Appendix B - RFP 114-26 Remote Terminal Unit Upgrade Scope of Work.pdf

PDF 9 MB Posted

Attached to
RFP 114-26 Remote Terminal Unit (RTU) Upgrade
Solicitation number
BD-27-1206-40000-40000-133014
Issued by
Massachusetts

About this file

This is a Scope of Work document for RFP 114-26, a Remote Terminal Unit (RTU) Upgrade project for the Massachusetts Bay Transportation Authority (MBTA), involving the modernization of eighteen existing power SCADA remote terminal units across traction power substations and unit substations. The project requires furnishing, installing, and testing either completely new RTUs or RTU upgrade kits to replace existing Micro 1/C and Sage RTUs manufactured by Tejas Electronics (Telvent) that have been in operation for approximately 30 years. The new RTUs must be capable of communicating with the MBTA's existing SCADA master station via both the existing copper wire system using Telvent Series V protocol and via fiber optic cable over the MBTA Secure Wide Area Network (SWAN) using DNP 3.0 protocol. The work encompasses modifications to the SCADA Master Station at 45 High Street and Cabot, as well as integration with the new Quincy Operations Control Center, including updates to SCADA databases, network topology, system displays, alarm reporting functions, and trend displays. The contractor must provide comprehensive training to MBTA operations and maintenance personnel, spare parts including one set of CPU hardware for every three substations (minimum of six) and ten percent of all I/O modules, two laptop computers with specified hardware requirements, and a full sixty-month warranty with technical and maintenance support including firmware and protocol updates.

Pricing is structured as a lump sum contract with no separate measurement and payment for individual sections; all costs related to design, materials, equipment, labor, installation, testing, commissioning, training, and support services must be included in the total contract price. The system vendor must be a firm engaged in supplying SCADA systems to electrical utilities or transit agencies for a minimum of five years, having supplied at least twenty systems and completed at least three previous RTU upgrade projects, with demonstrated expertise in Telvent Series V protocol and DNP 3.0. The contractor is responsible for all software integration, database modifications, network configuration, and coordination with the MBTA and other contractors; SCADA system modifications must be scheduled during non-revenue hours (12:00 a.m. to 5:00 a.m.) with PROD rollouts occurring on Sunday mornings, and point-to-point integration testing must be conducted on-site with all required parties present. The new RTU platform must support dual processors operating at or above 1 GHz, accommodate up to 16,384 inputs per station, record and timestamp up to 10,000 events in memory, include 4 GB of main memory with expansion to 1 TB, support sixteen communication interfaces including Ethernet LAN, fiber optic connections, and RS-232/485 serial ports, and provide local programmable logic control capabilities compliant with IEC 61131. All equipment must operate in harsh substation environments across temperature ranges of -10 to 40 degrees Celsius and humidity levels of 5 percent to 95 percent non-condensing, maintain a design life of 20 years, and comply with IEEE C37.90.1 surge withstand standards and ANSI/IEEE Standard 80 grounding requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OCEPS07, TASK 19 ELECTRICAL IDENTIFICATION 100% SUBMITTAL

2026 16195 - 1 1/3/2026

SECTION 16195

ELECTRICAL IDENTIFICATION

PART 1 - GENERAL

1.1 DESCRIPTION OF WORK

A. Work Included: This Section specifies the furnishing and installing of nameplates and labels, wire and cable markers, and conduit markers. Engraved nameplates shall be designed, furnished, and installed for every major piece of electrical equipment shown on the single-line diagrams. The single-line diagrams are shown on the Contract drawings.

B. Related requirements are included in, but not limited to, the following Sections.

1. Section 16050: BASIC MATERIALS AND METHODS FOR ELECTRICAL WORK

1.2 REFERENCES

A. National Fire Protection Association (NFPA)

1. NFPA 70 - National Electrical Code

1.3 SUBMITTALS

A. Submit in accordance with Section 01300- SUBMITTALS, except as modified herein.

B. Product Data/Catalog Cuts

1. Nameplates and labels.

2. Wire and cable markers.

3. Conduit markers.

C. Certificates of Compliance

1. Nameplates and labels.

2. Wire and cable markers.

3. Conduit markers.

D. Manufacturer's Instructions

1. Delivery, handling, transportation, storage, and protection.

2. Surface preparation, and application/installation of products.

3. Application conditions and limitations of use.

E. Engraved nameplate schedule shall be submitted for review and approval by the Engineer.

2026 16195 - 2 1/3/2026

1.4 DELIVERY, HANDLING, TRANSPORTATION, STORAGE AND PROTECTION

A. Delivery, handling, transportation, storage, and protection shall be in accordance with the manufacturer's instructions, unless otherwise required by Division 1.

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS

A. Conform to requirements of NFPA No. 70.

B. Provide products listed and classified by Underwriters Laboratories, or a testing firm acceptable to authorities having jurisdiction as suitable for purpose specified and indicated.

1. The Contractor shall submit certificates of compliance for products provided.

2. The Contractor shall provide the manufacturer's instructions indicating application conditions and limitations of use stipulated by the product testing agency.

2.2 NAMEPLATES AND LABELS FOR EQUIPMENT

A. Nameplates and Labels

1. Engraved three-layer laminated plastic, black letters on white background.

B. Locations

1. Electrical equipment including, but not limited to, each electrical distribution enclosure and control equipment enclosure, communication cabinets, transfer switches and panels.

C. Letter Sizes:

1. Use 1/4-inch letters for identifying individual equipment and loads.

2. Use 1/4-inch letters for identifying grouped equipment and loads.

3. Use 1/8-inch letters for identifying voltage, phase, and neutral.

2.3 WIRE MARKERS

A. Wire markers shall be manufactured by Panduit, Ideal, 3M, or approved equal.

1. Description: tubing type wire markers.

2. Locations: Each conductor at panelboard, gutters, pull boxes, outlet and junction boxes and each load connection.

B. Legend

1. Power and lighting circuits: Branch circuit or feeder number indicated on the Drawings.

a. Control circuits: Control wire number indicated on schematic and interconnection diagrams on the Drawings.

2026 16195 - 3 1/3/2026

2.4 CONDUIT MARKERS

A. Conduit markers shall be manufactured by Banded Labeling System, Brady USA, Inc., Panduit, or approved equal.

B. Location: Furnish markers for each conduit longer than 6 feet.

C. Spacing

1. Spacing shall be 20 feet on center, unless otherwise specified.

a. Fire alarm conduits shall be marked every 10 feet.

b. 13.8 kV system shall be marked for its entire length.

D. Color:

System Name Color

1. 480-volt system Orange

2. 208-volt system Blue

3. Fire alarm system Red

4. Telephone system Gray

5. 13.8 kV system Yellow

6. Management information system Purple

7. Passenger assistance system Green

8. Public address system White

9. Closed circuit television system Black

10. Power SCADA Pink

E. Legend:

System Name Legend

1. 480-volt system 480 V

2. 208-volt system 208 V

3. Fire alarm system FAS

4. Telephone system TS

5. 13.8 kV system 13.8 kV

6. Management information system MIS -

7. Passenger assistance system PNRA

8. Public address system PAS

9. Closed circuit television system CCTV

10. Power SCADA PSCADA

F. Conduit Markers shall be brass tags located on/at the conduit entrance for conduits that go through the floor or the wall. Markers / brass tags shall be provided at both ends of each conduit. The Brass tag indicates "to" and "from" and the equipment it serves.

PART 3 - EXECUTION

3.1 PREPARATION

A. Degrease and clean surfaces to receive nameplates, labels, and markers, in accordance with the manufacturer's instructions.

2026 16195 - 4 1/3/2026

3.2 APPLICATION INSTALLATION

A. Application/installation of products shall be in accordance with the manufacturer's instructions.

Nameplates and Labels

1. Install nameplates and labels parallel to equipment lines.

2. Secure nameplate to equipment front using screws.

3. Secure nameplate to inside surface of door on panelboard that is recessed in finished locations.

B. Conduit Identification by Markers

1. Identify conduit using conduit markers.

a. Apply conduit markers parallel to conduit runs.

C. Identify underground conduits using underground warning tape. Install one tape per trench at 12 inches below finished grade.

D. Install conduit markers / brass tags on each conduit or at the conduit entrance for conduits that go through the floor or the wall. Markers / brass tags shall be provided at both ends of each conduit.

PART 4 - MEASUREMENT AND PAYMENT

4.1 GENERAL

A. Separate measurement and payment will not be made for the work under this section. All costs in connection therewith shall be included in the total Contract Lump Sum price.

END OF SECTION

OCEPS07, Task 19 TRACTION POWER EQUIPMENT- 100% DESIGN

2026 GENERAL REQUIREMEMNTS 1/3/2026

16203 - 4

37. ICEA S-96-659

(NEMA WC71)

Standard for Nonshielded Cables Rated 2001-5000 Volts for Use in the Distribution of Electrical Energy

38. ICEA S-93-639

(NEMA WC 74)

Nonshielded Power Cables Rated 5000-46000 Volts for the Distribution of Electrical Energy

39. NEMA AB 3 Molded Case Circuit Breakers and Their Application

40. NEMA FU-1 Low Voltage Cartridge Fuses

41. NEMA ICS 1 Industrial Control and Systems: General Requirements

42. NEMA ICS 4 Industrial Control and Systems: Terminal Blocks

43. NEMA KS 1 Enclosed and Miscellaneous Distribution Equipment Switches

44. NEMA LA 1 Surge Arresters

45. NEMA LS 1 Low Voltage Surge Protection Devices

46. NEMA PE 5 Utility Type Battery Chargers

47. NEMA SG 4 Alternating Current High Voltage Circuit Breaker

48. NEMA SG 6

49. NFPA 70

Power Switching Equipment

National Electric Code

50. NEMA ST 20 Dry-Type Transformers for General Applications

51. NEMA TR 1 Transformers, Regulators, and Reactors

52. NEMA 250 Enclosures for Electrical Equipment (1000V Max.)

53. UL-44 Thermoset-Insulated Wires and Cables

54. UL-224 Extruded Insulating Tubing

55. UL-508 Industrial Control Equipment

56. UL-1581

57. EIA 232-F

58. EIA 455-11-177A

59. IEEE C37.90

Standard for Safety Electrical Wires, Cables and Flexible Chords

Interface Between Data Terminal Equipment and Data Circuit Terminating Equipment Employing Serial Binary Data Interchange

Standards for Test measurements and Inspection for Fiber optic Cables, Connectors and/or Other Fiber Optic devices.

Standard Electrostatic Discharge Tests for Protective Relays

OCEPS07, Task 19 TRACTION POWER EQUIPMENT- 100% DESIGN

2026 GENERAL REQUIREMEMNTS 1/3/2026

16203 - 5

60. IEEE 802.3

61. UL 1581

62. NETA ETT-2000

63. NETA ATS

64. IEC 61850

Carrier Sense Multiple Access with Collision Detection.

Standard for Safety Electrical Wires, Cables and Flexible Cords

Standard for Certification of Electrical Technicians

Standard for Acceptance testing Specifications for Electrical Power Equipment and Systems.

Communication Protocol for Network Automation in Substations

C. Where any requirements specified herein or shown on the Contract Drawings exceed those of the above listed standards, the Contractor shall adhere to the higher standard. In case of conflict in requirements between two or more standards, the decision of the Engineer shall be final.

D. In cases where equipment from U.S. suppliers is not available, equivalent British, European, Japanese or IEC standards are acceptable, provided a tabulation is furnished citing the comparison between the applicable U.S. and the equivalent non-U.S. standards. In addition, the non-U.S. suppliers shall note where U.S. standards are not met, for evaluation and approval by the Engineer. Factory testing shall be performed whenever possible. If factory testing must occur outside of the USA, then the Contractor shall bear the costs associated with the witness testing by the MBTA’s Engineer and one additional MBTA representative.

E. All equipment and materials furnished under Division 16 shall conform to all Federal, State or Municipal laws or ordinances, and if any requirement shown or specified conflicts with such laws or ordinances, the Contractor shall make such changes as are necessary to meet said requirements. The cost of such changes shall be borne by the Contractor and shall be included in the Contractor's original bid. Where any standards shown on contract plans or specified herein exceed the minimum standard set by law, the Contractor shall adhere to the higher standard.

F. Where materials or equipment are specified to conform to the standards of the Underwriters Laboratories, Inc., or to be constructed or tested in accordance with the standards of the National Electrical Manufacturers’ Association or American National Standards Institute, the Contractor shall submit proof that the item furnished conforms to such requirements. The label of, or listing by the Underwriters’ Laboratories, Inc. will be acceptable as sufficient evidence that the item is in accordance with the Underwriters' Laboratories standard. A company listed as a member company of NEMA for an item under consideration will be acceptable as sufficient evidence that the item conforms to the requirements of the National Electrical Manufacturers Association. In lieu of such stamp or certification label listing, the Contractor may submit a written certificate from any nationally recognized testing agency adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the requirements listed herein including methods of testing by the specified agencies. Conformance with the agency requirement does not relieve the item from complying with any other requirements of the Specifications.

G. The Contractor shall clearly state compliance / non-compliance with the traction power specifications however small, on a clause-by-clause basis. The list shall identify all specification clauses in the Traction Power Specifications and adjacent to each listed clause a category of ‘compliant’, or ‘non-compliant’. Each non-compliance shall be provided with a description or explanation and the Contractors proposed alternative or solution.

1.4 GENERAL

A. The design of the equipment shall provide features for the safety of personnel during operation, maintenance, and repair.

OCEPS07, TASK 19 GROUNDING 100% DESIGN

2026 16450-1 1/3/2026

SECTION 16450

GROUNDING

PART 1 - GENERAL

1.01 DESCRIPTION

A. Work Included: This Section specifies furnishing, installing, and testing of the complete grounding systems for each SCADA RTU or RTU Upgrade Kit. Also, this section specifies furnishing, installing, and testing of ground cable taps and ground rods. The grounding taps and rods, if needed, shall be provided in accordance with MBTA Standard Specification Section 16450, except as modified herein and as shown on the drawings.

B. All ground connections shall be bolted type. No exothermic connections shall be provided unless approved by the Engineer.

1.02 SUBMITTALS

A. Submit proposed design SCADA RTU Upgrade Kits grounding system to receive acceptance by Engineer prior to installation.

B. The following submittal data shall be furnished according to the General Conditions and Section 16050 and shall include but not limited to:

1. Grounding System Test, including report forms.

1.03 REFERENCES

A. All grounding system components shall be designed, manufactured and tested in accordance with the latest applicable industry standards including the following:

1. ANSI/IEEE Standard 80

2. UL Standard 467- Electrical Grounding and Bonding Equipment

3. NFPA 70- National Electrical Code (NEC)

B. All equipment and material to be furnished and installed on this project shall be UL or ELT listed, in accordance with the requirements of the authorities having jurisdiction, and suitable for its intended use of this project.

1.04 WARRANTY

A. Comply with the requirements of the General Conditions and Section 16050.

2026 16450-2 1/3/2026

PART 2 - PRODUCTS

2.01 GENERAL

A. All equipment and materials provided under this section of the Specifications shall be new; UL listed and bear the UL label.

B. Grounding and Bonding Equipment: Shall conform to UL 467.

2.02 ENCLOSURE GROUNDING

A. Each enclosure shall include suitable communications and safety ground networks within the enclosure. The safety ground shall be isolated from the communications ground and shall connect to the ground wire of the power input.

B. Enclosure grounding shall be subject to MBTA’s approval.

2.03 GROUNDING CONDUCTORS

A. All grounding electrode and all equipment grounding conductors shall be bare or green insulated copper conductors sized as indicated on the drawings. Where the Authorities having jurisdiction requires grounding electrode conductor sizing in excess of that shown on the Drawings or specified herein, the larger size conductor shall be installed.

B. All bonding conductors shall be flexible copper bonding jumpers sized in accordance with the NEC for grounding electrode conductors.

PART 3 - EXECUTION

3.01 INSTALLATION

A. Install all grounding as indicated in the Contract Documents.

B. Grounding shall be done in accordance with the requirements of and subject to the approval of the engineer and MBTA.

C. Protect ground conductors from physical and environmental damage. Wherever possible, and where indicated, grounding electrode and bonding conductors to be enclosed in a non-metallic raceway.

3.02 GENERAL GROUNDING REQUIREMENTS

A. General. Provide electrical grounding complying with procedures of NEC and ANSI/IEEE Standard 80.

2026 16450-3 1/3/2026

PART 4 - MEASUREMENT AND PAYMENT

4.01 GENERAL

A. No separate measurement or payment will be made for work required under this Section. All costs in connection therewith shall be considered incidental to the item or items of work to which they pertain.

2026 16450-4 1/3/2026

This page intentionally blank.

OCEPS07-TASK 19 SCADA MASTER STATION AND SCADA INTERFACE 100% DESIGN

2026 16492 - 1 1/3/2026

SECTION 16492

SCADA MASTER STATION AND SCADA INTERFACE

PART 1 - GENERAL

1.01 DESCRIPTION OF WORK

A. Work Included: This Section specifies the requirements for interfacing new or upgraded remote terminal units (RTUs) into the existing MBTA SCADA system.

B. The new or upgraded remote terminal unit shall provide the same functionality as the current SCADA RTU. The new unit shall be capable of communicating with the master terminal unit over the existing copper wire system using Telvent Series V protocol and via fiber optic cable over the MBTA Secure Wide Area Network (SWAN) using the DNP 3.0 protocol. This specification identifies the requirements of the interface of new or upgraded RTU at each location into the existing SCADA system for elements not addressed in Section 16841.

C. The work in this Section relates to the interfaces of the new or upgraded RTU into the existing systems, i.e.:

1. The communications system.

2. The existing SCADA system I/O at each affected substation.

3. Modifying the SCADA Master Station at 45 High Street, Cabot BOCC, and the new Quincy OCC as required to incorporate each new RTU and its associated SCADA points. The work may include, but not be limited to, updates to the SCADA database, the network topology database, TPSS system displays, alarm reporting functions, network status displays, main menu, and system trend displays. The Contractor shall be responsible in identifying this and implementing this work and coordinating with the Authority. The Contractor shall employ the services of the SCADA master system vendor/manufacturer as necessary to successfully complete the work and integrate the new and existing equipment. The manufacturer of the existing Master SCADA System is a proprietary system that was manufactured and installed by Open Systems International, Inc. This work also shall include incorporating the backup SCADA System, located at the Cabot Maintenance Facility and Quincy OCC.

4. Modifying the SCADA system to ensure the required controls and indications are available at the back-up control centers at Cabot Yard and Quincy OCC, if required by the MBTA.

5. The Contractor shall be responsible for providing equipment and software to achieve the specified system performance described herein and, by reference, realizes absolute and seamless compatibility with the existing systems and components. The Contractor shall employ the services of the existing vendors to meet this requirement.

6. It is anticipated that the work to be executed under this contract will not require modifications to the existing SCADA databases currently in place at the SCADA master terminal or to the existing RTU configuration used at each TPSS or USS. If the contractor’s proposed RTU replacement plan requires such changes, the Contractor shall submit proposed database changes to the MBTA for approval prior to proceeding with the work. If approval is granted, the Contractor shall be responsible for obtaining the necessary third-party support from the current Master SCADA and RTU vendors. The contractor should understand that any modifications to the SCADA Master System will require both PDS and PROD rollout operations, which shall be done during non-revenue hours (12:00 -5:00 a.m.). All SCADA PROD rollout operations must be scheduled for

2026 16492 - 2 1/3/2026

Sunday mornings with the support of the SCADA vendor. The contractor must quote this work according with the Master SCADA and RTU vendors.

7. Testing and Field Verifcation; During the new RTU commissioning testing and verification for all substation points, a full SCADA/RTU point to point (P2P) integration test for each substation must be done. The contractor should understand some P2P testing within the substation must be scheduled at night(s) due to the nature of live substation operations, and testing must be done after revenue service. As part of the testing and verification processes, SCADA System failover Testing will also be required to verify the Master SCADA can issue and execute proper controls to the new RTU from each SCADA backup servers (DAC2 at 45 High Street and BDAC 1 at Cabot BOCC). The SCADA failover testing must be scheduled at night(s), and after revenue service. The contractor must quote this work according with the SCADA and RTU vendors.

8. All parties who are required to be involved and participate in SCADA/RTU point to point test (P2P) integration testing must be onsite and in person. Remote support on point to point (P2P) integration testing is not allowed. If the master SCADA System is modified and altered to accommodate the RTU upgrade work so the Master SCADA vendor must be present onsite to support the point to point (P2P) integration testing. The contractor must quote this work accordingly. with the Master SCADA and RTU vendors.

D. As part of ongoing work being undertaken by the MBTA, the SCADA Master station will be capable for accepting internet protocols directly via Ethernet switches. If elements that are required are not in place within the SCADA master station, the Contractor shall identify this, and the requirements to the MBTA as soon as possible.

1.02 RELATED WORK

A. Related requirements are included in, but not limited to, the following Sections.

1. Section 16050, Basic Materials and Methods for Electrical Work .

2. Section 16203, Traction Power Equipment General Requirements

3. Section 16841, Modifications to Power SCADA Remote Terminal Unit Equipment

1.03 GENERAL REQUIREMENTS

A. Each TPSS will be connected to the MBTA SCADA network via both a two-wire serial copper circuit and a SCADA Ethernet switch(es) that utilizes the MBTA security wide area network (SWAN), for communications to the control center and SCADA master station at High Street, Cabot BOCC, and the new Quincy OCC.

B. Refer to communications systems drawings and specifications for details of the SCADA communications network and information about fiber optic interconnections and interfaces.

C. In conjunction with the MBTA, the Contractor shall provide the necessary software updates for the MBTA SCADA master station (at High Street and if applicable, Cabot Yard and Quincy OCC). The Contractor shall utilize the services of the Master System vendor to implement these changes and updates.

D. Configure the RTU system network devices and network switch(es) to communicate with SCADA using the appropriate protocol (DNP 3.0 or Telvent Series V).

2026 16492 - 3 1/3/2026

1.04 SUBMITTALS

A. System description of the interfaces and equipment and architecture.

B. SCADA interface points list and mapping, IP addresses and functional descriptions and configuration.

IP Addresses shall be provided by the MBTA, and the Contractor shall be responsible for coordinating these with his equipment vendor.

C. Master station software update, if required. The SCADA Master system vendor shall be engaged for this activity. Include the following:

1. Communication System Database

2. Status Point Database

3. Control Point Database

4. Analog Point Database

5. Accumulator Point database

D. Master Station system display updates shall include, but not be limited to, the following:

1. RTU Directory

2. RTU Communication Errors Page

3. RTU Trends Pages

E. Master station work plan referencing all required elements and work at the Master SCADA Stations due to expansion, modification and/or overall system upgrades needed to the Master SCADA System to facilitate the work of this project. Within sixty (60) days after a complete report has been submitted to the MBTA Engineer, the Authority will determine how to proceed for with this SCADA interface. A breakdown of the timeline to complete the main steps of the work and the interfaces shall be provided within this work plan.

F. The contractor shall submit detailed step-by-step instructions for all database software system alterations required to be implemented as part of the project. Alterations and modifications listed shall include, but not limited to, the head end (Master station) and field end (Substation).

G. Contractor shall provide the MBTA with the appropriate forms necessary to organize the system database inputs. Guidance shall also be provided to designated MBTA personnel in a timely manner to insure their understanding of database format requirements and constraints. The forms and guidance shall be presented to the MBTA not less than 60 days prior to scheduled system configuration changes.

H. Field installation plan including all installation steps with schedule attached.

I. Name and qualifications of personnel who will be performing the on-site installation work.

J. A brief corporate history of the firm performing the installation that confirms that they have been in business for five years and have successfully completed similar projects.

K. Detailed testing and commissioning procedures with attached schedule. The procedure shall include the following activities:

1. System database and display development

2. Communication System Tests

3. Data rollout into Project Development System (PDS)

2026 16492 - 4 1/3/2026

4. PDS Test and Review

5. Data rollout into Production System (Pre-Revenue Sunday only)

6. Production System Tests

a. Point to Point checkout of all data points and system display.

b. Failover Testing between primary and secondary communication channel

c. Confirm switching operation through network topology application (non-revenue only)

7. Confirmation of Data Changes on Back Up Operations Control Workstation (non-revenue only)

8. Punch-list resolution and final data verification.

L. Operating and Maintenance information.

1. Contractor shall provide an operation and maintenance (O&M) manual for each unique equipment type provided under the Contract.

M. Training.

1. In accordance with Section 16841, Article 3.12.

N. Spare Parts

1. As listed in Article 2.02, this Section.

O. Project Laptop Computer

1. As listed in Article 2.03, this Section

P. Warranty and Support Service

1. All equipment provided within this contract shall be covered by a full sixty (60) month warranty after date of field acceptance. As a condition of the warranty, the Vendor shall provide the Authority with technical and maintenance support including all applicable firmware and protocol updates that are released in the period of coverage. Optional extended coverage shall be available as well as service upgrades for 24/7 availability and response.

1.05 SCOPE OF WORK AND WORK LIMITS

A. The Contractor under the traction power system requirements shall provide, install, interconnect and test all SCADA interface equipment, including PLCs, at the traction power substation including the fiber optic cable from the PLC(s) to the Ethernet switches, as necessary.

B. The Contractor under the traction power system requirements, in conjunction with the MBTA, shall provide, install, interconnect and test a new SCADA RTU, TPSS Controller and SCADA interface equipment to accommodate all inputs and outputs related to the work including the fiber optic cable from the PLC(s) to the Ethernet switches, as necessary. The work includes interconnection and integration of the PLC Controller and testing all SCADA interface equipment at the traction power substation, as necessary.

2026 16492 - 5 1/3/2026

C. The Contractor shall be responsible to provide and implement all software integration between the SCADA communications network and the modular TPSS PLC. This shall include coordination between the Contractor and the MBTA for assigning TC/IP addresses between networks.

D. The Contractor shall be responsible for providing the necessary software, licenses, and hardware changes (if required) to provide a complete fully operated system at both of MBTA’s master stations (45 High Street, Cabot Yard Backup Control Center and the new Quincy Center OCC). The MBTA shall coordinate the implementation of the software changes with support from the Contractor’s SCADA specialist who is familiar with communications, SAS, TPSS PLC Controller, SCADA RTU and MBTA’s SCADA systems. Project work responsibilities shall include scheduling logistics, which before implementation is to be submitted to the Authority for prior approval. Concerning the implementation of the software changes, the Contractor shall coordinate with the assistance of the MBTA. The contractor should be responsible for working with the Master SCADA vendor to provide the initial SCADA Monarch Support Adders for the additional SCADA data/work being added into the SCADA System per this project.

E. The MBTA Power Department SCADA System and project modifications that affect the existing on-line system may involve multiple contractors. The Contractor shall coordinate with the MBTA and other applicable entities and contractors to ensure no negative impact is placed on the existing Supervisory Control Data Acquisition System. The Contractor working on the system upgrades/modifications shall properly schedule their work as to not impact the existing operational MBTA SCADA System. The Contractor working on the system is required to make system software backups prior to making any changes/alterations/improvements. The Contractor is also required to make a backup of the software after completing any changes/alterations/improvements to the system. Prior to any work performed on the system, the Contractor shall make the MBTA Engineer aware of any system modifications that will impact any and all MBTA on-line active systems. The system backups, (if applicable including any backup equipment) must be left on-site for the duration of the project and provided to the MBTA at the end of the Project. Each backup shall be labeled with the minimum; Contractor name, MBTA project name, MBTA contract number, date of backup and description of the backup.

F. RTU Configuration: The Contractor shall configure, program, setup and install new equipment required for the TPSS SAS / Traction Power Master Station in order to achieve a fully functional system integrated with the existing MBTA Master SCADA system. This shall include but is not limited to defining database points, mapping database points, nomenclature for devices, configuring default settings, and configuring network intelligent electronic devices (IED) telecommunication settings.

G. MBTA Master SCADA System Configuration: Regarding the addition of new supervisory and control monitoring points at the existing MBTA Master SCADA System, the Contractor shall configure, program, setup and modify all required elements in order to achieve a fully functional system integrated with the current existing MBTA Master SCADA system. At the head end, the Master SCADA System, this shall include but is not limited to expansion/modification changes to databases and display drawings, the Status Database, the Front-End Processor Database, the Alarm Database, and OpenNet databases. Expected changes are additional or editing existing display drawings, defining affected and new database points, nomenclature for devices, configuring protocol characteristic settings and defining time synchronization.

H. The Contractor shall coordinate with the MBTA regarding network rights and the provision of RTU network gateway IP addresses by the MBTA. This includes coordination of network rights including but not limited to establishing TCP/IP network component device communications to the MBTA Master SCADA TCP/IP communications network from the RTU/SAS.

2026 16492 - 6 1/3/2026

I. The Contractor, through the course of the Project, shall make known to the MBTA, any conflicts discovered which may affect the orderly completion or the specified performance of this work.

Cooperation with the MBTA and other trades to accommodate such changes as may be necessary to resolve found conflicts.

J. Training

1. Provide instruction to a level of detail necessary for operation, configuration, and preventive, corrective, and overhaul maintenance of the new RTU.

2. Location: The training program shall be conducted at location designated by the Engineer in the Greater Boston Area.

3. Training Format: Training shall include classroom and hands-on instruction. A minimum of fifty percent of the time shall be spent on hands-on instruction.

4. Training Duration:

a. Size of classes, time and location for the training shall be approved in advance by the MBTA. Contractor shall propose the training content and expected duration.

5. Training Instructors:

a. Provide qualified training instructors who have direct knowledge and experience in the subject matter that they will present.

b. Instructors shall be capable of providing detailed explanations of the operation and maintenance of both systems and individual devices and answering any questions that may arise during classes.

c. Instructors shall be fluent in English.

d. Instructors shall be able to provide instruction that can be understood by high school graduates with no basic experience in the SCADA system.

6. Training Instructor Orientation: If required, a minimum of 30 days before starting training, training instructors shall attend a 1-day orientation at the MBTA to become familiar safety regulations and facilities, and to be advised of student qualifications and expectations.

7. Trainees: MBTA Operation and Maintenance personnel.

8. Training Materials:

a. Submit training materials for approval by the MBTA.

b. The training materials shall be high quality, professionally prepared, and support the training courses. All training materials in the class shall be reflected in the operations manuals.

c. The same training materials shall be used for each class so that each class is exposed to the same information and comments can be collected on training manuals.

d. If the instructor modifies lesson plans or other elements of the training during actual training, update and distribute the affected training materials to trainees. Submit the revised training materials after training is complete.

e. All training materials shall become the property of the MBTA at the completion of the training program. Replace damaged training materials before delivering to the Engineer.

9. Document Format

2026 16492 - 7 1/3/2026

a. Documents shall be MS Windows compatible files using a software format agreed upon by the Engineer.

b. Drawings shall be in AutoCAD format.

c. Both documents and drawings shall also be provided in PDF format.

d. Photographic images shall be JPG files.

10. Media

a. Provide electronic files on USB flash drives.

b. Provide final versions of hard copy training materials printed on 8-1/2 x 11 paper.

c. Provide drawings on 11 x 17 paper.

d. Binders for hard copies shall be heavy duty D-ring style.

11. Training instruction shall include at a minimum the following:

a. Introduction to the equipment, including terminology, identification of major components

b. Problem symptoms, troubleshooting techniques and repair procedures

c. Hands-on experience in troubleshooting systems with faults by artificially introducing faults in the equipment

d. Programming and debugging of the RTU system.

e. Removal and replacement of components

f. Disassembly and reassembly for the purpose of component familiarity and any special processes

g. Instruction in the use and maintenance of all special tools and processes

h. Safety instruction for all maintenance activities

i. Overhaul procedures

PART 2 - PRODUCTS

2.01 GENERAL REQUIREMENTS

A. Refer to communications specifications for SCADA interface equipment requirements.

B. Refer to Section 16841, RTU system requirements.

C. Products submittals are to be made as part of the relevant specifications. The equipment required for the SCADA system interface at the TPSS is as follows:

1. Spare Parts

2. Laptop Computers

3. Ethernet switch(es).

4. Equipment rack or enclosure.

5. Fiber optic cable.

2.02 SPARE PARTS

A. The Contractor shall provide the following spare parts;

1. One (1) set of CPU (RTU Controller) hardware for every three substations. Minimum of six (6) for 18 substations.

2026 16492 - 8 1/3/2026

2. 10% of all I/O modules (status, analog, SBO), connectors and ribbon cables based on total volume of these items supplied under this contract. Minimum of six (6) each.

2.03 LAPTOP COMPUTERS

A. Provide two (2) laptop computers to the MBTA Power Department to enable configuring and troubleshooting of the new equipment after commissioning. Laptops shall be delivered with all required, software, firmware, licenses and supporting systems in place in advance of project implantation. The laptops shall meet with following hardware requirements:

1. CPU: Intel i7 Processor, 14th generation (or later), 4.3 GHz, 16GB cache

2. Memory: 16GB DDR RAM

3. Storage: 1TB SSD HD

4. Operating System: Widows 11

5. HMI/Display graphics: 20.1-inch diagonal with 1920 x 1620 resolution at @60 MHz

6. I/O ports: 4 USB, 2 serial ports

7. Software: Microsoft Office

8. Warranty: 12 months

PART 3 - EXECUTION

3.01 GENERAL

A. Refer to the requirements listed above.

B. Refer to communications specifications for SCADA interface equipment requirements.

3.02 MASTER SCADA INTERFACE

A. It is anticipated that the work to be executed under this contract will not require modifications to the existing SCADA databases currently in place at the SCADA master terminal or to the existing RTU configuration used at each TPSS or USS. If the contractor’s proposed RTU replacement plan requires such changes, the Contractor shall submit the proposed database changes to the MBTA for approval prior to proceeding with the work. If approval is granted, the Contractor shall be responsible for obtaining the necessary third-party support from the current Master SCADA and RTU vendors. The contractor should understand that any modifications to the SCADA Master System will require both PDS and PROD rollout operations, which shall be done during non-revenue hours (12:00 -5:00 a.m.).

All SCADA PROD rollout operations must be scheduled for Sunday mornings with the support of the SCADA vendor. The contractor must quote this work according with the Master SCADA and RTU vendors.

3.03 TESTING AND FIELD VERICATION

A. During the new RTU commissioning testing and verification for all substation points, a full SCADA/RTU point to point (P2P) integration test for each substation must be done. The contractor should understand some P2P testing within the substation must be scheduled at night(s) due to the nature of live substation operations, and testing must be done after revenue service. As part of the testing and verification processes, SCADA System failover Testing will also be required to verify the Master

2026 16492 - 9 1/3/2026

SCADA can issue and execute proper controls to the new RTU from each SCADA backup servers (DAC2 at 45 High Street and BDAC 1 at Cabot BOCC). The SCADA failover testing must be scheduled at night(s), and after revenue service. The contractor must quote this work accordingly with the SCADA and RTU vendors.

PART 4 - MEASUREMENT AND PAYMENT

4.01 GENERAL

A. Separate measurement and payment will not be made for the work under this section. All costs in connection therewith shall be included in the contract price as indicated in the SCHEDULE OF PRICES.

2026 16492 - 10 1/3/2026

SAMPLE SINGLE LINE DISPLAY

OCEPS07, TASK 19

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 1

100% DESIGN

1/3/2026

SECTION 16711

COMMUNICATIONS CABLES AND CONDUCTORS

PART 1 - GENERAL

1.1 DESCRIPTION

This specification section covers the furnishing and installation of conductors and cables to interconnect electronic equipment, devices and systems throughout the MBTA Stations and facilities.

1.2 REFERENCES AND STANDARDS

Provide the work under the applicable federal, state, and local codes and standards of the specification sections.

1.3 RELATED WORK

A. See Section 16050 for Basic Material and Methods for Electrical Work.

1.4 SUBMITTALS

Provide Shop Drawings and Equipment Submittals in accordance with this specification section to the Engineer for approval prior to ordering equipment.

PART 2 - PRODUCTS

2.1 CABLE GENERAL REQUIREMENTS

A. The Contractor shall provide wire and cable as specified, or as recommended by the manufacturer.

Wiring shall meet NFPA 70 standards. Cables and wiring shall be rated and approved for the intended use and environment.

B. Cables: Provide factory-fabricated cables of sizes, characteristics, ratings, materials, and jacketing/sheathing for applications indicated.

1. Cables shall be suitable for outdoor installation in conduit.

2. All indoor cables shall be Low-Smoke, Zero Halogen (LSZH), with the required electrical characteristics.

3. Exterior and direct burial wire shall be of water-blocked construction.

C. Contractor shall ensure wire gage is sufficient to deliver required power or signal to devices, regardless of the termination distance. Use larger gauge conductors with similar cable construction where required.

D. All UTP cabling shall be CAT6 or greater.

2.2 LOW SMOKE ZERO HALOGEN (LSZH) CATEGORY 6 (CAT6) CABLE

A. All CAT6 network cable shall be suitable for outdoor, aerial lashing, and buried conduit applications to support communications of Megapixel and IP VSS outdoor camera installations.

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 2

100% DESIGN

1/3/2026

B. All CAT6 network cabling and connections shall be labeled as shown on approved shop drawings for type, location and service.

C. All CAT6 network cabling shall be plenum rated.

D. All CAT6 cables and components installed shall comply with the following:

1. All CAT6 network cabling systems shall have EIA/TIA 568B Series standard pin/pair termination assignment. All conductors provided shall be properly and consistently terminated at both ends throughout the entire system.

2. ANSI/TIA/EIA-568-B.2-1

3. IEEE 802.3af DTE Power and MDI Verified

4. IEEE 802.ab Gigabit Ethernet Verified

5. ETL Verified

6. CSA Certified

7. FCC part 68.5, subpart F compliant

8. IEC-60603-7-4 compliant

9. ISO 11801 2nd Edition, Class E Compliant

E. Cable Physical Characteristics:

1. Jacket: Low Smoke Zero Halogen

2. Jacket Color: Green

3. Insulation: HDPE (High Density Polyethylene)

4. Conductors: #24 AWG Solid Bare Copper, or greater

5. Composition: 4 Pair #24 AWG UTP with Core Separator

6. Pair Assemblies: 2 Primaries twisted in varied lays

7. Operating Temperature: -30 to 140

8. Cable O.D. (Max): 6.3mm +\- .3 mm

9. Voltage Rating: 300 Volts RMS

2.3 CATEGORY 6 (CAT6) PATCH CABLES AND WORKSTATION CORDS

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 3

100% DESIGN

1/3/2026

A. Patch cables and workstation cords shall be factory pre-connectorized, TIA/EIA Category 6 Extended Frequency (UL Category 6E), 4 UTP, 8-position modular jack, utilizing stranded conductors.

B. Patch cables and workstation cords shall be able to withstand at least a minimum of 2000 jack mating cycles without any transmission degradation.

C. Workstation cords shall be a minimum of 15-feet in length.

2.4 CAT6 RJ45 END CONNECTORS

A. All RJ45 End Connectors shall be in compliance with the TIA-568B standards.

B. All RJ45 End Connectors shall be designed for Solid conductor CAT6 UTP.

C. All RJ45 End Connectors shall accommodate #24 AWG thru #26 AWG conductors.

D. All RJ45 End Connectors shall have 50 micro inches of gold plating on the contacts.

E. All RJ45 End Connectors shall have a plastic housing and a plastic insert with stepped entry for individual wires.

F. All RJ45 End Connectors shall be RoHS compliant.

G. All RJ45 End Connectors shall be specifically manufactured for the UTP cable to which they will attach.

2.5 24 PORT UTP CATEGORY 6 AND CATEGORY 5E PATCH PANEL

A. The 24 Port UTP Category 6 (CAT6) and Category 5e (CAT5e) Patch Panel shall meet or exceed the following specification:

1. EIA standard 19-inch cabinet

2. 110 terminations in the rear of the panel

3. TIA/EIA-T568-B.2 CAT6 connecting hardware specifications

4. RJ45 8P8C modular jacks

5. 50µ gold-plated contacts

6. Black electrostatic powder-coated steel

7. Accommodates top, bottom or side cable entry

8. Write-on designation label with clear holder UL Certified

2.6 MISCELLANEOUS DEVICE WIRING

Where not otherwise directed herein, provide wire and cable meeting the manufacturers’ recommended electrical performance for connecting the specified devices.

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 4

100% DESIGN

1/3/2026

PART 3 - EXECUTION

3.1 INSTALLATION

A. Wires shall be installed in conduit or in another approved raceway, where shown. Where a wire run is above a suspended ceiling, its conduit or raceway shall be tied up or clamped to independent supports and not left to sit on top of the ceiling panels.

1. Conduit Verification: Verify that conduit has been installed, de-burred and properly joined, routed and terminated prior to pulling of cables.

2. Wire Pulling: Apply a chemically inert conduit lubricant to wire and cable prior to pulling. Do not subject wire and cable to tension greater than recommended by the manufacturer.

3. Wire Routing: Secure wire and cable runs vertically in conduit for continuous distances greater than thirty (30) feet at the vertical run terminations. Non-coaxial cables shall be secured by screw-flange nylon cable ties or similar devices. Symmetrical clamping devices with split, circular or other wire conforming, non-metallic bushings shall be provided for other cables.

4. Verification of Continuity: After installation, and before termination, wiring shall be checked and tested to insure there are no grounds, opens, or shorts on any conductors or shields. In addition, wiring between buildings or underground and coax cables shall have insulation tested with a megohmeter and a reading of greater than 20 megohms shall be required to successfully complete the test.

B. Aerial Cabling

1. Where shown on the plans, new cabling shall use new aerial cable routing system, including but not limited to new supports, messenger systems, grounding systems, and building entry points.

2. Contractor shall be responsible for providing additional support, grounding, and other elements of the aerial cable system as may be required by the codes and standards.

C. Splicing

1. Run wires continuously from termination to termination without splices.

2. Splices at certain junction box locations may be allowed at the discretion of the Owner and the Engineer. Locations which may require spliced wires should first be established with the Owner and Engineer. Contractor shall obtain written approval before proceeding with splices.

3. If splices are required and approved, the wire shall be joined with solder, then enclosed in heat-shrink tubing and protected in an approved manner so as to provide mechanical and electrical integrity. Wire nuts and/or electrical tape connections shall not be acceptable. Final connections shall be made at terminal boards with full tagging, labeling and documentation.

D. Water Protection: Water-resistant protection shall be continuous throughout the cable in surface conduit, poles, in-slab pull-boxes, in-slab conduit, and underground conduit and pull-boxes, and in any areas subject to moisture and/or water infiltration.

1. Splices/Junctions: Provide water-proof protection of splices and junctions in exposed areas, in surface conduit and boxes, in-slab conduit and pull-boxes, underground conduit, and underground pull-boxes, to prevent the entry of moisture or water into cables, splices or connections.

2. Cable Entries: Provide water-blocking sealants at conduit entries into pull-boxes, junction boxes, back-boxes, cabinets, etc., to prevent the entry of moisture or water into the conduit and cable system.

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 5

100% DESIGN

1/3/2026

E. After installation, and before termination, wiring shall be checked and tested to insure there are no grounds, opens, or shorts on any conductors or shields. In addition, wiring between buildings or underground and coax cables shall have insulation tested with a megohmeter and a reading of greater than 20 megohms shall be required to successfully complete the test.

F. Boxes: Provide a box loop for wire and cable routed through pull boxes or distribution panels.

Cable loops and bends shall not be at a radius less than that recommended by the manufacturer.

Coordinate pull box size as necessary to accommodate this requirement.

G. Wire Labeling: Identify wire and cable clearly with permanent labels wrapped around the full circumference within one-inch of each connection. Locate the label so that it is visible, and so that wire does not need to be undressed or disassembled for clarity. Correlate the label with the number designated on the associated Shop or Field Drawings. Assign wire or cable designations consistently throughout a given system. Each wire or cable shall carry the same labeled designation over its entire run, regardless of intermediate terminations.

H. Wire Lacing and Dressing: Dress, lace, tie or harness wire and cable vertically, horizontally and at right angles to the enclosure surfaces to prevent mechanical stress on electrical connections as required herein and in accordance with accepted professional practice. No wire or cable shall be supported by a connection point. Use the specified cable management guides within enclosures and cabinets to ensure a neat wiring scheme.

I. Non-Coaxial Terminations: Make non-coaxial connections and splices to screw-connection terminal blocks with insulated crimp-type spade lugs or under terminal block pressure plates. Size terminal blocks and lugs properly to assure high electrical integrity. Connect only one (1) wire per spade lug and not more than two (2) lugs per screw terminal.

J. Shielded Cables: Shielded cables shall be insulated. Do not permit shields to contact conduit, raceway, boxes, terminal cabinets or equipment enclosures. Tin terminated shield drain wires and insulate with heat shrinkable tubing.

K. Cable and Wire Pulling

1. Contractor shall submit the following information for each segment of cable to be installed:

a. Cable pulling layout including distances, bends, and tension calculations for each section of the installation. The calculation submittals shall bear the printed name, date, and signature of the person who is responsible for the calculations.

b. Pulling equipment and tension monitoring devices. Calibration records for all monitoring equipment shall be submitted.

c. Chronological plan for installing cable, including estimated time for each pull and plan for protecting cable on reel, in slack loops during installation, and after the pull has been completed.

2. For pulling calculations, consideration shall be given to the following parameters - fill, coefficient of friction, clearance, configuration, jam ratio of the cables and conduit, weight correction factor, bend radii, maximum allowable tension, sidewall load, the method of attaching the conductors to the pulling equipment, and weight of the cables. These factors shall be calculated for each pull. The Contractor shall not exceed the manufacturer recommended values of sidewall pressure, pulling strain on conductors or sheath, limits of pulling device, and pulling tension.

3. The Contractor shall not exceed the following guidelines:

COMMUNICATIONS CABLES

AND CONDUCTORS

16711 - 6

100% DESIGN

1/3/2026

a. The maximum pulling strain on the cable with a pulling eye attached to the conductors is a function of the conductor area as follows: TM = 0.008 x n x CM., where TM = Maximum tension (lbs), n = number of conductors, CM = area of each conductor (circular mils).

b. When a basket-weave grip is used in lieu of a pulling eye, the maximum tension shall not exceed the value calculated for the…