FILLABLE BID SCHEDULE - REVISED 03182025.xlsx
XLSX spreadsheet 34 KB Posted
- Solicitation number
- S-C25102-00012961
- Issued by
- Marion County, Oregon
About this file
I apologize, but I cannot fully summarize the file as only a filename is provided without the actual content of the Excel spreadsheet. The related contract opportunity indicates this is an Invitation to Bid (ITB) for asphalt concrete resurfacing of various Marion County roads in Oregon, with the project number PW1651-25. Without access to the actual bid schedule spreadsheet, I can only provide limited context based on the filename and contract opportunity description. To provide a comprehensive summary, I would need to review the actual contents of the FILLABLE BID SCHEDULE spreadsheet, which would typically include line items, quantities, unit prices, total project costs, and other bidding details specific to the road resurfacing project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
rptBidSchedule BID SCHEDULE - Updated 3/18/25 Marion County Public Works
ASPHALT CONCRETE RESURFACING OF
VARIOUS MARION COUNTY ROADS
Marion County Bid Solicitation #: PW1651-25 OregonBuys Bid Solicitation #: S-C25102-00012961
ECMS #: 2025-101
PROJECT NUMBER 1 - MCKEE SCHOOL RD NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 |
| 1.804 | Railroad Insurance | 0.00 | As Authorized | $1.00 | $0.00 |
| 1.805 | Railroad Flaggers | 0.00 | As Authorized | $1.00 | $0.00 |
| 225.276 | Temporary Removable Tape | 100.00 | Feet | $0.00 | |
| 225.450 | Portable Changeable Message Signs | 2.00 | Each | $0.00 | |
| 225.490 | Flaggers | 280.00 | Hour | $0.00 | |
| 225.510 | Pilot Cars | 60.00 | Hour | $0.00 | |
| 490.200 | Minor Adjustment Of Catch Basins And Junction Boxes | 1.00 | Each | $0.00 | |
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 530.00 | Square Yard | $0.00 | |
| 620.211 | Cold Plane Pavement Removal, 2" Deep | 260.00 | Square Yard | $0.00 | |
| 641.190 | Aggregate Shoulders | 1,250.00 | Ton | $0.00 | |
| 738.200 | Safety Edge | 1.00 | Lump Sum | $0.00 | |
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 2,700.00 | Ton | $0.00 | |
| 749.095 | Extra For Asphalt Approach | 4.00 | Each | $0.00 | |
| 749.150 | Extra For Asphalt Road Connections | 1.00 | Each | $0.00 | |
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | |
| 1070.100 | Single Mailbox Supports | 11.00 | Each | $0.00 | |
| 1070.600 | Mailbox With Numbers | 2.00 | Each | $0.00 | |
| 9999.412 | Temporary Centerline Delineation | 957.00 | Each | $0.00 | |
| $0.00 | |||||
| $0.00 | |||||
| ECMS 2025-101 - PROJECT NUMBER 1 TOTAL | $0.00 |
PROJECT NUMBER 2 - MONITOR-MCKEE RD NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 |
| 1.804 | Railroad Insurance | 0.00 | As Authorized | $1.00 | $0.00 |
| 1.805 | Railroad Flaggers | 0.00 | As Authorized | $1.00 | $0.00 |
| 225.276 | Temporary Removable Tape | 260.00 | Feet | $0.00 | |
| 225.450 | Portable Changeable Message Signs | 4.00 | Each | $0.00 | |
| 225.490 | Flaggers | 1,140.00 | Hour | $0.00 | |
| 225.510 | Pilot Cars | 220.00 | Hour | $0.00 | |
| 280.100 | Erosion Control | 1.00 | Lump Sum | $0.00 | |
| 280.322 | Sediment Barrier, Type 3 | 350.00 | Feet | $0.00 | |
| 290.100 | Pollution Control Plan | 1.00 | Lump Sum | $0.00 | |
| 305.100 | Construction Survey Work | 1.00 | Lump Sum | $0.00 | |
| 310.100 | Removal Of Structures And Obstructions | 1.00 | Lump Sum | $0.00 | |
| 490.125 | Minor Adjustment Of Manholes | 1.00 | Each | $0.00 | |
| 490.300 | Adjust Boxes | 6.00 | Each | $0.00 | |
| 585.200 | Filled Joint Seal | 150.00 | Feet | $0.00 | |
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 2,840.00 | Square Yard | $0.00 | |
| 620.115 | Cold Plane Pavement Removal, Curb Line | 175.00 | Square Yard | $0.00 | |
| 620.211 | Cold Plane Pavement Removal, 2" Deep | 8,925.00 | Square Yard | $0.00 | |
| 620.305 | Cold Plane Pavement Removal, Repair Areas | 882.00 | Square Yard | $0.00 | |
| 641.190 | Aggregate Shoulders | 3,700.00 | Ton | $0.00 | |
| 736.100 | Scrub Seal | 36,857.00 | Square Yard | $0.00 | |
| 738.200 | Safety Edge | 1.00 | Lump Sum | $0.00 | |
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 8,550.00 | Ton | $0.00 | |
| 745.225 | Level 2, 3/8" Dense, PG 64-22, ACP In Leveling | 1,950.00 | Ton | $0.00 | |
| 745.262 | Level 2, 1/2" Dense, PG 64-22, ACP In Base Plug | 180.00 | Ton | $0.00 | |
| 749.095 | Extra For Asphalt Approach | 10.00 | Each | $0.00 | |
| 749.150 | Extra For Asphalt Road Connections | 6.00 | Each | $0.00 | |
| 810.220 | Guardrail End Pieces, Type C | 1.00 | Each | $0.00 | |
| 810.300 | Extra For 8' Posts | 12.00 | Each | $0.00 | |
| 810.302 | Extra For 11' Posts | 6.00 | Each | $0.00 | |
| 810.320 | Extra For Post Hole In Rock | 6.00 | Each | $0.00 | |
| 810.330 | Construct Grading at Guardrail Terminals | 2.00 | Each | $0.00 | |
| 810.350 | Guardrail Terminals, Non-Flared | 1.00 | Each | $0.00 | |
| 810.450 | Midwest Guardrail Anchor System Downstream Anchor Terminal | 1.00 | Each | $0.00 | |
| 810.500 | Midwest Guardrail System, Type 2A | 280.00 | Feet | $0.00 | |
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | |
| 1030.228 | Native Plant Seeding | 1.00 | Lump Sum | $0.00 | |
| 1070.100 | Single Mailbox Supports | 19.00 | Each | $0.00 | |
| 1070.600 | Mailbox With Numbers | 3.00 | Each | $0.00 | |
| 1070.650 | Mailbox, Locking, With Numbers | 1.00 | Each | $0.00 | |
| 9999.412 | Temporary Centerline Delineation | 3,050.00 | Each | $0.00 | |
| 9999.510 | Temporary Detour Route | 1.00 | Lump Sum | $0.00 | |
| 9999.570 | Preformed Expansion Joints | 1.00 | Lump Sum | $0.00 | |
| $0.00 | |||||
| $0.00 | |||||
| ECMS 2025-101 - PROJECT NUMBER 2 TOTAL | $0.00 |
PROJECT NUMBER 3 - WAYPARK DR NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT | |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 | |
| 225.276 | Temporary Removable Tape | 40.00 | Feet | $0.00 | ||
| 225.450 | Portable Changeable Message Signs | 2.00 | Each | $0.00 | ||
| 225.490 | Flaggers | 320.00 | Hour | $0.00 | ||
| 225.510 | Pilot Cars | 70.00 | Hour | $0.00 | ||
| 280.100 | Erosion Control | 1.00 | Lump Sum | $0.00 | ||
| 280.322 | Sediment Barrier, Type 3 | 800.00 | Feet | $0.00 | ||
| 290.100 | Pollution Control Plan | 1.00 | Lump Sum | $0.00 | ||
| 305.100 | Construction Survey Work | 1.00 | Lump Sum | $0.00 | ||
| 310.100 | Removal Of Structures And Obstructions | 1.00 | Lump Sum | $0.00 | ||
| 585.200 | Filled Joint Seal | 88.00 | Feet | $0.00 | ||
| 587.115 | Pedestrian Rail, Modified | 470.00 | Feet | $0.00 | ||
| 587.500 | Steel Bridge Rail Post | 118.00 | Each | $0.00 | ||
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 750.00 | Square Yard | $0.00 | ||
| 620.211 | Cold Plane Pavement Removal, 2" Deep | 420.00 | Square Yard | $0.00 | ||
| 641.190 | Aggregate Shoulders | 1,400.00 | Ton | $0.00 | ||
| 738.200 | Safety Edge | 1.00 | Lump Sum | $0.00 | ||
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 4,100.00 | Ton | $0.00 | ||
| 749.095 | Extra For Asphalt Approach | 1.00 | Each | $0.00 | ||
| 810.160 | Guardrail Anchors, Type 1 Modified | 2.00 | Each | $0.00 | ||
| 810.200 | Guardrail End Pieces, Type B | 1.00 | Each | $0.00 | ||
| 810.250 | Guardrail Transition | 8.00 | Each | $0.00 | ||
| 810.300 | Extra For 8' Posts | 12.00 | Each | $0.00 | ||
| 810.302 | Extra For 11' Posts | ` | 6.00 | Each | $0.00 | |
| 810.320 | Extra For Post Hole In Rock | 6.00 | Each | $0.00 | ||
| 810.330 | Construct Grading at Guardrail Terminals | 8.00 | Each | $0.00 | ||
| 810.350 | Guardrail Terminals, Non-Flared | 7.00 | Each | $0.00 | ||
| 810.500 | Midwest Guardrail System, Type 2A | 100.00 | Feet | $0.00 | ||
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | ||
| 1030.228 | Native Plant Seeding | 1.00 | Lump Sum | $0.00 | ||
| 1070.100 | Single Mailbox Supports | 2.00 | Each | $0.00 | ||
| 9999.412 | Temporary Centerline Delineation | 1,375.00 | Each | $0.00 |
ECMS 2025-101 - PROJECT NUMBER 3 TOTAL $0.00
PROJECT NUMBER 4 - WEST CHURCH RD NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 |
| 225.276 | Temporary Removable Tape | 60.00 | Feet | $0.00 | |
| 225.450 | Portable Changeable Message Signs | 3.00 | Each | $0.00 | |
| 225.490 | Flaggers | 370.00 | Hour | $0.00 | |
| 225.510 | Pilot Cars | 60.00 | Hour | $0.00 | |
| 490.200 | Minor Adjustment Of Catch Basins And Junction Boxes | 1.00 | Each | $0.00 | |
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 260.00 | Square Yard | $0.00 | |
| 620.115 | Cold Plane Pavement Removal, Curb Line | 65.00 | Square Yard | $0.00 | |
| 620.211 | Cold Plane Pavement Removal, 2" Deep | 1,875.00 | Square Yard | $0.00 | |
| 620.305 | Cold Plane Pavement Removal, Repair Areas | 775.00 | Square Yard | $0.00 | |
| 641.190 | Aggregate Shoulders | 1,150.00 | Ton | $0.00 | |
| 736.100 | Scrub Seal | 8,867.00 | Square Yard | $0.00 | |
| 738.200 | Safety Edge | 1.00 | Lump Sum | $0.00 | |
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 1,850.00 | Ton | $0.00 | |
| 745.225 | Level 2, 3/8" Dense, PG 64-22, ACP In Leveling | 1,000.00 | Ton | $0.00 | |
| 745.262 | Level 2, 3/8" Dense, PG 64-22, ACP In Base Plug | 150.00 | Ton | $0.00 | |
| 749.095 | Extra For Asphalt Approach | 9.00 | Each | $0.00 | |
| 749.150 | Extra For Asphalt Road Connections | 1.00 | Each | $0.00 | |
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | |
| 1070.100 | Single Mailbox Supports | 4.00 | Each | $0.00 | |
| 9999.412 | Temporary Centerline Delineation | 650.00 | Each | $0.00 | |
| $0.00 |
ECMS 2025-101 - PROJECT NUMBER 4 TOTAL $0.00
PROJECT NUMBER 5 -SARATOGA DR NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 |
| 225.276 | Temporary Removable Tape | 60.00 | Feet | $0.00 | |
| 225.450 | Portable Changeable Message Signs | 4.00 | Each | $0.00 | |
| 225.490 | Flaggers | 530.00 | Hour | $0.00 | |
| 225.510 | Pilot Cars | 110.00 | Hour | $0.00 | |
| 280.100 | Erosion Control | 1.00 | Lump Sum | $0.00 | |
| 280.332 | Sediment Barrier, Type B | 400.00 | Feet | $0.00 | |
| 290.100 | Pollution Control Plan | 1.00 | Lump Sum | $0.00 | |
| 305.100 | Construction Survey Work | 1.00 | Lump Sum | $0.00 | |
| 310.100 | Removal Of Structures And Obstructions | 1.00 | Lump Sum | $0.00 | |
| 490.300 | Adjust Boxes | 3.00 | Each | $0.00 | |
| 585.200 | Filled Joint Seal | 82.00 | Feet | $0.00 | |
| 587.115 | Pedestrian Rail, Modified | 645.00 | Feet | $0.00 | |
| 587.500 | Steel Bridge Rail Post | 162.00 | Each | $0.00 | |
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 1,085.00 | Square Yard | $0.00 | |
| 620.115 | Cold Plane Pavement Removal, Curb Line | 95.00 | Square Yard | $0.00 | |
| 620.305 | Cold Plane Pavement Removal, Repair Areas | 2,150.00 | Square Yard | $0.00 | |
| 641.190 | Aggregate Shoulders | 2,700.00 | Ton | $0.00 | |
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 5,500.00 | Ton | $0.00 | |
| 745.225 | Level 2, 3/8" Dense, PG 64-22, ACP In Leveling | 2,900.00 | Ton | $0.00 | |
| 745.262 | Level 2, 1/2" Dense, PG 64-22, ACP In Base Plug | 375.00 | Ton | $0.00 | |
| 749.095 | Extra For Asphalt Approach | 5.00 | Each | $0.00 | |
| 749.150 | Extra For Asphalt Road Connections | 2.00 | Each | $0.00 | |
| 810.250 | Guardrail Transition | 4.00 | Each | $0.00 | |
| 810.300 | Extra For 8' Posts | 12.00 | Each | $0.00 | |
| 810.302 | Extra For 11' Posts | 6.00 | Each | $0.00 | |
| 810.320 | Extra For Post Hole In Rock | 6.00 | Each | $0.00 | |
| 810.330 | Construct Grading for Guardrail Terminals | 4.00 | Each | $0.00 | |
| 810.350 | Guardrail Terminals, Non-Flared | 4.00 | Each | $0.00 | |
| 810.500 | Midwest Guardrail System, Type 2A | 50.00 | Feet | $0.00 | |
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | |
| 1030.228 | Native Plant Seeding | 1.00 | Lump Sum | $0.00 | |
| 1070.100 | Single Mailbox Supports | 18.00 | Each | $0.00 | |
| 1070.650 | Mailbox, Locking, With Numbers | 1.00 | Each | $0.00 | |
| 9999.412 | Temporary Centerline Delineation | 1,977.00 | Each | $0.00 | |
| $0.00 | |||||
| $0.00 | |||||
| ECMS 2025-101 - PROJECT NUMBER 5 TOTAL | $0.00 |
PROJECT NUMBER 6 - NORTH HOWELL RD NE
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT | |
| 1.801 | ACP Material Price Adjustment | 0.00 | As Authorized | $1.00 | $0.00 | |
| 225.276 | Temporary Removable Tape | 40.00 | Feet | $0.00 | ||
| 225.450 | Portable Changeable Message Signs | 2.00 | Each | $0.00 | ||
| 225.490 | Flaggers | 170.00 | Hour | $0.00 | ||
| 225.510 | Pilot Cars | 50.00 | Hour | $0.00 | ||
| 620.110 | Cold Plane Pavement Removal, Butt Joints | 200.00 | Square Yard | $0.00 | ||
| 641.190 | Aggregate Shoulders | 620.00 | Ton | $0.00 | ||
| 745.205 | Level 2, 3/8" Dense, PG 64-22, ACP | 1,100.00 | Ton | $0.00 | ||
| 745.225 | Level 2, 3/8" Dense, PG 64-22, ACP In Leveling | 775.00 | Ton | ` | $0.00 | |
| 861.050 | Striping Layout | 1.00 | Lump Sum | $0.00 | ||
| 1070.100 | Single Mailbox Supports | 5.00 | Each | $0.00 | ||
| 9999.412 | Temporary Centerline Delineation | 550.00 | Each | $0.00 | ||
| $0.00 | ||||||
| $0.00 | ||||||
| ECMS 2025-101 - PROJECT NUMBER 6 TOTAL | $0.00 |
PROJECT NUMBER 7 - REFLECTIVE PAVEMENT MARKERS
| ITEM # | DESCRIPTION | QTY | UNITS | UNIT PRICE | AMOUNT |
| 225.510 | Pilot Cars | 80.00 | Hour | $0.00 | |
| 860.200 | Bi-Directional Yellow Type I Markers | 2,145.00 | Each | $0.00 | |
| $0.00 | |||||
| $0.00 | |||||
| ECMS 2025-101 - PROJECT NUMBER 7 TOTAL | $0.00 | ||||
| ECMS 2025-101 - TOTAL EXTENSION | $0.00 |
&11&P
Compatibility Report
| Compatibility Report for Unlocked_bid_schedule.2019_Resurfacing.xls |
| Run on 2/21/2019 9:55 |
The following features in this workbook are not supported by earlier versions of Excel. These features may be lost or degraded when opening this workbook in an earlier version of Excel or if you save this workbook in an earlier file format.
Significant loss of functionality # of occurrences Version
| Some cells have overlapping conditional formatting ranges. Earlier versions of Excel will not evaluate all of the conditional formatting rules on the overlapping cells. The overlapping cells will show different conditional formatting. | 61 | |
| rptBidSchedule'!K387:K389 | Excel 97-2003 | |
| rptBidSchedule'!K87:K90 | ||
| rptBidSchedule'!K386 | ||
| rptBidSchedule'!K13 | ||
| rptBidSchedule'!K26:K29 | ||
| rptBidSchedule'!K30:K34 | ||
| rptBidSchedule'!K44:K51 | ||
| rptBidSchedule'!K58:K66 | ||
| rptBidSchedule'!K105:K120 | ||
| rptBidSchedule'!K146:K161 | ||
| rptBidSchedule'!K197:K218 | ||
| rptBidSchedule'!K225:K244 | ||
| rptBidSchedule'!K254 | ||
| rptBidSchedule'!K282:K284 | ||
| rptBidSchedule'!K307:K314 | ||
| rptBidSchedule'!K339 | ||
| rptBidSchedule'!K358 | ||
| rptBidSchedule'!K168 | ||
| rptBidSchedule'!K73:K80 |