5-07. Technical Specifications.pdf

PDF 1 MB Posted

Attached to
McBurney Road Culvert Remediation
Solicitation number
US.195400
Issued by
Washington County, Camp Hill Borough, Pennsylvania

View the file

Other files

File Type Posted
7-01. Signed Cover Sheet.pdf PDF
8-08. Project Plans (12 Sheets).pdf PDF
9-PWCAT010 - 2025.08.21 - Addendum 1.pdf PDF
3-05. Wage Rate Determination.pdf PDF
2-03. Proposal Section.pdf PDF
1-02. Notice to Bidders.pdf PDF
6-04. Information for Bidders.pdf PDF
4-06. General Conditions.pdf PDF
10-PWCAT010 - PennBid Bid Table.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

TECHNICAL SPECIFICATIONS

000000 - Scope of Work

010000 - General Requirements

017810 - Record Documents

020100 - Cleaning and Restorations

021400 - Dewatering and Flow Diversion

022270 - Excavation and Backfill

022700 - Temporary Soil Erosion & Sediment Control

023100 - Subbase

024310 - Drainage Structures

025130 - Superpave Asphalt

025500 - Sawcutting � Bituminous and Concrete Surfaces

026310 - HDPE Storm Pipe

027610 - Cleaning and Televising of Culverts

OTHER DOCUMENTS

1. Project Plans: �McBurney Road Culvert Remediation� (12 Sheets), dated June 19, 2025, prepared by

Remington & Vernick Engineers.

Scope of Work 000000-1

SECTION 000000

SCOPE OF WORK

PART 1 – GENERAL

1.01 Project Description

Canonsburg Borough is proposing to perform storm culvert maintenance to alleviate flooding along McBurney Road and the private properties in the area. In general, the Base Bid work consists of, but is not limited to heavy jet spraying or bucketed removal to clean sediment and debris from existing culverts at several strategic collection sites along the drainageway, removal and hauling of debris to designated location, CCTV inspection of culverts, installation of a new precast concrete trench drain across McBurney Road to capture and redirect runoff to the existing culverts and drainageway, and installation of a rip rap apron at the trench drain outlet. Added optional items to be determined by the Owner include extension of existing culverts, backfill, installation of new headwalls with trash racks, and rebuilding existing inlet grates and risers. Work will also include asphalt roadway restoration, asphalt wedge curb installation, temporary erosion and sediment controls, mobilization, maintenance and protection of traffic as necessary to perform the work. For all cleaning of culverts, Contractor shall assume 115-120 lb/ft3 debris will be cleaned out from the culverts.

1.02 Project Location

A. The proposed work is located on both public and private properties within an existing drainage easement along McBurney Road from the intersection with West Pike Street and extending approximately 800 linear feet north/upstream. The work is located within Canonsburg Borough and Chartiers Township, Washington County, PA.

1.03 Contract 1

A. The work for the Contract 1 Base Bid includes, but is not necessarily limited to, the following major work and contract items:

1. Mobilization.

2. Maintenance and protection of traffic.

3. Temporary fish preventor units set up prior to and maintained during construction to prevent the passage of fish upstream into the work area.

4. Temporary erosion and sediment controls, including compost sock sediment traps set up at designated debris removal locations to stop debris cleaned out from culverts from traveling further downstream.

5. Heavy jet spraying or bucketed removal of sediment in 48”-60” RCP culvert and hauling to location designated by Owner.

6. Heavy jet spraying or bucketed removal of sediment in 36”-42” SLCPP culvert and hauling to location designated by Owner.

Scope of Work 000000-2

7. Heavy jet spraying or bucketed removal of sediment in 84”-120” CMP culvert and hauling to location designated by Owner.

8. CCTV inspection of 48”-60” RCP culvert.

9. CCTV inspection of 36”-42” SLCPP culvert.

10. CCTV inspection of 84”-120” CMP culvert.

11. Street sweeping.

12. Supervisory coordination of jetter upstream to downstream.

13. Supervisory coordination of street sweeper and operator.

1.04 Contract 2

A. The work for the Contract 2 Base Bid includes, but is not necessarily limited to, the following major work and contract items:

1. Mobilization.

2. Maintenance and protection of traffic.

3. Installation of rip rap apron at outlet of proposed trench drain.

4. Installation of new precast concrete trench drain with grate.

5. Full depth asphalt pavement restoration associated with installation of the precast concrete trench drain installation, as shown on the project plans and details.

6. Surface course asphalt pavement restoration associated with installation of the precast concrete trench drain installation, as shown on the project plans and details.

7. Installation of asphalt wedge curb.

8. Record documents.

B. The work for the Contract 2 added optional items to be determined by the Owner includes, but is not necessarily limited to, the following major work and contract items:

1. Installation of 60” SLCPP to extend existing culverts, including excavation and backfill.

2. Installation of 84” SLCPP to extend existing culverts, including excavation and backfill.

3. Installation of new 60” & 84” concrete headwalls with trash racks at the inlets to existing culverts.

4. Installation of R-3 rip rap surface as shown on the project plans.

5. Rebuilding the existing grates and risers of Type M inlets.

1.05 General Requirements

A. The McBurney Road Culvert Remediation consists of Two (2) Contracts. Contract One

(1) requires the Heavy Jet Cleaning of sediments from the existing culverts. Contract Two (2) requires the installation of a twenty-four-inch sloped precast concrete trench drain in the roadway. Contract Two (2) Add Option Bid pricing is to include all elements of the Base Bid, and the installation of two contractor adjusted and measured headwalls at the culvert openings within the project worksite. Both Contracts require a 10% Bid Bond. Both contracts require 100% Performance and Payment Bonds.

Contract 1 is maintenance only and does not require prevailing wage rates or a warranty

Scope of Work 000000-3 bond. Contract 2 for structures requires a 100% warranty bond and state prevailing wage rates.

B. Construction layout of all proposed elements of construction to the specified lines and grades. All limits of work shall be marked out and approved by the Borough prior to excavation. Proposed grades are not guaranteed and shall be verified in the field during construction layout. Any discrepancies in proposed grades shall be brought to the attention of the Engineer so that design adjustments can be made prior to construction.

C. Setup and maintenance of temporary erosion and sediment controls. The contractor may be required to install erosion controls at the direction of the Borough. No payment will be made for erosion controls. The contractor will be required to clean and remove any material that erodes from excavations associated with the project. No payment will be made for clean-up and disposal of eroded material.

D. Removal of existing features as incidental to the contract work items, including but not limited to the following: metal plates, pipes, concrete slabs, stone, bricks, and all foreign materials encountered during excavation for contract items.

1.06 Additional Requirements.

A. Contract time limits and requirements for this project are as follows:

All work by the Contractor must be 100% completed within the contract time limit of 90 calendar days. The contract time limit shall begin once the written Notice to Proceed order has been issued to the contractor.

B. The cost of all related incidental work, maintenance and protection of vehicular and pedestrian traffic, dust control, erosion control, cleaning and restorations shall be included in the various unit prices bid. These activities are not separate pay items.

C. All materials, construction procedures, type and use of equipment, measurement and payment shall be in accordance with the Commonwealth of Pennsylvania Department of Transportation Specifications, Publication 408, unless otherwise noted and/or modified by these specifications.

D. The contractor is responsible for the construction layout of this project. The contractor shall forward all construction layout survey information to the Engineer for reference including: benchmarks, stationing and elevations.

E. All contractors and other persons utilizing this specification and the information contained herein are cautioned to comply with the requirements of Pennsylvania Act 172, entitles “Excavation and Demolition Work Protection of Underground Utilities.”

Each individual contractor using the project plans must verify the location and depth of

Scope of Work 000000-4 all underground utilities and facilities before starting work. The contractor shall notify “PA One Call” (1-800-242-1776) at least 72 hours prior to the start of any excavation.

F. The contractor shall establish contact with an individual from each local utility prior to commencement of excavation. The contractor shall notify the Engineer and the utility owner immediately should a conflict occur in the limits of construction. The contractor shall be responsible for coordination of all work to be performed by the utility owner with regards to the work included in this contract. Additional payment will not be made for any delays incurred or any additional work performed due to conflicts with existing utility mains or service lines.

G. All paved asphalt or concrete areas disturbed during construction shall be restored to a condition at least equal to that which existed prior to the start of construction.

H. All grassed areas disturbed during construction shall be topsoiled, fertilized and seeded.

No additional payment will be made for restoration of grassed areas, but the cost shall be included in the various items of the proposal.

I. All trench backfill shall be placed in four inch (4”) thick lifts and thoroughly compacted to the satisfaction of the Engineer. If borrow fill is required, it shall be subject to the approval of the Engineer.

J. The contractor shall be responsible for the location and preservation of underground and surface utilities and structures at / or adjacent to the site of construction. It shall be at the contractor’s own expense to repair or replace anything that is damaged by the contractor.

K. All construction details not shown shall be in accordance with PennDOT standards as detailed in:

1. PennDOT Specifications, Pub. 408, latest revision;

2. PennDOT Standards for Roadway Construction, Pub. 72, latest revision.

These standards can be purchased at: PA Department of Transportation, Sales Store, P.O. Box 2028, Harrisburg, PA 17105-2028, (717-787-6746).

L. If encountered, payment will not be made for the excavation of rock, but the cost shall be included in the various items of the proposal.

PART 2 – PRODUCTS

Not Used

Scope of Work 000000-5

PART 3 – EXECUTION

PART 4 – QUANTITY AND PAYMENT

END OF SECTION

General Requirements 010000-1

SECTION 010000

GENERAL REQUIREMENTS

PART 1 - GENERAL

1.01 General

A. Only major items of work are given in the Bid Form, but it is the intent of the specifications to secure a completely interconnected and functionable system, and should any workmanship or materials be required which are obviously necessary to carry out the full intent and meaning of the plans and specifications or to be reasonably inferred therefrom, the cost of such workmanship or materials shall be included in the items in the bid form.

B. Where construction is being performed in traveled roadways or rights-of-way, the

Contractor is to provide all necessary traffic controls and devices in accordance with the current Pennsylvania Department of Transportation standards.

C. The Contractor shall notify all utility companies prior to Construction of utilities, curbing and paving.

D. Prior to any excavation, the Contractor shall have all utilities marked and shall excavate or otherwise determine the exact location and elevations of said utilities. The

Contractor shall notify the Engineer of any conflicts. The Contractor shall arrange for any necessary utility relocations or field changes and shall reschedule his operations appropriately.

E. The Contractor, in the construction of the project, shall not stockpile materials or store equipment on any private property; except areas designated by the plans or as directed by the Engineer. If so required, the Engineer may direct the Contractor to have equipment removed from any project during weekend hours.

F. All work of refilling sunken ditches, repaving over trenches and keeping streets and sidewalks in passable condition shall be done to the satisfaction of the Owner during the construction of the project as well as during the maintenance period. If any remedial work is not done within three (3) days after written notice is given by the Engineer, the work may be done by the Owner and charged to the Contractor.

G. Special care shall be taken to prevent contamination, siltation, or interference of any kind with the stream flows or ponds along the line of work. No waste matter of any kind will be allowed to discharge into the stream flows or impounded water of any ponds or other bodies of water.

H. The Contractor is to ensure that proper measures for erosion control are employed and provide for the early establishment of vegetation that will help avoid erosion problems during and after construction. It is expected that the Contractor will anticipate possible

General Requirements 010000-2 problems and provide timely and adequate control to prevent or minimize adverse effects.

I. The Contractor shall apply and pay for all permits that may be required for any of the work involved with this project.

J. The Contractor is to notify residents by door-hangers, at least forty-eight (48) hours in advance, before starting construction work that will directly affect their property frontage, driveway(s) and/or on-street parking.

K. The Contractor will be provided with one (1) set of contract specifications and full size drawings, where applicable. Electronic copies will be available by request in .pdf format. The cost for any additional copies shall be included in various items of the proposal.

L. All notes on plans shall be made a part of the specifications.

M. The Contractor shall notify the Engineer at least forty-eight (48) hours in advance of any work scheduled for Saturdays. There will be no work permitted on Sundays or holidays. This project will receive full-time inspection and the normal working hours for the Inspector are from 7:00 AM to 3:30 PM, Monday through Friday. Any overtime inspection costs which are avoidable will be reimbursed by the Contractor.

N. During the construction phase of the project, travel lanes shall remain open at the end of each day.

O. The Contractor shall take extreme care in the placement of the asphaltic tack coat so as to not make it visible on the concrete curb or inlet top units. It shall be the Contractor's responsibility to keep the concrete curb and inlet top units clean of this material.

P. Separate payment will not be made for construction layout. The costs for construction layout for all site work shall be included in the various items of the proposal.

1.02 Public Utilities

A. The Contractor is required to ascertain all the facts concerning the location of utilities.

B. The Contractor shall cooperate with the utility Owners in the adjustment of their facilities and shall notify the utility Owners not less than ten (10) days in advance of the time scheduled to perform any work that will impact or affect their facilities.

C. The Contractor shall permit the Owners of utilities, or their agents, access to the site of the work at all times in order to relocate, construct or protect their lines and he shall cooperate with them in performing this work.

General Requirements 010000-3

D. Separate payments will not be made for the coordination and cooperation of the

Contractor with the utility companies, nor for the protection or replacement of utilities as specified hereinbefore and the bidder shall include all such costs in the prices bid for the various scheduled items in the Bid Form.

1.03 Preconstruction Video

A. The Contractor shall, at no extra cost to the Owner, take DVD video recordings of the site prior to the commencement of construction. The video recording shall accurately depict the existing preconstruction condition of all curbs, sidewalks, driveways, fences, lawns, landscaped area, mailboxes, street furniture and all other appurtenances within, or outside a 25 foot radius of the limits of the construction of the project. One (1) copy of the video recording shall be provided to the Engineer. The date of the DVD video, as well as identification as to the location which the video depicts must be provided.

1.04 Maintenance and Protection of Traffic

A. The Contractor shall erect or place and maintain in good condition, barricades, warning signs, lights, flares, approved yellow-flashing light units, rubber traffic cones, and other warning and danger signals and devices, appropriate and adequate for the specific needs and subject to the Engineer's approval, at working sites, closed roads, intersections, open excavations, locations of material storage, standing equipment and other obstructions, at points where the usable vehicular or pedestrian traffic width of the road or sidewalk is reduced, at points where traffic is deflected from its normal courses or lanes, and at other places of danger to vehicular or pedestrian traffic.

B. The Contractor shall provide sufficient watchmen and traffic directors and shall take all other precautions, including any that may be ordered by the Engineer, which are necessary for the safety of the public and protection of the work.

C. The Contractor shall obtain the approval of the Engineer and consent of all appropriate authorities having jurisdiction, for any detours which may be required. The Contractor shall make all necessary arrangements with such authorities regarding the establishment, maintenance and repair of such detours, the regulations and direction of traffic thereon, and the installation and maintenance of signs and traffic devices.

D. Before beginning work on any phase of the project, the Contractor shall furnish and install warning signals, barricades, wood traffic guides, lights, flares and other devices necessary, in the opinion of the Engineer, to protect the public during that phase of his operations.

E. If battery operated flashing warning lights are used, they shall conform to the specifications prepared by The Pennsylvania Department of Transportation, Official

Traffic Control Devices. These specifications require, in part, that the flashing lights be weatherproof and reasonably tamper-proof and theft proof, be equipped with seven inch

(7") minimum diameter amber plastic lens, shall operate with a flash rate of between 55

General Requirements 010000-4 and 75 flashes per minute with a flash duration of not less than 18% of each flash cycle;

and shall be inspected and cleaned daily so as to maintain the lights in the proper working condition.

F. Road construction signs shall be placed at each end of the project along with every connecting intersection. At the start and end of each day, detour signs shall be placed if required.

G. During the work on this project, the Contractor shall provide and/or be prepared to provide traffic protection devices in accordance with the Manual on Uniform Traffic

Control Devices and PennDOT Pub. 212. The minimum numbers set forth in the

Schedule shall be on hand at each separate project site prior to the commencement of any work (or phase of work) and shall be maintained available on the project site throughout the period of the project (or phase). Failure to provide and maintain the minimum number of devices shall be sufficient cause for the Engineer to order cessation of work. When lack of any required safety devices presents an immediate hazard, the

Engineer may order that such devices be provided by the Owner or by other

Contractors, deducting the cost thereof from any monies due or becoming due the

Contractor lacking the required devices.

H. Additional devices shall be provided by the Contractor as required or directed prior to the commencement of any operation or phase of an operation requiring such devices.

I. Uniform traffic directors (flagpersons) shall be provided whenever alternate two-way traffic is maintained in a single lane, whenever Contractor's operations require closing of a lane or portion of a lane on a multiple lane roadway, whenever the Contractor's equipment or vehicles are entering or leaving active roadways at other than normal street intersections, whenever a Contractor's operations will be contrary to or cause confusion regarding normal traffic control devices (traffic signals, signs, etc.) within a work area and whenever else, in the opinion of the Engineer, the Contractor's operations cause such hazards as to require the use of Traffic Directors.

J. Traffic Directors shall be responsible and thoroughly familiar with their responsibilities, and, while serving as Traffic Directors, shall not be required to perform any other duties. Traffic Directors shall be provided with an orange or red flag, an orange, orange and white, or lime green traffic safety vest and white or orange hard hat or other appropriate head gear. The Contractor may, at his option, secure the services of uniformed policemen having jurisdiction in the locality within which the project is located. Provision of such uniformed policemen will be deemed sufficient in meeting the requirements of this specification.

K. Traffic must be maintained throughout each separate work area during construction. At least one 12' lane must be maintained for traffic during all actual construction periods and at least two 10' lanes must be maintained for traffic at all other times.

General Requirements 010000-5

L. The Contractor is advised that there may be heavy commuter traffic during the morning from 7:30 AM to 9:00 AM and the afternoon from 3:00 PM to 5:30 PM.

M. Construction shall be so staged to maintain at least one lane for traffic in each direction throughout each separate work area during the morning 7:30 AM to 9:00 AM and the afternoon 3:00 PM to 5:30 PM weekday periods of peak traffic.

N. Any restriction of traffic at any time shall be subject to the approval of the Engineer, and the Municipal Police Department. Any restriction of traffic on a Pennsylvania State

Highway shall be subject to regulations and permitting prescribed by The Pennsylvania

Department of Transportation. The Contractor shall submit a schedule of staged construction to the Engineer for approval prior to any restriction of traffic.

O. Should construction be in close proximity to a school or school traffic route, and be commenced during an active school period, the Contractor shall provide open traffic lanes to accommodate school bus and school related traffic.

P. If detours are proposed by the Contractor, they are subject to the review and approval of the Engineer, the Municipal Police Department and/or The Pennsylvania Department of

Transportation, as applicable.

Q. A detour plan and schedule shall be prepared by the Contractor for each proposed detour and submitted to each of the approving agencies previously mentioned. All detour signs shall conform to the requirements for Traffic Control Devices.

R. Temporary traffic stripes will be necessary to control and guide traffic through individual work areas. The Contractor shall submit a scheme for approval by the

Engineer of all temporary traffic stripes prior to removal of any existing traffic stripes.

S. Construction of proposed utility pipes or storm pipes across existing roadways shall be so staged to maintain one lane in each direction. Trenches shall not remain open overnight.

T. The Contractor shall provide adequate means of access for fire, police and emergency vehicles throughout the length of the project. Contractor shall also provide for safe and adequate means of access to adjacent properties, both private and public.

U. The cost of all work as specified hereinbefore and all other work required to protect public safety and maintaining traffic flow shall be included in the prices bid for the various items in the Bid Form, unless specifically requested as a bid item in which case payment will be made as a lump sum.

1.05 Reference to the Standard Specifications

A. Portions of the work performed under this contract shall comply with the requirements of the Commonwealth of Pennsylvania Department of Transportation Publication 408, General Requirements 010000-6 latest edition and supplements and the Pennsylvania Department of Transportation

Standard Construction Details as applicable and all requirements modified, as amended or supplemented and whose specifications are made part of these specifications.

B. The Standard Specifications are made part of these specifications by this reference as if they were set forth in full. It is the responsibility of the prospective bidder to be familiar with these Standard Specifications.

1.06 Dust Control

A. The Contractor will be required to maintain all excavations, embankments, stockpiles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or outside the project boundaries free from dust which would cause a hazard or nuisance to others. Approved temporary methods of stabilization consisting of sprinkling, chemical treatment, light bituminous treatment or similar methods will be permitted to control dust. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor must have sufficient competent equipment on the job to accomplish this if sprinkling is used. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs. If any dust control is not done within twenty-four (24) hours after written notice is given by the Engineer, the work may be done by the Owner and charged to the Contractor. Costs for dust control shall be included in the prices bid for the various items in the bid form.

1.07 Testing Materials

A. Except as may be provided elsewhere, test or analysis of materials which are usually tested after delivery to the site, such as concrete aggregate, mixed and placed concrete, and similar materials; will be performed by a test laboratory which will be approved by the Engineer and selected and paid for by the Contractor. The preliminary testing of concrete mixtures and test or analysis of other materials, samples of which are to be submitted prior to delivery, will also be performed by the laboratory and paid for by the

Contractor.

B. If the Engineer orders sampling and analysis or tests of materials which are usually accepted on certification of the manufacturer but which appear defective or not conforming to the requirements of the Specifications, the Contractor will bear the reasonable costs of sampling, transportation, test and analysis.

1.08 Test Cores and Core Analysis

A. The Contractor shall be responsible for providing test cores and core analysis of all bituminous concrete surface course and bituminous stabilized leveling and base course items upon completion of these items. Test coring and core analysis shall be performed by a testing laboratory equipped and experienced in performing this work. The testing laboratory shall be approved by the Engineer. Coring and core analysis shall be

General Requirements 010000-7 performed in strict compliance with Section 106 of the Commonwealth of Pennsylvania

Department of Transportation Publication 408.

1.09 Mobilization

A. DESCRIPTION�This work is the assembly and set-up of the general plant required to comply with the contract and with local and State laws and regulations. General plant includes Contractor's offices, shops, plants, storage areas, and sanitary or other facilities.

This work includes obtaining the required permits, insurance, bonds, and any other initial items required for the start of the work.

B. MATERIAL�These material and furnishings will not be considered a part of the other completed contract items.

(a) Mobilization shall be performed in strict compliance with Section 608 of the

Commonwealth of Pennsylvania Department of Transportation Publication 408.

PART 2 � PRODUCTS

Not used

PART 3 � EXECUTION

Not used

PART 4 � QUANTITY AND PAYMENT

4.01 Mobilization

A. Quantity of �Mobilization� will not be measured for this project, but shall be bid as a lump sum (LS) as shown on the bid form.

B. Payment for �Mobilization� will be made as a lump sum (LS). Payment for

Mobilization will be recommended after a Performance Bond has been secured, all submittals have been approved, Notice to Proceed has been issued, and the physical work has commenced. Payment for Mobilization will only be made once. No additional payment will be made for remobilization.

4.02 Maintenance and Protection of Traffic

A. Quantity of �Maintenance and Protection of Traffic� will not be measured for this project, but shall be bid as a lump sum (LS) as shown on the bid form.

B. Payment for �Maintenance and Protection of Traffic� will be made at a percentage of the lump sum (LS) amount bid. The percentage estimated for each payment application

General Requirements 010000-8 shall be proportional to the dollar amount of the contract completed for that payment period.

4.03 General Requirements

A. Quantity of all other items covered in the General Requirements will not be measured for this project, but the work shall be performed as incidental to the proposed work.

B. Payment for all other items covered in the General Requirements will not be made for this project, but the cost shall be included in the various items of the proposal.

Record Documents 017810-1

SECTION 017810

RECORD DOCUMENTS

PART 1 � GENERAL

1.01 Summary

A. This section consists of the requirements for preparing and delivering record drawings.

B. This section describes only the minimum requirements for record drawings. Other contract sections may impose additional requirements on record drawings and documents and the more stringent requirements must be followed.

1.02 Definitions

A. Record Drawings. Record drawings consist of the collective plans, details, forms and other documents which have been annotated to describe the actual location of constructed improvements.

PART 2 � MATERIALS

2.01 Not used.

PART 3 � EXECUTION

1.01 Record Plans.

A. The Contractor shall be responsible for maintaining accurate records of all improvements as the project progresses.

B. All elevations, angles and measurements used for record drawings shall be obtained by the Contractor according to the standard practices of the surveying profession.

C. All elevations used for record drawings shall be based on the project benchmarks designated on the project plans. If all project benchmarks have been compromised or removed, then the Contractor shall notify the Engineer to establish an acceptable benchmark.

D. Record Drawing Tolerances.

1. Measured horizontal (±0.10 feet) and vertical (±0.05 feet) locations of underground utilities and appurtenances, referenced to permanent surface improvements.

2. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

3. Field changes of dimension and detail.

Record Documents 017810-2

E. Record Drawing Formatting.

1. PDF. Record drawings may be developed electronically using a PDF of the original project plans overlaid with as-built information. Record information must be clearly and accurately depicted in red. The Contractor shall provide (1) electronic copy and (1) hard copy to the Engineer.

2. CAD. Record Drawings may be developed using computer automated drafting

(CAD) software. Upon request, the Engineer may provide the Contractor with design CAD files for the purpose of developing record drawings. Record information must be placed on a separate layer within the CAD model. The

Contractor shall provide (1) electronic copy and (1) hard copy to the Engineer.

1.02 Record Details or Shop Drawings.

A. The Contractor shall provide accurate record details and/or shop drawings to describe any work that was not completed according to the details shown on either the project plans or in referenced standards.

1.03 Piped Underground Utilities (e.g. storm sewer, sanitary sewer, water, gas).

A. Actual size, type and length of each pipe segment.

B. Actual size and type of each fitting, bend and valve. Information shall include the type of each valve or fitting and the degree of each bend.

C. Actual invert elevations at each structure (including invert elevations in and out), actual invert elevations at each bend, actual grate and/or rim elevations, and high and low points. In general, the contractor shall verify each design elevation shown on the project plans and indicate on the record plan any actual elevation which deviates from the corresponding design elevation.

D. At each fitting, bend and valve, horizontal dimensions shall be provided to three permanent surface features.

1.04 Electrical/Communication.

A. Actual size, type and depth of each conduit, duct bank or cable, including empty conduits or duct banks, as well as the location of any hand holes, pull boxes or junction boxes.

1.05 Curb Ramps.

A. The requirements for recording distances, slopes and cross-slopes for curb ramps are based on requirements from the State Department of Transportation or the local municipality, depending on whether or not a curb ramp is located within a State

Right-of-Way. The requirements for recording actual curb ramp measurements are separate and distinct from the construction requirements for curb ramps (see

Record Documents 017810-3 applicable construction details and specifications for the construction of curb ramps).

B. State Right-of-Way: The Contractor shall provide all actual measured distances, slopes and cross-slopes at all points of interest on newly constructed curb ramps, as necessary to complete curb ramp inspection forms and verification for the State

Department of Transportation. The measurements and slopes shall be taken at each of the locations shown on the State Department of Transportation curb ramp inspection form for each individual curb ramp and may include taking measurements and slopes on the surrounding sidewalk areas and on the cartway surface.

C. Local Right-of-Way: The Contractor shall provide actual measured distances, slopes and cross-slopes for all curb ramp surfaces, including the ramp, side flares and turning spaces.

1.06 Building Construction.

A. Actual installation shall be indicated with all installed items clearly identified.

Location of installed items and any deviations from contract documents shall be so shown with boxes around the actual numbers or labels.

B. Actual finished floor elevation.

1.07 Record Drawings Verification.

A. After record drawings and documents have been delivered to the Engineer, the

Owner or the Engineer may make a written request to the Contractor for verification of any aspect of the record drawings and documents.

B. Upon receipt of a written request for verification of any aspect of the record drawings, the Contractor shall take measurements, take photographs, and create field sketches, as may be required by the Owner to verify the record drawings. This work may include digging test pits and making necessary restorations.

C. If the Contractor fails to complete record drawing verification to the satisfaction of the Owner or within a timely manner, then the Owner may direct the Engineer or an independent third party to perform record drawing verification work. The costs associated with record drawing verification work may be deducted from payment for other work completed by the Contractor.

PART 4 � QUANTITY AND PAYMENT

4.01 As-Built Drawings

A. Quantity of "As-Built Drawings" will not be measured for this project.

Record Documents 017810-4

B. Payment for "As-Built Drawings" will be made a lump sum (LS) for complete record documents provided for each base bid and alternate bid area. Payment for Record

Drawings will be made after all record drawings and documents have been delivered to the Engineer and have been accepted by the Engineer. Payment for record drawings will only be made once. There will be no additional payment for record drawings associated with change order work.

Cleaning and Restorations 020100-1

SECTION 020100

CLEANING AND RESTORATIONS

PART 1 - GENERAL

1.01 Description

A. Contractor shall provide all equipment, labor & materials required to clean and restore the site to at least the existing condition.

B. Maintain premises and public and/or private properties free from accumulations of waste, debris and rubbish caused by work operations.

C. At the completion of work, remove waste materials, rubbish, tools, equipment, machinery and surplus materials; clean all visually exposed surfaces; leave project clean and ready for occupancy.

D. At the completion of work, restore or replace, where and as directed by the Owner, any public or private property disturbed or damaged by Contractor's work operations to a condition at least equal to that existing prior to beginning work, or as otherwise specified. Materials, equipment and methods shall be approved by the Owner.

PART 2 - PRODUCTS

2.01 Materials

A. For restorations, use the following materials. All materials shall comply with the following Articles of the Commonwealth of Pennsylvania, Department of

Transportation Specifications latest revision and these specifications.

B. Grass restorations: See Sections 802, "Topsoil Furnished and Placed", Section 804

�Seeding and Soil Supplements�, and Section 809 "Sodding".

C. Pavement restorations: See Section 409 "Superpave Asphalt".

D. Restoration of curbs and other concrete structures:

1. Concrete:

a. Shall be Class AA conforming to Section 704, �Cement Concrete�

b. Design Compressive Strength: 3,500 psi at 28 days.

c. Air-entrainment shall be 6.0% + / - 1.5%.

2. Joint Fillers: Section 705.4.

3. Curing Compound: Section 711.2.

Cleaning and Restorations 020100-2

E. All other Materials: As approved by the Owner or authorities having jurisdiction.

PART 3 � EXECUTION

3.01 Methods of Conducting Work - Cleaning

A. Requirements of regulatory agencies:

All excess material shall be removed from the site and disposed of by the Contractor at his expense. Cost to be included in the Base Bid for the Project. The disposal site shall be in permanently established licensed landfills.

B. Cleaning during construction:

Provide periodic cleaning to keep the work, the site, and adjacent properties free from accumulations of waste materials, rubbish and windblown debris resulting from construction operations. This includes dust, dirt and mud.

Provide on-site containers for the collection of waste materials, debris and rubbish.

Maintain containers as required. Containers shall be covered as required to prevent unauthorized use.

C. The Contractor will be required to maintain all excavations, embankments, stockpiles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which would cause a hazard or nuisance to others. Approved temporary methods of stabilization consisting of sprinkling, chemical treatment, light bituminous treatment or similar methods will be permitted to control dust. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor must have sufficient competent equipment on the job to accomplish this if sprinkling is used.

Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs. If any dust control is not done within twenty four (24) hours after written notice is given by the Engineer, the work may be done by the Owner and charged to the Contractor.

3.02 Methods of Construction

A. General: All existing structures, unpaved areas and paved areas disturbed or damaged during the work under this contract shall be restored or replaced to a condition at least equal to that existing prior to beginning work, or as otherwise specified. The methods of conducting this work shall, as a minimum, conform to the following Articles of the

Commonwealth of Pennsylvania Department of Transportation Specifications.

Cleaning and Restorations 020100-3

B. Grass Restorations:

See Section 802 �Topsoil Furnished and Placed�, and Section 804 "Seeding and Soil

Supplements", and Section 809 "Sodding".

C. Pavement Restorations:

Restoration type and thickness shall be as shown on the contract drawings or as otherwise directed.

D. Restorations of Curbs and Other Concrete Structures:

1. Curbs: Section 630 �Plain Cement Concrete Curb�.

2. Other concrete structures: Restore in accordance with applicable Articles of the

Standard Specifications.

E. All Other Restorations:

Restore in accordance with applicable Articles of the Standard Specifications, or as approved by the Owner or authorities having jurisdiction.

PART 4 � QUANTITY AND PAYMENT

4.01 Cleaning and Restorations

A. Quantity of Cleaning and Restorations will not be measured for this project, but the work shall be performed as necessary to restore all disturbed areas to at least the pre-existing condition.

B. Payment for Cleaning and Restorations will not be made for this project, but the cost shall be included in the various items of the proposal.

Dewatering & Flow Diversions 021400-1

SECTION 021400

DEWATERING AND FLOW DIVERSION

PART 1 � GENERAL

1.01 Description

A. Dewatering of trenches and excavations.

B. Storm culvert flow diversion.

PART 2 � PRODUCTS

2.01 Materials

A. Furnish pumps, carrier pipe, hoses, plugs, temporary lighting, shoring, and other equipment required for dewatering and flow diversion work.

PART 3 � EXECUTION

3.01 Methods of Work

A. Performance:

1. Dewatering:

a. Prevent surface water and subsurface or groundwater from flowing into excavations and from flooding project site and surrounding area.

b. Keep excavations and structures dry until all work is completed. Do not use trench excavations as temporary drainage ditches.

c. Dispose of water in suitable manner, without damage to work site or adjacent property.

d. Any sediment laden water from trench dewatering shall be filtered through approved sediment barriers prior to discharging onto the surrounding areas.

2. Flow Diversion:

a. By-pass pumping of storm flows as necessary to complete construction of proposed storm sewer facilities.

b. The Contractor shall determine fluming pipe and pump sizes necessary for required flow by-pass and submit a by-pass plan to the Engineer for review.

Dewatering & Flow Diversions 021400-2

c. The flow diversion system components must be removable in the case of an emergency.

d. Any damage to the existing sewer system caused by flow diversion operations shall be the Contractor�s responsibility and shall be repaired at no cost to the Owner.

e. One week prior to all damming and diverting of flows the Contractor shall notify the

Owner and the Engineer.

PART 4 � QUANTITY AND PAYMENT

4.01 Dewatering and Flow Diversion

A. Quantity for Dewatering and Flow Diversion will not be measured for this project, but the work shall be performed as necessary to keep excavations, trenches and structures dry throughout the duration of the project.

B. Payment for Dewatering and Flow Diversion will not be made for this project, but the cost shall be included in the various items of the proposal.

Excavation and Backfill 022270-1

SECTION 022270

EXCAVATION AND BACKFILL

PART 1 � GENERAL

1.01 Description

A. Excavation and backfill shall include the excavation and backfilling for demolition and or removal of existing below grade structures or utilities as indicated in the specifications for all materials of whatsoever nature encountered.

PART 2 � PRODUCTS

2.01 Materials

A. The Contractor shall, at his expense, make such test pits and borings along the line and site of the work to satisfy himself regarding the character of the various strata of sub-surface materials and the amount of ground water that may be encountered in the course of construction and shall bid accordingly and the unit lump sum prices bid for the various pipes or structures requiring excavation shall include the difficulties to be encountered in excavation. Excavation shall include all materials excavated, encountered, including but not limited to rock, earth, shale, quicksand, gravel, sand, cinders, broken stone, concrete, paving, filled material, etc., and all miscellaneous excavation not herein specified and classified.

B. Backfill material:

All on-site backfill materials shall be subject to the approval of the Engineer, and to the following requirements.

1. Shall be as indicated on the plans.

2. Free from deleterious substances, stumps, brush, weeds, roots, sod, rubbish, garbage and matter that may decay.

3. Backfill to a height of two (2) feet above the top of the pipes, culverts and other structures with material free from stones or rock fragments larger than two inches

(2") in greatest dimension, or as directed by Engineer.

4. Free of large rocks or lumps that, in the opinion of the Engineer, may create voids or prevent proper compaction.

C. Additional backfill material shall conform to Section 205 of the Pennsylvania

Department of Transportation Publication 408 for Borrow Excavation.

Excavation and Backfill 022270-2

PART 3 � EXECUTION

3.01 Method of Construction

A. General Excavation - Excavation of all materials of whatsoever nature encountered shall be made to the lines and grades shown on the drawings, or as may be necessary to fully carry out the intent of the drawings, and of these specifications, where no grades are indicated or described. Surfaces of excavations in earth, exposed in the finished work, both level and sloped, shall be excavated in planes four inches lower than the finished surfaces, measured perpendicularly to the plans, and shall be brought up to the finished surfaces with 4" top soil as specified elsewhere. Finished surfaces shall be true to line and grade and shall be dressed to even planes. Unless otherwise shown or stated on the drawings, all exposed slopes excavated in earth shall be one vertical to two horizontal. Slopes shall be kept true to line and grade during the progress of the work, and should any slope be scoured by storm water, or otherwise disturbed, or should any excavation be scoured or disturbed before final payment is made, the Contractor shall promptly restore the slope or excavation so scoured, gullied or otherwise disturbed to line and grade before final payment is made. No additional compensation will be paid the Contractor by reason of the encountering of any unusual or unexpected subsoil conditions.

B. Unauthorized Excavation - Special care shall be taken to prevent the movement of disturbances of earth under the foundation of the pipelines, manholes and other structures by providing adequate sheathing and bracing. Where the excavation is carried beyond or below the lines and grades given by the Engineer, or wherever the

Engineer shall determine that any material has been loosened or disturbed sufficiently to reduce its supporting power, remove all such loosened material and refill all such excavated space to grade with sand or loam thoroughly rammed, in such manner as may be directed by the Engineer in order to ensure the adequate support and stability of the pipeline and other structures. All excavation and any other operation shall be confined to the width of the right-of-ways available.

C. Materials Excavated - The materials excavated shall be laid compactly on the side of the trench or excavation and kept trimmed as to be of as little inconvenience as possible to the travelling public and to adjoining tenants. Where the streets are paved, the paving materials shall be kept separate from the other materials excavated. All streets shall be kept open for travel unless otherwise directed by the Engineer.

D. Removal of Excavated Materials - The Contractor shall not, without permission from the Engineer, remove from the line of the work any excavated materials which may be suitable for filling the trench or excavation until the same has been refilled. All excess excavation shall remain the property of the Owner and shall be disposed of at the location so designated by the Owner within the limits of the Municipality at the

Contractor's expense. However, if the Owner has no real need for this excess

Excavation and Backfill 022270-3 excavation, it shall be the Contractor's responsibility to dispose of said material at no expense to the Owner. Excess excavation shall be immediately removed.

E. Removal of Water - Maintain and provide at all times during construction ample means and device which shall promptly remove and properly dispose of all water or sewage entering the excavation and structures, until all work to be built therein is completed.

Dispose of the water from the trenches and excavation in a suitable manner, without damage to adjacent property and in no case unless by special permission of the

Engineer, shall water be allowed to run through the new pipes. Furnish all necessary machinery, power and labor to pump, bail or otherwise remove any water which may be found or shall accumulate in the trenches or other excavation and shall perform all work necessary to keep them clear of water while the work is under construction.

If the ground water and subsoil conditions along the line of the work are such that the

Contractor cannot successfully handle the ditch water and provide a stable, hard trench bottom by ordinary trench pumping and bailing, the Contractor shall furnish and provide the necessary equipment, power and labor to employ the well point method of trench dewatering without additional compensation. All pipe, joint and concrete must be installed under absolutely dry conditions.

F. Backfilling - The backfilling of the trench will be filled by using properly compacted, common earth material. If sufficient earth cannot be obtained to completely fill the trenches, small pieces of rock may be used under the condition that the space between the walls of the trench and the outside of the pipe to a height one foot above the top of the pipe, be filled with loose, fine earth, free from stone and hand-tamped, and placed in separate layers of not more than six inches in depth and each layer covered with from six to ten inches of earth.

Should excavated material be clay that will not consolidate by ordinary methods of backfilling, it…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .