Form D v2.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Bus facility paving - Southampton
Solicitation number
BD-21-1206-40000-40000-58890
Issued by
Suffolk County, Massachusetts

About this file

The document provided is a Form D Invoice Backup form for a state and local contract opportunity related to bus facility paving in Southampton, Massachusetts. The form includes a detailed list of 23 line items such as hot mix asphalt pavement milling, unclassified excavation, gravel base course, manhole/catch basin adjustments, pavement markings, and various drainage and contingency work. The contract opportunity appears to be for a paving project at a bus facility located in Southampton, with quantities and unit costs provided for the various line items. No specific response dates, award dates, or contract term information is included in the provided documents.

The pricing terms, set asides, funding requirements, and other salient details are not explicitly stated in the provided documents. The form indicates a total lump sum amount, but does not provide any further information regarding pricing structure, funding sources, or incumbent contractors. Additional details regarding the overall contract opportunity would be needed to fully summarize the pricing and financial aspects.

View the file

Other files

File Type Posted
02 C.PDF PDF
Boston PW~9.pdf PDF
Addendum 2~15.pdf PDF
Site visit attendees~3.pdf PDF
210302 Southampton Paving Plan 002.pdf PDF
Addendum 1~23.pdf PDF
Boston PW~11.pdf PDF
Initial Bid Opening Summary RFP ~5.pdf PDF
RFP Southampton Paving RFP 25C-21 03.03.2021 v2.pdf PDF
Form C v2~1.xlsx XLSX spreadsheet
Form C~3.xlsx XLSX spreadsheet
RFP Southampton Paving RFP 25C-21 03.03.2021.pdf PDF
03 U.PDF PDF
Form D~5.xlsx XLSX spreadsheet
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Form D Invoice Backup

Form D: Standard Invoice Backup
CONTRACTOR NAME:
LOCATION:
DATE:
No.Item DescriptionInv. Qty.UnitUnit CostInvoice Amount
1Hot Mix Asphalt Pavement Milling 0-4"SY$ - 0$ - 0
2Hot Mix Asphalt Pavement Milling 4-8"SY$ - 0$ - 0
3Unclassified ExcavationCY$ - 0$ - 0
4Gravel Base CourseCY$ - 0$ - 0
5Adjust Manhole/Catch Basin/Valve CoverEA$ - 0$ - 0
6Install New Frame and Cover/GrateEA$ - 0$ - 0
7Crack RepairLF$ - 0$ - 0
8Tack CoatGAL$ - 0$ - 0
92.5" Superpave Surface Course 19.0 Polymer (SSC-19-P)TON$ - 0$ - 0
104.5" Superpave Base Course 37.5 (SBC-37.5)TON$ - 0$ - 0
11Saw Cut/Crack SealLF$ - 0$ - 0
12Pavement MarkingsLF$ - 0$ - 0
13Catch BasinEA$ - 0$ - 0
14ManholeEA$ - 0$ - 0
1512" Reinforced Concrete PipeLF$ - 0$ - 0
16HydrantEA$ - 0$ - 0
17Wire Loop InstallationLF$ - 0$ - 0
18Safety/Quality/Construction Management PlanLS$ - 0$ - 0
19Contingency (10%)LS$ - 0$ - 0
20Standpipe System RepairALL$ - 0$ - 0
21Drainage Install Contingency/PermittingALL$ - 0$ - 0
22Monitoring Well DecommissioningALL$ - 0$ - 0
23Police DetailsALL$ - 0$ - 0
TOTAL LUMP SUM (lines 1-23)$ - 0