Fire main SOW.1.docx

DOCX document 4 MB Posted

Attached to
Repair Leaking Fire Main Pipe
Solicitation number
70Z02926QNEWO0004
Issued by

About this file

This is a Statement of Work (SOW) for fire main pipe repair at Station Gulfport, a U.S. Coast Guard operational military installation located at 991 23rd Ave, Gulfport, MS 39501. The contractor must remove a cinder block wall to access a leaking fire main pipe, replace the existing 8-inch ductile pipe with galvanized steel pipe, and rebuild the cinder block wall to match existing conditions. The work is organized into three primary tasks: (1) removing the cinder block wall and cleaning the area, with debris disposal managed by unit personnel; (2) replacing the fire main pipe, including notification of the unit Point of Contact before taking utilities offline, removal of the existing flange and ductile pipe, installation of new galvanized steel pipe, leak testing, and returning the system to operation; and (3) replacing the cinder block wall with matching materials and reapplying outer coating to match surrounding walls. The contractor must provide all labor and equipment necessary to complete the scope.

The SOW establishes operational requirements for work on a Coast Guard installation, including compliance with station fire, traffic, and security regulations, designated storage area responsibilities, waste management and disposal in accordance with federal, state, and local regulations, and utility management protocols. The contractor must request utility interruptions at least two working days in advance and ensure utilities are restored to their original condition upon project completion. Water and electric utilities are available on-site. The primary Point of Contact is MKC Shelton Franklin at (228) 382-7615 or Shelton.k.franklin@uscg.mil. Bidders are advised to inspect the work site in place to verify the scope of work required.

View the file

Other files

File Type Posted
SF1442-14b.solicitation.offer.and.award.docx DOCX document
SF1442-14b.solicitation.offer.and.award.docx DOCX document
Constructions.Solicitation.1.docx DOCX document
ms50.txt TXT text file
Construction Terms and Conditions Under.docx DOCX document
SF1442-14b.solicitation.offer.and.award.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work for Station Gulfport Fire Main Repair At Gulfport, MS 39501

1.0 General

1.1 Scope: Remove cinder block wall to gain access to leaking fire main pipe. Replace existing 8” ductile pipe with galvanized steel pipe. Replace cinder block wall. The contractor shall provide all labor and equipment to accomplish the scope of this work.

1.2 Location of Site: Station Gulfport

991 23rd Ave Gulfport, MS 39501

1.2.1. POC: MKC Shelton Franklin (228) 382-7615. Shelton.k.franklin@uscg.mil

1.3 Examination of Site: It is recommended that bidders carefully inspect the work in place and verify the amount of work necessary to complete the job.

1.4 Availability of Utilities: Water and electric are available in reasonable quantities at the site.

1.5 Contractor Use of Premises: The Contractor will be working on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized. There is no smoking on the installation, but there is an authorized smoking area across the street.

1.6 Storage Area: The Contractor will be provided a storage area in a location determined by the COR. The Contractor shall be responsible for restoring the area to its original condition at the completion of work. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risk of loss.

1.7 Clean Up: The Contractor shall keep the work area, including the storage area, free from accumulation of waste materials and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes.

1.8 Underground and Concealed Utilities: Upon conclusion of the project, contractor will ensure utilities are in the same condition as before work was started.

1.9 Utility Outages: Before interrupting or shutting down any utility, make a request for the interruption to the COR at least two (2) working days before anticipated interruption. Identify utility, reason for interruption, proposed time of interruption, and duration of interruption.

2. Task 1: Remove cinder block wall to gain access to leaking fire main pipe.

2.1. Contractor to cut and remove only what is necessary of wall to remove and install new pipe.

2.2. Contractor to remove debris from area and place in area designated by Unit EPO to be deposed by unit personnel.

2.3. Contractor to clean area after demolition.

3. Task 2: Replace existing fire main pipe with appropriate steel galvanized pipe.

3.1. Notify unit POC before taking fire main or any other utility offline.

3.2. Remove existing flange and ductile pipe from wall.

3.3. Install new appropriate steel galvanized pipe.

3.4. Perform a leak test.

3.5. Place fire main system back in operation.

4. Task 3: Replace cinder block wall.

4.1. Replace cinder block wall with like size and material cinder blocks.

4.2. Replace outer coating over cinderblocks to match the rest of the walls.

5. Pictures:

Access point:

Bottom pipe flange:Inside of wall:Pipe and top flange:Wall to be taken out and replaced:

image3.jpeg image4.jpeg image5.jpeg image1.jpeg image2.jpeg