About this file
This document is Attachment C (Technical Project Scenarios) for FEMA solicitation 70FA2025Q00000006, outlining two technical scenarios that offerors must respond to as part of their proposal submissions. The first scenario requires conducting a national After-Action Report covering three FEMA Regions and 6 states/territories, involving over 3,000 deployed Federal Employees across six field offices. Offerors must detail their approach across six tasks: project management, requirements identification, data collection, analysis/validation, findings development, and report finalization. The final report must be 75-100 pages with 30-40 findings.
The second scenario involves designing, developing, and maintaining an external portal for the Continuous Improvement Information System (CIIS) accessible to federal agencies and state/local/tribal/territorial partners. The portal must enable sharing after-action reports, manage/track actions against findings, and provide analytical capabilities. Offerors must address six tasks: project management, design, development, testing, training, and release. For both scenarios, responses are limited to 15 pages using 12-point font, and offerors must complete provided tables detailing proposed resources, labor categories, technical skills, and key personnel experience. All proposed labor categories must align with the offeror's GSA Schedule SIN #874-1 and approved BPA price schedule.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment "C"
Solicitation 70FA2025Q00000006
Technical Project Scenarios
Date: 02-05-2025
Project Scenario One: National After-Action Report
Your company receives a BPA Call Order with a 12-month period of performance to conduct a national After-Action Report. The After-Action Report covers three separate events, that involve three FEMA Regions, and 6 states and/or territories. There are six field offices involved in the events where at least 100 FEMA staff have been deployed to each of the six field offices (for a total of over 3,000 deployed Federal Employees). The resulting product will be a final report approved by the FEMA Administrator to be released publicly. It is expected to be 75-100 pages, and a comprehensive set of 30-40 findings with courses of action for program offices to take actions on.
Please describe the methodologies and deliverables associated with performing each of the following tasks (and resources including labor mix and level of effort):
• Task 1: Project Management o Determine the appropriate project management products, processes, and systems to complete this task and deliverables in 12 months.
• Task 2: Identify the Requirements o Determine the report priorities and focuses.
o Determine the relevant stakeholders and engagement strategy.
• Task 3: Data Collection o Determine the recommended collection schedules.
o Determine the recommended sources to collect data from and approach to collecting the data.
• Task 4: Data Analysis and Validation o Outline the analytical methodologies and tools used to assess the data.
o Indicate the validation approaches to assess the initial data collection.
• Task 5: Findings and Product Development o Develop the findings.
o Develop the After-Action Report
• Task 6: Finalize the After-Action Report Approval and Release o Define the approach to getting the Report approved to release to the public.
o Describe the communication materials surrounding the release of the report.
Describe the resources you will use for this call order using table 1. Please crosswalk the relevant
PSS labor category(ies) anticipated to complete the work with the relevant labor categories under your GSA/FSS SIN #874-1 submitted with your BPA price quotation under Section B.6 of the
RFQ. Only labor categories including in your BPA price schedule (B.6) may be used. A complete GSA solution is required with no open-market item other than travel.
Offerors may associate more than one labor category with roles requiring more than one person.
Please describe the specific technical and specialized skills within each role that your team will bring to completing the requirements. Please include a proposed staffing plan with specific names of Proposed Key Personnel and brief summaries of experience for specific people who would fill the roles.
Table 1. Sample Project Scenario One- Proposed Resources
Role / (Number of Staff in Role)
Degree and
Years of
Experience1
Respondent’s
Mapped PSS
Labor
Category
Corresponding
BPA Price
Quotation Labor
Category
Estimated Hours
Project Scenario One Response Instructions
Please use the following outline and tables in preparing your response to Project Scenario One.
The entire response shall not exceed 15, single sided 8.5 inch by 11-inch pages and shall use a type-pitch that is no smaller than a standard 12-point font type as outlined in Section “B”
Volume-1 Technical Quotation Instructions. Pages exceeding the 15-page limit will not be considered. Respondents must use the tables provided for composing their response.
1. Response Overview/Summary of Benefits
2. Project Technical Approach/Methodology
3. Technical and Specialized Skills per Role
4. Staffing Plan and Staff Experience Summary
Table 2. Sample Project Scenario One, Project Role Technical and Specialized Skills
Role Technical and Specialized Skills
1 Proposer-specific equivalents included in approved PSS schedule may be substituted for education or years of experience requirements.
Table 3. Sample Project Scenario One, Proposed Key Personnel
Key Personnel Staff Member Experience
Project Scenario Two: Continuous Improvement Information System Design, Development, Operations and Maintenance
The Continuous Improvement Program maintains the Continuous Improvement Information
System (CIIS) as the Agency’s system of record for action and evaluation implementation and tracking for Agency findings and actions taken.
Your company receives a call order with a 12-month period of performance (efforts may be multiyear or extended based on the initial tasks, level of effort required. and scope of work) to build CIIS out to include an external portal accessible to other federal agencies and state, local, tribal, and territorial (SLTT) partners. The portal needs to accomplish three primary functions:
1) place where organizations can share their after-action review reports; 2) functionality to allow organizations to manage and track their actions against findings and observations in a secure and access-controlled manner, and 3) analytical capabilities that provide insight and learning from available data to users to inform their preparedness and operations.
Please describe the methodologies and deliverables associated with performing each of the following tasks:
• Task 1: Project Management o Determine the appropriate project management products, processes, and systems to support this task for a 12-month period of performance.
o Identify known or projected requirements or risks for project success (project timeline, risk matrix, QA/QC Plan etc.).
• Task 2: Design o Describe the tasks and activities for designing a solution for this functionality.
o Outline the critical information necessary for project success.
o Discuss the requirements analysis process and stakeholders to be involved.
• Task 3: Development o Describe the development process you would use, and how you would manage for quality.
o Note the success metrics to monitor throughout the development.
• Task 4: Testing o Describe the process to test the functionality.
o Articulate the revision processes to address testing findings and ensure requirements are met.
• Task 5: Training o Describe the approach to ensuring user adoption, success, and engagement.
o Specify details and factors that will help meet success factors from training.
• Task 6: Release o Describe the functionality release rollout plan.
o Outline critical success factors for the ongoing operations and maintenance of these system elements.
Describe the resources you will use for this call order using table 7. Please crosswalk the relevant
PSS labor category(ies) anticipated to complete the work with the relevant labor categories under your GSA/FSS and submitted with your BPA price quotation. Only labor categories including in your BPA price schedule may be used. A complete GSA solution is required with no open-market item other than travel. Offerors may associate more than one labor category with roles requiring more than one person. Please describe the specific technical and specialized skills within each role that your team will bring to completing the requirements. Please include a proposed staffing plan with specific names of Proposed Key Personnel and brief summaries of experience for specific people who would fill the roles.
Table 1. Sample Project Scenario Two, Proposed Resources
Role / (Number of Staff in Role)
Degree and
Years of
Experience2
Respondent’s
Mapped PSS
Labor
Category
Corresponding
BPA Price
Quotation
Labor
Category
Estimated
Hours
Project Scenario Two Response Instructions
The entire response shall not exceed 15, single sided 8.5 inch by 11-inch pages and shall use a type-pitch that is no smaller than a standard 12-point font type as outlined in Section “B”
Volume-1 Technical Quotation Instructions. Pages exceeding the 15-page limit will not be considered. Respondents must use the tables provided for composing their response.
1. Response Overview/Summary of Benefits
2. Project Technical Approach/Methodology
3. Technical and Specialized Skills per Role
4. Staffing Plan and Staff Experience Summary
Table 2. Sample Project Scenario Two, Project Role Technical and Specialized Skills
Role Technical and Specialized Skills
2 Proposer-specific equivalents included in approved PSS schedule may be substituted for education or years of experience requirements.
Table 3. Sample Project Scenario Two, Proposed Key Personnel
Key Personnel Staff Member Experience