FHPS - Structured Cabling RFP - Addendum #1.pdf
PDF 192 KB Posted
- Attached to
- Request for Structured Cabling System
- Solicitation number
- RFP FHP 210000000025 2
- Issued by
- Kent County, Grand Rapids City, Michigan
About this file
This is an Addendum #1 to a Structured Cabling Request for Proposal issued by Forest Hills Public Schools in Michigan, prepared by Plante Moran on October 16, 2020. The project involves the demolition and replacement of structured cabling infrastructure across multiple school buildings. Key project specifications include the demolition of approximately eight cables per classroom, including combinations of coaxial, unshielded twisted pair, and phone lines, along with the removal of cabling and racks from network closets as detailed in Appendix A. The existing single-mode fiber backbone will remain in place, with new fiber runs only required if specified in future change orders. The bid opening was scheduled for October 22, 2020, at 10:00 AM ET at the Forest Hills Public Schools Administration Building in Room #5. All project appendices and drawings (Appendix A and B) are available on the State of Michigan SIGMA website.
The addendum addresses vendor inquiries regarding demolition quantities, existing infrastructure specifications, and material standards. Forest Hills Public Schools has not established a standardized brand preference for premises wiring, indicating that vendors may propose solutions from various manufacturers such as Panduit or CommScope. Unit costs are requested for potential new fiber runs as contingency pricing, though the primary scope focuses on cabinet and cabling replacement within the existing infrastructure framework.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum # 1
To: Interested Vendors
From: Shae Sultes– Plante Moran
Date: October 16, 2020
Re: Forest Hills Public Schools – Structured Cabling RFP
The bid opening will be held at the Forest Hills Public Schools Administration Building on October 22nd @ 10AM ET in Room #5.
Below is list of vendor questions and answers received to date:
‐ End of Addendum 1 ‐
QUESTION ANSWER
1. Approximately how many cables will need to be demoed per classroom? Should I assume one for every cable installed?
Please assume a quantity of 8 cables per classroom for demolition. This may include a combination Coax, UTP, or phone lines.
2. How many coax cables are being demoed?
Does this include both drops and hardline cable?
See assumptions for demolition above. This includes both drops and hardline.
3. Approximately how many cables need to be demoed at each Closet Removal / Demolition? How many racks need to be removed?
Please refer to Appendix A for quantities.
4. Does the existing Backbone Fiber remain?
Appendix A indicates no new Fiber Runs.
Does this only entail replacing Cabinets and Cabling?
The existing fiber backbone is SMF and will remain.
Unit costs are requested in the event new runs are required.
5. Specify locations for Appendix A and Appendix B (Drawings).
All appendices can be found on the State of Michigan SIGMA website.
6. Does Forest Hills Public S have a current brand of premises wiring that they have standardized on up to this point....Panduit, Commscope, etc?
No set standard has been established.