RFIs Received 17June-Answer to Generator Questions (1).docx

DOCX document 20 KB Posted

Attached to
Spectrum Beacon Tower Federal contract opportunity
Solicitation number
FA930121R0003
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This document outlines a solicitation for the replacement of an aging beacon tower at Edwards Air Force Base in California. The project requires replacing the 108-foot self-supporting beacon tower constructed in 1959 with a new self-supporting tower not exceeding 180 feet in height including external protrusions. In addition to constructing the new tower, the contractor must demolish and dispose of the existing tower and its associated generator. The solicitation will use the Lowest Price Technically Acceptable source selection process with the project set aside for total small businesses. The NAICS code is 237130 and the project value is estimated between $500,000 to $1,000,000. The performance period is 180 days from notice to proceed. Offerors must be registered in SAM.gov and the responsible agency is the Air Force Materiel Command Test Center.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs Received 6/17/2021:

1. According to the SOW, I understand demolition and disposal of the existing tower is to be Completed by contractor. However, does this include the electrical power devices enclosed in fencing? If so, does that include any underground powerlines to it?

Answer: Demolition is for tower, generator and transformer, etc. However, power lines connected to the old beacon tower are to be disconnected and terminated ONLY after the construction and full operational status of the new Air Traffic Control Tower (July 2022). See SOW Sections 4.2.10 and 4.2.11 for additional information.

2. Also, where does the existing generator scope of work fall? Is the contractor also to remove and dispose of existing generator or will this be taken care of prior to work?

Answer: See Above.