The document is a Q&A file (falcon_flowmeters_questions_commercia 08_01.xlsx) related to a federal solicitation for the International Boundary and Water Commission (IBWC) to purchase and install new Penstock Flow Meters and Sensors at the Falcon Field Office in Texas. The solicitation (FY255701046) is a 100% small business set-aside for commercial items, specifically for instruments and related products manufacturing for measuring and displaying industrial process variables.

Key details include a site visit recommendation, with PPE requirements, by July 8, 2025, and offer submissions due by August 5, 2025, at 3:00 pm MST. The government will use a lowest price technically acceptable (LPTA) evaluation method, considering technical acceptability, technical approach, and past performance. The contract requires purchasing flow meters, sensors, installation, calibration, and associated services like programming, materials certification, and project scheduling. Invoicing will be electronic through the Invoice Processing Platform, and the contractor must provide performance and payment bonds equal to 100% of the contract price. Contractors must be SAM.gov registered small businesses with an active Unique Entity ID.

View the file

Other files

File Type Posted
falcon_flowmeters_questions_technical 07_31.xlsx XLSX spreadsheet
2- CLIN Structure - 08012025.docx DOCX document
falcon_flowmeters_questions_technical 07_31.xlsx XLSX spreadsheet
falcon_flowmeters_questions_commercia 07_31l.xlsx XLSX spreadsheet
1- PWS.pdf PDF
2- CLIN Structure.docx DOCX document
3- WD 15-5309.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Commercial

IDDATEDOCUMENTPAGESECTIONSUBJECTQUESTIONANSWER
16/20/25SAM.GOV notice2"The Government will award a contract resulting from this solicitation to the offer responsible, whose offer

conforming to the solicitation will be most advantageous to the Government, price and other factors considered.

The following factors shall be used to evaluate offers: Technical acceptability to meet IBWC requirements; Technical Approach and Past Performance.

The Government will award a contract resulting from this combined synopsis/solicitation to the lowest price

technically acceptable (LPTA), responsible offeror."Can we get confirmation and guidance on what percentage of the bid evaluation by the Government will consider technical competency?Evaluation would be in cost, technical approach, material quality and pasrt performance experience.
27/9/251 - PWS.pdf1610.2The order in which the project will be executed will require:

1. Material procurement

2. Development

3. Installation

4. Commissioning

5. Training

6. DemolitionUpon award, what is the milestone schedule for invoices, and which CLIN are associated with the milestones?There are different CLIN but on this case OTHER EXPENSES
37/15/251 - PWS.pdf1610.2 B"The Contractor may receive a progress payment for material delivered to the project site and accepted
by the COR."In typical projects, upon award there is an invoice submitted for materials, which are CLIN 001, 002, and 008. When the invoice is paid, the materials can be purchased by the vendor. It appears the PWS requires materials to be accepted onsite before payment is made. Is this correct?The IBWC does not make advance payments. We can pay invoices for materials once they are received and approved at the IBWC site. Invoicing upon award with the expectation of payment prior to receipt of parts or services should not be done.
47/15/252- CLIN Structure.docxCLIN 013: Performance and Payment BondIf we invoice for CLIN 013 upon project award, when would it be paid?The IBWC will pay for the payment and performance bond once received and verified by Acquisitions.
57/9/252- CLIN Structure.docxThe CLIN structure shows 15 days for "101: Electrical Technicians (3)" and "011: Lodging / Meals (3)"Is it required that the only people that will perform work onsite are electrical technicians?
Not Exactly, people designed by the Contractor
67/9/252- CLIN Structure.docxThe CLIN structure shows 15 days for "101: Electrical Technicians (3)" and "011: Lodging / Meals (3)"Does the number of days to perform work onsite have to be exactly 15 days?
The UOM of days is the number of days we anticipate it will take to complete task. If your estimation differs, we may ask you to clarify the hours and/or wage.
77/9/252- CLIN Structure.docxThe CLIN structure shows 15 days for "101: Electrical Technicians (3)" and "011: Lodging / Meals (3)"Does the designation "(3)" mean no more than 3 personnal will be permitted to work onsite?
tThe "(3)" is a figure is our setimation of the number of personnel needed to complete the task.
87/9/252- CLIN Structure.docxThe CLIN structure shows 15 days for "101: Electrical Technicians (3)" and "011: Lodging / Meals (3)"If there are onsoite personnel performing work other than electrical technicians, will they not be able to have their lodging/meals/expenses paid?
See above response for the use of the number 3.
97/9/25Notice ID FY255701046It is possible that there will be only one bidderWill multiple bids be required before an award is issued?We anticipate award from the offers received by the proposal due date.
107/9/251 - PWS.pdf42.1 HThe Contractor shall provide and install program or software to display the Flow Rate Meter
Information in the Display.When we program the HMI and it is commissioned, will the facility require programming software (which could have an annual license cost)?Need to be included in the submittal any cost related to the Project
117/16/251- PWS.pdf52.1 YThe Contractor shall submit a Job Safety Analysis (JSA) Form filled out to be reviewed by Power
Plant Personnel.Does IBWC have a form or will the contractor need to create one?The Contractor needs to provide one
127/16/251- PWS.pdf84.1 AMaterials Certification

The Contractor shall submit a materials certification package to COR which contains a checklist and supporting documentation for all materials used on the project. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist.

1. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a -

10d).Recognizing that electronic materials contain parts from a global market, is it only required that the brand for the product be a domestic firm?We ask you provide a list of Material, Brand, etc. so we can make a determination.
137/16/251- PWS.pdf95.1 A 1Project Schedule is to be delivered to COR within seven (7) Calendar Days of contract
award.Is it recognized that unforeseen circumstances can cause changes to the project schedule, so the initial schedule that is provided is a plan but not a firm guarantee?The Project schedule can be changed based in unforeseen circumstances equipment manufacuring delays, Power production Schedule, etc
147/16/251- PWS.pdf117.2 AAfter award of the Contract, the COR will coordinate with the Contractor to schedule a Kickoff
Meeting. The meeting shall take place prior to the beginning of any Contract work.Is it required that all attendees be physically onsite, or can there be remote online participation with an internet connection?Remote via Zoom or Teams. COR will schedule the meeting
157/16/251- PWS.pdf117.1 D 2Progress MeetingsCan these meeting be conducted remotely with an online internet connection?Yes
167/16/251- PWS.pdf139.2 C 1USIBWC is not required to obtain building permits from local jurisdictions on real estate owned

or controlled by USIBWC. However, work on utility connections, sewer connections, and fire-protection systems may require liaison with local jurisdictions. The Contractor shall be

responsible for identifying the coordination required.Can it be confirmed this is not applicable to this project?Not required
177/21/251- PWS.pdf139.2 APrior to the beginning of work, the Contractor shall be responsible for researching, coordinating,

obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities.

The Government is not responsible for any existing or newly introduced permits required before, during and/or after work on this project. What permits are required? Not required