This document is a detailed architectural drawing set for infrastructure and cabling routes at the St. Cloud VA Health Care System, specifically focused on installing remote generator annunciator panels. The drawings illustrate comprehensive routing instructions for new electrical conductors and pathways across multiple buildings (B112, B114, B113, B117, B119), including specifications for installing new conductors in existing conduits, wiretrays, and through steam tunnels. The technical drawings provide precise visual guidance for connecting generator locations to new remote annunciator panels, with detailed notes indicating specific installation requirements, such as utilizing existing J-hooks and ensuring all new conductors are placed in the same conduit.

The accompanying contract opportunity details reveal this is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside project valued between $100,000-$250,000. The project scope involves installing five hard-wired remote generator annunciator panels for emergency generators, with contractors responsible for procuring panels, creating communication networks, and ensuring compatibility with original equipment manufacturer (CAT EMCP 4 RS-485) specifications. The performance period is 100 calendar days from the Notice to Proceed, and the project requires precise coordination with generator manufacturers, proper cable labeling, and adherence to NFPA 99 Subsection 6.7.1.2.7 standards.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

16"

20"

8"

SIGNSIGN

TP TP

SN

T

S4 S

FIT;

MTFSI/

NNGS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

Existing Infrastructure

A

Fi le

P at h

/2 1/

1:

A

M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. CLOUD, MN

CAMPUS

Project Director

Issue date Chkd By Drwn ByRevisions: Date:

Existing Telecommunications Duct Bank

8"

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

Existing Infrastructure

A

Fi le

P at h

/2 1/

1:

A

M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. CLOUD, MN

CAMPUS

Project Director

Issue date Chkd By Drwn ByRevisions: Date:

Provide new pathway and conductor from B113 Generator to Existing pull-box

Install new conductor in existing conduit. Ensure all new conductors are in the same conduit.

Install new conductor for both generators in existing conduit.

Ensure all new conductors are in the same conduit.

Provide new pathway and conductor from B117 Generator to Existing pathway in B117

Install new conductor in existing conduit.

Provide new pathway and conductor from B114 Generator to Existing pull-box

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

Existing Infrastructure

A

Fi le

P at h

/2 1/

1:

A

M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. CLOUD, MN

CAMPUS

Project Director

Issue date Chkd By Drwn ByRevisions: Date:

Install new conductor for B114 and B113 Generators in existing conduit.

Provide new pathway and conductor from B113 Generator to Existing pull-box

Install new conductor and conduit from Pull Box in B7 to new Annunciator Panels.

Install new conductor for B117 Generator in existing conduit.

Install new conductor for B117 and B119 Generators in existing wiretray.

Install new conductor for B117 and B119 Generators in existing conduit.

Install new conductor for B112, 117 and B119 Generators in existing wiretray.

Install new conductor and conduit for B112, 117, and 119 Generators from end of wire tray in B7 to new Annunciator Panels.

Provide new pathway and conductor from B112 Generator to existing pathway in B112

FIELD LOCATED;

MAY BE OUT OF SERVICE/

NO LONGER USED

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

Existing Infrastructure

A

Fi le

P at h

/2 1/

1:

A

M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. CLOUD, MN

CAMPUS

Project Director

Issue date Chkd By Drwn ByRevisions: Date:

Provide new pathway and conductor from B117 Generator to Existing pathway in B117

Install new conductor for B117 Generator in existing conduit.

Install new conductor for B119 Generators in existing wiretray.

Install new conductor for B117 and B119 Generators in existing wiretray.

Install new conductor for B117 and B119 Generators in existing conduit.

S4 S

FIELD LOCATED;

MAY BE OUT OF SERVICE/

NO LONGER USED

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

Existing Infrastructure

A

Fi le

P at h

/2 1/

1:

A

M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. CLOUD, MN

CAMPUS

Project Director

Issue date Chkd By Drwn ByRevisions: Date:

Provide new pathway and conductor from B119 Generator to Existing pathway in B119

Provide new pathway and conductor from existing conduit from B119 to existing conduit to B111.

Install new conductor for B119 Generator through the steam tunnel, utilizing existing J-Hooks

Provide new pathway and conductor from steam tunnel to existing pull box.

Install new conductor in existing conduit. Ensure all new conductors are in the same conduit.

Install new conductor for B119 Generator in existing wiretray.

Install new conductor and conduit from Pull Box in B7 to new Annunciator Panels.

Install new conductor for B114 and B113 Generators in existing conduit.

Install new conductor and conduit for B112, 117, and 119 Generators from end of wire tray in B7 to new Annunciator Panels.

Install new conductor for B112, 117 and B119 Generators in existing wiretray.

Provide new pathway and conductor from B112 Generator to existing pathway in B112

Install new conductor for B117 and B119 Generators in existing conduit.

N

VHASTCWeberC Callout Install new conductor in existing conduit.

Building 7 – Details Notes:

- This drawing is for reference only.

- The yellow highlighted section below shows the path in which new conduit is needed.

- The red highlighted section below shows existing wire tray.

- Install new conduit where existing wire tray does not exist.

- New Remote Generator Annunciator Panels to be installed on south wall of 104.

- New UPS(s) for Remote Generator

Annunciator Panels to be installed on north wall of 103.

- Contractor shall be responsible for new circuit to feed Annunciator UPS(s).

Existing Wire Tray

New Conduit

New Remote Annunciator Panels

New Remote Annunciator Panel UPS(s)

Existing Pull Box

Gen Annunciator - PG5
Sheets and Views
ELEC-LOW-REDUNDANT TELE
Gen Annunciator - PG1
Sheets and Views
ELEC-LOW-REDUNDANT TELE
Gen Annunciator - PG2
Sheets and Views
ELEC-LOW-REDUNDANT TELE
Gen Annunciator - PG3
Sheets and Views
ELEC-LOW-REDUNDANT TELE
Gen Annunciator - PG4
Sheets and Views
ELEC-LOW-REDUNDANT TELE