Fire Alarm Industry Day Presentation.pdf

PDF 993 KB Posted

Attached to
Facilities Management (Infrastructure) Industry Day
Solicitation number
Not on record
Issued by

About this file

This document is an industry day presentation for the Bureau of Prisons (BOP) fire alarm system replacement projects scheduled for FY26. The BOP plans to replace or upgrade fire alarm systems at 12 federal prison institutions across four regional locations: three sites in the Mid-Atlantic Region (FCI Cumberland, USP Big Sandy, FCI Manchester), five sites in the North Central Region (MCC Chicago, FCI Marion, ADX Florence, FCI Florence, USMCFP Springfield), three sites in the Northeast Region (FCI Danbury, MDC Brooklyn, FCI Berlin), and one site in the Southeast Region (FCI Tallahassee). The acquisition will utilize the GSA Multiple Award Schedule (MAS) vehicle and is estimated at $5.0 million for the base year, with a total potential value of $15.9 million including two option years, spanning 36 months total.

The installation approach involves significant BOP staff and inmate participation, with inmates under BOP supervision performing conduit and field device installation. Up to 10 inmates per site will receive vendor-provided training on system basics and safety, while two BOP staff members per site will receive manufacturer-certified training on system operation, troubleshooting, and maintenance. The acquisition strategy incorporates structured contract line items (CLINs), clear evaluation criteria, and defensible market research to mitigate protest risk while ensuring life safety compliance and institutional readiness across the federal prison system.

View the file

Other files

File Type Posted
Security Electronics Industry Day Presentation.pdf PDF
Industry Day MEP new.pdf PDF
BOP Solicitation Process.pdf PDF
Industry Day Roofing new.pdf PDF
Registration Form.pdf PDF
BOP industry Day Flyer.pdf PDF
BOP Industry Day Flyer.pdf PDF
Registration Form_Updated.pdf PDF
Registration Form.pdf PDF
BOP Industry Day Flyer.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WELCOME TO THE BUREAU OF PRISONS INDUSTRY DAY

FIRE ALARM SYSTEM PROJECTS

PRESENTED BY CHARLIE KITTS, CONSTRUCTION REP, FMB

WHERE AT?

• BOP plans to replace or upgrade 12 institutions across 4 Regions in FY26.

• Mid-Atlantic Region Sites: FCI Cumberland, USP Big Sandy, FCI Manchester

• North Central Region Sites: MCC Chicago, FCI Marion, ADX Florence, FCI Florence, MCFP Springfield

• Northeast Region Sites: FCI Danbury, MDC Brooklyn, FCI Berlin

• Southeast Region Sites: FCI Talladega

BOP INVOLVEMENT FOR

INSTALLATION

Installation of conduit and field devices will be performed by inmates with BOP staff supervision.

Up to 10 inmates per site shall be trained on system basics and safety by the vendor/contractor.

Two (2) BOP staff per site trained by manufacturer-certified instructors on system operation, troubleshooting, and maintenance.

ESTIMATED FUNDING

• Estimated Base Year Value: $5.0M

• Estimated Total with Two Option Years: $15.9M

• Total Potential Period: 36 months.

This acquisition will provide critical fire alarm system replacements using the GSA MAS vehicle, ensuring life safety compliance and institutional readiness. The plan supports BOP operational needs while mitigating protest risk through structured CLINs, clear evaluation criteria, and defensible market research.

Welcome to the BUREAU OF PRISONS Industry Day�FIRE Alarm System Projects�Presented by Charlie Kitts, Construction Rep, FMB
WHERE AT?
Slide Number 3
BOP Involvement for installation
Estimated funding