This is a Technical Exhibit documenting the Performance Requirements Summary for a federal IT infrastructure support contract. The document establishes 16 Performance Requirement Standards (PRS) that define minimum acceptable service levels and surveillance methods for contractor delivery.

The contract encompasses comprehensive IT infrastructure support including network engineering, systems integration, installation, and testing (PRS #1); enterprise network, application server, and web server availability at 98% minimum (PRS #2-4); network account creation and desktop/software support work orders completed within 48 hours (PRS #5-6); service order response and corrective action within 48 hours with detailed problem analysis within 8 hours if resolution exceeds 48 hours (PRS #7); mobile telephone and wireless handheld device availability at 98% (PRS #8); enterprise management with no more than 2 substantiated customer complaints annually (PRS #9); telephone switch availability at 98% (PRS #10); VTC and audiovisual availability at 98% (PRS #11); weekly vulnerability scans with mitigation of identified vulnerabilities within 7 working days (PRS #12); maximum total system availability of 98% (PRS #13); weekly performance progress briefs documenting work accomplished, milestone status, and projected milestones (PRS #14); project task completion by due date (PRS #15); and continuity of operations (COOP) support with all deliverables complete and accurate within agreed milestone timelines (PRS #16). Performance monitoring occurs through monthly contractor-reported metrics validation, Quality Control Plan (QCP) review, service order logs, vulnerability scan inspection, and customer complaint tracking.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL EXHIBIT 1: Performance Requirements Summary

The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective PWS Performance Threshold Method of Surveillance

PRS #1:

Engineering/ Integration/ Installation/ Testing

3.2, 3.3, 3.4

All network and systems engineering support are 98% complete and 98% accurate.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #2:

Enterprise Network Availability

3.11 Enterprise network availability shall be

98%.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #3:

Application Server Availability

All enterprise application servers (file storage, database, etc.) availability shall be 98%.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #4: Web Server Availability 3 Web server availability shall be 98%.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #5:

Unclassified Network Account Creation

3.11 At least 95% of new network account

requests shall be completed within 48 hrs.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #6: Desktop/ Software Support Work Order

3.11 Work order/trouble tickets shall be

completed within 48 hrs.

Review/ Validate Contractor monthly reported metrics. QCP

PRS #7: Service Orders 3.11

Response and repair are made within the specified times: Provide corrective action within 48 hours. If Contractor cannot provide corrective action within 48 hours, a detailed description of the analysis and action taken to resolve the problem will be provided to the COR within eight (8) hrs.

Monthly Review Service Order Log, Validated Customer Complaints /

QCP

PRS #8: Mobile Telephone and Wireless Handheld Devices

5.2.1 Mobile Telephone and Wireless Handheld Devices availability shall be 98%.

Review of customer complaints.

PRS #9:

Enterprise Management

4.0 No more than two (2) substantiated

customer complaints in this area per year.

Review of customer complaint

PRS #10:

Telephone Work Order

3.11 Telephone switch availability shall be

98%.

Review of Monthly Telephone Work Order Log / QCP

PRS #11: VTC

and A/V Availability

6.4.16 VTC availability shall be 98%. Review Monthly VTC

Log/ QCP

PRS #12: Conduct Scheduled Vulnerability Scans

3.3

(1) Conduct weekly vulnerability scans and manage the actions necessary to mitigate vulnerabilities revealed by the scan. (2) Ensure all mitigating actions are completed within seven (7) working days.

Review/ Validate Contractor monthly reported metrics. 100 percent inspection

PRS #13:

Maximum availability of total system

3 Maximum availability of total system as a minimum of 98%.

Review/ Validate Contractor monthly reported metrics. 100 percent inspection / QCP

PRS #14:

Documentation Support

3.5

Conduct weekly performance progress briefs identifying work accomplished, scheduled milestone achievement/delays and projected future work milestones.

Review/Validate Contractor performance progress briefs / customer complaint, Review/Validate Contractor monthly reported metrics.

PRS #15: Project Management Support

3.5,

3.6 Complete project tasks by due date.

Review/Validate Contractor monthly reported metrics.

PRS #16: COOP

Support 4.1

All required deliverables are complete and accurate within the agreed milestone timelines.

Review/Validate Contractor monthly reported metrics / Customer complaint