About this file
This is a bidder price response form for RFP 114-26 Remote Terminal Unit (RTU) Upgrade issued by the Massachusetts Bay Transportation Authority (MBTA). The project encompasses the furnishing and installation of RTU upgrade kits at substations (17 units), a new RTU at Dewey TPSS (1 unit), and a new STB at Dewey TPSS (1 unit), along with technical support equipment. Bidders are required to submit firm fixed unit costs for each line item in accordance with the specifications and requirements outlined in the RFP. The form mandates that all individual items must be completed; failure to fill in any item will result in bid rejection at the MBTA's discretion.
The pricing structure includes an Asset Management Allowance of $20,000 and a Risk Allowance of $87,000, bringing the subtotal to $107,000 before the completion of the remaining line items. All quoted prices must be inclusive of ancillary charges such as prevailing wages, tooling, equipment, transportation costs, customs, duty charges, and other associated costs. Bidders must provide unit costs for items 1-3 through 1-6, which are currently showing zero values pending bidder submission. The form requires firm fixed pricing with no adjustments permitted for changes in labor, material, or overhead costs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form C
| Form C: Requested RFP Pricing Form |
| RFP 114-26 Remote Terminal (RTU) Upgrade |
| Bidder: |
| Date: |
Bidders are required to quote firm fixed Unit Cost(s) in the Unit Cost column below. The quoted prices shall be inclusive of ancillary charges including but not limited to prevailing wages, tooling, equipment, transportation costs, customs, duty charges, and other associated charges. Bidders shall quote only on goods and services in strict accordance with the specifications / requirements. Bidders must fill in each individual item. The MBTA reserves the right to reject any bid if one or more individual item is left blank.
| Line Item | Description | Measurement | Unit Cost | Quantity | Cost |
| 1-1 | Asset Management | Allowance | $ 20,000.00 | 1 | $ 20,000.00 |
| 1-2 | Risk Allowance | Allowance | $ 87,000.00 | 1 | $ 87,000.00 |
| 1-3 | Furnish and Install RTU Upgrade Kits at Substation | Per Unit | 17 | $ - 0 | |
| 1-4 | Furnish and Install New RTU at Dewey TPSS | Per Unit | 1 | $ - 0 | |
| 1-5 | Furnish and Install RTU New STB at Dewey TPSS | Per Unit | 1 | $ - 0 | |
| 1-6 | Technical Support Equipment | Lump Sum | 1 | $ - 0 | |
| TOTAL | $ 107,000.00 |