RATING REQUIREMENT: FREQUENCY:
OPERATIONS AREAS
Wash furniture to remove scuff marks 1 time per month
Dust all flat surfaces and ledges 1 day per week
Clean the console (top only—NOT instrument areas, NOT sloping surface)
3 days per week
Clean ceiling tiles 2 times per year
ADMINISTRATIVE AREAS
Wash furniture to remove scuff marks 4 times per year
Vacuum upholstered chairs 1 time per month
Dust office furniture and equipment 2 days per week
Clean all metal hardware throughout office 4 times per year
ALL AREAS
Empty wastebaskets 5 days per week
Wash wastebaskets (see comments) 1 time per month
Vacuum ceiling vents 1 time per month sweep and damp mop tile floors 1 time per month
Polish/clean door kick plates and thresholds 2 times per year
Clean light fixtures (removing & cleaning covers) 4 times per year
Vacuum all carpets in all areas 3 days per week
Shampoo all carpets (except in Cab—see operations area for Cab carpet shampooing frequency)
3 times per year
Dust Venetian blinds 1 time per month
Spot clean woodwork, walls and partitions As required
Clean handrails, steps & landings in stairwell 1 time per month
Strip and wax all tile floors 2 times per year
Clean door and partition glass 1 day per week
Wash all exterior windows inside and out 2 times per year
Replace burnt out light bulbs (except exit lights) As needed/ within 72 hours
Buff all tile floors throughout building 1 time per month
Wax all tile floors throughout building 1 time per quarter
Strip and recoat/wax all tile floors throughout building 1 time per year
ENTRY AREAS
Vacuum entrance areas 5 days per week
Clean/vacuum all entrance doormats 3 days per week
Wash entrance door glass 1 time per month
RESTROOMS AND SHOWER ROOM
Clean fixtures and chrome fittings 3 days per week
Clean/refill all dispensers with stock (see comments) 3 days per week
Clean mirrors 3 days per week
Sweep and mop floors 3 days per week
Sanitize toilets, urinals and toilet seats 3 days per week
Spot clean restroom walls, partitions and doors 1 time per month
Wash walls, partitions and doors 1 time per year
Linda C Williams Typewritten Text
FREQUENCY SCHEDULE
Linda C Williams Typewritten Text
Linda C Williams Typewritten Text
Disinfect and clean shower enclosure 2 times per month
KITCHEN/LOCKER AREA
Clean and deodorize refrigerators, wash inside and out 1 time per month
Clean and disinfect Kitchen sink and counter area 3 days per week
Clean outside of cabinets 3 days per week
Clean outside of all appliances 3 days per week
Spot clean walls 1 time per month
Clean microwave interior and exterior 3 days per week
Clean refrigerator handles 3 days per week
Empty trash compactor N/A
Sweep and mop floors 3 days per week
Machine scrub and wax tile floors 1 time per month
Strip and wax floors 2 times per year
ELEVATOR
Clean and wash paintwork N/A
MISCELLANEOUS
Wash and disinfect drinking fountains 3 days per week
Pick up trash in immediate tower parking lot 1 day per week
Check all windows and doors upon completion of work for building security.
End of each work period
Clean Mylar Tower Cab Shades using ONLY specified cleaning agent “Plexus” and COR approved soft cloths
1 time per month
Wash Tower Cab windows inside and out 1 time per month
PEST CONTROL
Inside building spray for bugs (flies, moths, bees, spiders, etc.)
As needed, not less than twice yearly
Outside perimeter of building spray for bugs (flies, moths, bees, spiders, etc.)
As needed, not less than 3times per year
Non-liquid methods of bug control (lights, etc.) As needed, not less than 2 times per year
Fly strips, sticks and other methods As needed, as often as daily Rodent Control; check & replace traps each visit As needed
COMMENTS:
Maintain adequate extra restroom supplies on site for use, if needed, between normal services
All cleaning supplies and equipment to be furnished by contractor
No requirement to wash wastebaskets if lined 1 time per month
RATING SYSTEM:
X = Work Not Scheduled to be Done This Reporting Period 1 = Work Apparently Not Done 2 = Work Done Poorly 3 = Work Done Satisfactorily 4 = Work Done Exceptionally Well