210302 Southampton Paving Plan 002.pdf
PDF 1 MB Posted
- Attached to
- Bus facility paving - Southampton
- Solicitation number
- BD-21-1206-40000-40000-58890
- Issued by
- Suffolk County, Massachusetts
About this file
This document outlines the proposed paving plan for the Southampton Bus Garage in Massachusetts. The project includes milling and overlaying approximately 182,790 square feet of asphalt paving over four concurrent phases, with work scheduled to take place over four total weekends. Phase 1 covers Moore Street, Phase 2 addresses the bus maintenance yard, Phase 3 focuses on the TPD parking area, and Phase 4 involves full depth reconstruction of the bus wash exit. The project also includes installing 65 linear feet of 12-inch RCP drainage piping and a new catch basin. Work is to be coordinated with bus operations to maintain access throughout construction.
The contract provides no pricing details, set-asides, or information about the incumbent or funding sources. The document indicates the project is being solicited by the state of Massachusetts, but does not provide the contract ID or other procurement details.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 02 C.PDF | ||
| Boston PW~9.pdf | ||
| Addendum 2~15.pdf | ||
| Site visit attendees~3.pdf | ||
| Addendum 1~23.pdf | ||
| Boston PW~11.pdf | ||
| Initial Bid Opening Summary RFP ~5.pdf | ||
| Form D v2.xlsx | XLSX spreadsheet | |
| RFP Southampton Paving RFP 25C-21 03.03.2021 v2.pdf | ||
| Form C v2~1.xlsx | XLSX spreadsheet | |
| Form C~3.xlsx | XLSX spreadsheet | |
| RFP Southampton Paving RFP 25C-21 03.03.2021.pdf | ||
| 03 U.PDF | ||
| Form D~5.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Gate 19
SOUTHAMPTON BUS GARAGE PAVING PROJECT
PROPOSED PAVING PLAN
NOTES:
1. LIMITS OF WORK DEPICTED ARE APPROXIMATE. TO BE VERIFIED IN CONSTRUCTION
WITH FIELD STAFF.
2. FOUR (4) TOTAL WEEKENDS WILL BE ALLOWED FOR CONSTRUCTION ACTIVITIES.
3. CONCURRENT PHASES PENDING APPROVAL FROM OPERATIONS.
Phase 1A – Moore St.
Limits: Southampton St - Gate 19 Type: 2.5” Mill & Inlay (19.0 mm) Days: Saturday/Sunday Times: Saturday 12PM-11:59PM Sunday – No Restriction Duration: 1 Weekend 2
2 Consecutive Calendar Days Phasing: Concurrent with all phases. 3 Limitations: Keep one lane access to Moore Street for Bus Operations. Keep access to Waldo Bros as required.
HMA Pvmt. Construction Type
2.5” Mill & Inlay (143,620 SF) Superpave Surface Course 19.0mm Polymer
2” Mill & Inlay (38,500 SF) Surface Course 12.5mm Polymer
Full Depth Reconstruction (670 SF) Install Drainage 10” 19.0mm Poly (SSC 19-P) [ 4 x 2.5” L ifts]
Phase 1B - Moore St.
Limits: Gate 19 to South Bay Ave Type: 2.5” Mill & Inlay (19.0 mm) Days – Saturday/Sunday Times – No Restrictions Duration: 1 Weekend 2
2 Consecutive Calendar Days Phasing: Concurrent with all phases. 3 Limitations – Keep Bus Operation access at intersection with Gate 19 and South Bay Ave.
Phase 2 – Bus Maintenance Yard Limits: Adjacent to Maint. Garage Type – 2.5” Mill & Inlay (19.0 mm) Days – Saturday/Sunday Times – No Restrictions Duration: 2 Weekends 2
2 Consecutive Calendar Days/Wknd Phasing: Concurrent with all phases. 3 Limitations – Keep Bus Operation access at all times.
Phase 3 - TPD Parking Limits: Parking Area and Access Type – 2” Mill & Inlay (12.5 mm) Days – Saturday/Sunday Times – No Restrictions Duration: 2 Weekends 2
2 Consecutive Calendar Days/Wknd Phasing: Concurrent with all phases.3 Limitations – Maintain Access to Transit Police Building
Phase 4 – Bus Wash Exit Limits: Adjacent to Maint. Garage Type – Full Depth Reconstruction Days – Saturday/Sunday Times – No Restrictions Duration: 1 Weekend 2
2 Consecutive Calendar Days Phasing: Concurrent with all phases. 3 Limitations – Coordinate with Bus Maint. for Bus Wash Closure eleguelaff Rectangle eleguelaff Line eleguelaff Text Box
INSTALL 12” RCP
(65LF)
eleguelaff Text Box
INSTALL NEW CATCH BASIN
eleguelaff Line eleguelaff Line