1- PWS.pdf
PDF 225 KB Posted
- Attached to
- Flow Meters
- Solicitation number
- FY255701046
About this file
This Performance Work Statement (PWS) details a contract for the United States Section of the International Boundary and Water Commission to purchase, install, and calibrate new water flow meters and sensors at the Falcon Power Plant in Starr County, Texas. The project requires the contractor to supply and install five (5) new water flow meters with thirteen (13) ultrasonic sensors - three sensors for each of the three penstock generators and two sensors for each of two hollow jet valves. Key project requirements include:
The contractor must provide a 16-inch electronic display for the control room, install new signal wiring, remove existing equipment, develop a preventive maintenance program, and provide employee training. The project has a 240-calendar day performance period, with work to be conducted between 7:00 AM and 5:30 PM Monday through Friday. The contractor is responsible for all safety measures, permits, regulatory compliance, and must follow specific guidelines from agencies like OSHA, IEEE, and NFPA. The project will involve extensive testing, calibration, and documentation, with the final deliverables including a comprehensive testing report in PDF format and training for power plant personnel.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| falcon_flowmeters_questions_technical 07_31.xlsx | XLSX spreadsheet | |
| falcon_flowmeters_questions_commercia 08_01.xlsx | XLSX spreadsheet | |
| 2- CLIN Structure - 08012025.docx | DOCX document | |
| falcon_flowmeters_questions_technical 07_31.xlsx | XLSX spreadsheet | |
| falcon_flowmeters_questions_commercia 07_31l.xlsx | XLSX spreadsheet | |
| 3- WD 15-5309.txt | TXT text file | |
| 2- CLIN Structure.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
International Boundary and Water Commission United States and Mexico United States Section
Front Cover
Performance Work Statement (PWS) Falcon Power Plant Purchase/Install New Penstock Flow Meters and Sensors Starr County, Texas
03/28/2025
February 11, 2020 Performance Work Statement
USIBWC Solicitation Page-i of ii
TABLE OF CONTENTS
Section 1 Project Specific Information
1.1 Project Overview
1.2 General
1.3 Description of Services
1.4 Objective
1.5 Project Location
1.6 Period of Performance
1.7 Investigation of Site Conditions
1.8 Duty to Inquire
1.9 Work Restrictions
1.10 Department of Homeland Security
Section 2 Project Requirements
2.1 General
2.2 Clean-Up and Disposal of Waste Materials
2.3 Testing and Training
2.4 Warranty
Section 3 Existing Conditions
3.1 General
3.2 Government Furnished Utilities
3.3 Use of Government Land
3.4 Hazardous Materials
Section 4 Quality Requirements
4.1 Common Product Requirements
Section 5 Deliverables
5.1 General
Section 6 Project Coordination & Administration
6.1 General
6.2 Security
6.3 Safety
Section 7 Project Meetings
7.1 General
7.2 Kickoff Meeting
7.3 Progress Meetings
Section 8 Project Schedule
8.1 Description / Purpose
8.2 Schedule Requirements
Section 9 Regulatory Requirements
9.1 Contractor's Responsibility
9.2 Permits
9.3 Dates
9.4 Summary of Regulatory Documents and Agencies
Performance Work Statement February 17,2025
Page-ii of ii USIBWC Solicitation
Section 10 Measurements and Payments
10.1 Schedule of Values
10.2 Progress Payment (Lump Sum CLIN)
10.3 USIBWC Payment Processing
10.4 Invoices ................................................................................ Error! Bookmark not defined.
Section 11 DEFINITIONS ............................................................................. Error! Bookmark not defined.
11.1 Definition of Terms .............................................................. Error! Bookmark not defined.
March 28,2025 Performance Work Statement
USIBWC Solicitation Page-1 of 16
SECTION 1
PROJECT SPECIFIC INFORMATION
1.1 Project Overview
The United States Section of the International Boundary and Water Commission (USIBWC) requires services to Purchase/Install/Calibrate a new set of Water Flow Meters for Three (3) Generators Penstocks and Two (2) Hollow Jet Valves Pipes, which includes a new set of Ultrasonic Sensors Mounted On or
Drilled inside of Generators Penstock and Hollow Jet Valves Pipes. This project would be performed at the
Falcon Power Plant located at FM2098, 1 Reservoir Rd., Falcon Heights, Texas 78545.
1.2 General
This is a non-personnel services Contract to Purchase/Install/Calibrate New Set of Water Flow Meters and
Sensors to be Mounted On or Drilled inside of current Penstocks/Hollow Jet Pipes to measure with more accuracy the water flow rate in all three Generators Penstocks and Two Hollow Jets Valves Pipes. The
Government for this project shall not exercise any supervision or control over the Contract service providers performing the services herein. Such Contract service providers shall be accountable solely to the
Contractor who, in turn is responsible to the Government.
1.3 Description of Services
The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work as defined in this
Performance Work Statement except for those items specified as government furnished property and services. The Contractor shall perform to the standards in this contract.
1.4 Objective
A. To Purchase/Install/Calibrate and Test Five (5) set of New Water Flow Meters and new Set of
Ultrasonic Sensors that would be installed/mounted/drilled on/in the Penstock and Hollow Jets Valves
Pipes to measure the Water Flow Rates during the process of water releases and Power Plant
Generation.
1. The Contractor Shall Supply/Install Five (5) New Set of Water Flow Meters.
2. The Contractor Shall Install/Calibrate fourth (4) New Set of Water Flow Ultrasonic Sensors
Mounted On or Drilled in Hollow Jet Valves Pipes two (2) set for each valve.
3. The Contractor shall install/Calibrate Nine (9) New Set of Water Flow Ultrasonic Sensors on
Generators Penstock Pipes three (3) set for each Penstock.
4. The Contractor Shall Supply/Install/Program Five (5) New Water Flow Meters
5. The Contractor Shall Install/Update/Compile Signal Data from New Water Flow Ultrasonic
Sensors with New Water Flow Meters and Display the information in a Touch Screen that will be installed in the Operators Control Room.
6. The Contractor Shall Test/Calibrate and Provide a Final Report for the new Set of Water Flow
Meters and Sensors.
B. Falcon Power Plant will provide all the drawings and data available for this project.
Performance Work Statement March 28,2025
Page-2 of 16 USIBWC Solicitation
1.5 Project Location
A. The work is within the United States on land owned by the USIBWC. The Falcon Power Plant site is located at, 1 Reservoir Rd. Falcon Heights, Texas 78545.
B. The work is located completely within the United States but is adjacent to the international border with Mexico.
C. Access to the Falcon Power Plant requires crossing through the United States Port of Entry and complying with proper documentation (passports or other) as required by U.S. Customs and Border
Protection officials.
1.6 Period of Performance
A. The Contractor shall complete this work within 240 calendar days after the Contract has been awarded to the Contractor.
1.7 Investigation of Site Conditions
A. The Contractor, as well as their subcontractors, is urged to visit the jobsite and to become fully aware as to the existing conditions affecting the work to be performed under this Contract.
B. Submission of a bid shall be conclusive evidence that the Contractor has reviewed, investigated, and acknowledged all items below.
1. Conditions bearing upon transportation, disposal, handling, and storage of materials.
2. The availability of labor, water, electric power, and roads.
3. Uncertainties of weather and similar physical conditions at the site.
4. The conformation and conditions of the ground.
5. The character of equipment and facilities needed preliminary to and during work performance.
C. Submission of a bid shall be conclusive evidence that the Contractor has investigated and is satisfied as to the conditions to be encountered, the character, quality, and work to be performed, and the quantities of materials to be furnished.
D. Submission of a bid constitutes agreement that Contractor has provided written notice of all conflicts, errors, ambiguities, and discrepancies discovered in PWS, that responses to these written notices are acceptable to Contractor, and that PWS is enough to indicate and convey understanding of all terms and conditions for performing and furnishing required work.
E. Contractor has the sole responsibility to make such independent instigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the PWS.
F. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this Contract, unless that understanding, or representation is expressly stated in this Contract.
G. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
USIBWC Solicitation Page-3 of 16
1.8 Duty to Inquire
A. Contractor shall review the full PWS.
B. If during review of these items, the Contractor finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire and shall notify the Contracting Officer prior to the question submission deadline as established in the solicitation. The Contractor shall also inquire about items that are unclear or open to interpretation.
C. The Contractor shall take no advantage of any item of which they have a duty to inquire.
1.9 Work Restrictions
A. The Contractor is responsible for conducting business between the hours of 7:00 AM thru 5:30 PM, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings.
B. The Contractor may request different working hours and must do so in writing to the COR. USIBWC
Principal Engineer of Operations will make final determination as to the approval of a different work schedule.
1.10 Department of Homeland Security
In any event the staff of the US Department of Homeland Security (DHS, also known as US Customs and
Border Protection or CBP) alerts and directs any field crews to stop work in for any security reasons in the area, the Contractor shall consider this as top priority and fully always cooperate with the directions of DHS until the security alert is cleared by the DHS. In addition, the Contractor shall contact and coordinate with the COR for any additional steps to be taken during and after the security alert from the DHS is cleared.
SECTION 2
PROJECT REQUIREMENTS
2.1 General
A. The Contractor shall review Penstocks and Hollow Jet Valves available Drawings for all Three (3)
Hydro-Generators and Two (2) Hollow Jet Valves in Falcon Power Plant.
B. IBWC will have a site visit available for all contractors bidding this project, highly recommended but it won’t be mandatory.
C. The Contractor shall submit a list of best Market Available Water Flow Meters with Flow Ultrasonic
Sensors Mounted or Drilled Type with Specifications to be reviewed and approved by Power Plant
Superintendent and COR for this project.
D. The Contractor shall supply/install/calibrate five (5) New Water Flow Meters with Thirteen (13) Set of Ultrasonic Water Flow Sensors Mounted Type or Dilled Type, Three for each Penstock Generator and Two for each Hollow Jet Valve
E. The contractor shall submit a quote/bid for this project with Mounted Type Sensors or Drilled Type
Sensors depends in their expertise and quote will include specifications for the equipment that will be evaluated by IBWC Team.
F. Falcon Power Plant will provide drawings/information/standards of existing Water Flow Meters and
Sensors to help the Contractor select new equipment and to exceed the accuracy of current equipment.
Page-4 of 16 USIBWC Solicitation
G. The Contractor shall provide/install at least 16 inches (Or Bigger) Electronic Display to monitor the new meters data, and this display would be installed at Power Controllers Main Control Room., This monitor display quality and specifications will be evaluated by IBWC Team prior to be approved and purchased by the Contractor. The main function of this Display is to provide information/data about water flow rate on every Penstock or Hollow Jet Valves.
H. The Contractor shall provide and install program or software to display the Flow Rate Meter
Information in the Display.
I. Meters and Sensors will be located at the Penstocks and Hollow Jet Valves locations. The Contractor is responsible to provide, run, and install signal wire from every location to the Control room to monitor the Flow Rate.
J. The Signal wire standards/specifications and Length would be according to New Meters and Sensors along with National Electric Safety Codes (NESC) and National Electric Codes (NEC) latest
Standards.
K. The Contractor shall remove Five (5) existing Water Flow Meters located at Falcon Power Plant
Control Room and dispose of them properly.
L. The Contractor shall Purchase/ Install/Calibrate/Program Five (5) New Water Flow Meters best available in the Market, to be installed on Five (5) different locations near the Penstocks and Hollow
Jets Valves
M. The Contractor shall Provide/Install/Test/Calibrate Thirteen (13) New Set of Ultrasonic Water Flow
Sensors that can be mounted on or drilled in for Three Set (3) on each Penstock and Two Set (2) on each Hollow Jet Valves.
N. The Contractor shall Provide/Install New Sensors Signal Wiring running from Penstock’s Pipes and
Hollow Jet Valves to New Flow Meters Locations, and new communication wire from new Flow
Meters all the way to the Operators Control Room for the New Display to monitor the flow rate meters.
O. The contractor is responsible to remove and properly dispose all the communication and signal wires, old sensors, flow meters of current flow metering system.
P. The Contractor shall make any adjustment, changes necessary on the Generators Control Panels to
Install/Set up the new Water Flow Rate Digital Display.
Q. The Contractor shall connect and label each Ultrasonic Water Flow Sensor Wiring coming from
Penstock/Hollow Jet Valves to the New Water Flow Meter. In addition, each Ultrasonic Water Flow
Sensor will be permanent labeled according to each Penstock and Hollow Jet Valve.
R. The Contractor shall Program/Compile/ and Calibrate New Ultrasonic Sensors with the New Water
Flow Meters.
S. The Contractor is responsible to remove and properly dispose any asbestos found during the process to remove all equipment and new equipment.
T. The Contractor shall develop a Preventive Maintenance Program and Testing/Troubleshooting procedure for the New Water Flow Meters and Flow Rate Sensors.
U. The Contractor shall provide employee training for annual testing and calibration procedure of all
Five (5) Water Flow Meters
V. The Contractor shall provide a testing report with all results and maintenance recommendations. The testing report shall include meter/sensors devices/equipment labeling and locations.
W. The Contractor shall provide test/calibration results in electronic format (PDF Format).
USIBWC Solicitation Page-5 of 16
X. The Contractor shall comply with all Agency Safety Guidelines, National Electric Safety Codes
(NESC), IEEE, and other mechanical guidelines, standards, and codes associated with this project.
Y. The Contractor shall submit a Job Safety Analysis (JSA) Form filled out to be reviewed by Power
Plant Personnel.
Z. The Contractor shall conduct a Safety Meeting with all the personnel involved in the project and
Power Plant Personnel prior to start this project.
2.2 Clean-Up and Disposal of Waste Materials
A. The Contractor shall be responsible for the cleanup and disposal of waste materials and rubbish from the site, field office(s), and staging area(s).
B. The Contractor is responsible to provide a Portable Restroom for their Personnel and
Subcontractors daily use until the project is completed.
C. The disposal of waste materials and rubbish shall be in accordance with applicable Federal, state, and local laws and regulations and with the requirements in these Contract documents. Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply.
1. All waste unless otherwise noted in these specifications shall be disposed of at a licensed landfill or waste disposal facility.
2. Recyclables
a. The Contractor shall dispose of recyclable and reusable products through waste disposal only as a last option.
b. Scrap metal shall be donated or sold to scrap dealers or recycle centers whenever possible.
D. No excess materials shall be deposited within Government property, unless compliance confirmed by the Government. Excess materials not compliance confirmed by the Government for placement on
Government property shall be disposed of or reused by the Contractor at another site.
E. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, shall remove all temporary facilities, including, buildings, unused materials, concrete forms, and other like materials, which are not a part of the permanent work.
2.3 Testing and Training
The Contractor shall Test/Calibrate/ Compile the New Water Flow Meters with New Water Flow Sensors and provide training to power plant personnel at project completion prior to project acceptance.
A. Prior to Contract closeout, the Contractor shall provide a comprehensive project-specific Government personnel training program for the systems and equipment designed and installed under this Contract.
B. When operating procedures are not detailed in the owner’s manuals, the Contractor shall write SOPs.
These SOPs shall be available prior to the scheduled training provided below.
a. The Contractor shall furnish factory-trained representatives as required to conduct training sessions on the operation and maintenance of constructed works. The trainers shall be qualified in providing all required training and have expert knowledge of all aspects of the operation and maintenance of their systems and associated components.
Page-6 of 16 USIBWC Solicitation
b. The Contractor shall furnish all necessary training materials and furnish each student with a detailed and comprehensive manual covering all course subjects.
c. Training materials shall become the property of the Government after completion of the training.
d. Attendance at this training course will not exceed twelve (12) Government personnel. The training sessions shall be conducted at the Falcon Power Plant Office / worksite or at a
Government provided classroom.
e. The training course length will be approved by the COR. The classes shall be conducted during regular working hours of 7:00 AM to 3:30 PM, Monday through Friday, and shall exclude Government holidays.
C. The selected time for training will be scheduled shortly after completion of the project but will be before the final walk-through inspection. The Government will coordinate with the Contractor to schedule this training.
D. The Contractor shall submit to the COR a Training Program Structure with the components listed below:
a. Basis of system design, operational requirements, and criteria.
b. Documentation and use of O&M Manuals.
c. Relevant health and safety issues.
d. Emergencies, including warnings, trouble indications, shutdown and special operating instructions.
e. Operations - Start-up, normal operation, shutdown, unoccupied operation, seasonal changeover, manual operation, controls set-up and programming, troubleshooting, and alarms.
f. Adjustments.
g. Troubleshooting.
h. Maintenance as well as special maintenance and replacement sources.
i. Repairs, including diagnostic instructions, disassembly, and instructions for identifying parts and components.
E. If, at the end of the training course, there are questions from trainees that remain unresolved, the instructor shall send the answers, in writing, to the COR for transmittal to the trainees.
F. Ensure that each attendee at each training session signs a class roster daily to confirm Government participation in the training.
2.4 Warranty
A. The Contractor shall warrant that work performed under this PWS conforms to the Contract requirements and is free of any defect in equipment, material, or workmanship performed by the
Contractor or any subcontractor or supplier at any tier for a period of at least one (1) year.
1. The Contractor is responsible for providing warranties on items when the manufacturer's warranty is less than the time indicated in Paragraph 2.4B A or when the manufacturer's warranty does not cover full repair and/or replacement as appropriate.
B. The Contractor shall obtain warranties from responsible subcontractors, suppliers, and manufacturers, within sixty (60) days after completion of the applicable item of work, but no later than the date of warranty commencement.
C. The starting date of a warranty is date of substantial completion.
USIBWC Solicitation Page-7 of 16
D. A warranty requires that if a warranted item fails to meet Contract requirements, it shall be repaired, replaced, or have other remedial actions taken to bring the item into compliance with the Contract requirements. Any item damaged due to failure or malfunction of item warranted under this Contract shall be repaired or replaced at no cost to the Government.
E. The Contractor shall supply the CO with a telephone number, mailing address, email address, and contact name for the point of contact for any required warranty work.
SECTION 3
EXISTING CONDITIONS
3.1 General
A. Falcon Power Plant includes a power station with three 10.5 MW hydroelectric generating units.
Power at the plant was first generated commercially in 1954.
B. Falcon Power Plant owns a Three (3) Penstocks 14 Ft. Diameter Pipes that were installed on 1954’s all the Water Ultrasonic Sensors and Meters were installed 2010. All Water Flow meters are located inside Falcon Power Plant Control Room.
C. Testing Data:
Electric Reliability Council of Texas (ERCOT) requires all electric grid connected resource to keep a record of all relevant hardware performance information, which includes performance test for all electrical protective devices.
D. Texas Commission on Environment Quality (TCEQ) monitor water releases on Rio Grande River and water consumption is reported to this Agency.
3.2 Government Furnished Utilities
A. The Government will not be furnishing any utilities for this project including, but not limited to electricity, telephone, sewer, and natural gas.
3.3 Use of Government Land
A. The Contractor's facilities shall be arranged and operated in a manner to preserve and protect existing features, trees, and vegetation to the maximum extent practicable. The location, construction, operation, maintenance, and removal of Contractor's facilities on Government land shall be subject to the approval of the COR.
B. USIBWC land is not available for use for the Contractor's field office and/or sheds.
C. USIBWC property is available for use as the Contractor's staging and/or storage areas.
D. Housing for Contractor personnel will not be permitted on Government land.
3.4 Hazardous Materials
A. The Contractor is responsible for evaluating the existing systems to determine the presence of lead or asbestos-containing materials.
B. The Contractor shall provide a finding report to the COR to include a plan for handling and proper disposal of lead and/or asbestos-containing materials prior to the removal of the existing systems.
Page-8 of 16 USIBWC Solicitation
SECTION 4
QUALITY REQUIREMENTS
4.1 Common Product Requirements
A. Materials Certification
The Contractor shall submit a materials certification package to COR which contains a checklist and supporting documentation for all materials used on the project. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist.
1. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a -
10d).
B. Source Control
1. The Contractor shall use only materials that meet the Contract requirements.
2. Unless otherwise specified or compliance confirmed, the Contractor shall use new materials for the work. Material can be reused onsite upon written approval of COR.
3. All materials installed shall be free of defects.
4. The Contractor shall secure the Government’s compliance confirmation of the proposed source of materials to be used before their delivery.
C. Quality Control / Quality Assurance of Materials
1. Source Limitations
To the greatest extent possible for each item of work, the Contractor shall provide materials of a singular generic kind from a single source.
2. Compatibility of Options
Where more than one choice is available as an option for Contractor's selection of a product, material, or equipment, the Contractor shall select an option which is compatible with other products, materials, or equipment. Compatibility is a basic general requirement of product, material, and equipment selections.
3. Field Measurements
Verify field measurements, lines, grades, locations, and details at the jobsite prior to fabrication.
It shall be the Contractor's responsibility to conform to and satisfy actual field conditions, for accuracy of dimensions, proper fit, and for adequacy of use intended.
4. The Contractor shall correct or remove materials that fail to meet Contract requirements or that do not produce satisfactory results. The Contractor shall reimburse the Government for cost incurred if additional quality assurance sampling and testing is required by a change of source.
5. Materials not meeting Contract requirements will be rejected, unless the Government approves corrective actions in writing. Upon rejection, the Contractor shall immediately remove and replace rejected materials. Should the Contractor fail to comply with the removal of rejected materials, the Government may remove and replace defective material and the cost of testing, removal, and replacement will be deducted from the Contractor’s monthly pay estimate or final payment.
D. Hazardous Materials
The Contractor shall use materials that are free of hazardous materials. The Contractor shall notify the Government immediately when a visual observation or odor indicates that materials in required material sources or on sites owned or controlled by the Government may contain hazardous materials.
USIBWC Solicitation Page-9 of 16
E. Surplus Materials
1. The Contractor shall not take ownership of surplus materials unless otherwise indicated in the
Contract documents.
2. The Contractor shall remove and dispose of materials in accordance with Paragraph 2.2 If requested or otherwise noted in these specifications, the Contractor shall provide an appropriate level of documentation to verify proper disposal.
F. Storage and Protection
1. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area to minimize waste due to excessive materials handling and misapplication.
2. Store and protect products in accordance with manufacturers' instructions.
3. Store with seals and labels intact and legible.
4. Prevent contact with material that may cause corrosion, discoloration, or staining.
5. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
6. The Contractor shall store and handle materials to preserve their quality and fitness for the work and shall store materials so that they can be easily inspected and retested. When required by the
Government, the Contractor shall protect the material with cover, on wooden platforms, or on other hard, clean surfaces as necessary.
SECTION 5
DELIVERABLES
5.1 General
A. Deliverables include, but are not limited to:
1. Project Schedule
a. Project Schedule is to be delivered to COR within seven (7) Calendar Days of contract award.
2. Licenses and Certifications
a. The Contractor shall submit all Licenses and Certifications to perform this type of electrical work
3. Testing Program
a. The Contractor shall provide a procedure to perform the testing with minor interruption to the power plants’ daily operations.
4. Test Report
a. The Contractor shall provide the testing report with all results and recommendations.
b. The Contractor shall provide two hard copies of the report and an electronic file (PDF format).
Page-10 of 16 USIBWC Solicitation
SECTION 6
PROJECT COORDINATION & ADMINISTRATION
6.1 General
A. The Contractor shall provide all materials, equipment, labor, and services required by this
Performance Work Statement to perform the work for the Contract sum and within the Contract time.
B. The Contractor shall be responsible for ensuring that all its suppliers, manufacturers and
Subcontractors have reviewed all applicable documents relative to their work. The Contractor shall provide all labor, material, equipment, and services not provided by the Contractor’s suppliers, manufacturers, fabricators, and/or Subcontractors.
6.2 Security
The Contractor is responsible for securing the work site, equipment, and materials from vandalism and theft.
6.3 Safety
A. The Contractor is solely responsible for worksite safety while performing work or inspections on
Government property. The Contractor shall implement a safety program that protects the lives and health of personnel in the project area, prevents damage to property, and avoids work interruptions.
B. The Contractor is responsible for being cognizant of and ensuring compliance with the requirements set forth. Such responsibility shall apply to both the Contractor’s operations and those of the
Contractor’s Subcontractors.
C. The Contractor shall comply with all provisions of all applicable regulations of the Occupational
Safety and Health Administration (OSHA), 29 CFR 1910, Occupational Safety and Health Standards, and 29 CFR 1926, Construction Standards.
1. The OSHA 29 CFR 1910 and 29 CFR 1926 can be accessed at http://www.osha.gov or http://www.gpo.gov/fdsys/.
D. The Contractor’s personnel shall be required to use appropriate personal protective equipment such as, but not limited to hard hats, safety goggles, welding shields, face shields, protective footwear, protective gloves, and hearing protection.
E. The Contractor shall perform daily housekeeping. The Government will not provide trash dumpsters.
SECTION 7
PROJECT MEETINGS
7.1 General
A. The Contractor, the COR, or the CO may schedule project meetings at any time.
B. When USIBWC schedules a meeting, the COR shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The COR shall prepare the meeting agenda and distribute to all invited attendees.
C. When the Contractor schedule's a meeting, the Contractor shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The Contractor shall prepare the meeting agenda and distribute it to all invited attendees.
http://www.osha.gov/ http://www.gpo.gov/fdsys/
USIBWC Solicitation Page-11 of 16
D. The following meetings are anticipated, and the Contractor shall identify them in the Schedule:
1. Kickoff Meeting
2. Progress Meetings
7.2 Kickoff Meeting
A. After award of the Contract, the COR will coordinate with the Contractor to schedule a Kickoff
Meeting. The meeting shall take place prior to the beginning of any Contract work.
B. The purpose of the meeting is to introduce project personnel and to review responsibilities and procedures.
C. The Contractor shall reach an understanding with the Government regarding the project requirements as stated is this Performance Work Statement. This understanding shall be documented in writing and approved by the CO after the Kickoff Meeting.
D. Attendees include, but are not limited to:
1. Contractor's Project Manager
2. COR
3. Falcon Power Plant Representative
4. It is recommended that Contractor's engineers, inspectors, Subcontractors, suppliers, and other concerned parties also attend the conference. The Contractor may invite anyone they wish to this meeting.
5. All participants at the conference shall be familiar with the project and authorized to conclude matters relating to the work.
E. Agenda
Discussion of items of significance that could affect the work and project, including the following:
1. Introduction/designation of key personnel and their duties.
2. Review of the current phasing, critical work sequencing, and long-lead items.
3. Review of minimum project requirements.
4. Review of procedures for handling and processing modifications, RFIs, deliverables, and applications for payment.
5. Preparation of deliverable documents.
6. Use of site.
7. Work restrictions.
8. USIBWC and other occupancy requirements.
9. Safety and first aid.
10. Security.
11. Maintenance of project site.
12. Working hours.
F. Meeting Minutes
The Contractor will record the discussions of the meeting and distribute the minutes to all attendees for review prior to finalizing.
Page-12 of 16 USIBWC Solicitation
7.3 Progress Meetings
A. The COR will schedule progress meetings once the Contractor has mobilized onsite. The COR will conduct and issue minutes of the meetings. Meeting minutes will become official Contract correspondence.
B. The Government may call other meetings on an "as needed" basis.
C. The purpose of these meetings shall be to analyze the progress of the work, resolve conflicts, and in general coordinate the operation of all organizations active at the project site.
SECTION 8
PROJECT SCHEDULE
8.1 Description / Purpose
A. The Contractor shall prepare a project schedule which shall reflect completion of all work under this
Performance Work Statement and shall include allotted time for all related activities by other agencies within the allotted Contract period.
B. The first compliance confirmed schedule that properly shows all activities within the allotted period shall be the baseline schedule.
8.2 Schedule Requirements
A. Project schedule submittals for compliance confirmation shall include an electronic pdf file.
1. All abbreviations shall be defined.
2. Each project schedule shall show a revision date.
B. The Contractor shall provide an updated schedule with any invoices.
C. Schedule Requirements
1. Baseline Schedule
a. A complete baseline schedule shall be submitted. The Government will review the project schedule and submit comments and required revisions within fourteen (14) calendar days of receipt.
(1) Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Government's compliance confirmation of the schedule.
b. Upon compliance confirmation of the baseline schedule, save the schedule as a baseline and update monthly. The schedule update will be used to evaluate the Contractor's progress and invoice payments.
2. Baseline Schedule Preparation
Prepare a list of all activities required to complete the work. The baseline schedule shall include all planned work activities and sequences and show Contract completion within the number of calendar days specified in the Contract.
a. Activities
(1) Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
USIBWC Solicitation Page-13 of 16
b. The baseline schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work.
c. Time Frame
The proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
(1) Incorporate inspections, permitting, repairs, and other activities that may affect the completion of the Contract in the project schedule.
(2) Show a beginning date, ending date, and duration in number of calendar days for each activity.
(3) Show float for each work activity.
d. Constraints
Include constraints and work restrictions in schedule and show how the sequence of work is affected.
e. Milestones
Include milestones indicated in this document in schedule, including, but not limited to, the cleaning, inspection, repair, or other items as determined by the Contractor.
SECTION 9
REGULATORY REQUIREMENTS
9.1 Contractor's Responsibility
A. It is the Contractor’s responsibility to perform work in compliance with all applicable requirements of federal, state, and local laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined in 9.4 below.
B. It shall be the responsibility of the Contractor to acquire copies of all applicable codes, regulations, and standards for ready reference.
C. In instances where requirements are in conflict, the stricter standard shall apply.
D. All inspections, observations, or tests required for code compliance are the responsibility of the
Contractor.
9.2 Permits
A. Prior to the beginning of work, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities.
The Government is not responsible for any existing or newly introduced permits required before, during and/or after work on this project.
B. The Contractor shall be responsible for and shall give and maintain all notices required by applicable regulations, laws, or permitting authorities pertaining to work on of this project.
C. Building Permits
1. USIBWC is not required to obtain building permits from local jurisdictions on real estate owned or controlled by USIBWC. However, work on utility connections, sewer connections, and fire-protection systems may require liaison with local jurisdictions. The Contractor shall be responsible for identifying the coordination required.
Danilo Martinez Highlight
Page-14 of 16 USIBWC Solicitation
2. Though the USIBWC is not required to obtain building permits from local jurisdiction, the
Contractor shall comply with state and local building codes to the maximum extent practicable.
USIBWC has the final authority to accept or reject any recommendation from state and/or local government officials.
9.3 Dates
A. For all related standards and regulatory requirements in this document, the version, edition, or year shown indicates the governing version.
B. All Public Laws, Code of Federal Regulations (CFR), Federal Acquisition Regulation (FAR), Executive Orders (EOs), Management Policies, Government Directives, Government Standards, refer to the original document as well as any subsequent amendments, corrections, and/or additions.
1. The latest amendments, corrections and additions are to be assumed applicable in the same way as the document itself.
2. The version in effect as of the issuing date of the Solicitation for this project governs unless the law, regulation, order, policy, directive, or standard is updated with a retroactive clause.
9.4 Summary of Regulatory Documents and Agencies
Regulatory requirements applicable to this project are listed below.
A. Institute of Electrical and Electronics Engineers (IEEE)
1. 2017 National Electrical Safety Code (NESC)
B. National Fire Protection Association (NFPA)
1. NFPA 70-2017 Standard for Electrical Safety in the workplace (also known as the National
Electrical Code [NEC]), with Errata through 70-17-4 and TIA through 17-4
C. Occupational Safety and Health Administration (OSHA)
1. Occupational Safety and Health Standards (29 CFR 1910)
a. https://www.osha.gov/law-regs.html
2. Construction Standards (29 CFR 1926)
a. https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS& p_toc_level=1&p_keyvalue=Construction
D. Public Laws and Acts
All Public Laws and Acts can be found at http://www.gpo.gov/fdsys/
1. An Act Authorizing the Transfer of Certain Real Property for Wildlife, or other purposes [16
USC 667b]
2. Buy American Act [41 USC 10a - 10d]
3. Clean Air Act
4. Clean Water Act
5. Endangered Species Act (ESA)
6. Federal Environmental Pesticide Control Act [7 USC Chapter 6]
7. Fish and Wildlife Act of 1956 [16 USC 742f (a) (4) and 16 USC 742f(b)(1)]
8. Migratory Bird Treaty Act (MBTA) [16 USC 703 through 712]
9. National Environmental Policy Act (NEPA) [42 USC 4321-4347]
10. National Historic Preservation Act (NHPA) of 1966
11. National Wildlife Refuge System Improvement Act of 1997 https://www.osha.gov/law-regs.html https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction http://www.gpo.gov/fdsys/
USIBWC Solicitation Page-15 of 16
12. Refuge Recreation Act [16 USC 460k-1 and 2]
13. Resource Conservation and Recovery Act (RCRA)
14. Solid Waste Disposal Act
15. Toxic Substance Control Act
16. Wild and Scenic Rivers Act
E. State of Texas
1. Texas Engineering Practice Act and Rules Concerning the Practice of Engineering and
Professional Engineering Licensure
a. http://www.tbpe.state.tx.us/downloads/law&rules.pdf
SECTION 10
MEASUREMENTS AND PAYMENTS
10.1 Schedule of Values
A. Breakdown each lump sum item into component work activities used in the schedule for which invoices may be requested. The work activities broken out within the Schedule of Values shall be integrated into and made a logical part of the baseline schedule submitted under this section.
1. The total costs for the component work activities shall equal the Contract price for that lump sum item.
2. Overhead, general, and administrative expenses, escrow, bonds, profit, and other across the board markups shall be applied to each line in the Schedule of Values uniformly.
3. An unbalanced Schedule of Values providing for overpayment to the Contractor for items of work to be performed first will not be compliance confirmed but shall be revised by the
Contractor and resubmitted until acceptable to the COR. If requested by the Government, the
Contractor shall furnish full copies of subcontracts showing actual costs.
4. The Government may request data to verify accuracy of dollar values.
B. Do not break down unit price items. Use only the Contract price for unit price items.
C. An acceptable Schedule of Values shall be agreed upon by the Contractor and COR before the first invoice is processed.
D. The following items shall have an entry in the Schedule of Values. The Contractor may breakdown each item listed into subsections if they so choose. The Contractor may add additional items. The items shown are the minimum required.
1. Mobilization/Demobilization
2. Inventory of current Flow Meter System
3. New Flow Meters
4. Calibration and Testing
5. New Flow Meters and Sensors Equipment and Training http://www.tbpe.state.tx.us/downloads/law&rules.pdf
Page-16 of 16 USIBWC Solicitation
10.2 Progress Payment (Lump Sum CLIN)
A. The Schedule of Values shall be used to prepare an invoice request for the items, or portions of items, of the work completed during the monthly progress period.
B. The Contractor may receive a progress payment for material delivered to the project site and accepted by the COR.
C. As the activity progresses, the Contractor will be paid the value based on the percentage associated with the activity in the Schedule of Values.
D. The progress payments are made to benefit the Contractor. These payments are made based upon preliminary deliverables, preliminary field inspections, preliminary testing data, and/or preliminary reports. Progress payments do not constitute acceptance of any portion of the work and do not reduce the Contractor’s liability to replace unsatisfactory work, material, or equipment.
E. No progress payment will be made when, in the judgment of the Government, the work is not proceeding in accordance with the provisions of the Contract.
10.3 USIBWC Payment Processing
A. The Contractor shall submit invoices via the Invoice Processing Platform (IPP) System. Further information on IPP will be provided at the time of the award.
B. The invoice for this Contract shall not be combined with any other work or other Contracts; it shall be for this Contract only.
10.4 Invoices
A. USIBWC Payment Processing
B. A. The Contractor shall submit an electronic invoice pursuant to FAR 5.212-4(g) to be processed via the IPP system at www.ipp.gov. B. A copy of the invoice shall be emailed to the CO and COR concurrently.
C. C. The invoice for this Contract shall not be combined with any other work or other Contracts; it shall be for this Contract only.
--End of Performance Work Statement--