=15.6
TRACE IRON ROCK
2-4 FT SAMPLE: 18/12/6/4
*HAMMER BLOWS:
c ~ 4500+
(6")
(6")
(6")
0.5-2 FT SAMPLE: 32/14/9
*HAMMER BLOWS:
c ~ 4250
(2")
(7 12")
(3") w=20.2
LL=49
PL=18
PI=32
LI=0.08
-200=46.9 c ~ 0000 w=16.7
LL=60
PL=21
PI=39
LI=-0.21
-200=87.4 c ~ 4500 w=17.2
LL=38
PL=19
PI=18
LI=-0.12
-200=53.9 c ~ 3500 w=23.0
LL=42
PL=22
PI=19
LI=0.05
-200=55.9 c ~ 2000 w=19.2
LL=57
PL=27
PI=31
LI=-0.24
-200=74.0 c ~ 4500+ w=19.3
LL=19
PL=16
PI=3
LI=0.99
-200=49.0 c ~ 3500
(6")
ASPHALT (8")
1 38" 2 18" 3"
ASPHALTIC CONCRETE
SAND ASPHALT
ASPHALTIC CONCRETE
1 12" ASPHALTIC CONCRETE 5 12" ASPHALTIC CONCRETE
1 58" 1 34"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
SAND ASPHALT
1 12"
ASPHALTIC CONCRETE
4 12"
ASPHALTIC CONCRETE
1 12"
2 12" 1"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
6 12"
1 34"
LIGHT GRAY CRUSHED LIMESTONE; GRADED
AGGREGATE BASE (BASE)(A-1-a, A-1-b)
TAN/BROWN, TAN/ORANGE SLIGHTLY SILTY
SAND AND SILTY SAND (-200<15%)(A-3)(A-2-4)
2 4
ORANGE, TAN, BROWN SILTY SAND,
TRACE CLAY (A-2-4)
TAN/ORANGE SLIGHTLY CLAYEY SILTY SAND
AND CLAYEY SILTY SAND (A-2-4)(A-2-6)(A-4)5
DARK BROWN/BROWN SLIGHTLY SILTY SAND
AND SILTY SAND WITH ROOTS (TOPSOIL)(A-2-4)6
B-26
GNE
01-29-25
N
B-27
GNE
01-29-25
N
B-28
GNE
01-29-25
N
B-29
01-29-25
N
B-30
GNE
01-29-25
3 2-6 FT TAN WITH ORANGE
MOTTLING
WITH ROOT/WOOD (VERTICAL
GRAIN)(0.5-2 FT SAMPLE)3
TRACE MICA (2-4 FT)
TRACE MICA
ASPHALT (3 34")
WITH PEA GRAVEL, PIECE
OF FABRIC AND GEO GRID 1
ASPHALT (4")
DARK GRAY, TRACE ORGANICS 5.5-6 FT
w=13.7 -200=15.2 w=9.6 -200=19.0 w=19.3 -200=20.8 O.C.=2.6 w=30.8 -200=47.1 w=31.6 -200=10.0 O.C.=1.7 w=7.9 -200=15.6 w=7.8 -200=15.9 w=5.2 -200=8.6
(6")
(14")
4 5+
(4")
(2")
(2")
WITH ROOTS (DARK GRAY)
w=16.4
LL=28
PL=15
PI=12
LI=0.08
-200=30.4
-200=7.2
1 12" 1 14" 1 14"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
ASPHALT (3 14")
1 12" 1 34"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
3 34" ASPHALTIC CONCRETE
N
B-25
GNE
04-01-25
ASPHALT (3 34")
2 58" 1 18"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
N
B-31
GNE
04-01-25
ASPHALT (2 34")
N
B-32
GNE
6*
04-01-25 ASPHALT (3 18")
(CORE CRACKED FULL DEPTH)
(3")(3 14") w=4.8 -200=14.1 w=12.4 -200=15.3 w=15.0 -200=24.0 w=9.9 -200=21.8
1 12" 1 14"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
1 34" 1 38"
ASPHALTIC CONCRETE
ASPHALTIC CONCRETE
2-4 FT SAMPLE: 6/4/2/1
*HAMMER BLOWS:
(18")
(18")
LIGHT GRAY CRUSHED LIMESTONE; GRADED
AGGREGATE BASE (BASE)(A-1-a, A-1-b)
TAN/BROWN, TAN/ORANGE SLIGHTLY SILTY
SAND AND SILTY SAND (-200<15%)(A-3)(A-2-4)
2 4
ORANGE, TAN, BROWN SILTY SAND,
TRACE CLAY (A-2-4)
TAN/ORANGE SLIGHTLY CLAYEY SILTY SAND
AND CLAYEY SILTY SAND (A-2-4)(A-2-6)(A-4)5
DARK BROWN/BROWN SLIGHTLY SILTY SAND
AND SILTY SAND WITH ROOTS (TOPSOIL)(A-2-4)6
Lab Test Results Summary
Laboratory testing for this project included wash #200 sieve, natural moisture content, and Atterberg Limits tests run on selected samples to assist in soil classification and to evaluate and document basic properties. The results of these tests are shown on the boring logs adjacent to the samples tested and are summarized in the following tables.
Lab Testing Summary
Atterberg Limits Test Results Summary
Stratum Liquid Limit Plastic Limit
Range Average Number of Tests Range Average Number of
Tests
5 19-28 24 2 15-16 16 2
7 38-60 47 8 18-27 21 8
Limerock Bearing Ratio (LBR) Testing Laboratory testing also included seven limerock bearing ratio (LBR) tests on samples of the base and subgrade collected from the borings. Grainsize analysis tests were also run on the LBR samples. The results of the LBR tests are summarized in the following table, and the LBR and grainsize test results are graphed below.
LBR and Proctor Test Results Summary
Stratum Boring Sample Type
Maximum Dry Unit
Weight (pcf)
Optimum Moisture
Content (%)
LBR
Value
3 B-13 Subgrade 119.9 8.2 61 3 B-13 Base 124.2 8.2 120 7 B-20 Subgrade 120.4 12.5 27 4 B-24 Base 113.4 11.7 64 4 B-24 Subgrade 110.0 12.4 36 4 B-27 Base 116.5 9.0 88 3 B-27 Subgrade 117.9 8.0 58
Stratum Moisture Content (%) Percent Passing #200 Sieve
Range Average Number of Tests Range Average Number of
Tests
1 12.5-17.6 15 3 15.0-24.2 18.1 3
2 2.4 2.4 1 7.2-18.7 13.0 2
3 5.4-19.3 10.0 18 15.0-28.8 18.9 18
4 4.8-31.6 9.8 10 4.2-14.5 11.0 10
5 13.1-19.3 16.5 9 25.3-49.0 34.9 9
7 14.8-30.8 19.6 15 37.8-97.4 57.8 15
Lab
3% 4% 5% 6% 7% 8% 9% 10% 11%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
3% 4% 5% 6% 7% 8% 9% 10% 11%
LB
R
V al ue
LBR Results B-13 Subgrade Sample
Boring Type Sample Description
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-13 Subgrade Orange/Tan Silty Sand w/ Gravel (Stratum 3) 119.9 8.2 61 12.2
5% 6% 7% 8% 9% 10% 11% 12%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
5% 6% 7% 8% 9% 10% 11% 12%
LB
R
V
LBR Results B-13 Base Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-13 Base Dark Orange Silty Sand w/ Gravel (Stratum 3) 124.2 8.2 120 14.3
9% 10% 11% 12% 13% 14% 15% 16%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
9% 10% 11% 12% 13% 14% 15% 16%
LB
R
V
LBR Results B-20 Subgrade Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-20 Subgrade Light Gray/Tan/Orange Sandy Clay (Stratum 7) 120.4 12.5 27 70.4
7% 8% 9% 10% 11% 12% 13% 14% 15%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
7% 8% 9% 10% 11% 12% 13% 14% 15%
LB
R
V
LBR Results B-24 Base Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-24 Base Orange/Brown Slightly Silty Sand w/ Gravel (Stratum 4) 113.4 11.7 64 9.4
9% 10% 11% 12% 13% 14% 15% 16%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
9% 10% 11% 12% 13% 14% 15% 16%
LB
R
V
LBR Results B-24 Subgrade Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-24 Subgrade Tan/Orange Slightly Silty Sand (Stratum 4) 110.0 12.4 36 10.6
7% 8% 9% 10% 11% 12% 13% 14%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
7% 8% 9% 10% 11% 12% 13% 14%
LB
R
V
LBR Results B-27 Base Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-27 Base Tan/Orange Slightly Silty Sand w/ Gravel (Stratum 4) 116.5 9.0 88 11.9
4% 5% 6% 7% 8% 9% 10% 11% 12%
D ry
U ni t W ei gh t ( pc f)
Moisture Content (%)
4% 5% 6% 7% 8% 9% 10% 11% 12%
LB
R
V
LBR Results B-27 Subgrade Sample
Maximum Dry
Density (pcf)
Optimum Moisture Content
LBR
Value % fines
B-27 Subgrade Light Tan Silty Sand (Stratum 3) 117.9 8.0 58 17.1
3" 2" 1.
5" 1" 3/ 4"
1/ 2"
3/ 8"
1/ 4" #4 #1
#2
#4
#6
#8
#1
#2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.0010.010.1110100
Pe rc en t F in er
B y
W ei gh t
Grainsize in Millimeters
GRAVEL SILT OR CLAYSAND
COARSE FINE COARSE MEDIUM FINE
Grainsize Test Results
Boring Type Sample Description Stratum
B-13 Subgrade Orange/Tan Silty Sand w/ Gravel 3
B-13 Base Dark Orange Silty Sand w/ Gravel 3
B-20 Subgrade Light Gray/Tan/Orange Sandy Clay 7
B-24 Base Orange/Brown Slightly Silty Sand w/ Gravel 4
3" 2" 1.
5" 1" 3/ 4"
1/ 2"
3/ 8"
1/ 4" #4 #1
#2
#4
#6
#8
#1
#2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0.0010.010.1110100
Pe rc en t F in er
B y
W ei gh t
Grainsize in Millimeters
GRAVEL SILT OR CLAYSAND
COARSE FINE COARSE MEDIUM FINE
Grainsize Test Results
Boring Type Sample Description Stratum
B-24 Subgrade Tan/Orange Slightly Silty Sand 4
B-27 Base Tan/Orange Slightly Silty Sand w/ Gravel 4
B-27 Subgrade Light Tan Silty Sand 3
Photos
B-1 3½ inches Asphalt
1⅜-inch AC 1⅛-inch AC
1-inch Sand Asphalt Cracked and Separated
B-3 3½ inches Asphalt
1¾-inch AC 1¾-inch AC
Upper layer cracked Separated
B-5 3¾ inches AC
Cracked on Bottom
B-7 3¼ inches AC
B-9 7¼ inches Asphalt
Four 1-inch Layers AC 2 inches Sand Asphalt
1¼-inch AC
B-11 5 inches AC 1¾-inch AC 1½-inch AC 1¾-inch AC
B-13 6¾ inches Asphalt Two 1¾-inch AC
(Separated between layers) 1¾-inch Sand Asphalt
B-15 3 inches AC
B-17 8 inches Asphalt
1⅜-inch AC (Cracked) (Separated between layers)
2⅛ AC (Cracked) 3-inch Sand Asphalt
B-19 12 inches Asphalt
5½ inches AC Separated from 6½ inches of Sand Asphalt (Not Pictured)
B-21 7½ inches Asphalt Two 1½ Layers AC
(Separated) 4½ inches of Sand Asphalt
B-23 3⅜ inches AC 1⅝ inches AC 1¾ inches AC (Separated)
B-24 3½ inches AC 2½ inches AC 1 inches AC
B-25 3¾ inches AC 2⅝ inches AC 1⅛ inches AC
B-27 3¾ inches AC Visible Voids
B-29 3¼ inches AC 1½ inch AC 1¾ inch AC
B-30 4 inches AC 1½ inch AC 1¼ inch AC 1¼ inch AC
All Layers Separated and Cracked
B-31 2¾ inches AC 1½ inch AC 1¼ inch AC
B-32 3⅛ inches AC 1¾ inch AC 1⅜ inch AC
Cracked Full Depth
Basis of Recommendations Recommendations rendered herein are based on assumed and/or design information available at the time of this report, the subsurface conditions encountered in the test borings, generally accepted geotechnical engineering principles and practices, and our experience with similar soil and groundwater conditions. Should final project information or existing conditions differ from the information used in this report or should any soil conditions not discussed in this report be encountered during construction, our office should be notified and retained so that this report can be modified as needed. LMJ should be provided with the final plans and specifications for review to determine if any changes to our report are needed based on the final design and that our recommendations have been properly interpreted.
This report and any correspondence are intended for the exclusive use of our client for the specific application to the project discussed. LMJ is not responsible for the interpretations, conclusions, or recommendations made by others based on the information in this report.
Regardless of the care exercised in performing a Geotechnical Exploration, the possibility always exists that soil and/or groundwater conditions will differ from those encountered at the specific boring locations. In addition, construction operations may alter the soil conditions. Therefore, it is recommended that a representative from LMJ be involved during the construction phases discussed in this report.
Test Methods
Standard Penetration Test
The Standard Penetration Test (SPT) consists of driving a 2-inch diameter split spoon sampler into the ground using a 140-pound hammer dropped 30 inches. The number of blows required to drive the sampler one foot (after seating it 6 inches) is referred to as the blow count or “N” value and represents the relative density of subsurface soils. “N” values can be found on the boring logs. The SPT borings were drilled in general accordance with ASTM D1586 using a truck mounted drill rig and were sampled by driving back-to-back 2-foot split spoons to 6 feet.
Each sample was removed from the sampler, classified in the field by the driller, and packaged for visual classification by our engineering staff and laboratory testing.
Other Test Methods Atterberg Limits (ASTM D4318), Wash #200 Sieve (ASTM D1140), Moisture Content (ASTM D2216), Sieve Analysis (ASTM C136), LBR (FM5-515), and Organic Content (ASTM D2974).
Appendix
LEGEND
SAFETY HAMMER AUTOMATIC HAMMER
GRANULAR SOILS
SPT
BLOWS/FOOT (N) RELATIVE DENSITY
0-2 VERY LOOSE
3-8 LOOSE
9-24 MEDIUM DENSE
25-40 DENSE
> 40 VERY DENSE
COHESIVE SOILS
BLOWS/FOOT (N) RELATIVE DENSITY
<1 VERY SOFT
1-3 SOFT
4-6 MEDIUM STIFF
7-12 STIFF
13-24 VERY STIFF
> 24 HARD
GRANULAR SOILS
SPT
BLOWS/FOOT (N) RELATIVE DENSITY
0-3 VERY LOOSE
4-10 LOOSE
11-30 MEDIUM DENSE
31-50 DENSE
> 50 VERY DENSE
COHESIVE SOILS
BLOWS/FOOT (N) RELATIVE DENSITY
0-1 VERY SOFT
2-4 SOFT
5-8 MEDIUM STIFF
9-15 STIFF
16-30 VERY STIFF
> 30 HARD
SAND
SILTY SAND
CLAY
PEAT
SLIGHTLY
SILTY SAND
SILT
CLAYEY
SAND
GRAVEL
GROUNDWATER NOT ENCOUNTERED
AT TIME OF DRILLING
STANDARD PENETRATION RESISTANCE
IN BLOWS PER FOOT
STANDARD PENETRATION RESISTANCE
USING AUTOHAMMER
ENCOUNTERED GROUNDWATER LEVEL
ENCOUNTERED PERCHED WATER
LEVEL
NUMBER OF BLOWS REQUIRED (50) TO
ADVANCE SPLIT SPOON SAMPLER A
SPECIFIC DISTANCE (2) INCHES
SPLIT SPOON SAMPLE ADVANCED
UNDER WEIGHT OF ROD AND HAMMER
SAMPLER ADVANCED UNDER WEIGHT
OF ROD
HAND AUGER
SHELBY TUBE SAMPLER
NATURAL MOISTURE CONTENT (%)
FINES PASSING #200 SIEVE (%)
ORGANIC CONTENT (%)
LIQUID LIMIT
PLASTIC LIMIT
LIQUIDITY INDEX
APPROXIMATE COHESION VALUE (PSF)
BASED ON POCKET PENETROMETER
OR TORVANE READINGS
SATURATED VERTICAL HYDRAULIC
CONDUCTIVITY (FT/DAY)
DRY UNIT WEIGHT (PCF)
ESTIMATED MOIST UNIT WEIGHT (PCF)
ESTIMATED BUOYANT UNIT WEIGHT
(PCF)
ESTIMATED ANGLE OF INTERNAL
FRICTION (DEGREES)
w
Kv γ d
NOTES
1) SPT BORINGS PERFORMED
IN GENERAL ACCORDANCE
WITH ASTM D1586
2) SUBSURFACE CONDITIONS
ARE AT BORING LOCATIONS
AND ACTUAL CONDITIONS
BETWEEN BORINGS MAY
VARY
3) ALL CLASSIFICATIONS ARE
BASED ON VISUAL
EXAMINATION UNLESS
ACCOMPANIED BY
LABORATORY TEST RESULTS
4) BOUNDARIES BETWEEN SOIL
LAYERS SHOULD BE
CONSIDERED APPROXIMATE
AS THE ACTUAL TRANSITION
MAY BE GRADUAL
5) DEPTH OF BORING IS BELOW
EXISTING GRADE AT TIME OF
DRILLING
6) ELEVATIONS, IF SHOWN,
WERE ESTIMATED FROM
PROVIDED TOPOGRAPHIC
SURVEY
7) COLORS USED FOR BORING
HATCHING MAY NOT
REPRESENT THE ACTUAL
SOIL COLORS
RW
HW
HA
Appendix
| Appendix |
| Appendix |
| Appendix |
| Appendix |
| Appendix |
| Appendix |
| Appendix |
| 2025-05-10T12:04:52-0500 | |
| Keith V Jacobs |