10-PWCAT010 - PennBid Bid Table.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- McBurney Road Culvert Remediation
- Solicitation number
- US.195400
- Issued by
- Washington County, Camp Hill Borough, Pennsylvania
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Legend
Pricing Section (BT-68HY)
Legend
| The green cells with bolded numbers indicate that this bid was the lowest price. | $ 123 |
| The orange cells indicate that this item from that vendor was selected. | |
| The green cells with orange outline indicate that this item from that vendor was selected, and has the lowest price. |
Sheet 1
| AMS Construction & Remodeling LLC | Cronin Enterprises LLC | Greenland Const., Inc. | N & N Landscaping LLC | ||||||||
| Total Cost | $98,500.00 | $109,362.00 | $618,000.00 | $335,408.44 | |||||||
| Selected # | 0 | 0 | 0 | 0 | |||||||
| Selected ($) | $0 | $0 | $0 | $0 | |||||||
| # | Locked | Items | Selected | Lowest | Unit of | ||||||
| Measure | Quantity | ||||||||||
| Required | Unit | ||||||||||
| Price | Total | ||||||||||
| Cost | Unit | ||||||||||
| Price | Total | ||||||||||
| Cost | Unit | ||||||||||
| Price | Total | ||||||||||
| Cost | Unit | ||||||||||
| Price | Total |
Cost
| 1 | Contract 1 - Base Bid (13) | |||||||||||||
| #1-1 | FALSE | Mobilization | $0.00 | $0.00 | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $28,060.00 | $28,060.00 | $5,000.00 | $5,000.00 |
| #1-2 | FALSE | Maintenance & Protection of Traffic | $0.00 | $0.00 | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 |
| #1-3 | FALSE | Temporary Fish Preventive & Exclusion Units Install, Maintenance, and Removal | $0.00 | $0.00 | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $3,000.00 | $3,000.00 | $10,000.00 | $10,000.00 |
| #1-4 | FALSE | Temporary Erosion & Sediment Control Maintenance and Removals | $0.00 | $0.00 | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $3,500.00 | $3,500.00 | $10,000.00 | $10,000.00 |
| #1-5 | FALSE | Heavy Jet Spray or Bucketed Removal of Sediment in 48"-60" RCP Culvert to Owner Excavator Removal Location | $0.00 | $0.00 | LF | 310 | $0.00 | $0.00 | $0.00 | $0.00 | $500.00 | $155,000.00 | $210.00 | $65,100.00 |
| #1-6 | FALSE | Heavy Jet Spray or Bucketed Removal of Sediment in 36"-42" SLCPP Culvert to Ower Excavator Removal Location | $0.00 | $0.00 | LF | 100 | $0.00 | $0.00 | $0.00 | $0.00 | $400.00 | $40,000.00 | $200.00 | $20,000.00 |
| #1-7 | FALSE | Heavy Jet Spray or Bucketed Removal of Sediment in 72"-120" CMP Culvert to Ower Excavator Removal Location | $0.00 | $0.00 | LF | 130 | $0.00 | $0.00 | $0.00 | $0.00 | $900.00 | $117,000.00 | $295.38 | $38,399.40 |
| #1-8 | FALSE | CCTV Record Inspection 48"-60" RCP Culvert | $0.00 | $0.00 | LF | 310 | $0.00 | $0.00 | $0.00 | $0.00 | $30.00 | $9,300.00 | $10.00 | $3,100.00 |
| #1-9 | FALSE | CCTV Record Inspection 36"-42" SLCPP Culvert | $0.00 | $0.00 | LF | 100 | $0.00 | $0.00 | $0.00 | $0.00 | $30.00 | $3,000.00 | $10.00 | $1,000.00 |
| #1-10 | FALSE | CCTV Record Inspection 72"-120" CMP Culvert | $0.00 | $0.00 | LF | 130 | $0.00 | $0.00 | $0.00 | $0.00 | $30.00 | $3,900.00 | $10.00 | $1,300.00 |
| #1-11 | FALSE | SkidSteer Class 2000#-2800# Street Sweeper and Operator | $0.00 | $0.00 | HRS | 40 | $0.00 | $0.00 | $0.00 | $0.00 | $300.00 | $12,000.00 | $200.00 | $8,000.00 |
| #1-12 | FALSE | Supervisory Coordination of Jetter Upstream to Downstream | $0.00 | $0.00 | HRS | 40 | $0.00 | $0.00 | $0.00 | $0.00 | $272.00 | $10,880.00 | $150.00 | $6,000.00 |
| #1-13 | FALSE | Supervisory Coordination of Street Sweeper Upstream to Downstream | $0.00 | $0.00 | HRS | 5 | $0.00 | $0.00 | $0.00 | $0.00 | $272.00 | $1,360.00 | $150.00 | $750.00 |
| 2 | Contract 2 - Base Bid (8) | |||||||||||||
| #2-1 | FALSE | Mobilization | $0.00 | $5,000.00 | LS | 1 | $5,000.00 | $5,000.00 | $7,400.00 | $7,400.00 | $25,946.00 | $25,946.00 | $5,000.00 | $5,000.00 |
| #2-2 | FALSE | Maintenance & Protection of Traffic | $0.00 | $2,500.00 | LS | 1 | $3,800.00 | $3,800.00 | $2,500.00 | $2,500.00 | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 |
| #2-3 | FALSE | Rip Rap Apron | $0.00 | $2,300.00 | EA | 1 | $6,000.00 | $6,000.00 | $2,300.00 | $2,300.00 | $3,200.00 | $3,200.00 | $3,000.00 | $3,000.00 |
| #2-4 | FALSE | Precast Trench Drain with Grate | $0.00 | $10,400.00 | LF | 32 | $325.00 | $10,400.00 | $560.00 | $17,920.00 | $2,000.00 | $64,000.00 | $703.22 | $22,503.04 |
| #2-5 | FALSE | Full Depth Pavement Restoration | $0.00 | $1,254.00 | SY | 11 | $120.00 | $1,320.00 | $370.00 | $4,070.00 | $114.00 | $1,254.00 | $300.00 | $3,300.00 |
| #2-6 | FALSE | Surface Course Asphalt Pavement Restoration | $0.00 | $2,520.00 | SY | 36 | $70.00 | $2,520.00 | $232.00 | $8,352.00 | $90.00 | $3,240.00 | $200.00 | $7,200.00 |
| #2-7 | FALSE | Asphalt Wedge Curb | $0.00 | $2,900.00 | LF | 145 | $20.00 | $2,900.00 | $28.00 | $4,060.00 | $188.00 | $27,260.00 | $50.00 | $7,250.00 |
| #2-8 | FALSE | As-Built Drawings | $0.00 | $100.00 | LS | 1 | $300.00 | $300.00 | $2,000.00 | $2,000.00 | $1,100.00 | $1,100.00 | $100.00 | $100.00 |
| 3 | Contract 2 - Add Alternate (6) | |||||||||||||
| #3-1 | FALSE | Added Option Headwall 60" | $0.00 | $13,800.00 | LS | 1 | $24,630.00 | $24,630.00 | $13,800.00 | $13,800.00 | $19,500.00 | $19,500.00 | $22,000.00 | $22,000.00 |
| #3-2 | FALSE | Added Option 60" SLCPP & Backfill | $0.00 | $4,500.00 | LF | 8 | $562.50 | $4,500.00 | $660.00 | $5,280.00 | $2,200.00 | $17,600.00 | $2,791.00 | $22,328.00 |
| #3-3 | FALSE | Added Option Headwall 72" | $0.00 | $18,500.00 | LS | 1 | $24,630.00 | $24,630.00 | $18,500.00 | $18,500.00 | $27,000.00 | $27,000.00 | $26,000.00 | $26,000.00 |
| #3-4 | FALSE | Added Option 72" SLCPP & Backfill | $0.00 | $4,500.00 | LF | 8 | $562.50 | $4,500.00 | $1,250.00 | $10,000.00 | $3,000.00 | $24,000.00 | $2,791.00 | $22,328.00 |
| #3-5 | FALSE | Added Option PADOT R-3 Surface | $0.00 | $3,395.00 | Ton | 35 | $100.00 | $3,500.00 | $128.00 | $4,480.00 | $97.00 | $3,395.00 | $150.00 | $5,250.00 |
| #3-6 | FALSE | Added Option Rebuild Existing Grate and Riser on Type M Inlet | $0.00 | $4,500.00 | EA | 3 | $1,500.00 | $4,500.00 | $2,900.00 | $8,700.00 | $1,835.00 | $5,505.00 | $3,500.00 | $10,500.00 |
File details come from the government source that posted it. Updated .