Generator Annunciator - Recommended Work Details.pdf

PDF 102 KB Posted

Attached to
Z1DA--656-24-501 Install Remote Generator Annunciators
Solicitation number
36C26325R0029
Issued by

About this file

The file is a detailed technical document describing work requirements for installing remote generator annunciator panels at the St. Cloud VA Health Care System. The project involves installing communication networks and hardwired signals for five emergency generators across multiple buildings (Buildings 112, 113, 114, 117, and 119), using Caterpillar generators ranging from 500 kW to 1500 kW. The work requires installing copper-to-fiber converters, uninterruptible power supplies, CAT EMCP 4 RS-485 Remote Generator Annunciators, copper and fiber cables, and necessary conduits across various building locations.

This is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside contract with a NAICS code 238210 and a small business size standard of $19 million. The solicitation (36C26325R0029) is for a firm fixed-price contract with a performance period of 100 calendar days from the Notice to Proceed. The total project value is between $100,000 and $250,000, and requires contractors to be registered and certified in the Veteran Small Business Certification (VetCert). Offerors must coordinate with the original equipment manufacturer, label all new cables, and ensure compliance with NFPA 99 Subsection 6.7.1.2.7 standards.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 112:

- Existing Generator Details:

Caterpillar 1500 kW

Model Number: SR4B-GD

Serial Number: G4W01002

- Recommended Work Approach:

o Install OEM recommended cable from the Generator in Building 112 through the

Steam tunnel to the Remote Annunciator Panel in Building 7 Room 104.

o Utilize existing wire tray in the steam tunnel. Install new conduit wherever existing wire tray does not exist, in both Building 112 and Building 7.

Building 113:

Caterpillar 1500 kW

Model Number: SR4B-GD

Serial Number: G4W01010

- Existing Engineering Fiber Cabinet Details:

o Building 50 (Room 23A):

▪ Multimode Fiber

▪ Connection Type: ST

▪ Available Fiber Strands: 11 o Building 51 (Room 22):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 13 o Building 5 (Room 117):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Building 7 (Room 104)

▪ Multimode Fiber

▪ ST Connection Type

▪ Available Fiber Strands: 14

- Recommended Work Approach o Construct a communication network to provide data transmission from the

Generator in Building 113 to the Remote Annunciator Panel in Building 7 Room

104, utilizing the existing Engineering Fiber Infrastructure Loop:

▪ Install copper-to-fiber converter, along with a suitable uninterruptable power supply, in B50 Room 23A and in B7 Room 102A.

▪ Install CAT EMCP 4 RS-485 Remote Generator Annunciator in B7 Room

104, along with the necessary power to supply the annunciator.

▪ Install OEM recommended copper cable from the generator in B113 to

B50.

▪ In B50 Room 23A, install fiber patch cable from the fiber converter to the fiber termination cabinet, to provide a signal to the fiber termination cabinet in B51.

▪ In B51 Room 22, install fiber patch cable in fiber termination cabinet to transmit data from B51 to B5.

▪ In B5 Room 117, install fiber patch cable in fiber termination cabinet to transmit data from B5 to B7.

▪ Install fiber patch cable from the fiber termination cabinet in B7 Room

104 to the fiber converter in B7 Room 102A.

▪ Install OEM recommended copper cable from the fiber converter to the remote generator annunciator.

o Contractor shall utilize existing conduit from B113 to B50. Contractor shall install new conduit wherever existing wire tray does not exist, in Buildings 113, 50, and

7.

Building 114:

Caterpillar 500 kW

Model Number: C15-PKGG

Serial Number: 0C5E03595

- Existing OIT Fiber Details:

o Building 96 (Room 104B):

▪ Single-mode Fiber

▪ Connection Type: LC o Building 7 (Room 102A):

▪ Single-mode Fiber

▪ Connection Type: LC

- Construct a communication network to provide data transmission from the Generator in

Building 114 to the Remote Annunciator Panel in Building 7 Room 104, utilizing the existing OIT Fiber Infrastructure:

o Install copper-to-fiber converter, along with a suitable uninterruptable power supply, in B96 Room 104B and in B7 Room 102A.

o Install CAT EMCP 4 RS-485 Remote Generator Annunciator in B7 Room 104, along with the necessary power to supply the annunciator.

o Install OEM recommended copper cable from the generator in B114 to B96.

o Install fiber patch cable from the fiber converter to OIT’s fiber switch, in both

B96 Room 104B and in B7 Room 102A.

o Install OEM recommended copper cable from the fiber converter to the remote generator annunciator.

o Contractor shall utilize existing conduit from B114 to B96. Contractor shall install new conduit wherever existing conduit does not exist, in Buildings 114, 96, and 7.

Building 117:

Caterpillar 1500 kW

Model Number: SR4B-GD

Serial Number: G4W01052

- Existing Engineering Fiber Cabinet Details:

o Building 51 (Room 22):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 13 o Building 5 (Room 117):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Building 7 (Room 104)

▪ Multimode Fiber

▪ ST Connection Type

▪ Available Fiber Strands: 14

- Recommended Work Approach o Construct a communication network to provide data transmission from the

Generator in Building 117 to the Remote Annunciator Panel in Building 7 Room

104, utilizing the existing Engineering Fiber Infrastructure Loop:

▪ Install copper-to-fiber converter, along with a suitable uninterruptable power supply, in B51 Room 22 and in B7 Room 102A.

▪ Install CAT EMCP 4 RS-485 Remote Generator Annunciator in B7 Room

104, along with the necessary power to supply the annunciator.

▪ Install OEM recommended copper cable from the generator in B117 to

B51.

▪ In B51 Room 22, install fiber patch cable from the fiber converter to the fiber termination cabinet, to provide a signal to the fiber termination cabinet in B5.

▪ In B5 Room 117, install fiber patch cable in fiber termination cabinet to transmit data from B5 to B7.

▪ Install fiber patch cable from the fiber termination cabinet in B7 Room

104 to the fiber converter in B7 Room 102A.

▪ Install OEM recommended copper cable from the fiber converter to the remote generator annunciator.

o Contractor shall utilize existing conduit from B117 to B51. Contractor shall install new conduit wherever existing conduit does not exist, in Buildings 117, 51, and 7.

Building 119:

Caterpillar 500 kW

Model Number: 500

Serial Number: CAT00C15KNAP00288

- Existing Engineering Fiber Cabinet Details:

o Building 9 (Room 15):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Building 111 (Room 27):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Building 28 (Room 72B):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Parking Structure (Room B10):

▪ Multimode

▪ Connection Type: ST

▪ Available Strands: 14 o Building 118 (Room 4):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 11 o Building 8 (Room 11):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 12 o Building 4 (Room 1):

▪ Multimode

▪ Connection Type: ST

▪ Available Fiber Strands: 14 o Building 7 (Room 104)

▪ Multimode Fiber

▪ ST Connection Type

▪ Available Fiber Strands: 14

- Recommended Work Approach o Construct a communication network to provide data transmission from the

Generator in Building 119 to the Remote Annunciator Panel in Building 7 Room

104, utilizing the existing Engineering Fiber Infrastructure Loop:

▪ Install copper-to-fiber converter, along with a suitable uninterruptable power supply, in B9 Room 15 and in B7 Room 102A.

▪ Install CAT EMCP 4 RS-485 Remote Generator Annunciator in B7 Room

104, along with the necessary power to supply the annunciator.

▪ Install OEM recommended copper cable from the generator in B119 to

B9.

▪ In B9 Room 15, install fiber patch cable from the fiber converter to the fiber termination cabinet, to provide a signal to the fiber termination cabinet in B111.

▪ In B111 Room 27, install fiber patch cable in fiber termination cabinet to transmit data from B111 to B28.

▪ In B28 Room 72B, install fiber patch cable in fiber termination cabinet to transmit data from B28 to the Parking Structure.

▪ In the Parking Structure Room B10, install fiber patch cable in fiber termination cabinet to transmit data from the Parking Structure to B118.

▪ In B118 Room 4, install fiber patch cable in fiber termination cabinet to transmit data from B118 to B8.

▪ In B8 Room 11, install fiber patch cable in fiber termination cabinet to transmit data from B8 to B4.

▪ In B4 Room 1, install fiber patch cable in fiber termination cabinet to transmit data from B4 to B7.

▪ Install fiber patch cable from the fiber termination cabinet in B7 Room

104 to the fiber converter in B7 Room 102A.

▪ Install OEM recommended copper cable from the fiber converter to the remote generator annunciator.

o Contractor shall utilize existing conduit from B119 to B9. Contractor shall install new conduit wherever existing conduit does not exist, in Buildings 119, 9, and 7.